CN108439189A CN201810400255.5A CN201810400255A CN108439189A CN 108439189 A CN108439189 A CN 108439189A CN 201810400255 A CN201810400255 A CN 201810400255A CN 108439189 A CN108439189 A CN 108439189A
Authority
CN
China
Prior art keywords
suspender
hole
pedestal
lifting
tension battery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810400255.5A
Other languages
Chinese (zh)
Inventor
李云
张厚宝
葛东伟
孟威
陶康军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Ankai Automobile Co Ltd
Original Assignee
Anhui Ankai Automobile Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Ankai Automobile Co Ltd filed Critical Anhui Ankai Automobile Co Ltd
Priority to CN201810400255.5A priority Critical patent/CN108439189A/en
Publication of CN108439189A publication Critical patent/CN108439189A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses a kind of toolings for the lifting of integral new-energy passenger high-tension battery comprising suspender pedestal, several suspenders and several pedestal hanging rings, pedestal hanging ring interval are symmetrically set at the top of suspender pedestal;Several suspender support bases, the suspender and suspender support seat hinge are symmetrically fixed on the suspender pedestal;Suspender hanging ring is equipped at the top of the suspender, the suspender bottom is equipped with suspension hook.The suspender top is equipped with through-hole, and the both ends upper and lower directions of suspender pedestal both sides is correspondingly provided with first positioning hole and second location hole, and the through-hole of the first positioning hole and second location hole respectively with suspender top is located by connecting by axis pin.This is used for the tooling of integral new-energy passenger high-tension battery lifting, and the rotational structure of suspender is conducive to the installation between the hoisting fixture and high-tension battery and dismounting, improves the convenience of operation;The problem of difficult, inconvenience which solve the liftings of existing integral new-energy passenger high-tension battery and hoisting process easily cause cell damage or casualties.

Description

A kind of tooling for the lifting of integral new-energy passenger high-tension battery
Technical field
The present invention relates to a kind of toolings of lifting, are specifically related to a kind of work for the lifting of integral new-energy passenger high-tension battery Dress.
Background technology
With the continuous development of society, all trades and professions are all advanced by leaps and bounds.Wherein, integral new-energy passenger is widely available, uses High-tension battery provides electric energy as stored energy power source, by high-tension battery to motor, and drive motor operating is new to push Energy bus driving.However due to the high-tension battery of integral new-energy passenger, length dimension >=1000mm, weight is sometime up to 300KG, It is difficult to install and be not easy to lift by crane, to need to carry out transfer, dismounting and the installation of high-tension battery position using hoisting fixture auxiliary.
However in practical operation, during being lifted to high-tension battery, on the one hand due to suspender and suspender pedestal Relative immobility, i.e., spreader position is stable, can not transfer;Thus when carrying out hooking lifting to high-tension battery, due to high pressure The stationarity of cell shapes size, to there are suspender hook it is inconvenient;Or after being hooked there are suspender and high-tension battery, even Connect the safety problems such as shakiness;It is easy that there are hoisting process mesohigh batteries to fall off, high-tension battery is caused to damage or casualties etc. Situation.
In addition, only carrying out hook operation by the suspension hook of suspender bottom and high-tension battery, high-tension battery was being hung Requirement for horizontality in journey is relatively high;When being operated for the steering in hoisting process, gradient, it is susceptible to unhook, it is then high The phenomenon that piezoelectric battery falls off, safety are insufficient.
Invention content
To overcome the deficiencies of existing technologies, it is an object of the invention to:It provides a kind of for integral new-energy passenger high-tension battery The tooling of lifting solves existing integral new-energy passenger high-tension battery lifting difficulty, inconvenience, and hoisting process easily causes battery damage The problem of wound or casualties;Wherein, the rotational structure of suspender be conducive to installation between the hoisting fixture and high-tension battery with Dismounting, improves the convenient of operation, safety and working efficiency, reduces labor intensity.
The present invention solves technical problem and adopts the following technical scheme that:
A kind of tooling for the lifting of integral new-energy passenger high-tension battery comprising if suspender pedestal, several suspenders and butt Seat hanging ring, pedestal hanging ring interval are symmetrically set at the top of suspender pedestal;It is symmetrically fixed on the suspender pedestal several Suspender support base, the suspender and suspender support seat hinge;Suspender hanging ring is equipped at the top of the suspender, the suspender bottom is equipped with Suspension hook.
There is also following technical characteristics by the present invention:
The suspender top is equipped with through-hole, and the both ends upper and lower directions of suspender pedestal both sides is correspondingly provided with the first positioning Hole and second location hole, and the first positioning hole and second location hole are positioned by axis pin with the through-hole on suspender top connect respectively It connects.
The hinge joint of the suspender and suspender support base is apart from first positioning hole and second location hole apart from identical.
When the through-hole on suspender top is coaxial with first positioning hole, suspender is automatically sagging, and suspender and suspender pedestal are in 90 ° Angle;When the through-hole on suspender top is coaxial with second location hole, suspender is with suspender pedestal at 135 ° of angles.
The suspender top is in inverted L-shaped.
The suspender hanging ring is fixed on the level board of suspender, and is fixed between the level board and vertical plate of suspender Reinforcing rib, the through-hole are set on reinforcing rib.
The suspender support base is symmetrically set in suspender both sides;Wherein, it is fixed with positioning plate on the suspender support base, institute It states and is fixed with articulated slab on suspender lateral wall, the articulated slab on positioning plate and suspender on the suspender support base uses axis pin Connection.
Several threaded holes are uniformly provided on the suspender support base, the suspender support base is bolted set on suspender On the corresponding position of pedestal.
Compared with the prior art, beneficial effects of the present invention are embodied in:
1, the tooling for being used for the lifting of integral new-energy passenger high-tension battery first adjusts suspender when lifting by crane high-tension battery , at 135 ° of positions (i.e. the through-hole on suspender top is coaxial with second location hole), to be inserted into axis pin with suspender pedestal;It then will be high Piezoelectric battery is integrally put into corresponding suitable position inside suspender, extracts axis pin, suspender is made to reset, at this point, suspender and suspender pedestal (i.e. the through-hole on suspender top is coaxial with first positioning hole) in 90 ° realizes that the suspension hook of suspender bottom is hooked into high-tension battery Axis pin location lifting apparatus is inserted into lifting point;Pedestal hanging ring and suspender hanging ring are connect with rope with lifting appliance then, complete lifting Operation.Which solve the problems that the lifting of existing integral new-energy passenger high-tension battery is difficult, inconvenient, improve working efficiency, reduce labor Fatigue resistance.
2, in addition, suspender and suspender support base are hinged by axis pin, it is conducive to realize the installation and dismounting of hoisting fixture, to It is easy to implement assembling and the transfer transmission of the hoisting fixture;It is easy to utilize.
This is used for the tooling of integral new-energy passenger high-tension battery lifting, and the rotational structure of suspender is conducive to the hoisting fixture and height Installation between piezoelectric battery and dismounting improve convenient, the safety of operation;Which solve existing integral new-energy passenger high-voltage electricity The problem of pond lifting is difficult, inconvenient and hoisting process easily causes cell damage or casualties.
Description of the drawings
Fig. 1 is dimensional structure diagram of the present invention.
Fig. 2 is the symmetrical half section structure diagram of main view of the present invention.
Fig. 3 is side structure schematic view of the present invention.
Fig. 4 is overlooking structure diagram of the present invention.
Fig. 5 is suspender side view broken section structural schematic diagram of the present invention.
Fig. 6 is suspender support base main structure diagram of the present invention.
Fig. 7 is suspender support base side structure schematic view of the present invention.
Wherein:1- suspender pedestals, 11- pedestal hanging rings, 12- suspender support bases, 13- first positioning holes, 14- second are positioned Hole, 15- positioning plates, 16- threaded holes, 2- suspenders, 21- suspender hanging rings, 22- suspension hooks, 23- through-holes, 24- reinforcing ribs, 25- auxiliary are logical Hole, 26- assist suspension hook, 27- auxiliary positionings hole, 28- positioning pins, 29- articulated slabs.
Specific implementation mode
Shown in 7, this structure feature for the tooling of integral new-energy passenger high-tension battery lifting is described in detail such as Under:
A kind of tooling for the lifting of integral new-energy passenger high-tension battery comprising suspender pedestal 1, several suspenders 2 and several Pedestal hanging ring 11, the pedestal hanging ring 11, which is spaced, is symmetrically set to 1 top of suspender pedestal;It is symmetrically fixed on the suspender pedestal 1 Equipped with several suspender support bases 12, the suspender 2 is hinged with suspender support base 12;2 top of the suspender is equipped with suspender hanging ring 21, 2 bottom of the suspender is equipped with suspension hook 22;And suspender 2 is integrally formed with suspension hook 22.
Wherein, suspender pedestal 1 is in " day " word framework, and there are two the pedestal hanging ring 11 is set, and pedestal hanging ring 11 is symmetrically solid The fixed intermediate position set on 1 top of " day " word framework suspender pedestal;There are six the suspender support base 12 is set altogether, wherein suspender Respectively three suspender support bases 12 of setting, and three suspender support bases 12 interval that suspender pedestal 1 is often held on the inside of 1 framework both ends of pedestal Uniform both sides are symmetrical arranged;The suspender 2 is corresponding hinged with each suspender support base 12.
This is used for tooling of integral new-energy passenger high-tension battery lifting, and when lifting by crane high-tension battery, rotary hanger 2 first makes The space that high-tension battery is placed inside the hoisting fixture increases;Then high-tension battery is integrally put into corresponding inside the hoisting fixture Suitable position makes suspender 2 reset, and realizes that the suspension hook 22 of suspender 2 bottom hooks the lifting point into high-tension battery, with rope by two A pedestal hanging ring 11 and six suspender hanging rings 21 are connect with lifting appliance, complete lifting operation.This is used for integral new-energy passenger high pressure The tooling of battery lifting solves the problems, such as that existing integral new-energy passenger high-tension battery lifting is difficult, inconvenient, improves work effect Rate reduces labor intensity.
As the preferred embodiment of the present invention, in conjunction with shown in Fig. 1 to 7;
Wherein, 2 top of the suspender is equipped with through-hole 23, and the both ends upper and lower directions correspondence of 1 both sides of suspender pedestal is set Have a first positioning hole 13 and second location hole 14, and the first positioning hole 13 and second location hole 14 respectively with 2 top of suspender Through-hole 23 be located by connecting by axis pin.When lifting by crane high-tension battery, suspender 2 is adjusted to the through-hole 23 on 2 top of suspender first It is coaxial with second location hole 14, is inserted into axis pin along second location hole 14 and through-hole 23, realizes and place height inside the hoisting fixture The space of piezoelectric battery increases;High-tension battery is then integrally put into corresponding suitable position inside the hoisting fixture, extracts axis pin, So that suspender 2 is resetted, at this point, the through-hole 23 on 2 top of suspender is coaxial with first positioning hole 13, realizes the suspension hook 22 of 2 bottom of suspender The lifting point into high-tension battery is hooked, axis pin, location lifting apparatus are inserted into along first positioning hole 13 and through-hole 23;Then with rope by base Seat hanging ring 11 and suspender hanging ring 21 are connect with lifting appliance, complete lifting operation.Which solve existing integral new-energy passenger high pressures Difficult, the inconvenient problem of battery lifting, improves working efficiency, reduces labor intensity.
Specifically, the hinge joint of the suspender 2 and suspender support base 12 is apart from first positioning hole 13 and second location hole 14 Apart from identical., it can be achieved that logical when ensureing the through-hole 23 on 2 top of suspender around the rotation of the hinge joint of suspender 2 and suspender support base 12 Hole 23 is coaxial with first positioning hole 13 and second location hole 14 respectively on corresponding position, then makes the rotation of suspender 2 to different positions When setting, it can be positioned by axis pin.
Specifically, when the through-hole 23 on 2 top of suspender is coaxial with first positioning hole 13, automatic sagging, the suspender 2 of suspender 2 With 1 angle in 90 ° of suspender pedestal;When the through-hole 23 on 2 top of suspender is coaxial with second location hole 14, suspender 2 and suspender base Seat 1 is at 135 ° of angles.When lifting by crane high-tension battery, suspender 2 is adjusted to suspender pedestal 1 into 135 ° of position (i.e. suspenders 2 first The through-hole 23 on top and second location hole 14 are coaxial), it is inserted into axis pin along second location hole 14 and through-hole 23, realizes the slinger The internal space for placing high-tension battery of dress increases;High-tension battery is then integrally put into corresponding suitable position inside the hoisting fixture It sets, extracts axis pin, suspender 2 is made to reset, at this point, suspender 2 and (the i.e. through-hole 23 and first on 2 top of suspender in 90 ° of suspender pedestal 1 Location hole 13 is coaxial), realize that the suspension hook 22 of 2 bottom of suspender hooks the lifting point into high-tension battery, along 13 He of first positioning hole Through-hole 23 is inserted into axis pin, location lifting apparatus;Pedestal hanging ring 11 and suspender hanging ring 21 are connect with rope with lifting appliance then, completed Lifting operation.Which solve the problem that the lifting of existing integral new-energy passenger high-tension battery is difficult, inconvenient, improve work efficiency, Reduce labor intensity.
For ensure the hoisting fixture suspender 2 lifting intensity;2 top of the suspender is in inverted L-shaped.Wherein, the suspender Hanging ring 21 is fixed on the level board of suspender 2, and reinforcing rib 24 is fixed between the level board and vertical plate of suspender 2, institute Through-hole 23 is stated on reinforcing rib 24.Wherein, reinforcing rib 24 is symmetrically set in the both sides of each suspender 2, and reinforcing rib 24 is used with suspender 2 It is wholely set;And the through-hole 23 on the reinforcing rib 24 of 1 the same end of suspender pedestal is coaxial.Then ensure that 2 top of suspender has For 21 fixed position of suspender hanging ring, and the setting of through-hole 23 is avoided to influence the lifting intensity of suspender 2, ensures the hoisting fixture Lifting intensity and lifting weight.
Wherein, the suspender support base 12 is symmetrically set in 2 both sides of suspender;Wherein, fixation is set on the suspender support base 12 Have positioning plate 15, articulated slab 29 be fixed on 2 lateral wall of the suspender, the positioning plate 15 on the suspender support base 12 with hang Articulated slab 29 on tool 2 is connected using axis pin.To on the one hand realize the hinge between suspender 2 and fixed suspender support base 12 It connects, suspender 2 is made to realize rotatable operation, the placement convenient for high-tension battery and hook operation;On the other hand it is conducive to realize the lifting The installation and dismounting of tooling are easy to implement assembling and the transfer transmission of the hoisting fixture;It is easy to utilize.
Specifically, being uniformly provided with several threaded holes 16 on the suspender support base 12, the suspender support base 12 passes through spiral shell Bolt is fixed on the corresponding position of suspender pedestal 1.To conducive to the installation and dismounting of the hoisting fixture is realized, be easy to implement this The assembling and transfer transmission of hoisting fixture;It is easy to utilize.
The phenomenon that avoid hoisting process mesohigh battery from falling off;2 low side of the suspender is equipped with 25 He of auxiliary through hole Suspension hook 26, the auxiliary suspension hook 26 is assisted to be equipped with auxiliary positioning hole 27, the auxiliary suspension hook 26 passes through positioning pin 28 with suspender 2 It is fixedly connected.When lifting by crane high-tension battery, suspender 2 is adjusted to suspender pedestal 1 into 135 ° of positions (i.e. 2 top of suspender first Through-hole 23 and second location hole 14 be coaxial), be inserted into axis pin along second location hole 14 and through-hole 23, realize in the hoisting fixture The space that high-tension battery is placed in portion increases;High-tension battery is then integrally put into corresponding suitable position inside the hoisting fixture, Axis pin is extracted, suspender 2 is made to reset, at this point, suspender 2 and (the i.e. positioning of through-hole 23 and first on 2 top of suspender in 90 ° of suspender pedestal 1 Hole 13 is coaxial), realize that the suspension hook 22 of 2 bottom of suspender hooks the lifting point into high-tension battery, along first positioning hole 13 and through-hole 23 are inserted into axis pin, location lifting apparatus;Then adjusting auxiliary suspension hook 26 keeps auxiliary positioning hole 27 thereon and the auxiliary of 2 low side of suspender logical Hole 25 is corresponding, then uses positioning pin 28 to sequentially pass through and assists the auxiliary of 2 low side of auxiliary positioning hole 27 and suspender on suspension hook 26 Through-hole 25 is helped to carry out auxiliary positioning;Pedestal hanging ring 11 and suspender hanging ring 21 are connect with lifting appliance with rope, complete lifting behaviour Make.22 collective effect of suspension hook of the auxiliary suspension hook 26 and 2 bottom of suspender is, it can be achieved that the lifting point to high-tension battery is clamped; The auxiliary suspension hook 26 helps to carry out emphasis clamping to the lifting point of high-tension battery, smoothly realizes the steering in hoisting process and inclines Tiltedly transmission, avoids causing casualties, and improves safety.
The present invention provides a kind of tooling for the lifting of integral new-energy passenger high-tension battery, and the rotational structure of suspender is conducive to this Installation between hoisting fixture and high-tension battery and dismounting;Auxiliary suspension hook contributes to the emphasis of high-tension battery Hoisting Position to clamp, Improve convenient, the safety of operation;And the hoisting fixture is easily installed and dismantles, consequently facilitating carry out repeating assembling and transport, It is easy to operate, it is easy to utilize;Solve difficult existing integral new-energy passenger high-tension battery lifting, inconvenience and hoisting process The problem of easily causing cell damage or casualties.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case of without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Profit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent requirements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiment being appreciated that.

Claims (8)

1. a kind of tooling for the lifting of integral new-energy passenger high-tension battery comprising suspender pedestal, several suspenders and several pedestals Hanging ring, pedestal hanging ring interval are symmetrically set at the top of suspender pedestal;It is characterized in that:It is symmetrically fixed on the suspender pedestal Equipped with several suspender support bases, the suspender and suspender support seat hinge;Suspender hanging ring, the suspender are equipped at the top of the suspender Bottom is equipped with suspension hook.
2. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 1, it is characterised in that:It is described Suspender top is equipped with through-hole, and the both ends upper and lower directions of suspender pedestal both sides is correspondingly provided with first positioning hole and the second positioning Hole, and the through-hole of the first positioning hole and second location hole respectively with suspender top is located by connecting by axis pin.
3. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 2, it is characterised in that:It is described The hinge joint of suspender and suspender support base is apart from first positioning hole and second location hole apart from identical.
4. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 2, it is characterised in that:When hanging When through-hole and the first positioning hole for having top are coaxial, suspender is automatically sagging, suspender and suspender pedestal angle in 90 °;Work as suspender When the through-hole on top and second location hole are coaxial, suspender is with suspender pedestal at 135 ° of angles.
5. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 2, it is characterised in that:It is described Suspender top is in inverted L-shaped.
6. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 5, it is characterised in that:It is described Suspender hanging ring is fixed on the level board of suspender, and is fixed with reinforcing rib between the level board and vertical plate of suspender, described Through-hole is set on reinforcing rib.
7. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 1, it is characterised in that:It is described Suspender support base is symmetrically set in suspender both sides;Wherein, positioning plate, the suspender lateral wall are fixed on the suspender support base On be fixed with articulated slab, the articulated slab on positioning plate and suspender on the suspender support base using axis pin connect.
8. a kind of tooling for the lifting of integral new-energy passenger high-tension battery according to claim 7, it is characterised in that:It is described Several threaded holes are uniformly provided on suspender support base, the suspender support base is bolted set on the correspondence position of suspender pedestal It sets.
CN201810400255.5A 2018-04-28 2018-04-28 A kind of tooling for the lifting of integral new-energy passenger high-tension battery Pending CN108439189A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810400255.5A CN108439189A (en) 2018-04-28 2018-04-28 A kind of tooling for the lifting of integral new-energy passenger high-tension battery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810400255.5A CN108439189A (en) 2018-04-28 2018-04-28 A kind of tooling for the lifting of integral new-energy passenger high-tension battery

Publications (1)

Publication Number Publication Date
CN108439189A true CN108439189A (en) 2018-08-24

Family

ID=63202372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810400255.5A Pending CN108439189A (en) 2018-04-28 2018-04-28 A kind of tooling for the lifting of integral new-energy passenger high-tension battery

Country Status (1)

Country Link
CN (1) CN108439189A (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3124695U (en) * 2006-06-14 2006-08-24 株式会社アステック入江 Automatic lifting device
CN201971544U (en) * 2011-01-04 2011-09-14 浙江吉利汽车研究院有限公司 Universal hanger for car body
CN202072395U (en) * 2011-05-13 2011-12-14 浙江金刚汽车有限公司 Transshipment lifting appliance for BIW (body in white)
CN202687767U (en) * 2012-04-27 2013-01-23 济南吉利汽车有限公司 Car body hanger
JP2013082541A (en) * 2011-10-11 2013-05-09 Mitsubishi Motors Corp Lifting implement
CN203048403U (en) * 2012-12-20 2013-07-10 北汽福田汽车股份有限公司 Car body lifting tool
CN103253592A (en) * 2013-05-13 2013-08-21 武汉海王机电工程技术公司 Machine lifting tool for automatically grabbing and releasing goods
CN203486725U (en) * 2013-08-13 2014-03-19 浙江吉利汽车有限公司 Semi-automatic pneumatic type cover gripper
CN204310694U (en) * 2014-10-18 2015-05-06 济南留安石膏机械设备制造有限公司 A kind of dual-purpose building block fixture
CN205527318U (en) * 2016-02-23 2016-08-31 河南平高电气股份有限公司 Hanger tooling
CN106365036A (en) * 2016-09-19 2017-02-01 哈尔滨工程大学 Submarine pipeline press cake release combined hanging bracket
CN206244266U (en) * 2016-09-30 2017-06-13 包头中创节能装备科技有限公司 A kind of bundling aluminium ingot hoisting tool special
CN206447476U (en) * 2016-12-29 2017-08-29 深圳市科陆电子科技股份有限公司 A kind of stone tongs
CN207090797U (en) * 2017-08-07 2018-03-13 海门市品一铝业有限公司 A kind of special hanger for being used to lift waste paper bag
CN208361699U (en) * 2018-04-28 2019-01-11 安徽安凯汽车股份有限公司 A kind of tooling for the lifting of integral new-energy passenger high-tension battery

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3124695U (en) * 2006-06-14 2006-08-24 株式会社アステック入江 Automatic lifting device
CN201971544U (en) * 2011-01-04 2011-09-14 浙江吉利汽车研究院有限公司 Universal hanger for car body
CN202072395U (en) * 2011-05-13 2011-12-14 浙江金刚汽车有限公司 Transshipment lifting appliance for BIW (body in white)
JP2013082541A (en) * 2011-10-11 2013-05-09 Mitsubishi Motors Corp Lifting implement
CN202687767U (en) * 2012-04-27 2013-01-23 济南吉利汽车有限公司 Car body hanger
CN203048403U (en) * 2012-12-20 2013-07-10 北汽福田汽车股份有限公司 Car body lifting tool
CN103253592A (en) * 2013-05-13 2013-08-21 武汉海王机电工程技术公司 Machine lifting tool for automatically grabbing and releasing goods
CN203486725U (en) * 2013-08-13 2014-03-19 浙江吉利汽车有限公司 Semi-automatic pneumatic type cover gripper
CN204310694U (en) * 2014-10-18 2015-05-06 济南留安石膏机械设备制造有限公司 A kind of dual-purpose building block fixture
CN205527318U (en) * 2016-02-23 2016-08-31 河南平高电气股份有限公司 Hanger tooling
CN106365036A (en) * 2016-09-19 2017-02-01 哈尔滨工程大学 Submarine pipeline press cake release combined hanging bracket
CN206244266U (en) * 2016-09-30 2017-06-13 包头中创节能装备科技有限公司 A kind of bundling aluminium ingot hoisting tool special
CN206447476U (en) * 2016-12-29 2017-08-29 深圳市科陆电子科技股份有限公司 A kind of stone tongs
CN207090797U (en) * 2017-08-07 2018-03-13 海门市品一铝业有限公司 A kind of special hanger for being used to lift waste paper bag
CN208361699U (en) * 2018-04-28 2019-01-11 安徽安凯汽车股份有限公司 A kind of tooling for the lifting of integral new-energy passenger high-tension battery

Similar Documents

Publication Publication Date Title
CN104276510A (en) Turnover lifting appliance for generator and use method of turnover lifting appliance
CN106586811A (en) Hoisting overturning device for concrete tower drum and hoisting overturning method
CN208361699U (en) A kind of tooling for the lifting of integral new-energy passenger high-tension battery
CN106129901A (en) A kind of 35kV circuit single pole porcelain pole arm repairing instrument
CN108439189A (en) A kind of tooling for the lifting of integral new-energy passenger high-tension battery
CN205275002U (en) Installation hoist of generator
CN216444881U (en) Hook for heat treatment of large-scale seal head
CN212609004U (en) Self-adjusting surface contact lifting device
CN213085198U (en) Balance hanging beam group lifting appliance
CN211644534U (en) Portable disassembly and assembly tool for transformer substation well cover
CN201261681Y (en) Sling for mounting RH furnace circulating pipe
CN207719623U (en) A kind of novel distribution cabinet of mounting plate easy disassembly
CN208883427U (en) A kind of killer switch inspection trolley
CN207434890U (en) A kind of device for being used for vertical lifting and overturning
CN112283018A (en) Three-dimensional adjustable hub blade assembling platform and blade mounting method thereof
CN219885487U (en) Balance beam structure
CN215160229U (en) Lifting appliance
CN108869879B (en) Application of heat collecting pipe mounting tool
CN210558883U (en) Improve wind-powered electricity generation fan of hoist and mount stability and use impeller hoist
CN215626317U (en) Hoisting device
CN209583404U (en) A kind of large size bearing hanger for assembling
CN208394603U (en) A kind of power battery suspender
CN208631961U (en) Horizontal permanent-magnetic synchronizes submersible motor kludge experimental rig
CN206232846U (en) A kind of polycrystalline ingot furnace and its support platform hanging apparatus
CN210214532U (en) Connecting device for engine lifting appliance and bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination