CN108590705A - A kind of shield beginning well north and south side reserved opening formwork support system - Google Patents

A kind of shield beginning well north and south side reserved opening formwork support system Download PDF

Info

Publication number
CN108590705A
CN108590705A CN201810421469.0A CN201810421469A CN108590705A CN 108590705 A CN108590705 A CN 108590705A CN 201810421469 A CN201810421469 A CN 201810421469A CN 108590705 A CN108590705 A CN 108590705A
Authority
CN
China
Prior art keywords
support system
shield
reserved opening
south side
north
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810421469.0A
Other languages
Chinese (zh)
Inventor
杨祥亮
蔡志勇
张亮
薛春苗
李海峰
王涛
杨海健
郭玉海
王牧月
张晟源
陈雪峰
李星晨
吕金彪
张涛
王英波
苏世宗
石文正
王越
张建珍
李文新
庞梦月
姜宁宁
李丹丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Original Assignee
Beijing Municipal Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201810421469.0A priority Critical patent/CN108590705A/en
Publication of CN108590705A publication Critical patent/CN108590705A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of shield beginning well north and south side reserved opening formwork support systems, transverse passage-way is reserved including template system, support system, reserved opening and shield beginning well north and south side, the template system and support system are arranged at shield beginning well north and south side and reserve in the reserved opening of transverse passage-way;The support system includes design of coupler scaffold, shield well north and south side reserved opening is synchronized with shield well sidewall structure and is poured, the support of reserved opening bottom is using design of coupler scaffold as support system, using to supportting steel pipe, reserved opening inner support body system connect integral with shield well support system for side wall support;By setting template system and support system in the reserved opening that transverse passage-way is reserved in shield beginning well north and south side, the arch arch section and ring beam side wall of reserved opening are supported, formwork structure intensity is high;The bearing strength for improving support system keeps its support more secured, reliable, reduces construction risk.

Description

A kind of shield beginning well north and south side reserved opening formwork support system
Technical field
The present invention relates to constructing metro tunnel technical fields, more specifically, it relates to which a kind of shield beginning well north and south side is pre- Box out mouth template support system.
Background technology
In subway work, " shield construction " is used as a kind of advanced method for tunnel construction, has mechanical automation journey Degree is high, speed of application is fast, ground disturbance is small, road traffic, ground surface environment is not interfered to influence the advantages that small, at present in China tunnel Engineering field has obtained extensive utilization, and later shield tunnel proportion shared in China's field of traffic will be increasingly Greatly.
It is shield launching construction to build the work that tunnel first has to carry out using shield construction, if shield launching is constructed It is not interior AT STATION carry out, it usually needs then shield machine is hung in and originated in vertical shaft by a shield launching vertical shaft of first constructing again Carry out shield launching construction.Shield machine cannot carry out tuning in the when of being promoted on the track of bracket that originates originated in vertical shaft, and Shield launching construction often carries out in having performed the vertical shaft soil layer that grouting and reinforcing or rotary churning pile are reinforced, and the resistance of driving is very Greatly, thus shield launching construction be all the time shield construction tunnel heavy difficult point and risk point, be one in shield construction A particularly important link, is often related to the success or failure of entire shield tunnel construction.
At present when shield beginning well north and south side reserved opening carries out shield launching construction, for the shield of north and south side reserved opening Structure is very important link in subway work, needs manually or mechanically to cut portal glass in the construction of north and south side reserved opening Fiber bar stake cuts, portal poor flatness longer with clearance time, and when originating the soil body cave in the risk of soil erosion compared with Height, the waste of portal plugging material are serious.When being supported to north and south side reserved opening using template, need preferable north and south side reserved Opening mould plate support system satisfies the use demand.
Invention content
In view of the deficiencies of the prior art, the present invention intends to provide a kind of shield beginning well north and south side reserved opening Form bracing system, to solve the problems mentioned in the above background technology.
To achieve the above object, the present invention provides the following technical solutions:
A kind of shield beginning well north and south side reserved opening formwork support system, including template system, support system, reserved opening Transverse passage-way is reserved with shield beginning well north and south side, it is reserved that the template system and support system are arranged at shield beginning well north and south side In the reserved opening of transverse passage-way;The template system includes arch arch section template, circumferential keel, longitudinal keel, adjustable Jacking, ring beam side template panel, vertical back cord and lateral back cord;The support system includes design of coupler scaffold, shield well North and south side reserved opening is synchronized with shield well sidewall structure and is poured, and the support of reserved opening bottom is using design of coupler scaffold as branch Support body system, using to supportting steel pipe, reserved opening inner support body system connect integral with shield well support system for side wall support.
Further, the ring beam side template panel that transverse passage-way is reserved in launching shaft north and south side is 18mm thickness glued boards, Vertical back cord is 100mm × 50mm lumps of wood, and spacing 200mm, lateral back cord is 100mm × 100mm lumps of wood, spacing 600mm.
Further, the scaffold upright rod spacing of the design of coupler scaffold is 500 × 175mm, and scaffold waling stripe is perpendicular It it is 0.5 meter to spacing.
Further, the side wall support is using to supportting steel pipe, vertical spacing 0.5m.
Further, by adjustable jack connect with support system on the inside of template system.
Further, it is internally provided with bridging in support system.
Further, in leading for support system both sides and shield well construction of guide wall is equipped between wall stitches.
Further, it is equipped in support system bottom and pads the lumps of wood, the size for padding the lumps of wood is the lumps of wood of 100 × 50mm.
In conclusion the present invention has the advantages that compared with prior art:
The present invention passes through setting template system and supporter in the reserved opening that transverse passage-way is reserved in shield beginning well north and south side System, template system use arch arch section template, circumferential keel, longitudinal keel, adjustable jack, ring beam side template panel, erect To back cord and lateral back cord, the arch arch section and ring beam side wall of reserved opening are supported, in circumferential keel, Zong Xianglong Under the reinforcing of bone and vertical back cord and lateral back cord, formwork structure intensity is high;Secondly, the support being made of design of coupler scaffold System improves the bearing strength of support system, keeps its support more secured, reliable, reduces construction risk.
More clearly to illustrate the structure feature and effect of the present invention, come below in conjunction with the accompanying drawings to this hair with specific embodiment It is bright to be described in detail.
Description of the drawings
Fig. 1 is the shield well north side reserved opening formwork support system figure of the present invention.
Fig. 2 is the shield well southern side reserved opening formwork support system figure of the present invention.
Fig. 3 is form bracing system sectional view at the reserved opening of the present invention.
Reference numeral:The arch 1- arch section template, 2- circumferential directions keel, 3- longitudinal keels, 4- adjustable jacks, 5- ring beams side The vertical back cord of form surfacing, 6-, 7- transverse directions back cord, 8- construction of guide wall seam, 9-, which pad the lumps of wood, 10- reserved openings, 11- shields, to be begun Transverse passage-way, 12- bridgings, 13- are reserved to supportting steel pipe in well north and south side.
Specific implementation mode
The following further describes the technical solution of the present invention in the following with reference to the drawings and specific embodiments.
Referring to Fig. 1-Fig. 3, a kind of shield beginning well north and south side reserved opening formwork support system, including template system, support Transverse passage-way 11 is reserved in system, reserved opening 10 and shield beginning well north and south side, and the template system and support system are arranged at It reserves in the reserved opening 10 of transverse passage-way 11 shield beginning well north and south side.
The template system includes arch arch section template 1, circumferential keel 2, longitudinal keel 3, adjustable jack 4, ring Side template panel 5, vertical back cord 6 and lateral back cord 7;
Template system:The ring beam side template panel 5 that transverse passage-way 11 is reserved in launching shaft north and south side is thick glued using 18mm Plate, vertical back cord 6 use 100mm × 50mm lumps of wood, spacing 200mm, lateral back cord 7 to use 100mm × 100mm lumps of wood, spacing 600mm;
Arch arch section template 1 uses 18mm thickness wood plywoods, carries out assembly according to arch radian, circumferential keel 2 are adopted WithSteel pipe is bent according to radian, ring beam bottom sets 4 altogether, spacing 175mm;Longitudinal keel 3 uses 100mm × 100mm The lumps of wood, spacing 0.5m refer to lower Fig. 1, Fig. 2.
The support system includes design of coupler scaffold;
Support system:Shield well north and south side reserved opening is synchronized with shield well sidewall structure and is poured, reserved opening bottom branch Support is using design of coupler scaffold as support system, and scaffold upright rod spacing is 500 × 175mm, and scaffold waling stripe is vertical Spacing is 0.5 meter, as shown in Figure 2 and Figure 3;Side wall support is using to supportting steel pipe 13, vertical spacing 0.5m;Inside reserved opening 10 Support system connect integral with shield well support system, refers to lower Fig. 3.
Preferably, in the present embodiment, by adjustable jack 4 connect with support system on the inside of template system.
It is internally provided in support system referring to Fig. 3 in order to further improve the structural strength and stability of support system Bridging 12 is equipped with construction of guide wall between wall and stitches 8, propping up for increasing structural strength in leading for support system both sides and shield well Support body system bottom is equipped with and pads the lumps of wood 9, and the size for padding the lumps of wood 9 is the lumps of wood of 100 × 50mm.
The technical principle that the present invention is described above in association with specific embodiment, is only the preferred embodiment of the present invention.This The protection domain of invention is not limited merely to above-described embodiment, and all technical solutions belonged under thinking of the present invention belong to the present invention Protection domain.Those skilled in the art would not require any inventive effort the other specific realities that can associate the present invention Mode is applied, these modes are fallen within protection scope of the present invention.

Claims (8)

1. a kind of shield beginning well north and south side reserved opening formwork support system, including template system, support system, reserved opening (10) and transverse passage-way (11) is reserved in shield beginning well north and south side, which is characterized in that the template system and support system is respectively provided with In the reserved opening (10) that transverse passage-way (11) is reserved in shield beginning well north and south side;The template system includes arch arch section Template (1), circumferential keel (2), longitudinal keel (3), adjustable jack (4), ring beam side template panel (5), vertical back cord (6) and cross To back cord (7);The support system includes design of coupler scaffold, and shield well north and south side reserved opening is the same as shield well sidewall structure It synchronizes and pours, the support of reserved opening bottom is using design of coupler scaffold as support system, and side wall support is using to supportting steel pipe (13), reserved opening (10) inner support body system connect integral with shield well support system.
2. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 1, which is characterized in that institute It is 18mm thickness glued boards, vertical back cord (6) to state launching shaft north and south side and reserve the ring beam side template panel (5) of transverse passage-way (11) For 100mm × 50mm lumps of wood, spacing 200mm, lateral back cord (7) is 100mm × 100mm lumps of wood, spacing 600mm.
3. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 1 or 2, feature exist In the scaffold upright rod spacing of the design of coupler scaffold is 500 × 175mm, and the vertical spacing of scaffold waling stripe is 0.5 Rice.
4. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 3, which is characterized in that institute Side wall support is stated using to support steel pipe (13), vertical spacing 0.5m.
5. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 1, which is characterized in that By adjustable jack (4) connect with support system on the inside of template system.
6. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 1, which is characterized in that Support system is internally provided with bridging (12).
7. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 6, which is characterized in that The leading of support system both sides and shield well is equipped with construction of guide wall between wall and stitches (8).
8. a kind of shield beginning well north and south side reserved opening formwork support system according to claim 7, which is characterized in that Support system bottom is equipped with and pads the lumps of wood (9), and the size for padding the lumps of wood (9) is the lumps of wood of 100 × 50mm.
CN201810421469.0A 2018-05-04 2018-05-04 A kind of shield beginning well north and south side reserved opening formwork support system Pending CN108590705A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810421469.0A CN108590705A (en) 2018-05-04 2018-05-04 A kind of shield beginning well north and south side reserved opening formwork support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810421469.0A CN108590705A (en) 2018-05-04 2018-05-04 A kind of shield beginning well north and south side reserved opening formwork support system

Publications (1)

Publication Number Publication Date
CN108590705A true CN108590705A (en) 2018-09-28

Family

ID=63619858

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810421469.0A Pending CN108590705A (en) 2018-05-04 2018-05-04 A kind of shield beginning well north and south side reserved opening formwork support system

Country Status (1)

Country Link
CN (1) CN108590705A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252880A (en) * 2018-11-14 2019-01-22 天津三建建筑工程有限公司 The component of leak at a kind of shield duct piece for preventing shield tunnel
CN109681239A (en) * 2019-01-16 2019-04-26 北京市政建设集团有限责任公司 A kind of unearthed tunnel mould bases construction method of shield
CN110645022A (en) * 2019-10-29 2020-01-03 中建八局轨道交通建设有限公司 Self-anchored formwork support system for connecting channel and construction method
CN115263342A (en) * 2022-07-29 2022-11-01 华东交通大学 Multifunctional operation frame for chiseling construction of earth pressure balance shield tunnel portal

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2701972Y (en) * 2004-07-01 2005-05-25 北京建工一建工程建设有限公司 Bending column wood template with saw gullet
CN1730909A (en) * 2005-08-04 2006-02-08 上海隧道工程股份有限公司 Steel formwork support system for extruded concrete lining method for shielding rectangular tunnel
CN102322149A (en) * 2011-06-27 2012-01-18 中国建筑第二工程局有限公司 Full-section overall casting construction method for circulating water pipe ditch of nuclear power plant
CN204716257U (en) * 2015-03-31 2015-10-21 中交二航局第四工程有限公司 Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction
CN204716252U (en) * 2015-06-12 2015-10-21 中铁六局集团有限公司 Gate type support frame
CN105201518A (en) * 2015-10-13 2015-12-30 铁道第三勘察设计院集团有限公司 Method for receiving and disassembly of large-diameter slurry balance shield in hole
CN105421490A (en) * 2015-12-25 2016-03-23 北京市政建设集团有限责任公司 Structure formwork support system free from support replacement and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2701972Y (en) * 2004-07-01 2005-05-25 北京建工一建工程建设有限公司 Bending column wood template with saw gullet
CN1730909A (en) * 2005-08-04 2006-02-08 上海隧道工程股份有限公司 Steel formwork support system for extruded concrete lining method for shielding rectangular tunnel
CN102322149A (en) * 2011-06-27 2012-01-18 中国建筑第二工程局有限公司 Full-section overall casting construction method for circulating water pipe ditch of nuclear power plant
CN204716257U (en) * 2015-03-31 2015-10-21 中交二航局第四工程有限公司 Guarantee that shield whole starts and the variable door opening cribbing of station main body synchronous construction
CN204716252U (en) * 2015-06-12 2015-10-21 中铁六局集团有限公司 Gate type support frame
CN105201518A (en) * 2015-10-13 2015-12-30 铁道第三勘察设计院集团有限公司 Method for receiving and disassembly of large-diameter slurry balance shield in hole
CN105421490A (en) * 2015-12-25 2016-03-23 北京市政建设集团有限责任公司 Structure formwork support system free from support replacement and construction method thereof

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘兵科: "盾构始发预留洞口模板体系的设计与施工", 《施工技术》 *
徐明霞: "<混凝土结构工程施工 第2版>", 28 February 2016 *
陈立锦等: "单侧模板支撑体系在地铁明挖车站施工中的应用", <建筑技术> *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252880A (en) * 2018-11-14 2019-01-22 天津三建建筑工程有限公司 The component of leak at a kind of shield duct piece for preventing shield tunnel
CN109252880B (en) * 2018-11-14 2024-03-19 天津三建建筑工程有限公司 A component for preventing shield segment department of shield tunnel leaks
CN109681239A (en) * 2019-01-16 2019-04-26 北京市政建设集团有限责任公司 A kind of unearthed tunnel mould bases construction method of shield
CN110645022A (en) * 2019-10-29 2020-01-03 中建八局轨道交通建设有限公司 Self-anchored formwork support system for connecting channel and construction method
CN115263342A (en) * 2022-07-29 2022-11-01 华东交通大学 Multifunctional operation frame for chiseling construction of earth pressure balance shield tunnel portal
CN115263342B (en) * 2022-07-29 2023-03-31 华东交通大学 Multifunctional operation frame for earth pressure balance shield tunnel portal chiseling construction

Similar Documents

Publication Publication Date Title
CN108590705A (en) A kind of shield beginning well north and south side reserved opening formwork support system
CN102996133B (en) Construction method applicable to intersection between inclined shaft and slant hole of weak surrounding rock tunnel
CN106050245A (en) Supporting structure for zero distance underneath pass of existing station of rectangular tunnel section and construction method
CN101864959A (en) Method for tunneling construction of main structure of underground station
CN109488330A (en) The open cut tunnel for passing through half Packing character solution cavity adds the tunnel bottom stake hardened structure of raft
CN205578016U (en) Shield constructs quick -witted section of jurisdiction handling system
CN110578525A (en) micro-disturbance construction method for crossing operation subway tunnel by overlapping shield tunnel
CN108691552A (en) Big cross section shape of a hoof shield cutting receives construction method
CN108643918A (en) A kind of side wall template of launching shaft and the installation method of support system
CN109667601A (en) A kind of construction method that glass fibre main reinforcement portal is originated with steel bushing and off-axis line
CN107237638A (en) Both wired concealed tunneling structure and its construction method are worn under a kind of
CN202659247U (en) Back templates and combined steel die for tunnel inverted arch construction
CN108590179A (en) A kind of side wall form bracing system of launching shaft
CN103967052B (en) A kind of method of protecting the new and old frame core-tube system substrate discrepancy in elevation soil body
CN209444345U (en) A kind of tunnel arch prefabricated pipe section constructing device
CN108252307A (en) A kind of foundation pit construction method for underground tunnel upper
CN108661652A (en) Shield launching and reception end bracing means and method in Tunneling by mining method
CN208518679U (en) The supporting construction of template at a kind of shield well construction reserved opening ring beam
CN103669220A (en) Installing method for long, large and light-weight heavy-load rail-crossing trestle in tunnel inverted arch construction
CN207959020U (en) It is a kind of based on ballast balance pushing tow frame structure method road under wear high ferro device
CN208184750U (en) Shuttering supporting body at a kind of haunch of shield well side wall armpit Angle formwork
CN206111182U (en) Wear supporting construction at existing station under rectangle tunnel section zero distance
CN205638459U (en) Slurry shield passes through interval pressure -bearing water sand bed ventilating shaft and seals soil box
CN208396716U (en) A kind of shield well construction reserved opening arch formwork structure
CN207761668U (en) A kind of supporting construction of novel tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928