CN108575580A CN201810038947.XA CN201810038947A CN108575580A CN 108575580 A CN108575580 A CN 108575580A CN 201810038947 A CN201810038947 A CN 201810038947A CN 108575580 A CN108575580 A CN 108575580A
Authority
CN
China
Prior art keywords
mud
ecological
plate
river bottom
urban construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810038947.XA
Other languages
Chinese (zh)
Inventor
张敏特
吴庆
陈晨
朱袁洁
孙梦蝶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu University of Science and Technology
Original Assignee
Jiangsu University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu University of Science and Technology filed Critical Jiangsu University of Science and Technology
Priority to CN201810038947.XA priority Critical patent/CN108575580A/en
Publication of CN108575580A publication Critical patent/CN108575580A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G22/00Cultivation of specific crops or plants not otherwise provided for
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G31/00Soilless cultivation, e.g. hydroponics
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor

Abstract

The invention discloses a kind of plate and frame river bottom mud ecological revetments and preparation method for sponge urban construction, the bank protection includes the slopes being inclined to set, set on slope surface, stepped several ecological basins, several ecological module units are equipped in the ecology basin, the ecological module unit is equipped with metalling, mud and water plant layer successively from bottom to up;Its preparation method is to establish slopes, and several ecological basins are arranged in the slopes, fills metalling, mud and water plant layer into the ecology basin respectively, you can.The remarkable advantage of the present invention is the bank protection by using whole ecological revetment system; it is capable of the Ecological Stabilization structure of effective protection side slope; and the value of river bottom mud is taken full advantage of when preparing; form the ecological basin for including " bed mud conditioned soil+Porous permeable bricks+amphibious plant " ecomodel; have the characteristics that easy for construction, ecological beauty, mud reuse ratio are high and easy to maintain, at low cost.

Description

A kind of plate and frame river bottom mud ecological revetment and preparation for sponge urban construction Method
Technical field
The invention belongs to river corridor restoration field more particularly to a kind of plate and frame river bottoms for sponge urban construction Mud ecological revetment and preparation method.
Background technology
China In Middle And Lower Reaches of Changjiang River be all the time rainwater multiplely, thus bring up the south of the lower reaches of the Yangtze River be distributed it is dense each Class branch water system, and since southern area of Jiangsu Province is mostly Plain, most of rainwater often via Urban Rainwater Pipe Networks be discharged into arround water body, Rainy season river average water face height is caused significantly to rise.In addition, the mud that korneforos is accumulated for a long time is often to the unimpeded flowing of water body Larger resistance is generated, causes river water can not proper flow.Therefore, the mode that Ha Noi dredging is usually taken dredges river and by building It makes bank protection and maintenance is increased to riverbank.Channel cleanout can dredge river, reduce water level, rushed to Channel slope to reduce water body Brush, but cost is higher, and mud recycle value can not be promoted.Though traditional bank engineering such as cement bank protection, piling bank protection etc. can be compared with Side slope avalanche phenomenon is reduced to limits, protection side slope protects against the water level constantly risen and washes away, but it usually destroys river Road periphery plant, makes the ecosystem arround river water by expendable destruction.Adaptation to local conditions is taken economical and practical, naturally beautiful And the plate and frame river bottom mud ecological bank protecting method with self-loopa function is the current inexorable trend for carrying out dredging waterway.
At present China ecological vestige continuously improve, but lay particular emphasis on from superstructure face, such as Patent No. more 201621213261.2 utility model discloses a kind of hydraulic engineering ecological protection slope, this bank protection technique is relatively complicated, expense compared with Height, and without carrying out river dredging, the water level for not solving fundamentally to rise steadily washes away river, is more not carried out river The resources advantage of bed mud.The utility model of Patent No. 201621117910.9 discloses a kind of novel ecological revetment, this shield Slope focuses on improving ecological revetment matrix, and the manufacture difficulty of revetment brick is higher, and process is complex, and the brick body of this bank protection Density is larger, does not play vegetation slope pavement effect to greatest extent.
Invention content
Goal of the invention:The first object of the present invention is to provide a kind of plate and frame river bottom mud life for sponge urban construction State bank protection, the bank protection are capable of the Ecological Stabilization structure of effective protection side slope by using whole ecological revetment system;
The second object of the present invention is to provide the preparation method of the bank protection, and this method takes full advantage of the valence of river bottom mud Value, forms the ecological basin for including " bed mud conditioned soil+Porous permeable bricks+amphibious plant " ecomodel, has construction party Just, ecological beauty, the features such as mud reuse ratio is high, and it is easy to maintain, at low cost.
Technical solution:The present invention is used for the plate and frame river bottom mud ecological revetment of sponge urban construction, including inclined sets The slopes set are set to slope surface, stepped several ecological basins, several ecological module units, institute are equipped in the ecology basin It states ecological module unit and is equipped with metalling, mud and water plant layer successively from bottom to up.
Furtherly, ecological basin is circumferentially enclosed by wedge-shaped porous preforming brick and is made.Novel porous special precast brick is to slope Face carries out ecological modular processing, and uses wedge-shaped, and when construction is inserted directly into plain soil, and slope surface difference in height is utilized to constitute ecology Module volume, convenient for construction, and entire work progress does not apply any artificial material, and landfill mud is convenient and simple, at modularization Reason can effectively prevent fluidity pollutant further to spread, and it is good to seep water and intercept soil effect.Preferably, the depth of the ecology basin is 200~300mm is conducive to the leakage of ponding in ecological basin in this depth bounds, and can resist rainwash, provides plant By the amount of soil needed for growth.
The method that the present invention prepares the plate and frame river bottom mud ecological revetment for sponge urban construction, including walk as follows Suddenly:Slopes are established, several ecological basins are set in the slopes, respectively filling metalling, mud and aquatic into the ecology basin Layer of plants.
It further says, the preparation method of mud includes the following steps:Ha Noi dredging is extracted, cation is added in mud Polyacrylamide solution, 1~1.5h of stirring at low speed, subsequent addition powder slag and calcium carbide waste slag, control mud pH value 7.0~ 9.0, after stirring, it is placed on metalling.
The present invention is produced by the way that positively charged cationic polyacrylamide (CPAM) is added with negatively charged riverway sludge Raw charging neutrality reaction, changes the hydrophobic property of mud so that is adsorbed in muck surface attached water and its hole elutriation of inside Go out.A certain amount of powder slag and calcium carbide waste slag is then added, since the mineral facies in powder slag are tricalcium silicate, silicic acid two Calcium, calcium aluminoferrite etc. can generate flocculation and neutralization reaction, the precipitation of reinforcement sludge pore water, while combination reaction with sludge Calcium hydroxide, iron hydroxide and the magnesium hydroxide of generation have hydration curing characteristic, can further increase the solidification effect of mud Fruit.Calcium carbide waste slag main component is calcium hydroxide, and high alkalinity, water-retaining property is strong, is acted synergistically with powder slag, and mud is being reinforced On the basis of intensity, the performance of mud conditioned soil is adjusted, it is made to be more conducive to vegetation growth.
Furtherly, the mass concentration of cationic polyacrylamide solution can be 0.03~0.05g/L, with mud Volume ratio can be 0.8~1:100, muck surface attached water and its hole of inside can be effectively precipitated in the concentration and volume ratio Water;The mass-volume concentration of powder slag and mud ratio can be 50~100:1, the mass-volume concentration ratio of calcium carbide waste slag and mud Can be 0.8~1:100, which can enhance the solidification effect of mud, increase the intensity of mud, and can increase in mud Nutritional ingredient.
Advantageous effect:Compared with prior art, remarkable advantage of the invention is:The protective slope structure is simple, convenient for safeguarding (only Ecological brick position need to suitably be adjusted), can not only effective protection side slope Ecological Stabilization structure, and can be to mud waste water Filtering in time, rainwater can pass through several ladder modules by " amphibious plant → improvement mud → rubble filters " when rainwater is more It successively handles, finally flows slowly into water body, to which rainwater break the whole up into parts, preliminary purification is carried out to initial rainwater.
When method using the present invention prepares the bank protection, river slope surface can be remolded according to river actual conditions, And by carrying out ecological modular processing to slope surface with novel porous special precast brick;River is cleared up in combination with channel cleanout On the one hand road is dredged and has been removed to riverway sludge so that streamflow is unimpeded, and the water surface declines, and reduces side slope It corrodes, solves riverway sludge and solve difficult, of high cost and issuable secondary pollution problems, on the other hand by becoming silted up Mud is improved, the good test effects such as intensity of conditioned soil, while with containing in river bottom mud and dump slag, calcium carbide waste slag Nutritional ingredient is high, can supply sufficient nutriment so that mud constitutes ecological vegetable medium body, on the mud of improvement Amphibious plant is planted, the utilization rate of riverway sludge is larger improved, turns waste into wealth, and the amphibious plant planted is in U.S. The water body with arround forms the ecosphere while seeing greening, root system ambient microorganisms and conditioned soil, gravel at natural ecological film, into One step controls the pollution sources that various waste water flow into river, and the slope surface soil body, structure are fixed in the interdependence of root system of plant and conditioned soil Build stable ecological slope protection structure.
Description of the drawings
Fig. 1 is the plate and frame river bottom mud ecological slope protection structure schematic diagram of the present invention;
Fig. 2 is the enlarged drawing in the portions A in Fig. 1;
Specific implementation mode
Technical scheme of the present invention is described in further details with reference to the accompanying drawings and embodiments.
As shown in Figure 1, the present invention is used for the plate and frame river bottom mud ecological revetment of sponge urban construction, including inclined set The slopes 1 set be set to it is 1 surface of slopes, stepped it is several ecological basin 2 made of system is circumferentially enclosed by wedge-shaped porous preforming brick, Several ecological modules Unit 3 is equipped in the ecology basin 2, ecological module Unit 3 is equipped with metalling 4, becomes silted up successively from bottom to up Mud layer 5 and water plant layer 6, as shown in Figure 2.
Embodiment 1
The method that the present invention prepares the plate and frame river bottom mud ecological revetment for sponge urban construction, including walk as follows Suddenly:
(1) mud is improved:
A. sludge pump is utilized tentatively to remove the mud of bottom of river channel, the river of wide 5m, every meter of dredging 4m3Mud;
B. the CPAM solution that mass concentration is 0.05g/L, stirring at low speed 1h are added in mud, while adding 200kg powder As modifying agent, control mud pH value 7.0 obtains about 2m for last slag, 2kg calcium carbide waste slags3Mud conditioned soil;Wherein, CPAM The addition of solution and the volume ratio of mud are 1:100.
(2) river bottom mud ecological revetment is built:
A. river slope surface standardization leveling, river slope surface is levelling, after precipitation, compacting element soil, simultaneously according to slope surface actual conditions Consider the infrastructure such as peripheral path, building, establishes the slopes 1 of height h=4m, width D=5m;
B. ecological basin 2 is built by Prefabricated porous brick in the slope of slopes 1, forming difference in height using slope constitutes ditch Slot, rams in flat groove element soil, forms the ecological basin 2 that depth is 300mm per side slope, and the slope surface of 5m wide is arranged 3 groups of ladders lifes altogether State basin 2, every group of wide 1.2m of ladder;
C. cloth builds permeable layer in ecological basin 2, forms preliminary filtering, i.e., thickness 50mm blotters of arranging in ecological basin 2 4;
D. above-mentioned conditioned soil is inserted in ecological basin 2, each ecology basin 2 inserts 0.3m3Conditioned soil is placed in blotter 4 On;
E. amphibious plant is uniformly planted in mud conditioned soil.
In conclusion the river of high H=4m, the slope surface of width D=5m and width 5m, every meter is removed mud 4m3, it can be filled with life altogether 2 both sides of state basin totally 6 groups of ladders are more than 90% mud in fixed river.
Embodiment 2
The method that the present invention prepares the plate and frame river bottom mud ecological revetment for sponge urban construction, including walk as follows Suddenly:
(1) mud is improved:
A. sludge pump is utilized tentatively to remove the mud of bottom of river channel, the river of wide 8m, every meter of dredging 6m3Mud;
B. the CPAM solution that mass concentration is 0.05g/L is added in mud, stirring at low speed 1h then adds 300kg powder As modifying agent, control mud pH value 7.5 obtains about 3.0m for last slag, 3kg calcium carbide waste slags3Mud conditioned soil;Wherein, The addition of CPAM solution and the volume ratio of mud are 1:100.
(2) river bottom mud ecological revetment is built:
A. river slope surface standardization leveling, river slope surface is levelling, after precipitation, compacting element soil, simultaneously according to slope surface actual conditions Consider the infrastructure such as peripheral path, building, establishes the slopes 1 of height h=6m, width D=10m;
B. ecological basin 2 is built by Prefabricated porous brick in the slope of slopes 1, forming difference in height using slope constitutes ditch Slot, rams in flat groove element soil, forms the ecological basin 2 that depth is 300mm per side slope, and the slope surface of 5m wide is arranged 7 groups of ladders lifes altogether State basin 2, every group of wide 1m of ladder;
C. cloth builds permeable layer in ecological basin 2, forms preliminary filtering, i.e., thickness 50mm blotters of arranging in ecological basin 2 4;
E. above-mentioned conditioned soil is inserted in ecological basin 2, each ecology basin 2 inserts 0.3m3Conditioned soil is placed in blotter 4 On;
F. amphibious plant is uniformly planted in mud conditioned soil.
In conclusion the river of high H=6m, the slope surface of width D=10m and width 8m, every meter is removed mud 6m3, can be filled with altogether Totally 14 groups of 2 both sides of ecological basin are more than 90% mud in fixed river.
Embodiment 3
The method that the present invention prepares the plate and frame river bottom mud ecological revetment for sponge urban construction, including walk as follows Suddenly:
(1) mud is improved:
A. sludge pump is utilized tentatively to remove the mud of bottom of river channel, the river of wide 12m, every meter of dredging 10m3Mud;
B. the CPAM solution of a concentration of 0.05g/L is added in mud, stirring at low speed 1h then adds 500kg powder steels As modifying agent, control mud pH value 8.0 obtains about 5.0m for slag, 5kg calcium carbide waste slags3Mud conditioned soil;Wherein, CPAM is molten The addition of liquid and the volume ratio of mud are 1:100.
(2) river bottom mud ecological revetment is built:
A. river slope surface standardization leveling, river slope surface is levelling, after precipitation, compacting element soil, simultaneously according to slope surface actual conditions Consider the infrastructure such as peripheral path, building, establishes the slopes 1 of height h=9m, width D=15m;
B. ecological basin is built by Prefabricated porous brick in the slope of slopes 1, forming difference in height using slope constitutes ditch Slot, rams in flat groove element soil, forms the ecological basin 2 that depth is 300mm per side slope, and the slope surface of 5m wide is arranged 10 groups of ladders lifes altogether State basin 2, every group of wide 1m of ladder;
C. cloth builds permeable layer in ecological basin 2, forms preliminary filtering, i.e., thickness 50mm blotters of arranging in ecological basin 2 4;
D. above-mentioned conditioned soil is inserted in ecological basin 2, each ecology basin 2 inserts 0.3m3Conditioned soil is placed in blotter On;
E. amphibious plant is uniformly planted in mud conditioned soil.
In conclusion the river of high H=9m, the slope surface of width D=15m and width 12m, every meter is removed mud 10m3, can fill out altogether Totally 20 groups of 2 both sides of state basin are freeed, are more than 90% mud in fixed river.
Embodiment 4
Basic step is same as Example 1, the difference is that:It is 0.03g/L's that mass concentration is added in mud CPAM solution, control mud pH value 9.0, stirring at low speed 1.5h, while by every cubic metre of mud add 50kg powder slag, 0.8kg calcium carbide waste slags obtain the mud conditioned soil of certain volume as modifying agent, wherein the addition and mud of CPAM solution Volume ratio be 0.8:100, the depth of the ecological basin 2 of preparation is 200mm.

Claims (9)

1. a kind of plate and frame river bottom mud ecological revetment for sponge urban construction, including the slopes (1) that are inclined to set, It is characterized in that:The bank protection further includes being set in slopes (1) surface, stepped several ecological basins (2), the ecology basin (2) There are several ecological modules (3) unit, ecological module (3) unit to be equipped with metalling (4), mud (5) successively from bottom to up And water plant layer (6).
2. the plate and frame river bottom mud ecological revetment according to claim 1 for sponge urban construction, it is characterised in that: The ecology basin (2) is circumferentially enclosed by wedge-shaped porous preforming brick makes.
3. the plate and frame river bottom mud ecological revetment according to claim 1 for sponge urban construction, it is characterised in that: The depth of the ecology basin (2) is 200~300mm.
4. a kind of method preparing the plate and frame river bottom mud ecological revetment described in claim 1 for sponge urban construction, It is characterized in that including the following steps:Slopes (1) are established, several ecological basins (2) are set in the slopes (1), respectively to the ecology Filling metalling (4), mud (5) and water plant layer (6) in basin (2).
5. the method according to claim 4 for preparing the plate and frame river bottom mud ecological revetment for sponge urban construction, It is characterized in that:The preparation method of the mud (5) includes the following steps:Ha Noi dredging is extracted, cation is added in mud Polyacrylamide solution, 1~1.5h of stirring at low speed, subsequent addition powder slag and calcium carbide waste slag, control mud pH value 7.0~ 9.0, after stirring, it is placed on metalling (4).
6. the method for preparing the plate and frame river bottom mud ecological revetment for sponge urban construction according to claim 5, It is characterized in that:The mass concentration of the cationic polyacrylamide solution is 0.03~0.05g/L.
7. the method for preparing the plate and frame river bottom mud ecological revetment for sponge urban construction according to claim 5, It is characterized in that:The volume ratio of the cationic polyacrylamide solution and mud is 0.8~1:100.
8. the method for preparing the plate and frame river bottom mud ecological revetment for sponge urban construction according to claim 5, It is characterized in that:The mass-volume concentration ratio of the powder slag and mud is 50~100:1.
9. the method for preparing the plate and frame river bottom mud ecological revetment for sponge urban construction according to claim 5, It is characterized in that:The mass-volume concentration of the calcium carbide waste slag and mud ratio is 0.8~1:1.
CN201810038947.XA 2018-01-16 2018-01-16 A kind of plate and frame river bottom mud ecological revetment and preparation method for sponge urban construction Pending CN108575580A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810038947.XA CN108575580A (en) 2018-01-16 2018-01-16 A kind of plate and frame river bottom mud ecological revetment and preparation method for sponge urban construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810038947.XA CN108575580A (en) 2018-01-16 2018-01-16 A kind of plate and frame river bottom mud ecological revetment and preparation method for sponge urban construction

Publications (1)

Publication Number Publication Date
CN108575580A true CN108575580A (en) 2018-09-28

Family

ID=63608377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810038947.XA Pending CN108575580A (en) 2018-01-16 2018-01-16 A kind of plate and frame river bottom mud ecological revetment and preparation method for sponge urban construction

Country Status (1)

Country Link
CN (1) CN108575580A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109305744A (en) * 2018-11-27 2019-02-05 上海城市水资源开发利用国家工程中心有限公司 A kind of black and odorous water biological renovation method and system
CN109429610A (en) * 2019-01-04 2019-03-08 杰瑞(莱州)矿山治理有限公司 It is a kind of to carry out the artificial soil and its reclamation method that land reclamation uses using gold mine tailings slag backfill mining area
CN111519685A (en) * 2020-05-11 2020-08-11 李冰梅 River channel dredging structure and dredging method thereof
CN113598012A (en) * 2021-08-05 2021-11-05 中建生态环境集团有限公司 Organic base material for ecological greening of rock slope and preparation method and application thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203530807U (en) * 2013-07-22 2014-04-09 中国十七冶集团有限公司 Grass planting water permeable brick
CN103771935A (en) * 2013-03-05 2014-05-07 杭州爱立特生态环境科技有限公司 Method for preparing plant nutrient soil
CN105002916A (en) * 2015-07-15 2015-10-28 杭州江润科技有限公司 Immerseable embankment high slope interlocked ecological brick flexible protection structure and construction method
CN205329626U (en) * 2015-11-18 2016-06-22 上海海洋大学 Ecological purification of water can prevent soil erosion and water loss view ecological revetment
CN106242753A (en) * 2016-07-28 2016-12-21 天津海泰市政绿化有限公司 A kind of mellow earth and preparation method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103771935A (en) * 2013-03-05 2014-05-07 杭州爱立特生态环境科技有限公司 Method for preparing plant nutrient soil
CN203530807U (en) * 2013-07-22 2014-04-09 中国十七冶集团有限公司 Grass planting water permeable brick
CN105002916A (en) * 2015-07-15 2015-10-28 杭州江润科技有限公司 Immerseable embankment high slope interlocked ecological brick flexible protection structure and construction method
CN205329626U (en) * 2015-11-18 2016-06-22 上海海洋大学 Ecological purification of water can prevent soil erosion and water loss view ecological revetment
CN106242753A (en) * 2016-07-28 2016-12-21 天津海泰市政绿化有限公司 A kind of mellow earth and preparation method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109305744A (en) * 2018-11-27 2019-02-05 上海城市水资源开发利用国家工程中心有限公司 A kind of black and odorous water biological renovation method and system
CN109429610A (en) * 2019-01-04 2019-03-08 杰瑞(莱州)矿山治理有限公司 It is a kind of to carry out the artificial soil and its reclamation method that land reclamation uses using gold mine tailings slag backfill mining area
CN111519685A (en) * 2020-05-11 2020-08-11 李冰梅 River channel dredging structure and dredging method thereof
CN113598012A (en) * 2021-08-05 2021-11-05 中建生态环境集团有限公司 Organic base material for ecological greening of rock slope and preparation method and application thereof

Similar Documents

Publication Publication Date Title
CN106193247B (en) Integral rain system and its construction method for sponge city
CN108575580A (en) A kind of plate and frame river bottom mud ecological revetment and preparation method for sponge urban construction
CN102071697B (en) Hard reinforced concrete revetment slope biological repairing method
CN101434420B (en) Riverway permeable reaction wall system and use thereof
CN104631380A (en) Shore type ladder-grade two-dimensional surface flow water filtering riverbed in-situ ecological remediation method
CN101012643A (en) Construction method of ecological bank slope effectively removing area-source pollution fleetly
CN105155463B (en) A kind of river course or the ecological dredging processing method in lake
CN105401552B (en) A kind of method that salt-alkali shoaly land is transformed into low-pollution water wetland advanced treatment system
CN101486555A (en) Cast-in-situ invert filter type pervious ecological concrete and method for constructing slope protection thereof
CN106702980B (en) Prevent the agricultural ecological drainage ditch construction method of furrow bank soil losses
CN110002669A (en) A kind of city heavily contaminated river comprehensive processing method
CN210421010U (en) Farmland ecological ditch for reducing leakage, strengthening and purifying
CN112158958B (en) Artificial rainwater wetland system for sponge city construction for removing pollutants in strengthening manner
CN111315932A (en) Modular soil body pressure-applying forming device and soft soil foundation treatment method
CN102107936A (en) Technique for treating remaining water of desilted sediment in Lake Tai
CN100491271C (en) Method of purifying city surface source pollution and river lake water by new type shore protection function member
CN110642384A (en) Artificial wetland system for reducing river beach and platform land pollution
CN109928573A (en) A kind of black-odor riverway sunk type greenery patches processing system and its processing method
CN204982778U (en) High -efficient artifical lake system that adjusts that purifies
CN108265580B (en) Construction method of sludge resource-based river channel ecological system with functions of sewage interception, slope protection and water purification
CN109437477A (en) A kind of river channel ecology environmental reconstruction system
CN210559648U (en) Step multi-section undercurrent artificial wet land treating pool
CN105540859B (en) A kind of dystopy original position coupling gravel bed Water Ecological Recovery system
CN212982714U (en) Combined ecological filter bed for improving water quality of river channel
CN102936884A (en) Method for reducing permeability of regenerated water riverway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180928