CN108560546A - A kind of underwater ground anchor structure - Google Patents
A kind of underwater ground anchor structure Download PDFInfo
- Publication number
- CN108560546A CN108560546A CN201810203694.7A CN201810203694A CN108560546A CN 108560546 A CN108560546 A CN 108560546A CN 201810203694 A CN201810203694 A CN 201810203694A CN 108560546 A CN108560546 A CN 108560546A
- Authority
- CN
- China
- Prior art keywords
- steel strand
- line
- isolating frame
- ground anchor
- strand wires
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 76
- 239000010959 steel Substances 0.000 claims abstract description 76
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 43
- 238000004873 anchoring Methods 0.000 claims abstract description 24
- 239000011083 cement mortar Substances 0.000 claims abstract description 12
- 239000006185 dispersion Substances 0.000 claims abstract description 7
- 230000015572 biosynthetic process Effects 0.000 claims abstract description 3
- 239000011440 grout Substances 0.000 claims description 39
- 230000001681 protective effect Effects 0.000 claims description 9
- 229920001903 high density polyethylene Polymers 0.000 claims description 4
- 239000004700 high-density polyethylene Substances 0.000 claims description 4
- 229910000851 Alloy steel Inorganic materials 0.000 claims description 3
- 239000004593 Epoxy Substances 0.000 claims description 3
- 239000004698 Polyethylene Substances 0.000 claims description 3
- VYPSYNLAJGMNEJ-UHFFFAOYSA-N Silicium dioxide Chemical compound O=[Si]=O VYPSYNLAJGMNEJ-UHFFFAOYSA-N 0.000 claims description 3
- 238000005452 bending Methods 0.000 claims description 3
- 238000002347 injection Methods 0.000 claims description 3
- 239000007924 injection Substances 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 230000010412 perfusion Effects 0.000 claims description 3
- 239000000741 silica gel Substances 0.000 claims description 3
- 229910002027 silica gel Inorganic materials 0.000 claims description 3
- 239000007921 spray Substances 0.000 claims description 2
- 239000003292 glue Substances 0.000 claims 1
- 239000007787 solid Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 8
- 230000002421 anti-septic effect Effects 0.000 abstract description 2
- 239000011435 rock Substances 0.000 description 11
- 239000002689 soil Substances 0.000 description 3
- 230000000903 blocking effect Effects 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000009826 distribution Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 238000005192 partition Methods 0.000 description 2
- 230000007704 transition Effects 0.000 description 2
- 241000251468 Actinopterygii Species 0.000 description 1
- 229920002472 Starch Polymers 0.000 description 1
- 230000003044 adaptive effect Effects 0.000 description 1
- 230000002411 adverse Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000005260 corrosion Methods 0.000 description 1
- 230000006378 damage Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000002706 hydrostatic effect Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 239000010410 layer Substances 0.000 description 1
- 235000013336 milk Nutrition 0.000 description 1
- 239000008267 milk Substances 0.000 description 1
- 210000004080 milk Anatomy 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 235000019698 starch Nutrition 0.000 description 1
- 239000008107 starch Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 230000002123 temporal effect Effects 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
- E02D27/525—Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/805—Ground anchors with deformable anchoring members
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/808—Ground anchors anchored by using exclusively a bonding material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of underwater ground anchor structures, it includes cable body and socket, the cable body is arranged in the anchor hole for the formation that drills under water, the cable body includes the anchoring section set gradually, changeover portion and free segment, the anchor hole has passed through severely-weathered lower limit line, the anchoring section, changeover portion is located in the severely-weathered lower limit line anchor hole below, the part that the cable body is located at the severely-weathered lower limit line or more is the free segment, the free segment stretches out subsea floor line and is connected with the socket, the anchoring section includes the individual steel strand of more dispersions, the more individual steel strands are in the changeover portion, free segment position is pressed into a branch of whole steel strand wires, the cement mortar for fixing the cable body is perfused in the anchor hole.The underwater ground anchor structure of the present invention has the characteristics that bear large change oblique pulling, adapts to that soft stratum condition, antiseptic property are good, required input construction equipment is few, quick, low cost of constructing, with good investment.
Description
Technical field
The present invention relates to a kind of underwater ground anchor structures, belong to water conservancy and hydropower technical field.The present invention relates to one kind being used for water
The anchoring underwater structure of hydropower reservoir station water proof, water blocking curtain wall construction.
Background technology
High dam big library in power station will generate important shadow after building up to the water temperature spatial and temporal distributions in reservoir area waters and dam lower reache
It rings.Especially at the end of spring and the beginning of summer cause reservoir to go out flowing water temperature and be less than natural river course, low-temperature discharge is to downstream fish and other are aquatic
Biological self reproducing etc. adversely affects.To improve the temperature that sluices under Built hydropower station reservoir, under certain engineering measure need to be taken to ensure
Swim the normal existence environment of aquatile.In recent years, the flexible water blocking curtain wall knot that a kind of structural shape is simple, investment is relatively low
Structure is being proposed for administering the big library low-temperature discharge problem of high dam.Low temperature water harnessing water partition curtain wall is in the previous positioning of dam
Yokogawa is set to the impermeable water curtain wall of flexibility for arranging suitable water retaining height, underlying low temperature water, overcurrent surface layer high temperature are stopped by curtain wall
Water achievees the purpose that improve the lower warm curtain formula layered water drawing structure that sluices.
Water proof curtain wall bears hydrostatic pressure caused by water pressure load, including flowing pressure and temperature, mainly by water pressure
Load passes to longitudinal drag-line by flexible curtain wall, and load is transferred to top Sarasota structure and bottom storehouse earth anchor knot by longitudinal drag-line again
Structure.Wherein the pulling force of curtain wall longitudinal direction drag-line, stress are born in bottom storehouse ground anchor structure upper end for hanging water proof curtain wall longitudinal direction drag-line
And design feature has:
1)Curtain wall longitudinal direction drag-line is oblique pulling to the pulling force of ground anchor structure.Water proof curtain wall construction is during running use, curtain wall
With vertical direction there are certain angle, curtain wall longitudinal direction drag-line is obliquely to underwater ground anchor structure direction of pull for longitudinal drag-line lower end
Side.
2)Curtain wall longitudinal direction drag-line is directed varying forces to the pulling force of ground anchor structure.Water proof curtain wall is with reservoir level in normal pool level
Change and automatic lifting between level of dead water, curtain wall and longitudinal adaptive SEA LEVEL VARIATION of drag-line adjust its form.Difference operation water
The position cross-section of river, water velocity, pressure distribution are all different, thus curtain wall and longitudinal drag-line build form are also different, pass
The pulling force size and Orientation for being handed to underwater ground anchor structure is also all different.
3)Curtain wall longitudinal direction drag-line is larger to the pulling force magnitude of ground anchor structure.It is estimated that water proof curtain wall water retaining height 140m is left
When right, longitudinal drag-line is arranged to spacing for 10m by Yokogawa, water proof curtain wall longitudinal direction drag-line is transferred to the maximum value of ground anchor structure resultant force
About 800kN or so, after being decomposed into vertical force and horizontal force, vertical force and horizontal force maximum value are much larger than up to 500-600kN
The pulling force magnitude that general ground anchor structure is born, especially horizontal pull.
4)Ground anchor structure upper end need to be useful for hanging the connecting elements of water proof curtain wall longitudinal direction drag-line.
Existing earth anchor(Anchoring)Structure cannot meet the underwater ground anchor structure requirement of water proof curtain wall:
1)Rock anchor assembly is a kind of common ground anchor structure, is to pour into dowel and mortar (or concrete) in rock-boring, with
Rock bonding is integral, bears the ground anchor structure pattern of certain pulling force to the wedge action of pile body by Rock And Soil.By deep water
Underwater construction condition limits, and water partition curtain wall rock anchor assembly bore diameter is generally less than 150mm(When bore diameter is more than 150mm, apply
Work steel pile casting size, dead weight etc. will increase, and underwater construction, operation difficulty is significantly greatly increased), the rock under the bore diameter restrictive condition
The horizontal pull that killagh stake provides is limited, particularly when anchoring pile passes through weak, loose rock-soil layer because of Rock And Soil lateral spacing drag not
Foot, rock anchor assembly easily fracture destruction, failure, can not adapt to curtain wall longitudinal direction drag-line to the pulling force of ground anchor structure be size with
The complicated operating condition that direction changes.
2)Traditional prestressed anchor Cable Structure can bear larger axial tension, but cannot bear greater level power, can not
Adapt to the complex working condition of curtain wall operation, and anchor cable anchor pier pours deep water underwater construction there are larger difficulty, the upper end arrangement and curtain
There is also difficulties for the connecting elements of wall longitudinal direction drag-line.
Invention content
In order to overcome problems of the prior art, the present invention provide it is a kind of bear large change oblique pulling under water
Anchor structure, specific technical solution are as follows.
A kind of underwater ground anchor structure comprising have cable body and socket, the cable body that the anchor hole for the formation that drills under water is set
In, it is characterised in that:The cable body includes the anchoring section, changeover portion and free segment set gradually, and the anchor hole has passed through high wind
Change lower limit line, the anchoring section, changeover portion are located in the severely-weathered lower limit line anchor hole below, and the cable body is located at institute
The part for stating severely-weathered lower limit line or more is the free segment, and the free segment stretches out subsea floor line and is connected with the socket,
The anchoring section includes the individual steel strand of more dispersions, and the more individual steel strands are at the changeover portion, free segment position
A branch of whole steel strand wires are pressed into, the cement mortar for fixing the cable body is perfused in the anchor hole.
The steel strand wires of anchoring section are dispersion anchoring in grout pouring as a result, ensure bond stress of the cement mortar to cable body,
More than exposure subsea floor line free segment and the socket that is attached thereto more than ground line can freely swing under water, adapt to curtain
Variable pulling force of the wall longitudinal direction drag-line to ground anchor structure.
Further, the individual steel strand is that epoxy sprays non-bending steel cable.It is anti-with preferable groundwater environment
Rotten antirust function.
Further, it is dispersion anchoring in grout pouring in order to ensure more individual steel strands of anchoring section, ensures
Bond stress of the cement mortar to steel strand wires.It is arranged at intervals with isolating frame on the individual steel strand, is set between two neighboring isolating frame
It is equipped with the galvanized wire for tying up the more individual steel strands, the distance between adjacent two individual steel strands portion where galvanized wire
Position is less than position where isolating frame.It is in this way the basis of dispersion anchoring when ensuring more individual steel strands in grout pouring
On so that individual steel strand is in bending state in anchoring section, increases the length of anchoring section individual steel strand, improves cement mortar
To the bond stress of steel strand wires.Preferably, an isolation is arranged every 1.5m on the individual steel strand in the anchoring segment length 6-9m
Frame.
Further, it is provided with protective case on the outer surface of the whole steel strand wires of the free segment.Protective case is provided with
Conducive to protecting the whole steel strand wires of free segment not influenced by underwater environment, the whole steel strand wires of the changeover portion are not provided with protecting
Set is to improve bond stress of the cement mortar to the whole steel strand wires of changeover portion.Preferably, the transition section length is 1m.Preferably,
The protective case is made of high density polyethylene (HDPE).
Further, the free segment be located at the aperture of the anchor hole outside be cased with wearing bush, the one of the wearing bush
Part is located at subsea floor line or more, and another part is located in the anchor hole, and it is pre- that the wearing bush is provided with wearing bush steel strand wires
Box out, wearing bush grout pipe preformed hole and gas vent, the wearing bush steel strand wires preformed hole for wearing the whole steel strand wires,
The wearing bush grout pipe preformed hole for wearing grout pipe, the gas vent is used to that air to be discharged when grout injection.Abrasionproof
Cover the whole steel strand wires for preventing free segment and rock frictional test, cutting.Preferably, the long 4.5m of the wearing bush, subsea floor
The above exposure 0.5m of line is embedded in 4.0m in the anchor hole.Preferably, the material of the wearing bush is that abrasive rubber or high resiliency are resistance to
Grind silica gel.It is tensioning state after the pulling force that free segment upper end is transmitted by curtain wall longitudinal direction drag-line, steel strand wires can exist according to pulling force size
Free elastic telescopic in protective case.
Further, the socket is suppressed by steel alloy and the whole steel strand wires of free segment end through whole, described
Drag-line preformed hole, drag-line preformed groove and socket grout pipe preformed groove are provided on socket, the drag-line preformed hole runs through the rope
Section and axial perpendicular to the whole steel strand wires, the drag-line preformed groove setting there are two and about the center line pair of the socket
Claim, the socket grout pipe preformed groove is for accommodating grout pipe.When the underwater ground anchor structure of the present invention is used to fix water proof curtain wall,
The drag-line of water proof curtain wall passes through drag-line preformed hole and is contained in two drag-line preformed grooves, and drag-line fixation is reliable.
Further, it is pre- that multiple isolating frame steel strand wires preformed holes, two isolating frame grout pipes are provided on the isolating frame
Box out and isolating frame overfall reserved passageway, the isolating frame steel strand wires preformed hole for wearing the individual steel strand, it is described every
From frame grout pipe preformed hole for wearing grout pipe, the isolating frame overfall reserved passageway is for cement mortar in perfusion from described
It is flowed toward the top of the isolating frame lower section of isolating frame.Preferably, the isolating frame overfall reserved passageway includes that isolating frame returns
Starch preformed hole and/or isolating frame overfall preformed groove.Preferably, the isolating frame is made of PE plates.
The present invention underwater ground anchor structure have can bear large change oblique pulling, adapt to soft stratum condition, anti-corrosion
Performance is good, required input construction equipment is few, construction quickly, low cost, it is with good investment the features such as.
Description of the drawings
Fig. 1 is the sectional view of the underwater ground anchor structure of the present invention;
Fig. 2 is anchoring section isolating frame schematic diagram in Fig. 1;
Fig. 3 is wearing bush schematic diagram in Fig. 1;
Fig. 4 is socket vertical view in Fig. 1.
In figure:1-guiding cap, 2-isolating frames, 3-cement mortars, 4-galvanized wires, 5-anchor holes, 6-changeover portions, 7-protections
Set, 8-wearing bush, 9-grout pipes, 10-sockets, 11-drag-line preformed holes, 12-individual steel strands, 13-- free segments,
14-severely-weathered lower limit lines, 15-subsea floor lines, 16-isolating frame steel strand wires preformed holes, 17-isolating frame grout pipes are reserved
Hole, 18-isolating frame overfall preformed holes, 19-isolating frame overfall preformed grooves, 20-wearing bush steel strand wires preformed holes, 21-abrasionproofs
Cover grout pipe preformed hole, 22-gas vents, 23-socket grout pipe preformed holes, 24-drag-line preformed grooves.
Specific implementation mode
Present invention is further described in detail below in conjunction with the accompanying drawings.
Referring to Fig. 1-Fig. 4, a kind of underwater ground anchor structure for bearing variable oblique pull load, the present embodiment relies on some hydropower station low
The underwater ground anchor structures of warm water managemental experiment engineering 1500kN.5 aperture of anchor hole of earth anchor be 145mm, ground anchor structure include cable body and
Socket, cable body are made of 10 beam, 7 Ф, 5 prestressing force individual steel strands 12, cable body be from bottom to top divided into anchoring section, changeover portion 6 and from
By section 13.Anchoring section is the individual steel strand of dispersion, and the top of individual steel strand 12 is connected with guiding cap 1, changeover portion 6 and freedom
Section 13 is 10 beam individual steel strand 12 of anchoring section dispersity through whole pressed a branch of whole steel strand wires, in the anchor hole 5
It is perfused with the cement mortar 3 for fixing the cable body.Free segment upper end steel strand wires extend in socket 11, are carried out with socket 11 whole
Body is suppressed, and bonding strength is more than cable body pulling force design value after compacting.Steel strand wires use prestress wire, viscous for epoxy spraying nothing
Steel strand wires are tied, there is the antiseptic and rustproof function of groundwater environment.Segment length 9m is anchored, 10 beam individual steel strands are dispersity, every
1.5m is equipped with isolating frame 2, and the galvanized wire 4 for tying up the more individual steel strands is provided between two neighboring isolating frame 2,
The distance between adjacent two individual steel strands are less than 2 place position of isolating frame at 4 place position of galvanized wire.Transition section length is
1m, it is without protective case that changeover portion, which integrally suppresses steel strand wires,.Freedom length is 9m, and free segment is located at the severely-weathered lower limit line of rock mass
14 or more, 15 or more 1m of free segment upper end exposure subsea floor line, free segment are the whole compacting steel strand wires with protective case, freely
It is tensioning state after the pulling force that Duan Shangduan is transmitted by curtain wall longitudinal direction drag-line, it can free elasticity be stretched in protective case according to pulling force size
Contracting.
Free segment cable body at 5 aperture of anchor hole outside be cased with wearing bush 8, for preventing free segment steel strand wires and rock from rubbing
It wipes, cutting, the wearing bush 8 is provided with wearing bush steel strand wires preformed hole 20, wearing bush grout pipe preformed hole 21 and gas vent 22,
The wearing bush steel strand wires preformed hole 20 is for wearing the whole steel strand wires, and the wearing bush grout pipe preformed hole 21 is for wearing
If grout pipe, the gas vent 22 is used to that air to be discharged when grout injection, and wearing bush grout pipe preformed hole 21 is preferably provided with two
A, two grout pipes 9 are in the milk simultaneously, when monitoring earth anchor aperture overfall and meeting design requirement, are slowly dialled from ground anchor structure
Go out grout pipe 9, can ensure the closely knit of grouting in this way, is conducive to the bearing load for improving ground anchor structure.8 long 4.5m of wearing bush,
15 or more exposure 0.5m of subsea floor line is embedded in 4.0m in the anchor hole 5 of rock mass.8 material of wearing bush is high elasticity abrasion-proof silica gel.
The socket 10 is suppressed by steel alloy and the whole steel strand wires of free segment end through whole, on the socket 10
It is provided with drag-line preformed hole 11, drag-line preformed groove 24 and socket grout pipe preformed groove 23, the drag-line preformed hole 11 is through described
Socket and axial perpendicular to the whole steel strand wires, the setting of drag-line preformed groove 24 there are two and about the center of the socket
Line is symmetrical, and the socket grout pipe preformed groove 23 is for accommodating grout pipe.When fixed water proof curtain wall, the drag-line of water proof curtain wall passes through
It drag-line preformed hole and is contained in two drag-line preformed grooves.
Be provided on the isolating frame 2 16, two isolating frame grout pipe preformed holes 17 of multiple isolating frame steel strand wires preformed holes,
Isolating frame overfall preformed hole 18 and isolating frame overfall preformed groove 19, the isolating frame steel strand wires preformed hole 16 is for wearing the list
Beam steel strand wires, the isolating frame grout pipe preformed hole 17 are returned for wearing grout pipe, isolating frame overfall preformed hole 18 and isolating frame
Preformed groove 19 is starched to flow from the lower section of the isolating frame toward the top of the isolating frame in perfusion for cement mortar.Preferably,
The isolating frame is made of PE plates.
The present embodiment ground anchor structure free segment and socket more than ground line can freely swing under water, and it is longitudinal to adapt to curtain wall
Drag-line can bear the variable oblique pull load of 1500kN to the variable pulling force of ground anchor structure, underwater ground anchor structure maximum.
The embodiment of the present invention is described with above attached drawing, in the absence of conflict, the reality in the present invention
The feature applied in example and embodiment can be combined with each other.For sake of convenience, the "upper" that above occurs, "lower" printed words, only indicate
With the upper and lower of attached drawing itself to consistent, restriction effect is not played to structure.The invention is not limited in above-mentioned specific implementations
Mode, the above mentioned embodiment is only schematical, rather than limitation, those skilled in the art are at this
Under the enlightenment of invention, without breaking away from the scope protected by the purposes and claims of the present invention, many forms can be also made,
Within these are all belonged to the scope of protection of the present invention.
Claims (10)
1. a kind of underwater ground anchor structure comprising there are cable body and socket, the cable body to be arranged in the anchor hole for the formation that drills under water,
It is characterized in that:The cable body includes the anchoring section, changeover portion and free segment set gradually, the anchor hole have passed through it is severely-weathered under
Line is limited, the anchoring section, changeover portion are located in the severely-weathered lower limit line anchor hole below, and the cable body is located at described strong
Part more than weathering lower limit line is the free segment, and the free segment stretches out subsea floor line and is connected with the socket, described
Anchoring section includes the individual steel strand of more dispersions, and the more individual steel strands are suppressed at the changeover portion, free segment position
At a branch of whole steel strand wires, the cement mortar for fixing the cable body is perfused in the anchor hole.
2. a kind of underwater ground anchor structure according to claim 1, which is characterized in that the individual steel strand sprays for epoxy
Non-bending steel cable.
3. a kind of underwater ground anchor structure according to claim 1, which is characterized in that be spaced setting on the individual steel strand
There is isolating frame, the galvanized wire for tying up the more individual steel strands, adjacent two lists are provided between two neighboring isolating frame
The distance between beam steel strand wires are less than position where isolating frame at position where galvanized wire.
4. a kind of underwater ground anchor structure according to claim 3, which is characterized in that be provided on the isolating frame it is multiple every
From frame steel strand wires preformed hole, two isolating frame grout pipe preformed holes and isolating frame overfall reserved passageway, the isolating frame steel strand wires
Preformed hole is for wearing the individual steel strand, and the isolating frame grout pipe preformed hole is for wearing grout pipe, the isolating frame
Overfall reserved passageway is flowed in perfusion from the lower section of the isolating frame toward the top of the isolating frame for cement mortar.
5. a kind of underwater ground anchor structure according to claim 4, which is characterized in that the isolating frame overfall reserved passageway packet
Include isolating frame overfall preformed hole and/or isolating frame overfall preformed groove;Preferably, the isolating frame is made of PE plates.
6. a kind of underwater ground anchor structure according to claim 1, which is characterized in that the whole steel strand wires of the free segment
Protective case is provided on outer surface;Preferably, the protective case is made of high density polyethylene (HDPE).
7. a kind of underwater ground anchor structure according to claim 1, which is characterized in that the free segment is located at the anchor hole
Wearing bush is cased with outside at aperture, a part for the wearing bush is located at subsea floor line or more, and another part is located at the anchor
In hole, the wearing bush is provided with wearing bush steel strand wires preformed hole, wearing bush grout pipe preformed hole and gas vent, the wearing bush
For steel strand wires preformed hole for wearing the whole steel strand wires, the wearing bush grout pipe preformed hole is described for wearing grout pipe
Gas vent is used to that air to be discharged when grout injection.
8. a kind of underwater ground anchor structure according to claim 7, which is characterized in that the material of the wearing bush is wear-resisting rubber
Glue or high elasticity abrasion-proof silica gel.
9. a kind of underwater ground anchor structure according to claim 1, which is characterized in that the socket is by steel alloy and free segment
The whole steel strand wires of end are suppressed through whole, and drag-line preformed hole, drag-line preformed groove and socket are provided on the socket and is filled
Pipe preformed groove is starched, the drag-line preformed hole is through the socket and axial perpendicular to the whole steel strand wires, and the drag-line is reserved
Center line there are two slot is arranged and about the socket is symmetrical, and the socket grout pipe preformed groove is for accommodating grout pipe.
10. a kind of underwater ground anchor structure according to claim 1, which is characterized in that the underwater ground anchor structure is for solid
Determine the drag-line of water proof curtain wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810203694.7A CN108560546B (en) | 2018-03-13 | 2018-03-13 | Underwater ground anchor structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810203694.7A CN108560546B (en) | 2018-03-13 | 2018-03-13 | Underwater ground anchor structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108560546A true CN108560546A (en) | 2018-09-21 |
CN108560546B CN108560546B (en) | 2023-11-07 |
Family
ID=63531570
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810203694.7A Active CN108560546B (en) | 2018-03-13 | 2018-03-13 | Underwater ground anchor structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108560546B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112647499A (en) * | 2021-01-12 | 2021-04-13 | 中国电建集团中南勘测设计研究院有限公司 | Deepwater ground anchor grouting method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4360292A (en) * | 1980-05-28 | 1982-11-23 | Keeler Andrew L | Grouted strand anchor and method of making same |
EP1589146A1 (en) * | 2004-04-21 | 2005-10-26 | AVT Anker + Vorspanntechnik AG | Wire bundle anchor |
CN106065624A (en) * | 2016-07-12 | 2016-11-02 | 浙江省交通工程建设集团有限公司 | It is applicable to pass through the permanent seal cooling prestress anchorage cable of broken rock and construction method thereof |
CN205742181U (en) * | 2016-05-18 | 2016-11-30 | 中国葛洲坝集团三峡建设工程有限公司 | A kind of lowering anchor cable protection device |
CN208072402U (en) * | 2018-03-13 | 2018-11-09 | 中国电建集团中南勘测设计研究院有限公司 | A kind of underwater ground anchor structure |
-
2018
- 2018-03-13 CN CN201810203694.7A patent/CN108560546B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4360292A (en) * | 1980-05-28 | 1982-11-23 | Keeler Andrew L | Grouted strand anchor and method of making same |
EP1589146A1 (en) * | 2004-04-21 | 2005-10-26 | AVT Anker + Vorspanntechnik AG | Wire bundle anchor |
CN205742181U (en) * | 2016-05-18 | 2016-11-30 | 中国葛洲坝集团三峡建设工程有限公司 | A kind of lowering anchor cable protection device |
CN106065624A (en) * | 2016-07-12 | 2016-11-02 | 浙江省交通工程建设集团有限公司 | It is applicable to pass through the permanent seal cooling prestress anchorage cable of broken rock and construction method thereof |
CN208072402U (en) * | 2018-03-13 | 2018-11-09 | 中国电建集团中南勘测设计研究院有限公司 | A kind of underwater ground anchor structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112647499A (en) * | 2021-01-12 | 2021-04-13 | 中国电建集团中南勘测设计研究院有限公司 | Deepwater ground anchor grouting method |
Also Published As
Publication number | Publication date |
---|---|
CN108560546B (en) | 2023-11-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106320346B (en) | Campshed adds anchor cable grouting behind shaft or drift lining deep foundation pit supporting construction method | |
CN100535263C (en) | Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment | |
CN105926617B (en) | A kind of structure and its construction method that protection can be provided anti-float anchor rod | |
CN104929117B (en) | Construction method of concrete pole body composite anchor rod | |
CN201746840U (en) | Foundation pit support system equipped with a plurality of inclined rear anchors capable of recycling | |
CN208844589U (en) | Ecological Slope safeguard structure and guard system | |
CN102002957A (en) | Slope retaining structure | |
CN112431213B (en) | Ecological comprehensive treatment structure for semi-rigid support of artificial slope and construction method thereof | |
CN104912088A (en) | Slope protection structure and construction method thereof | |
CN107044107A (en) | Side slope geotechnical fabric bag slope protection construction method and device | |
CN208072402U (en) | A kind of underwater ground anchor structure | |
CN110486070A (en) | A kind of constructing structure of the prestressed anchor of tunnel or Culvert engineering | |
CN108560546A (en) | A kind of underwater ground anchor structure | |
CN204959745U (en) | Compound stock of concrete pole body | |
CN207959206U (en) | A kind of underwater ground anchor structure with wearing bush | |
CN107711657B (en) | Stagger double-column flexible shallow sea aquaculture purse seine | |
CN108265712A (en) | A kind of underwater ground anchor structure with wearing bush | |
CN105257315A (en) | Anti-floating structure for underground tunnel | |
CN205954623U (en) | Durable type prestressed anchorage cable suitable for pass through broken rock stratum | |
CN207933975U (en) | A kind of high stability concrete structure for slope protection system | |
CN109868830A (en) | The impervious safeguard structure of immerseable embankment side slope and construction method | |
CN206784401U (en) | Locking anchor cable structure is anchored outside tension and compression complementary type | |
CN210459233U (en) | Pile anchor foundation pit supporting structure for soft soil area | |
CN205712098U (en) | A kind of structure that anti-float anchor rod can be provided protection | |
CN113005991A (en) | High-strength anti-seismic water conservancy slope anchor cable structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |