CN108540378A - A kind of method of industry things-internet gateway ladder power saving - Google Patents

A kind of method of industry things-internet gateway ladder power saving Download PDF

Info

Publication number
CN108540378A
CN108540378A CN201810371932.5A CN201810371932A CN108540378A CN 108540378 A CN108540378 A CN 108540378A CN 201810371932 A CN201810371932 A CN 201810371932A CN 108540378 A CN108540378 A CN 108540378A
Authority
CN
China
Prior art keywords
data
gateway
battery
electricity
power saving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810371932.5A
Other languages
Chinese (zh)
Inventor
陈再明
陈小军
陶洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Lu Bangtong Networking Technology Co Ltd
Original Assignee
Guangzhou Lu Bangtong Networking Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Lu Bangtong Networking Technology Co Ltd filed Critical Guangzhou Lu Bangtong Networking Technology Co Ltd
Priority to CN201810371932.5A priority Critical patent/CN108540378A/en
Publication of CN108540378A publication Critical patent/CN108540378A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L12/00Data switching networks
    • H04L12/66Arrangements for connecting between networks having differing types of switching systems, e.g. gateways
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/42Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells
    • H01M10/4207Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells for several batteries or cells simultaneously or sequentially
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/42Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells
    • H01M10/425Structural combination with electronic components, e.g. electronic circuits integrated to the outside of the casing
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/42Methods or arrangements for servicing or maintenance of secondary cells or secondary half-cells
    • H01M10/48Accumulators combined with arrangements for measuring, testing or indicating the condition of cells, e.g. the level or density of the electrolyte
    • H01M10/482Accumulators combined with arrangements for measuring, testing or indicating the condition of cells, e.g. the level or density of the electrolyte for several batteries or cells simultaneously or sequentially
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Selective Calling Equipment (AREA)

Abstract

The invention belongs to industrial gateway control fields, and it discloses a kind of methods of industrial things-internet gateway ladder power saving, include the following steps:Step 1:Battery is set in electricity as the time interval Tx of the data collection in the cycle of operation of the Wx~Wx 1 and required time Ta of data of collection;Wherein, the power in gateway when collecting data is P, and power when interval of the gateway between data collection twice is Ps;Step 2:In the case that the gateway is using battery powered, the electricity data Wm of present battery is obtained;Step 3:The time interval Tm of current data collection is set according to Wm, then calculating electricity according to Tm, Ps, Ta, P, Wm, Wm 1 is reduced to the number Xm run during Wm 1 from Wm;Wm Wm 1=(Tm*Ps+Ta*P) * Xm;Step 4:Constantly current battery charge data are obtained until battery capacity data are Wm 1;Step 5:Repeat step 24.The purpose of the present invention is to provide a kind of methods for the industrial things-internet gateway ladder power saving effectively improving gateway cruising ability.

Description

A kind of method of industry things-internet gateway ladder power saving
Technical field
The present invention relates to industrial gateway control field, specially a kind of method of industrial things-internet gateway ladder power saving.
Background technology
CN 201711307575.8 discloses a kind of gateway device of effectively pre- anti-power failure, including gateway device ontology, net It closes and is coated with shell outside apparatus body, the gateway device ontology is connected with plug by conducting wire, electricity is additionally provided on conducting wire The upper surface of source adapter, the shell is connected with one layer of optical energy power layer, and the optical energy power layer is connected with solar energy power accumulating Pond, solar storage battery are connected with controller, and the controller is connected with power supply adaptor.The gateway device is long cruise duration, It can work under power failure, promote the convenience that gateway device uses.
It is not to be suitable for being equipped with solar power generation unit it should be noted that in many application environments.This In the case of, the cruising ability of gateway how is improved, the collecting method of a set of rational gateway is needed.
Invention content
The purpose of the present invention is to provide a kind of industrial things-internet gateway ladder power savings effectively improving gateway cruising ability Method.
To achieve the above object, the present invention provides the following technical solutions:A kind of side of industry things-internet gateway ladder power saving Method includes the following steps:
Step 1:Set data collection of the battery within the cycle of operation of the electricity as Wx~Wx-1 time interval Tx and Collect the required time Ta of a data;Wherein, the power in gateway when collecting data is P, and gateway is received in data twice Power when interval between integrating is Ps;
Step 2:In the case that the gateway is using battery powered, the electricity data Wm of present battery is obtained;
Step 3:The time interval Tm that current data collection is set according to Wm, then according to Tm, Ps, Ta, P, Wm, Wm-1 It calculates electricity and is reduced to the number Xm run during Wm-1 from Wm;Wm-Wm-1=(Tm*Ps+Ta*P) * Xm;
Step 4:Constantly current battery charge data are obtained until battery capacity data are Wm-1;
Step 5:Step 2-4 is repeated, until dead battery capability or external power restore electricity.
In the method for above-mentioned industrial things-internet gateway ladder power saving, in the step 1, the section of Wx~Wx-1 is long Degree is voluntarily arranged by user.
In the method for above-mentioned industrial things-internet gateway ladder power saving, in step 1, Wx > Wx-1, Ta < Ta-1.
Further include step 6 in the method for above-mentioned industrial things-internet gateway ladder power saving:Calculating battery according to Wm can also The time Tlive that enough runs and the server that Tlive is sent to peripheral hardware;
Tlive=(Tm+Ta) * Xm+ (Tm-1+Ta) * Xm-1 ... (T0+Ta) * X0;X0 is a fortune before electricity exhausts The data times of collection in row period.
Compared with prior art, the beneficial effects of the invention are as follows:
The present invention is the lifting means continuity operating time to power-saving working mode further purposefully on demand, and can It to send the different of interval to data according to client requires that multiple ladders are arranged, industrial environment is utmostly adapted to realize And meet the purpose of the requirement of client.
Description of the drawings
Fig. 1 is the flow diagram of the embodiment of the present invention 1
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Embodiment 1
Referring to Fig. 1, a kind of method of industry things-internet gateway ladder power saving, includes the following steps:
Step 1:Set data collection of the battery within the cycle of operation of the electricity as Wx~Wx-1 time interval Tx and Collect the required time Ta of a data;Wherein, the power in gateway when collecting data is P, and gateway is received in data twice Power when interval between integrating is Ps;
It is illustrated with a simply example:
When setting electricity as 100-90%, it is divided into 3min between acquisition time, which is known as battery saving mode;Collect one It is that 0.5min (does not change, which is known as normal work when different electricity of the time below the time required to secondary data Operation mode);
When setting electricity as 90-80%, 5min is divided between acquisition time;
When setting electricity as 80-70%, 8min is divided between acquisition time;
When setting electricity as 70-60%, 10min is divided between acquisition time;
When setting electricity as 60-50%, 12min is divided between acquisition time;
When setting electricity as 50-40%, 15min is divided between acquisition time;
When setting electricity as 40-30%, 18min is divided between acquisition time;
When setting electricity as 30-20%, 21min is divided between acquisition time;
When setting electricity as 20-10%, 25min is divided between acquisition time;
When setting electricity as 10-0%, 30min is divided between acquisition time;
Power when P is normal mode of operation, Ps are the power under battery saving mode.
Above-mentioned data are only to enumerate, the specific demand designed, designed needed according to client.In general, the cycle of operation is about Short, power saving is more accurate.
Step 2:In the case that the gateway is using battery powered, the electricity data Wm of present battery is obtained;
Step 3:The time interval Tm that current data collection is set according to Wm, then according to Tm, Ps, Ta, P, Wm, Wm-1 It calculates electricity and is reduced to the number Xm run during Wm-1 from Wm;Wm-Wm-1=(Tm*Ps+Ta*P) * Xm;
Tm, Ps, Ta, P of the cycle of operation of Wm~Wm-1 can be compareed according to the preset parameter of step 1 and be obtained.
Step 4:Constantly current battery charge data are obtained until battery capacity data are Wm-1;
Step 5:Step 2-4 is repeated, until dead battery capability or external power restore electricity.
Step 6:The time Tlive that can also run of battery is calculated according to Wm and Tlive is sent to the server of peripheral hardware;
Tlive=(Tm+Ta) * Xm+ (Tm-1+Ta) * Xm-1 ... (T0+Ta) * X0;X0 is a fortune before electricity exhausts The data times of collection in row period.
In the present embodiment, Xm=(Wm-Wm-1)/(Tm*Ps+Ta*P) can be calculated.
And Xm-1 ... X0 carry out computational theory value according to the pre-set parameter in step 1.
By above-mentioned design, gateway can be made according to actual electric quantity consumption situation, it is flexible to carry out single operation week The adjustment of number of run in phase and the adjustment of interval realize the purpose of high-precision electricity control, prolong as far as possible The cruise duration of long battery.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.

Claims (4)

1. a kind of method of industry things-internet gateway ladder power saving, which is characterized in that include the following steps:
Step 1:Set time interval Tx and the collection of data collection of the battery within the cycle of operation of the electricity as Wx~Wx-1 The required time Ta of data;Wherein, the power in gateway when collecting data be P, gateway data collection twice it Between interval when power be Ps;
Step 2:In the case that the gateway is using battery powered, the electricity data Wm of present battery is obtained;
Step 3:The time interval Tm of current data collection is set according to Wm, is then calculated according to Tm, Ps, Ta, P, Wm, Wm-1 Electricity is reduced to the number Xm run during Wm-1 from Wm;Wm-Wm-1=(Tm*Ps+Ta*P) * Xm;
Step 4:Constantly current battery charge data are obtained until battery capacity data are Wm-1;
Step 5:Step 2-4 is repeated, until dead battery capability or external power restore electricity.
2. the method for industry things-internet gateway ladder power saving according to claim 1, which is characterized in that the step 1 In, the siding-to-siding block length of Wx~Wx-1 is voluntarily arranged by user.
3. the method for industry things-internet gateway ladder power saving according to claim 1, which is characterized in that in step 1, Wx > Wx-1, Ta < Ta-1.
4. the method for industry things-internet gateway ladder power saving according to claim 1, which is characterized in that further include step 6: The time Tlive that can also run of battery is calculated according to Wm and Tlive is sent to the server of peripheral hardware;
Tlive=(Tm+Ta) * Xm+ (Tm-1+Ta) * Xm-1 ... (T0+Ta) * X0;X0 is an operation week before electricity exhausts The data times of collection of phase.
CN201810371932.5A 2018-04-24 2018-04-24 A kind of method of industry things-internet gateway ladder power saving Pending CN108540378A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810371932.5A CN108540378A (en) 2018-04-24 2018-04-24 A kind of method of industry things-internet gateway ladder power saving

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810371932.5A CN108540378A (en) 2018-04-24 2018-04-24 A kind of method of industry things-internet gateway ladder power saving

Publications (1)

Publication Number Publication Date
CN108540378A true CN108540378A (en) 2018-09-14

Family

ID=63478364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810371932.5A Pending CN108540378A (en) 2018-04-24 2018-04-24 A kind of method of industry things-internet gateway ladder power saving

Country Status (1)

Country Link
CN (1) CN108540378A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110278147A (en) * 2019-06-20 2019-09-24 深圳市中创工业互联网有限公司 A kind of power-saving method of gateway, device and economize on electricity gateway
CN112995941A (en) * 2021-03-08 2021-06-18 莫毓昌 Industrial Internet of things data transmission system and method for dormancy awakening mechanism

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1917677A (en) * 2005-08-19 2007-02-21 鸿富锦精密工业(深圳)有限公司 Handset with function of saving electricity, and method of saving electricity
CN101853166A (en) * 2010-06-07 2010-10-06 北京大学 Application-oriented method and system for indicating use time of intelligent mobile phone battery
CN202663561U (en) * 2012-03-11 2013-01-09 上海宜云物联科技有限公司 Internet of Things gateway capable of long-term operation without electricity
CN104216501A (en) * 2014-08-21 2014-12-17 刘勇 Electricity saving method for mobile terminal, electricity saving system for mobile terminal and mobile terminal
CN105978971A (en) * 2016-05-11 2016-09-28 北京奇虎科技有限公司 Message pushing method and device, and message pushing server
KR20170039471A (en) * 2015-10-01 2017-04-11 엘지전자 주식회사 Mobile termianl and method for controlling the same
CN107404533A (en) * 2017-07-29 2017-11-28 深圳市盛路物联通讯技术有限公司 A kind of method for monitoring biological activity, and monitoring device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1917677A (en) * 2005-08-19 2007-02-21 鸿富锦精密工业(深圳)有限公司 Handset with function of saving electricity, and method of saving electricity
CN101853166A (en) * 2010-06-07 2010-10-06 北京大学 Application-oriented method and system for indicating use time of intelligent mobile phone battery
CN202663561U (en) * 2012-03-11 2013-01-09 上海宜云物联科技有限公司 Internet of Things gateway capable of long-term operation without electricity
CN104216501A (en) * 2014-08-21 2014-12-17 刘勇 Electricity saving method for mobile terminal, electricity saving system for mobile terminal and mobile terminal
KR20170039471A (en) * 2015-10-01 2017-04-11 엘지전자 주식회사 Mobile termianl and method for controlling the same
CN105978971A (en) * 2016-05-11 2016-09-28 北京奇虎科技有限公司 Message pushing method and device, and message pushing server
CN107404533A (en) * 2017-07-29 2017-11-28 深圳市盛路物联通讯技术有限公司 A kind of method for monitoring biological activity, and monitoring device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110278147A (en) * 2019-06-20 2019-09-24 深圳市中创工业互联网有限公司 A kind of power-saving method of gateway, device and economize on electricity gateway
CN110278147B (en) * 2019-06-20 2023-10-20 深圳市中创工业互联网有限公司 Power saving method and device for gateway and power saving gateway
CN112995941A (en) * 2021-03-08 2021-06-18 莫毓昌 Industrial Internet of things data transmission system and method for dormancy awakening mechanism
CN112995941B (en) * 2021-03-08 2022-07-15 莫毓昌 Industrial Internet of things data transmission system and method for dormancy awakening mechanism

Similar Documents

Publication Publication Date Title
WO2016037303A1 (en) Evaluation method for online accommodating capacity of new energy power generation
EP3182581B1 (en) Power distribution priority controller and control method for photovoltaic power generation system
JP6168060B2 (en) Power management method, power management apparatus and program
CN203455714U (en) ZigBee wireless monitoring system of power line towers
CN105510779A (en) Arrester on-line monitoring system and application method thereof
CN103956887A (en) Wind power converter IGBT module junction temperature online computing method
CN103187735A (en) Bidirectional intelligent gateway device for distributed new energy grid connection
CN105162113A (en) Sensitivity analysis based interaction cost calculation method for microgrid and power distribution grid
CN105375477A (en) Rural power distribution network line loss calculation method and system
CN108540378A (en) A kind of method of industry things-internet gateway ladder power saving
CN103455716A (en) Ultra-short-term wind power prediction-based voltage stability margin calculation method for power system
CN201955410U (en) Remote online arrester monitoring device
CN107257130A (en) The low-voltage network loss computing method of decoupling is measured based on region
CN103942429A (en) Satellite on-orbit transient temperature simulation and prediction system
CN201945641U (en) Distributed electric energy metering device of power transformation and distribution station
CN108551205A (en) A kind of electricity saving method, gateway and the gateway system of super low-power consumption industry things-internet gateway
CN201503468U (en) Electric energy meter for voltage quality
CN103245850B (en) The feeder line peak load predictor method of substation transformer
CN106972498B (en) Power demand response control system and load control method thereof
CN205375815U (en) Wisdom energy modularization monitoring system based on smart electric meter
CN206226013U (en) A kind of Distributed Multi sampling Short-Term Power Load Forecasting System
CN211905518U (en) Anti-electricity-theft online monitoring device
CN204790388U (en) A on --spot monitor control device for long -range monitor platform of water treatment
CN207427180U (en) A kind of internet device restarts system automatically
CN206523996U (en) A kind of wireless collector-shoe gears of ZigBee

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180914