CN108408554A CN201810446184.2A CN201810446184A CN108408554A CN 108408554 A CN108408554 A CN 108408554A CN 201810446184 A CN201810446184 A CN 201810446184A CN 108408554 A CN108408554 A CN 108408554A
Authority
CN
China
Prior art keywords
wire rope
steel wire
rope
clamping
blast furnace
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810446184.2A
Other languages
Chinese (zh)
Inventor
蒋建波
朱永刚
李传斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yonggang Group Co Ltd
Original Assignee
Jiangsu Yonggang Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yonggang Group Co Ltd filed Critical Jiangsu Yonggang Group Co Ltd
Priority to CN201810446184.2A priority Critical patent/CN108408554A/en
Publication of CN108408554A publication Critical patent/CN108408554A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/02Installing or exchanging ropes or cables
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16GBELTS, CABLES, OR ROPES, PREDOMINANTLY USED FOR DRIVING PURPOSES; CHAINS; FITTINGS PREDOMINANTLY USED THEREFOR
    • F16G11/00Means for fastening cables or ropes to one another or to other objects; Caps or sleeves for fixing on cables or ropes
    • F16G11/12Connections or attachments, e.g. turnbuckles, adapted for straining of cables, ropes, or wire

Abstract

The invention discloses a kind of replacement charging of blast furnace truck rope wire rope tension devices, include the wire cable clamp to clamping steel wire rope and the haulage gear to traction steel wire rope fixture, and the structure of the wire cable clamp includes:In the two clamping plates of left and right distribution, it is provided with the retaining mechanism that two clamping plates can be made in the opposite shape clamping steel wire rope in left and right between two clamping plates, is provided with the lifting lug being connected with haulage gear on one piece of clamping plate wherein.It is an advantage of the invention that:It is simple in structure, it is easy to use, it is time saving and energy saving and steel rope replacing operating efficiency can be effectively improved.

Description

A kind of replacement charging of blast furnace truck rope wire rope tension device
Technical field
The invention patent relates to charging of blast furnace truck steel rope replacing technical field of auxiliary equipment, and in particular to a kind of replacement Charging of blast furnace truck rope wire rope tension device.
Background technology
Steel wire rope is important one of the spare part of Research for Feeding Raw Materials System equipment.Currently, replacing charging of blast furnace truck steel wire rope Process is:One end of new steel wire rope is first passed through into charging of blast furnace truck connecting rod pulley, then artificial tense wire rope again, connect It and steel wire rolling head is installed in the steel cord ends for having passed through charging of blast furnace truck connecting rod pulley, to complete steel wire rope more It changes.The disadvantages such as there are labor intensities for the mode of operation of this artificial tense wire rope greatly, steel rope replacing operating efficiency is low.
Invention content
The object of the present invention is to provide a kind of time saving and energy saving and can improve on the replacement blast furnace of steel rope replacing operating efficiency Expect truck rope wire rope tension device.
To achieve the above object, present invention employs following technical solutions:A kind of replacement charging of blast furnace truck steel Rope wire rope tension device includes to the wire cable clamp of clamping steel wire rope and to traction steel wire rope fixture The structure of haulage gear, the wire cable clamp includes:In the two clamping plates of left and right distribution, energy is provided between two clamping plates Two clamping plates are made to be provided on one piece of clamping plate match with haulage gear wherein in the retaining mechanism of the opposite shape clamping steel wire rope in left and right Close the lifting lug of connection.
Further, a kind of replacement charging of blast furnace truck rope wire rope tension device above-mentioned, wherein:At two pieces A steel wire rope locating slot for corresponding to clamping plate up and down is respectively arranged on the relative inner wall of clamping plate, between two clamping plates Steel wire rope locating slot is in the corresponding distribution in left and right, when two clamping plates shape clamping steel wire rope opposite in left and right by retaining mechanism, steel Cord, which is just clamped and fixed, to be collectively formed in two steel wire rope locating slots in steel wire rope location hole.
Further, a kind of replacement charging of blast furnace truck rope wire rope tension device above-mentioned, wherein:At every piece It is respectively arranged with anti-skid chequer on the cell wall of steel wire rope locating slot on clamping plate.
Further, a kind of replacement charging of blast furnace truck rope wire rope tension device above-mentioned, wherein:Anti-skid chequer For internal thread.
Further, a kind of replacement charging of blast furnace truck rope wire rope tension device above-mentioned, wherein:Locking machine The structure of structure is:The locking holes of the corresponding clamping plates of several left and right perforations are respectively arranged on every piece of clamping plate, between two clamping plates Locking hole is corresponded in left and right, and a clamping screw, every clamping screw are respectively arranged in each pair of corresponding locking hole Screw rod be threadedly coupled that there are one locking nuts respectively after being pierced by corresponding a pair of of locking hole.
Further, a kind of replacement charging of blast furnace truck rope wire rope tension device above-mentioned, wherein:Dragger Structure is electric block.
Through the implementation of the above technical solution, the beneficial effects of the invention are as follows:It is simple in structure, it is easy to use, it is time saving and energy saving And steel rope replacing operating efficiency can be effectively improved.
Description of the drawings
Fig. 1 is a kind of structural representation for replacing charging of blast furnace truck rope wire rope tension device of the present invention Figure.
Fig. 2 is the structural schematic diagram of the overlook direction of wire cable clamp shown in Fig. 1.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
As shown in Figure 1 and Figure 2, a kind of replacement charging of blast furnace truck rope wire rope tension device, including with With the wire cable clamp of clamping steel wire rope and to the haulage gear 1 of traction steel wire rope fixture, the knot of the wire cable clamp Structure includes:In the two clamping plates 2 of left and right distribution, being provided between two clamping plates 2 can be such that two clamping plates are pressed from both sides in the opposite shape in left and right The retaining mechanism of tight steel wire rope, is provided with the lifting lug 3 being connected with haulage gear 1 on one piece of clamping plate 2 wherein;In this implementation In example, it is respectively arranged with a steel wire rope locating slot for corresponding to clamping plate 2 up and down on the relative inner wall of two clamping plates, two Steel wire rope locating slot between block clamping plate 2 is in the corresponding distribution in left and right, when two clamping plates are pressed from both sides by retaining mechanism in the opposite shape in left and right When tight steel wire rope, steel wire rope, which is just clamped and fixed, to be collectively formed in two steel wire rope locating slots in steel wire rope location hole 4, in this way Wire cable clamp can more easily be operated to be clamped steel wire rope;In the present embodiment, the steel wire rope on every piece of clamping plate 2 It is respectively arranged with anti-skid chequer on the cell wall of locating slot, when steel wire rope is clamped and fixed two steel wire ropes between two clamping plates 2 When locating slot is collectively formed in steel wire rope location hole 4, the anti-skid chequer on the internal groove side wall of the steel wire locating slot on every piece of clamping plate 2 can be embedding Enter in clamped steel wire rope, to make wire cable clamp more firmly clamping steel wire rope;In the present embodiment, anti-skid chequer is interior Screw thread, this anti-skid chequer are easy to process;In the present embodiment, the structure of retaining mechanism is:It is respectively arranged on every piece of clamping plate 2 Several left and right perforations correspond to the locking hole of clamping plates, and the locking hole between two clamping plates is corresponded in left and right, each pair of corresponding A clamping screw 5 is respectively arranged in locking hole, the screw rod of every clamping screw 5 in corresponding a pair of of locking hole after being pierced by It is threadedly coupled respectively there are one locking nut 6, two common shapes of steel wire rope locating slot between steel wire rope is placed in two clamping plates 2 When in steel wire rope location hole 4, all locking nuts 6 are inwardly screwed, to make two clamping plates 2 clamp steel in the opposite shape in left and right Cord;In the present embodiment, haulage gear is electric block, above-mentioned electric block cost relative moderate, reduce enterprise's use at This;
Working principle of the present invention is as follows:
One end of new steel wire rope is first passed through into charging of blast furnace truck connecting rod pulley, then by two clamping plates 2 or so to co-clip The steel cord ends of charging of blast furnace truck connecting rod pulley are firmly passed through, steel cord ends are placed exactly in two clamping plates 2 at this time In the steel wire rope location hole 4 that two steel wire rope locating slots are formed, then in each pair of corresponding locking hole between two clamping plates 2 A clamping screw 5 is worn respectively, and screw thread connects the screw rod of every clamping screw 5 respectively after being pierced by corresponding a pair of of locking hole A locking nut 6 is connect, all locking nuts 6 are then inwardly screwed, to make two clamping plates 2 clamp steel in the opposite shape in left and right Cord, during 2 clamping steel wire rope of two clamping plates, the anti-skid chequer on the internal groove side wall of the steel wire locating slot on every piece of clamping plate 2 It can be embedded in clamped steel wire rope, to make wire cable clamp more firmly clamping steel wire rope;Then by the extension of electric block Hook hooks the lifting lug on wire cable clamp, then by electric block traction steel wire rope fixture, to being pressed from both sides by wire cable clamp Steel wire rope firmly is tensed, and steel wire rolling head can be installed in steel cord ends at this time, to smoothly complete the replacement of steel wire rope.
It is an advantage of the invention that:It is simple in structure, it is easy to use, it is time saving and energy saving and can effectively improve steel rope replacing operation effect Rate.

Claims (6)

1. a kind of replacement charging of blast furnace truck rope wire rope tension device, it is characterised in that:Including to clamping steel wire The wire cable clamp of rope and haulage gear to traction steel wire rope fixture, the structure of the wire cable clamp include:In a left side The two clamping plates of right distribution are provided with the locking that two clamping plates can be made in the opposite shape clamping steel wire rope in left and right between two clamping plates Mechanism is provided with the lifting lug being connected with haulage gear on one piece of clamping plate wherein.
2. a kind of replacement charging of blast furnace truck rope wire rope tension device according to claim 1, feature exist In:It is respectively arranged with a steel wire rope locating slot for corresponding to clamping plate up and down on the relative inner wall of two clamping plates, two pieces Steel wire rope locating slot between clamping plate is in the corresponding distribution in left and right, when two clamping plates clamp steel by retaining mechanism in the opposite shape in left and right When cord, steel wire rope, which is just clamped and fixed, to be collectively formed in two steel wire rope locating slots in steel wire rope location hole.
3. a kind of replacement charging of blast furnace truck rope wire rope tension device according to claim 2, feature exist In:It is respectively arranged with anti-skid chequer on the cell wall of steel wire rope locating slot on every piece of clamping plate.
4. a kind of replacement charging of blast furnace truck rope wire rope tension device according to claim 3, feature exist In:Anti-skid chequer is internal thread.
5. a kind of replacement charging of blast furnace truck rope wire rope tension device according to claim 1 or 2 or 3 or 4, It is characterized in that:The structure of retaining mechanism is:The locking of several corresponding clamping plates of left and right perforation is respectively arranged on every piece of clamping plate Hole, the locking hole between two clamping plates are corresponded in left and right, and a locking is respectively arranged in each pair of corresponding locking hole Bolt, there are one locking nuts for threaded connection respectively after being pierced by corresponding a pair of of locking hole for the screw rod of every clamping screw.
6. a kind of replacement charging of blast furnace truck rope wire rope tension device according to claim 1 or 2 or 3 or 4, It is characterized in that:Haulage gear is electric block.
CN201810446184.2A 2018-05-11 2018-05-11 A kind of replacement charging of blast furnace truck rope wire rope tension device Pending CN108408554A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810446184.2A CN108408554A (en) 2018-05-11 2018-05-11 A kind of replacement charging of blast furnace truck rope wire rope tension device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810446184.2A CN108408554A (en) 2018-05-11 2018-05-11 A kind of replacement charging of blast furnace truck rope wire rope tension device

Publications (1)

Publication Number Publication Date
CN108408554A true CN108408554A (en) 2018-08-17

Family

ID=63138794

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810446184.2A Pending CN108408554A (en) 2018-05-11 2018-05-11 A kind of replacement charging of blast furnace truck rope wire rope tension device

Country Status (1)

Country Link
CN (1) CN108408554A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2272882Y (en) * 1995-11-20 1998-01-21 江汉建筑工程机械厂 Lifter wire rope nondestructive clamp device for construction
US20040231113A1 (en) * 2003-05-19 2004-11-25 Warren Robert E. U-shaped wire rope clamp
CN202481082U (en) * 2012-03-14 2012-10-10 中国十七冶集团有限公司 Traction fixture for steel wire rope of cableway
CN202988481U (en) * 2012-12-25 2013-06-12 江南嘉捷电梯股份有限公司 Jumping-resisting rope clamping device of elevator
CN203513150U (en) * 2013-10-31 2014-04-02 湖南新天和工程设备有限公司 Hydraulic steel wire rope clamp
CN203593565U (en) * 2013-11-29 2014-05-14 重庆起重机厂有限责任公司 Fixing device and steel wire rope fixing structure
CN204848081U (en) * 2015-07-20 2015-12-09 安庆卓联信息技术有限公司 A dolly wire rope clamp plate for bank crane
CN208345554U (en) * 2018-05-11 2019-01-08 江苏永钢集团有限公司 A kind of replacement charging of blast furnace truck rope wire rope tension device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2272882Y (en) * 1995-11-20 1998-01-21 江汉建筑工程机械厂 Lifter wire rope nondestructive clamp device for construction
US20040231113A1 (en) * 2003-05-19 2004-11-25 Warren Robert E. U-shaped wire rope clamp
CN202481082U (en) * 2012-03-14 2012-10-10 中国十七冶集团有限公司 Traction fixture for steel wire rope of cableway
CN202988481U (en) * 2012-12-25 2013-06-12 江南嘉捷电梯股份有限公司 Jumping-resisting rope clamping device of elevator
CN203513150U (en) * 2013-10-31 2014-04-02 湖南新天和工程设备有限公司 Hydraulic steel wire rope clamp
CN203593565U (en) * 2013-11-29 2014-05-14 重庆起重机厂有限责任公司 Fixing device and steel wire rope fixing structure
CN204848081U (en) * 2015-07-20 2015-12-09 安庆卓联信息技术有限公司 A dolly wire rope clamp plate for bank crane
CN208345554U (en) * 2018-05-11 2019-01-08 江苏永钢集团有限公司 A kind of replacement charging of blast furnace truck rope wire rope tension device

Similar Documents

Publication Publication Date Title
CN207310222U (en) One kind stretches out reinforcing bar fixing tool
CN202481895U (en) Auxiliary device for lifting large grinding wheel
CN202840374U (en) Tension puller
CN204577993U (en) Cable drawing head
CN202023497U (en) Special rope ladder between tower and lead
CN208345554U (en) A kind of replacement charging of blast furnace truck rope wire rope tension device
CN108408554A (en) A kind of replacement charging of blast furnace truck rope wire rope tension device
CN203282420U (en) Double conductor tension indicating wire grip
CN210481878U (en) Device for inserting and weaving steel wire rope rigging
CN104682263A (en) Hot-line work operation lever single-lever work head
CN203096597U (en) Bridge suspender connecting device
CN202717889U (en) Silk hanging structure for nylon production
CN204947456U (en) The device of mutually single insulator string in charged for replacement 220kV tangent tower
CN203438182U (en) Chain tensioning tool
CN202910983U (en) Spring bolt of tension plate
CN207530433U (en) For replacing the specific purpose tool of suspension clamp shield lines
CN206599390U (en) A kind of crane receives hook mechanism automatically
CN201690325U (en) Traction motor armature disconnecting clamp
CN209974129U (en) Hoisting device for flange
CN203474251U (en) Crane suspension hook anti-falloff locking plate device
CN205960521U (en) Overhead line overhauls and uses rope ladder
CN216235585U (en) Track hoisting device
CN215071352U (en) Ultra-high molecular weight polyethylene rope fastener
CN203553852U (en) Parallel groove clamp for power transmission and transformation
CN204125839U (en) A kind of tight cable device for the construction of suspension bridge tight cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination