A kind of automated construction factory of Intelligent integrated Download PDFInfo
- Publication number
- CN108612325A CN108612325A CN201810552330.XA CN201810552330A CN108612325A CN 108612325 A CN108612325 A CN 108612325A CN 201810552330 A CN201810552330 A CN 201810552330A CN 108612325 A CN108612325 A CN 108612325A
- Authority
- CN
- China
- Prior art keywords
- guide rail
- fixing element
- fixedly mounted
- guide
- riser guide
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 33
- 239000000463 material Substances 0.000 claims abstract description 53
- 230000001603 reducing effect Effects 0.000 claims abstract description 23
- 238000007710 freezing Methods 0.000 claims abstract description 21
- 239000011248 coating agent Substances 0.000 claims abstract description 8
- 238000000576 coating method Methods 0.000 claims abstract description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 8
- 230000001681 protective effect Effects 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 4
- 230000032258 transport Effects 0.000 claims description 4
- 238000009435 building construction Methods 0.000 abstract description 3
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 6
- 230000002528 anti-freeze Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000000630 rising effect Effects 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 108010053481 Antifreeze Proteins Proteins 0.000 description 1
- 206010019345 Heat stroke Diseases 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/24—Safety or protective measures preventing damage to building parts or finishing work during construction
- E04G21/28—Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of automated construction factories of Intelligent integrated, it is related to Construction Engineering Equipment technical field, including riser guide, guide rail fixing element, material move horizontally the vertical transfer device of guide rail, material, the flat carriage of material water, lifting platform machinery, coating automatic open/closing device;Guide rail fixing element is fixedly mounted on concrete placings and completes on floor, and riser guide is passed through from guide rail fixing element, and concrete placings are completed corresponding to be provided with through-hole on floor;Lifting platform machinery is fixedly mounted on the side wall of riser guide;The coating automatic open/closing device includes sunshading and temperature reducing anti-freezing and heat-insulating layer, sliding roof and driving device, the beneficial effects of the invention are as follows:Suitable for the construction of various floors, the adjusting of position can be automatically carried out, is had wide range of applications, floor summer sunshading and temperature reducing, the preventing freeze in winter of concrete placings kept the temperature, rainy season rain-proof lightning protection, to reach project building construction full-automation purpose.
Description
Technical field
The present invention relates to Construction Engineering Equipment technical field, more particularly, it relates to a kind of Intelligent integrated
Automated construction factory.
Background technology
When architectural engineering chassis body structure construction, work surface is exposed to sun high temperature, rainy season, winter low temperature construction more,
It can not ensure the estimated completion duration, in torridity summer, temperature is higher in direct sunlight, operation side, and rainy season is unrestrained
Long, winter stops work, and being normally carried out for construction is seriously affected, to avoid shadow of the torridity summer high temperature climate to building engineering construction
It rings, some units take construction of staggering the time, and increase is avoided heat the methods of labour protection measure, but produce effects and bad, and high temperature influences construction and imitates
Worker's heatstroke is fallen in a swoon in rate problem, construction, and problem is not resolved yet.
Invention content
In order to overcome the shortcomings of that existing skyscraper technology, the present invention provide a kind of automated construction work of Intelligent integrated
Automatic lifting may be implemented in the automated construction factory of factory, the Intelligent integrated, to the floors of concrete placings carry out sunshade, rain cover,
It is antifreeze, it is easy to use, it is easy for removal and installation.
The technical solution adopted by the present invention to solve the technical problems is:A kind of automated construction work of Intelligent integrated
Factory thes improvement is that:Including riser guide, guide rail fixing element, material move horizontally the vertical transfer device of guide rail, material,
The flat carriage of material water, lifting platform machinery, coating automatic open/closing device;
The guide rail fixing element is fixedly mounted on concrete placings and completes on floor, and the riser guide is from guide rail fixing element
On across and concrete placings are completed corresponding to be provided with through-hole on floor;The lifting platform machinery is fixedly mounted on lifting and leads
On the side wall of rail, the lifting platform machinery is for driving riser guide to be risen or fallen in guide rail fixing element;
The material moves horizontally guide rail and is fixedly mounted on two vertical riser guides, the vertical transfer device of material
The lower position that guide rail is moved horizontally mounted on material realizes the transhipment of material vertical direction by the vertical transfer device of material;
The flat carriage of material water is slidably mounted on material and moves horizontally on guide rail, is used for the transhipment of material in the horizontal direction;
The coating automatic open/closing device includes sunshading and temperature reducing anti-freezing and heat-insulating layer, sliding roof and driving device,
The sunshading and temperature reducing anti-freezing and heat-insulating layer is fixedly mounted on the top of the riser guide, and the sliding roof is slidably mounted on
On sunshading and temperature reducing anti-freezing and heat-insulating layer, sliding roof is back and forth transported by the driving of driving device on sunshading and temperature reducing anti-freezing and heat-insulating layer
It is dynamic.
In such a configuration, the vertical transfer device of the material includes that material vertically transports protective cover, which hangs down
Straight transhipment protective cover is fixedly mounted on concrete placings and completes on floor, for protecting the rope for vertically transporting material.
In such a configuration, the automated construction factory of the Intelligent integrated further includes strenthening member, the reinforcing
One end of component is fixed on concrete placings and completes on floor, and the other end of strenthening member is fixedly mounted on riser guide.
In such a configuration, the lifting platform machinery includes lifting motor, lifting wirerope and rotating wheel;
A fixed platform is provided on the riser guide, the lifting motor is installed on the stationary platform, described
Rotating wheel be rotatably installed in the bottom end of riser guide, one end of the lifting wirerope is fixed on the motor shaft of lifting motor,
The other end for lifting wirerope bypasses rotating wheel, is fixed in guide rail fixing element.
In such a configuration, the through-hole being provided through on the sunshading and temperature reducing anti-freezing and heat-insulating layer, driving dress
It sets for driving sliding roof to be moved back and forth in through hole.
The beneficial effects of the invention are as follows:The automated construction factory of such Intelligent integrated of the present invention is suitable for various
The construction of floor after the completion of once mounting, can automatically carry out the adjusting of position, have wide range of applications, to the building of concrete placings
Layer summer sunshading and temperature reducing, preventing freeze in winter heat preservation, rainy season rain-proof lightning protection, to reach project building construction full-automation purpose;In addition
Due to its features simple structure, amount of parts is less, consequently facilitating disassembly and installation.
Description of the drawings
Fig. 1 is a kind of structural schematic diagram of the automated construction factory of Intelligent integrated of the present invention.
Specific implementation mode
Present invention will be further explained below with reference to the attached drawings and examples.
The technique effect of the design of the present invention, concrete structure and generation is carried out below with reference to embodiment and attached drawing clear
Chu is fully described by, to be completely understood by the purpose of the present invention, feature and effect.Obviously, described embodiment is this hair
Bright a part of the embodiment, rather than whole embodiments, based on the embodiment of the present invention, those skilled in the art are not being paid
The other embodiment obtained under the premise of creative work, belongs to the scope of protection of the invention.In addition, being arrived involved in patent
All connection/connection relations, not singly refer to component and directly connect, and refer to can according to specific implementation situation, by addition or
Couple auxiliary is reduced, to form more preferably coupling structure.Each technical characteristic in the invention, in not conflicting conflict
Under the premise of can be with combination of interactions.
Shown in referring to Fig.1, present invention is disclosed a kind of automated construction factories of Intelligent integrated, in the present embodiment,
The automated construction factory of the Intelligent integrated includes that riser guide 10, guide rail fixing element 20, material move horizontally guide rail 30, object
Expect the flat carriage 50 of vertical transfer device 40, material water, lifting platform machinery 60, coating automatic open/closing device;Described
Guide rail fixing element 20 is fixedly mounted on concrete placings and completes on floor 70, and it is floor 701 yet to be built that concrete placings, which complete 70 top of floor,;
The riser guide 10 is passed through from guide rail fixing element 20, and concrete placings are completed corresponding to be provided with through-hole on floor 70;Institute
The lifting platform machinery 60 stated is fixedly mounted on the side wall of riser guide 10, and lifting platform machinery 60 is for driving lifting to lead
Rail 10 rises or falls in guide rail fixing element 20;In the present embodiment, the described lifting platform machinery 60 include lifting motor,
Lift wirerope and rotating wheel;A fixed platform is provided on the riser guide 10, the lifting motor is mounted on solid
On fixed platform, the rotating wheel is rotatably installed in the bottom end of riser guide 10, and one end of the lifting wirerope is fixed on lifting
On the motor shaft of motor, the other end for lifting wirerope bypasses rotating wheel, is fixed in guide rail fixing element 20, therefore, passes through control
The positive and negative rotation of lifting motor can then control the raising and lowering of riser guide 10.
Further, as shown in Figure 1, the material, which moves horizontally guide rail 30, is fixedly mounted on vertical riser guide 10
On, it is of course also possible to more riser guides 10 be arranged, to ensure stability when running;The vertical transfer device 40 of material is pacified
The lower position that guide rail 30 is moved horizontally mounted in material realizes turning for material vertical direction by the vertical transfer device 40 of material
Fortune;In the present embodiment, the vertical transfer device 40 of the material vertically transports protective cover 401 including material, and the material is vertical
Transhipment protective cover 401 is fixedly mounted on concrete placings and completes on floor 70, for protecting the rope for vertically transporting material, keeps away
Exempt from rope or material touches other components.The flat carriage of the material water 50, which is slidably mounted on material and moves horizontally, leads
On rail 30, it to be used for the transhipment of material in the horizontal direction;In addition, the coating automatic open/closing device includes that sunshading and temperature reducing is anti-
Freeze insulating layer 801, sliding roof 802 and driving device (being not marked in figure), the sunshading and temperature reducing anti-freezing and heat-insulating layer 801 is solid
Dingan County is mounted in the top of the riser guide 10, and the sliding roof 802 is slidably mounted on sunshading and temperature reducing anti-freezing and heat-insulating layer 801
On, sliding roof 802 is moved back and forth by the driving of driving device on sunshading and temperature reducing anti-freezing and heat-insulating layer 801;The sunshade drop
The through-hole being provided through on warm anti-freezing and heat-insulating layer 801, the driving device is for driving sliding roof 802 past in through hole
Multiple movement is in closed state when sliding roof 802 is covered in the through hole of sunshading and temperature reducing anti-freezing and heat-insulating layer 801, at this time can be with
It is normally constructed, when the lid of sliding roof 802 is removed from the through hole of sunshading and temperature reducing anti-freezing and heat-insulating layer 801, in opening
State, can be with materials such as handling reinforcing bars.
In the above-described embodiment, the automated construction factory of the Intelligent integrated further includes strenthening member 901, should
One end of strenthening member 901 is fixed on concrete placings and completes on floor 70, and the other end of strenthening member 901 is fixedly mounted on lifting and leads
On rail 10, symmetrically the structure that isosceles triangle is formed in the both sides of riser guide 10 is arranged in two strenthening members 901, to rising
Drop guide rail 10 is supported, and improves the stability of operation,
By above-mentioned structure, when being constructed, by the effect of driving device, driving sliding roof 802 moves to
Sunshade and rain cover are realized in the through hole at the center of sunshading and temperature reducing anti-freezing and heat-insulating layer 801, when needing from the driving antifreeze guarantor of sunshading and temperature reducing
When being put into material on warm layer 801, due to being provided with through-hole on sunshading and temperature reducing anti-freezing and heat-insulating layer 801, material is put by the through-hole
Enter on floor 701 yet to be built;Hereafter, by the effect of driving device, driving sliding roof 802 moves, and sliding roof 802 is made to cover
Through-hole on sunshading and temperature reducing anti-freezing and heat-insulating layer 801 carries out sunshade and rain cover;After the completion of floor 701 yet to be built construction, pass through platform
The effect of elevation and subsidence mechanical 60 realizes the rising of sunshading and temperature reducing anti-freezing and heat-insulating layer 801, is oriented to, is kept away by guide rail fixing element 20
The position for exempting from riser guide 10 deviates, meanwhile, the vertical transfer device 40 of material and the flat carriage of material water 50 can be real
Existing material in the horizontal direction with the movement of vertical direction so that the transfer of material is very convenient quick.Therefore, of the invention
Such Intelligent integrated automated construction factory, be suitable for the construction of various floors, can be automatic after the completion of once mounting
Progress position adjusting, have wide range of applications, the floor summer sunshading and temperature reducings of concrete placings, preventing freeze in winter are kept the temperature, rainy season it is anti-
Rain lightning protection, to reach project building construction full-automation purpose;Additionally, due to its features simple structure, amount of parts is less, to
It is easy for removal and installation.
It is to be illustrated to the preferable implementation of the present invention, but the invention is not limited to the implementation above
Example, those skilled in the art can also make various equivalent variations or be replaced under the premise of without prejudice to spirit of that invention
It changes, these equivalent deformations or replacement are all contained in the application claim limited range.
Claims (5)
1. a kind of automated construction factory of Intelligent integrated, it is characterised in that:Including riser guide, guide rail fixing element, material
Move horizontally the vertical transfer device of guide rail, material, the flat carriage of material water, lifting platform machinery, coating automatic open-close dress
It sets;
The guide rail fixing element is fixedly mounted on concrete placings and completes on floor, and the riser guide is worn from guide rail fixing element
It crosses, and concrete placings are completed corresponding to be provided with through-hole on floor;The lifting platform machinery is fixedly mounted on riser guide
On side wall, the lifting platform machinery is for driving riser guide to be risen or fallen in guide rail fixing element;
The material moves horizontally guide rail and is fixedly mounted on two vertical riser guides, the vertical transfer device installation of material
The lower position of guide rail is moved horizontally in material, the transhipment of material vertical direction is realized by the vertical transfer device of material;It is described
The flat carriage of material water is slidably mounted on material and moves horizontally on guide rail, is used for the transhipment of material in the horizontal direction;
The coating automatic open/closing device includes sunshading and temperature reducing anti-freezing and heat-insulating layer, sliding roof and driving device, described
Sunshading and temperature reducing anti-freezing and heat-insulating layer be fixedly mounted on the top of the riser guide, the sliding roof is slidably mounted on sunshade
Cool down on anti-freezing and heat-insulating layer, sliding roof is moved back and forth by the driving of driving device on sunshading and temperature reducing anti-freezing and heat-insulating layer.
2. a kind of automated construction factory of Intelligent integrated according to claim 1, it is characterised in that:The material
Vertical transfer device includes that material vertically transports protective cover, which vertically transports protective cover and be fixedly mounted on concrete placings completion building
On layer, for protecting the rope for vertically transporting material.
3. a kind of automated construction factory of Intelligent integrated according to claim 1, it is characterised in that:The intelligence
Integrated automated construction factory further includes strenthening member, and one end of the strenthening member is fixed on concrete placings and completes on floor,
The other end of strenthening member is fixedly mounted on riser guide.
4. a kind of automated construction factory of Intelligent integrated according to claim 1, it is characterised in that:The platform
Elevation and subsidence mechanical includes lifting motor, lifting wirerope and rotating wheel;
A fixed platform is provided on the riser guide, the lifting motor is installed on the stationary platform, and described turns
Wheel rotation is mounted on the bottom end of riser guide, and one end of the lifting wirerope is fixed on the motor shaft of lifting motor, lifts
The other end of wirerope bypasses rotating wheel, is fixed in guide rail fixing element.
5. a kind of automated construction factory of Intelligent integrated according to claim 1, it is characterised in that:The sunshade drop
The through-hole being provided through on warm anti-freezing and heat-insulating layer, the driving device is for driving sliding roof back and forth to be transported in through hole
It is dynamic.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810552330.XA CN108612325B (en) | 2018-05-31 | 2018-05-31 | Intelligent integrated automatic construction factory |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810552330.XA CN108612325B (en) | 2018-05-31 | 2018-05-31 | Intelligent integrated automatic construction factory |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108612325A true CN108612325A (en) | 2018-10-02 |
CN108612325B CN108612325B (en) | 2024-04-26 |
Family
ID=63664503
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810552330.XA Active CN108612325B (en) | 2018-05-31 | 2018-05-31 | Intelligent integrated automatic construction factory |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108612325B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594773A (en) * | 2018-12-12 | 2019-04-09 | 湖南易兴建筑有限公司 | Automated construction system and construction method |
CN109629837A (en) * | 2019-01-15 | 2019-04-16 | 深圳汇林达科技有限公司 | A kind of automated construction factory of Intelligent integrated |
CN113958162A (en) * | 2021-11-08 | 2022-01-21 | 无锡工业建筑设计研究院有限公司 | Green ecological wisdom mill |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05321469A (en) * | 1992-05-20 | 1993-12-07 | Kumagai Gumi Co Ltd | All-weather type automatic construction of building |
JPH11223020A (en) * | 1998-02-06 | 1999-08-17 | Kawasaki Heavy Ind Ltd | Building construction method under temporary roof structure |
CN102182315A (en) * | 2011-03-31 | 2011-09-14 | 中广核工程有限公司 | All-weather construction method and construction device for nuclear power station |
CN107777262A (en) * | 2017-09-06 | 2018-03-09 | 湖北中浩建筑有限责任公司 | A kind of skyscraper various dimensions material-transporting system and its installation method |
CN208792798U (en) * | 2018-05-31 | 2019-04-26 | 深圳汇林达科技有限公司 | A kind of automated construction factory of Intelligent integrated |
-
2018
- 2018-05-31 CN CN201810552330.XA patent/CN108612325B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05321469A (en) * | 1992-05-20 | 1993-12-07 | Kumagai Gumi Co Ltd | All-weather type automatic construction of building |
JPH11223020A (en) * | 1998-02-06 | 1999-08-17 | Kawasaki Heavy Ind Ltd | Building construction method under temporary roof structure |
CN102182315A (en) * | 2011-03-31 | 2011-09-14 | 中广核工程有限公司 | All-weather construction method and construction device for nuclear power station |
CN107777262A (en) * | 2017-09-06 | 2018-03-09 | 湖北中浩建筑有限责任公司 | A kind of skyscraper various dimensions material-transporting system and its installation method |
CN208792798U (en) * | 2018-05-31 | 2019-04-26 | 深圳汇林达科技有限公司 | A kind of automated construction factory of Intelligent integrated |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109594773A (en) * | 2018-12-12 | 2019-04-09 | 湖南易兴建筑有限公司 | Automated construction system and construction method |
CN109629837A (en) * | 2019-01-15 | 2019-04-16 | 深圳汇林达科技有限公司 | A kind of automated construction factory of Intelligent integrated |
CN113958162A (en) * | 2021-11-08 | 2022-01-21 | 无锡工业建筑设计研究院有限公司 | Green ecological wisdom mill |
Also Published As
Publication number | Publication date |
---|---|
CN108612325B (en) | 2024-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108612325A (en) | A kind of automated construction factory of Intelligent integrated | |
CN105417450B (en) | Integrated hanger rail type external wall construction, cleaning and maintenance machine | |
CN208792798U (en) | A kind of automated construction factory of Intelligent integrated | |
CN207039532U (en) | A kind of roof linkage tracking photovoltaic bracket and photovoltaic generating system | |
CN205604955U (en) | Intelligent ventilating window | |
CN206554412U (en) | A kind of open-close type ventilation clerestory | |
CN103302278B (en) | Automatic cover adding and taking device of torpedo tank car | |
CN210767444U (en) | Novel steel construction for construction | |
CN107461059A (en) | A kind of steel-structure factory building | |
CN109629837A (en) | A kind of automated construction factory of Intelligent integrated | |
CN2837138Y (en) | Protection means for automobile | |
CN106958356A (en) | Automatic glass room and building | |
CN210976665U (en) | Cement protection device for construction | |
CN205134922U (en) | Platform basket is used in slope roofing construction | |
CN207332385U (en) | A kind of steel-structure factory building | |
CN206927496U (en) | The crane-men's house of the row's of being provided with rain device | |
CN207092605U (en) | A kind of distribution box protection canopy easy to remove | |
CN212403241U (en) | Weather-proof gantry crane | |
CN107605037B (en) | Can accomodate mobilizable outline window wall composite set | |
CN106638701B (en) | The lock chamber cover board and its installation method of electronic opening and closing | |
CN210012468U (en) | A safe lift for construction | |
CN215888430U (en) | Novel circulating water pump room structure of power plant | |
CN205653061U (en) | Take bridge crane that bulkhead cover | |
CN204754673U (en) | A prevent wind sand, winter protection door socket for transformer substation's building | |
CN221029638U (en) | Integrated operation room for cap beam construction and maintenance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |