CN108512134B - 浅水域分支缆铺设工艺 - Google Patents
浅水域分支缆铺设工艺 Download PDFInfo
- Publication number
- CN108512134B CN108512134B CN201810255888.1A CN201810255888A CN108512134B CN 108512134 B CN108512134 B CN 108512134B CN 201810255888 A CN201810255888 A CN 201810255888A CN 108512134 B CN108512134 B CN 108512134B
- Authority
- CN
- China
- Prior art keywords
- cable
- connection box
- main
- cable laying
- laying ship
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/10—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water
Abstract
本发明一种浅水域分支缆铺设工艺,包含有以下步骤:步骤1、在铺缆船上连接好线缆;步骤2、主缆的起始端部连接至监测站内的信号发生器;步骤3、铺缆船在定位系统的引导下铺设主缆至主接驳盒放置点;步骤4、待主接驳盒释放至泥面后,铺缆船在定位系统的引导下驶向与步骤3中主接驳盒相连的次接驳盒的放置点;步骤5、铺缆船航行至次接驳盒放置点后释放次接驳盒,然后返航至步骤3中主接驳盒的放置点;步骤6、铺缆船前往下一主接驳盒放置点,并且重复步骤3~6直至主接驳盒全部释放完毕。本发明一种浅水域分支缆铺设工艺,铺设效率高且施工安全可靠。
Description
技术领域
本发明涉及一种铺缆工艺,尤其是涉及一种用于对分支缆进行铺设的工艺,其有助于提高铺设效率。
背景技术
目前,在内陆湖泊、沿海浅水区域内铺设分支海缆,常规的工艺方法为采取分支缆和主缆分别铺设后设标,然后打捞进行接驳,但是由于水中施工工况的复杂性,由于洋流、暗流甚至水生动物的干扰,水下打捞困难重重,即便接驳盒下水前进行定位,往往实际打捞点往往偏离该打捞点,因此这种作业方式增加海上施工时间,而海上作业的时间窗口本身就及其有限,因此增加了施工风险;并且增加了海缆双头下水工艺,相应的风险及施工成本都有所提高;因此继续一种铺设效率高且施工安全性能高的分支缆铺设工艺。
发明内容
本发明的目的在于克服上述不足,提供一种铺设效率高且施工安全可靠的浅水域分支缆铺设工艺。
本发明的目的是这样实现的:
一种浅水域分支缆铺设工艺,其特征在于:所述工艺包含有以下步骤:
步骤1、在铺缆船上连接好线缆,所述线缆包含有串接在主缆上的主接驳盒、由主接驳盒引出的分支缆、以及连接在分支缆末端的次接驳盒;
步骤2、主缆的起始端部连接至监测站内的信号发生器,带有连接好的线缆的铺缆船起航;
步骤3、铺缆船在定位系统的引导下铺设主缆至主接驳盒放置点,主接驳盒在铺缆船上的滑轮组的引导下释放至水底泥面;
步骤4、待主接驳盒释放至泥面后,铺缆船在定位系统的引导下驶向与步骤3中主接驳盒相连的次接驳盒的放置点,在航行的过程中释放分支缆,并且在主缆上绑扎浮球使得主缆浮于水面上;
步骤5、铺缆船航行至次接驳盒放置点后释放次接驳盒,然后返航至步骤3中主接驳盒的放置点,并且在返回的过程中回收浮球和主缆;
步骤6、铺缆船前往下一主接驳盒放置点,并且重复步骤3~6直至主接驳盒全部释放完毕;
步骤7、铺缆船携带主缆的收尾端铺设至监测站,并且主缆的收尾端连接至监测站内的信号接收器。
与现有技术相比,本发明的有益效果是:
本发明在铺设前将主缆和分支缆与主次接驳盒均接续完成,利用工艺方法铺缆作业,可大大缩短海上作业周期(无需打捞接驳盒再行接线),节省施工成本(仅需一条施工船即可进行施工,且无需配备水下打捞机器人进行打捞作业,降低了设备投入成本)。
附图说明
图1为本发明一种浅水域分支缆铺设工艺的流程示意图。
图2为本发明一种浅水域分支缆铺设工艺的分支缆处的施工流程示意图。
具体实施方式
参见图1和图2,本发明涉及的一种浅水域分支缆铺设工艺,所述工艺包含有以下步骤:
步骤1、在铺缆船上连接好线缆,所述线缆包含有串接在主缆上的主接驳盒、由主接驳盒引出的分支缆、以及连接在分支缆末端的次接驳盒;
线缆连接过程中,后铺设的线缆先行进行连接,前铺设的线缆后行连接,从而保证铺缆过程中,连接好的线缆不会造成缠绕;
步骤2、主缆的起始端部连接至监测站内的信号发生器,带有连接好的线缆的铺缆船起航;
步骤3、铺缆船在定位系统的引导下铺设主缆至主接驳盒放置点,主接驳盒在铺缆船上的滑轮组的引导下释放至水底泥面;
步骤4、待主接驳盒释放至泥面后,铺缆船在定位系统的引导下驶向与步骤3中主接驳盒相连的次接驳盒的放置点,在航行的过程中释放分支缆,并且在主缆上绑扎浮球使得主缆浮于水面上;
步骤5、铺缆船航行至次接驳盒放置点后释放次接驳盒,然后返航至步骤3中主接驳盒的放置点,并且在返回的过程中回收浮球和主缆;
步骤6、铺缆船前往下一主接驳盒放置点,并且重复步骤3~6直至主接驳盒全部释放完毕;
步骤7、铺缆船携带主缆的收尾端铺设至监测站,并且主缆的收尾端连接至监测站内的信号接收器。
另外:需要注意的是,上述具体实施方式仅为本专利的一个优化方案,本领域的技术人员根据上述构思所做的任何改动或改进,均在本专利的保护范围之内。
Claims (1)
1.一种浅水域分支缆铺设工艺,其特征在于:所述工艺包含有以下步骤:
步骤1、在铺缆船上连接好线缆,所述线缆包含有串接在主缆上的主接驳盒、由主接驳盒引出的分支缆、以及连接在分支缆末端的次接驳盒;
步骤2、主缆的起始端部连接至监测站内的信号发生器,带有连接好的线缆的铺缆船起航;
步骤3、铺缆船在定位系统的引导下铺设主缆至主接驳盒放置点,主接驳盒在铺缆船上的滑轮组的引导下释放至水底泥面;
步骤4、待主接驳盒释放至泥面后,铺缆船在定位系统的引导下驶向与步骤3中主接驳盒相连的次接驳盒的放置点,在航行的过程中释放分支缆,并且在主缆上绑扎浮球使得主缆浮于水面上;
步骤5、铺缆船航行至次接驳盒放置点后释放次接驳盒,然后返航至步骤3中主接驳盒的放置点,并且在返回的过程中回收浮球和主缆;
步骤6、铺缆船前往下一主接驳盒放置点,并且重复步骤3~6直至主接驳盒全部释放完毕;
步骤7、铺缆船携带主缆的收尾端铺设至监测站,并且主缆的收尾端连接至监测站内的信号接收器。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810255888.1A CN108512134B (zh) | 2018-03-27 | 2018-03-27 | 浅水域分支缆铺设工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810255888.1A CN108512134B (zh) | 2018-03-27 | 2018-03-27 | 浅水域分支缆铺设工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108512134A CN108512134A (zh) | 2018-09-07 |
CN108512134B true CN108512134B (zh) | 2020-05-19 |
Family
ID=63378618
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810255888.1A Active CN108512134B (zh) | 2018-03-27 | 2018-03-27 | 浅水域分支缆铺设工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108512134B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111327974A (zh) * | 2020-03-05 | 2020-06-23 | 深圳欧特海洋科技有限公司 | 基于环网拓扑结构的海底观测网络冗余系统及使用方法 |
CN111780743B (zh) * | 2020-06-05 | 2021-03-02 | 上海中车艾森迪海洋装备有限公司 | 水下挖沟敷缆机的定位系统和定位方法 |
CN112803303A (zh) * | 2021-02-05 | 2021-05-14 | 周宏勤 | 一种管缆施工工艺 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103527851B (zh) * | 2013-10-18 | 2015-06-03 | 中国海洋石油总公司 | 海底管道起始铺设系统的预布设工艺 |
CN107667203B (zh) * | 2015-05-29 | 2020-09-29 | 海瑞克股份公司 | 用于将地下电缆或地下管线近表面地敷设在地下的系统和方法 |
CN205101675U (zh) * | 2015-09-23 | 2016-03-23 | 中国石油集团海洋工程(青岛)有限公司 | 长距离海底管线预挖沟后铺管施工系统 |
-
2018
- 2018-03-27 CN CN201810255888.1A patent/CN108512134B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN108512134A (zh) | 2018-09-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108512134B (zh) | 浅水域分支缆铺设工艺 | |
AU2008229904B2 (en) | Apparatus and method for operating Autonomous Underwater Vehicles (AUVs) | |
US9395021B2 (en) | System and method for interconnecting umbilicals for conveying energy, fluids and/or data in a marine environment | |
KR102431006B1 (ko) | 분리형 해양 에너지 장치의 어레이 케이블 연결 시스템 | |
CN103527851B (zh) | 海底管道起始铺设系统的预布设工艺 | |
CN109790697B (zh) | 用于安装海底线缆的组件和方法 | |
EP3781471B1 (en) | Rov deployed power buoy system | |
AU2013100495A4 (en) | Buoy | |
JP2017178253A (ja) | 水中ロボット制御システムおよび水中ロボットの制御方法 | |
EP3499662A1 (en) | Assembly and method for installing a submarine line | |
Kojima et al. | Development of autonomous underwater vehicle'AQUA EXPLORER 2'for inspection of underwater cables | |
DK181182B1 (en) | An offshore drilling vessel with an external cable connection and method therefor | |
CN103236660A (zh) | 应用于海上风机基础的海底电缆敷设、保护方法及导引装置 | |
CN203242966U (zh) | 一种用于风机基础海底电缆保护及敷设的导引装置 | |
CN110901840A (zh) | 一种海上新型探测平台 | |
CN212259173U (zh) | 一种水下维修辅助工装 | |
CN218118839U (zh) | 一种深水海管弃管自动脱扣装置 | |
CN112937766B (zh) | 一种三锚浮标布放回收系统及方法 | |
AU2014100817A4 (en) | Buoy | |
CN219039256U (zh) | 基于水下信标的海底电缆故障定位系统 | |
CN115140241A (zh) | 一种水下缆绳、锚链自动脱扣装置 | |
CN113602452B (zh) | 一种声学打捞装置及方法 | |
CN215663926U (zh) | 一种声学打捞装置 | |
CN110716273A (zh) | 一种水下接驳站海上布放和回收方法及系统 | |
US20220289345A1 (en) | An offshore drilling vessel with an external cable connection and method therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |