CN108403244A - The screw of planting body superstructure-cemented retention analogy method and fixing device - Google Patents

The screw of planting body superstructure-cemented retention analogy method and fixing device Download PDF

Info

Publication number
CN108403244A
CN108403244A CN201810367229.7A CN201810367229A CN108403244A CN 108403244 A CN108403244 A CN 108403244A CN 201810367229 A CN201810367229 A CN 201810367229A CN 108403244 A CN108403244 A CN 108403244A
Authority
CN
China
Prior art keywords
base station
planting body
artificial tooth
screw
planting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810367229.7A
Other languages
Chinese (zh)
Inventor
崔玲玲
张辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Affiliated Hospital of Jinzhou Medical University
Original Assignee
First Affiliated Hospital of Jinzhou Medical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Affiliated Hospital of Jinzhou Medical University filed Critical First Affiliated Hospital of Jinzhou Medical University
Priority to CN201810367229.7A priority Critical patent/CN108403244A/en
Publication of CN108403244A publication Critical patent/CN108403244A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61CDENTISTRY; APPARATUS OR METHODS FOR ORAL OR DENTAL HYGIENE
    • A61C19/00Dental auxiliary appliances
    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61CDENTISTRY; APPARATUS OR METHODS FOR ORAL OR DENTAL HYGIENE
    • A61C13/00Dental prostheses; Making same
    • A61C13/0001In-situ dentures; Trial or temporary dentures
    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61CDENTISTRY; APPARATUS OR METHODS FOR ORAL OR DENTAL HYGIENE
    • A61C13/00Dental prostheses; Making same
    • A61C13/34Making or working of models, e.g. preliminary castings, trial dentures; Dowel pins [4]
    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61CDENTISTRY; APPARATUS OR METHODS FOR ORAL OR DENTAL HYGIENE
    • A61C8/00Means to be fixed to the jaw-bone for consolidating natural teeth or for fixing dental prostheses thereon; Dental implants; Implanting tools
    • A61C8/0048Connecting the upper structure to the implant, e.g. bridging bars
    • AHUMAN NECESSITIES
    • A61MEDICAL OR VETERINARY SCIENCE; HYGIENE
    • A61CDENTISTRY; APPARATUS OR METHODS FOR ORAL OR DENTAL HYGIENE
    • A61C8/00Means to be fixed to the jaw-bone for consolidating natural teeth or for fixing dental prostheses thereon; Dental implants; Implanting tools
    • A61C8/0089Implanting tools or instruments

Landscapes

  • Health & Medical Sciences (AREA)
  • Oral & Maxillofacial Surgery (AREA)
  • Dentistry (AREA)
  • Epidemiology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Animal Behavior & Ethology (AREA)
  • General Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Veterinary Medicine (AREA)
  • Orthopedic Medicine & Surgery (AREA)
  • Dental Prosthetics (AREA)

Abstract

The invention discloses the screw cemented retention analogy methods and fixing device of planting body superstructure, are related to technical field of oral medicine, step 1, planting body implantation:Several planting bodies are implanted into jawbone model, planting body and jawbone models coupling are made;Step 2 installs compound base station:Compound base station is installed on planting body, carries out root transfer, top base station of polishing makes more planting body superstructures have common path of insertion, beveller is used in combination to adjust.The present invention simulates the anchoring methods of planting body superstructure, keep doctor more accurate when carrying out planting body superstructure maintenance, the fixation of planting body superstructure is completed well, simulation, which removes bonding agent extra between compound base station and artificial tooth outside mouth and is formed by, simultaneously overhangs, reduce the gap of base station and artificial tooth interface, the probability occurred the problems such as bacterium is detained caused bone regeneration around implant chronic inflammation or bone information is reduced, to maintain the health of bone regeneration around implant hard and soft tissue.

Description

The screw of planting body superstructure-cemented retention analogy method and fixing device
Technical field
The present invention relates to technical field of oral medicine, the more particularly to screw of planting body superstructure-cemented retention simulation Method and fixing device.
Background technology
Implant denture refers to that the alveolar bone in oral cavity edentulous region is implanted into planting body, i.e. artificial tooth root, waits for that planting body survives Afterwards, then on it end makes the reparation that dummy completes implant denture.Since implant denture technology proposes, by decades Research and probe, it has also become an important subject and rapid development are simultaneously ripe, and planting body is two sections by the gradual development evolvement of one-part form Formula, is divided into two component parts of planting body and base station, this differentiation allows planting body not by external interference, better shape Skeletonization integrated interface.Meanwhile by such a component that can be selected, adjust, replace of base station, dummy and planting body being made to gather around There is better harmony.
Superstructure, that is, base station of implant denture and the artificial tooth of upper part, there are mainly two types of maintenance modes, i.e. screw retained With cemented retention, the two respectively has advantage and disadvantage.Existing screw retained is directly by artificial tooth and base station by screw retained, and screw is solid Position implant denture takes and wears facility, can be with when occurring that abutment screw loosens, dummy collapses the complication such as porcelain or peri-implantitiss Dummy is easily removed to be handled.Screw retained implant denture provides retention by dummy screw, is wanted to jaw gum distance It asks low, is suitable for being engaged the case of insufficient space, but it is expensive, skilled worker's manufacturing process is cumbersome, and the presence of screw hole influences Dummy aesthetics.It is not suitable for more Dental implantion reparations, because more teeth cannot reach parallel, can only select bonding solid at this time Position.
Cemented retention dummy aesthetics is good, the compensatory non-passive stress generated in place of bonding agent energy, and cheap, faces Bed is widely used, but since bonding agent in the case that non-is visually unable to thorough cleaning, it is possible to bonding agent is remained, to peri-implant Soft tissue is enclosed there are hidden danger, and denture border at a specified future date can not remove cleaning.When crown margin is located under gum, extra bonding in gingival sulcus Agent is difficult to completely remove, and the gap that bonding agent is formed after gradually dissolving provides space for bacterial accumulation, easily causes bone regeneration around implant Catarrh even peri-implantitiss.Severe patient can cause bone regeneration around implant bone information, planting body to loosen, fall off.Simultaneously as The difference of each patient individual's oral condition will if carrying out the maintenance of planting body superstructure directly in human oral cavity Lead to the inaccuracy of implantation position and angle, while the fixation of planting body superstructure and artificial tooth cannot be completed well, so Just need the screw-cemented retention analogy method and fixing device of planting body superstructure.
Invention content
An embodiment of the present invention provides the screw of planting body superstructure-cemented retention analogy method and fixing devices, use To solve problems of the prior art.
The screw of planting body superstructure-cemented retention analogy method, is as follows:
Step 1, planting body implantation:Several planting bodies are implanted into jawbone model, planting body and jawbone models coupling are made;
Step 2 installs compound base station:Compound base station is installed on planting body, carries out root transfer, top base station of polishing makes More planting body superstructures have common path of insertion, and beveller is used in combination to adjust;
Step 3, modulus record model, make artificial tooth:The model for producing root transfer records the gypsum of planting body root transfer Model makes artificial tooth on the abutment structure of top;
Step 4, artificial tooth cemented retention:The artificial tooth of completion is adhered on the abutment structure of top, waits for bonding agent firmly solid;
Step 5 removes top integral structure artificial tooth:Top abutment structure screw is screwed off, integrated take is removed The artificial tooth of portion's base station, thorough cleaning thereon with the residual bonding agent on the base station of top;
Step 6, screw retained:By the integrated artificial tooth with top base station by screw retained on substrate base station;
Step 7 closes screw hole:Screw hole is closed, artificial tooth is completed.
The fixing device of planting body superstructure, including multiple planting bodies, the planting body upper center are spirally connected maintenance spiral shell Silk one, the planting body top edges anchoring base base station, the substrate base station upper center are spirally connected retaining screw two, the base Base platform top edges fix top base station, top base station top cemented retention artificial tooth, and the planting body passes through gum mould Type is fixed on alveolus bone model, while the top base station of not parallel artificial tooth is carried out mill and is changed, to make multiple artificial teeth of reparation It is integrally concordant with original tooth, it is more advantageous to mankind's occlusion.
Advantageous effect of the present invention:The present invention simulates the anchoring methods of planting body superstructure, and doctor is made to carry out planting body Can be more accurate when superstructure maintenance, the fixation of planting body superstructure is completed well, while simulation removes outside mouth Extra bonding agent, which is formed by, between compound base station and artificial tooth overhangs, and reduces the gap of base station and artificial tooth interface, reduces bacterium The probability that the problems such as bone regeneration around implant chronic inflammation caused by being detained or bone information occurs is soft to maintain bone regeneration around implant The health of sclerous tissues.
In terms of repair and maintenance (R and M), mode of the center with screw openings is also to provide a convenient in the future, and pontic is passively The bonding agent of position adhesion type dummy can the compensatory non-passive stress generated in place well, ensure that planting body and top justice The stability of toothing.
Description of the drawings
Fig. 1 is the structural schematic diagram of the fixing device of planting body superstructure provided in an embodiment of the present invention;
Fig. 2 is the structural schematic diagram of not parallel implant denture maintenance;
Fig. 3 is the screw-cemented retention analogy method and maintenance dress of planting body superstructure provided in an embodiment of the present invention The flow diagram set.
Reference sign:
1- planting bodies, 2- retaining screws one, 3- substrate base stations, the tops 4- base station, 5- retaining screws two, 6- artificial teeth, 7- teeth Slot bone model, 8- gingival models.
Specific implementation mode
With reference to the attached drawing in inventive embodiments, technical solution in the embodiment of the present invention carries out clear, complete Description, it is to be understood that protection scope of the present invention is not restricted by specific implementation.
The present invention provides the screw of planting body superstructure-cemented retention analogy method and fixing device,
Referring to Fig.1, the present invention provides the fixing device of planting body superstructure, including planting body 1,1 tops of planting body Middle part is spirally connected retaining screw 1,1 top edges anchoring base base station 3 of planting body, and 3 upper center of substrate base station is spirally connected maintenance spiral shell Silk 25,3 top edges of substrate base station fix top base station 4,4 top cemented retention artificial tooth 6 of top base station.
With reference to Fig. 2, the present invention provides the structural schematic diagram of not parallel implant denture maintenance, multiple planting bodies 1 pass through tooth Gum model 8 is fixed on alveolus bone model 7, while the top base station 4 of not parallel artificial tooth is carried out mill and is changed, to make the more of reparation A artificial tooth and original tooth are integrally concordant, are more advantageous to mankind's occlusion.
With reference to Fig. 3, the present invention provides the screw of planting body superstructure-cemented retention analogy methods, and specific steps are such as Under:
Step 1, planting body implantation:Several planting bodies are implanted into jawbone model, planting body and jawbone models coupling are made;
Step 2 installs compound base station:Compound base station is installed on planting body, carries out root transfer, top base station of polishing makes More planting body superstructures have common path of insertion, and beveller is used in combination to adjust;
Step 3, modulus record model, make artificial tooth:The model for producing root transfer records the gypsum of planting body root transfer Model makes artificial tooth on the abutment structure of top;
Step 4, artificial tooth cemented retention:The artificial tooth of completion is adhered on the abutment structure of top, waits for bonding agent firmly solid;
Step 5 removes top integral structure artificial tooth:Top abutment structure screw is screwed off, integrated take is removed The artificial tooth of portion's base station, thorough cleaning thereon with the residual bonding agent on the base station of top;
Step 6, screw retained:By the integrated artificial tooth with top base station by screw retained on substrate base station;
Step 7 closes screw hole:Screw hole is closed, artificial tooth is completed.
Embodiment:The screw of planting body superstructure provided by the invention-cemented retention analogy method and fixing device, kind Artificial tooth primary structure is planted by planting body, compound base station (including substrate base station and top base station) and fixed bridge or holder artificial tooth group At.
When making plantation fixed bridge or holder denture prosthesis, it is shown that steps are as follows:
(1), make planting body and jawbone mould by the columnar several planting body implantation jawbone models of the threaded circular of pure titanium first Type combines;.
(2), the mounting substrate base station on planting body, substrate base station are made by pure titanium, taper, height about 2-3mm, polymerization About 6 degree of angle.By pure titanium screw retained on planting body.
(3) and then by top base station by pure titanium screw retained on substrate base station, the high about 4-6mm of top base station, taper, About 15 degree of converging angle, compound base station are the pre- at the compound base station of pure titanium of mechanical processing, and surfaces externally and internally is smooth.
(4), top base station is unloaded after trying on properly, silicon rubber produces stamp in oral cavity, records the transfer of planting body root Anhydrite model, on it mounting substrate base station and top base station.
(5), since various subjective and objective conditions limit, it cannot be substantially parallel between each plantation long axis of body, cause to install thereon Base station it is not parallel.After manual grinding top base station keeps each base station substantially parallel, be placed on beveller carry out it is parallel grind, make each Top base station, which reaches, to be substantially parallel.
(6) and then on the base station of top complete crown fixed bridge or holder artificial tooth are made, wherein the material of complete crown fixed bridge is by gold Belong to porcelain, the full porcelain of zirconium oxide or resin to be made, holder artificial tooth makes holder by cobalt chromium or pure titanium metal, on the base station of top Base is made with heat-curing resin, and puts Albertol's tooth, abutment screw channel is reserved in corona jaw face or preceding corona lingual surface.
(7), base station is retightened on planting body, the fixed bridge to complete or holder artificial tooth is bonded with resin type Agent is bonded and fixed on the base station of top, to be bonded dose of solidification.
(8), artificial tooth is unloaded out of oral cavity by screw, carries out the visualization thorough cleaning of bonding agent, clean-up port intracavitary And artificial tooth and top base station joining place binder.
(9), by with top base station fixed bridge or holder artificial tooth be secured by threads on planting body substrate base station, use Torque wrench is reinforced to 25Ncm, seals screw hole.
(10), abutment screw duct is closed using cotton pellet+temporarily envelope agent, then is sealed hole with resin, completes implant denture It repairs.
In conclusion the present invention simulates the anchoring methods of planting body superstructure, doctor is made to carry out planting body top knot Can be more accurate when structure maintenance, the fixation of planting body superstructure is completed well, while simulation removes composite base outside mouth Extra bonding agent, which is formed by, between platform and artificial tooth overhangs, and reduces the gap of base station and artificial tooth interface, reduces bacterium and is detained institute The probability that the problems such as bone regeneration around implant chronic inflammation or bone information for bringing occurs, to maintain bone regeneration around implant hard and soft tissue Health.
In terms of repair and maintenance (R and M), mode of the center with screw openings is also to provide a convenient in the future, and pontic is passively The bonding agent of position adhesion type dummy can the compensatory non-passive stress generated in place well, ensure that planting body and top justice The stability of toothing.
Disclosed above is only the specific embodiment of the present invention, and still, the embodiment of the present invention is not limited to this, is appointed What what those skilled in the art can think variation should all fall into protection scope of the present invention.

Claims (2)

1. the screw of planting body superstructure-cemented retention analogy method, which is characterized in that be as follows:
Step 1, planting body implantation:Several planting bodies are implanted into jawbone model, planting body and jawbone models coupling are made;
Step 2 installs compound base station:Compound base station is installed on planting body, carries out root transfer, top base station of polishing makes more Planting body superstructure has common path of insertion, and beveller is used in combination to adjust;
Step 3, modulus record model, make artificial tooth:The model for producing root transfer records the plaster mold of planting body root transfer Type makes artificial tooth on the abutment structure of top;
Step 4, artificial tooth cemented retention:The artificial tooth of completion is adhered on the abutment structure of top, waits for bonding agent firmly solid;
Step 5 removes top integral structure artificial tooth:Top abutment structure screw is screwed off, integrated band top base is removed The artificial tooth of platform, thorough cleaning thereon with the residual bonding agent on the base station of top;
Step 6, screw retained:By the integrated artificial tooth with top base station by screw retained on substrate base station;
Step 7 closes screw hole:Screw hole is closed, artificial tooth is completed.
2. the fixing device of planting body superstructure, which is characterized in that including multiple planting bodies (1), above the planting body (1) Middle part is spirally connected retaining screw one (2), planting body (1) the top edges anchoring base base station (3), on the substrate base station (3) Be spirally connected retaining screw two (5) in the middle part of side, and substrate base station (3) top edges fix top base station (4), the top base station (4) top cemented retention artificial tooth (6), the planting body (1) are fixed on across gingival model (8) on alveolus bone model (7), simultaneously The top base station (4) of not parallel artificial tooth is carried out mill to change, the multiple artificial teeth and original tooth to make reparation are integrally concordant, more have It is engaged conducive to the mankind.
CN201810367229.7A 2018-04-23 2018-04-23 The screw of planting body superstructure-cemented retention analogy method and fixing device Pending CN108403244A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810367229.7A CN108403244A (en) 2018-04-23 2018-04-23 The screw of planting body superstructure-cemented retention analogy method and fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810367229.7A CN108403244A (en) 2018-04-23 2018-04-23 The screw of planting body superstructure-cemented retention analogy method and fixing device

Publications (1)

Publication Number Publication Date
CN108403244A true CN108403244A (en) 2018-08-17

Family

ID=63136276

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810367229.7A Pending CN108403244A (en) 2018-04-23 2018-04-23 The screw of planting body superstructure-cemented retention analogy method and fixing device

Country Status (1)

Country Link
CN (1) CN108403244A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110368114A (en) * 2019-08-05 2019-10-25 四川大学 With the digitalized design method for repairing screw hole at inlay closing Dental implantion top in advance
CN110942573A (en) * 2020-01-02 2020-03-31 东南大学 Self-detection type artificial dental implant alarm

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1750796A (en) * 2003-03-13 2006-03-22 许永九 Method for treating a screw-cement retained prosthesis, abutment for a screw-cement retained prosthesis
CN102499770A (en) * 2011-11-25 2012-06-20 同济大学 Manufacturing method of upper structure of screw-retained implant
CN203943753U (en) * 2013-12-26 2014-11-19 比亚迪股份有限公司 Dental implant
CN104602642A (en) * 2012-08-13 2015-05-06 凯姆洛格生物科技股份公司 Secondary part, set, dental implant, gingiva shaper, impression part, dental implant system, and method for producing an implant
WO2016005045A1 (en) * 2014-07-11 2016-01-14 Frank Löring Dentaltechnik GmbH Implant system and implant

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1750796A (en) * 2003-03-13 2006-03-22 许永九 Method for treating a screw-cement retained prosthesis, abutment for a screw-cement retained prosthesis
CN102499770A (en) * 2011-11-25 2012-06-20 同济大学 Manufacturing method of upper structure of screw-retained implant
CN104602642A (en) * 2012-08-13 2015-05-06 凯姆洛格生物科技股份公司 Secondary part, set, dental implant, gingiva shaper, impression part, dental implant system, and method for producing an implant
CN203943753U (en) * 2013-12-26 2014-11-19 比亚迪股份有限公司 Dental implant
WO2016005045A1 (en) * 2014-07-11 2016-01-14 Frank Löring Dentaltechnik GmbH Implant system and implant

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110368114A (en) * 2019-08-05 2019-10-25 四川大学 With the digitalized design method for repairing screw hole at inlay closing Dental implantion top in advance
CN110368114B (en) * 2019-08-05 2021-06-22 四川大学 Digital design method for closing dental implant upper repair screw hole by preformed inlay
CN110942573A (en) * 2020-01-02 2020-03-31 东南大学 Self-detection type artificial dental implant alarm
CN110942573B (en) * 2020-01-02 2022-01-25 东南大学 Self-detection type artificial dental implant alarm

Similar Documents

Publication Publication Date Title
US9801697B2 (en) Integrated support device for providing temporary primary stability to dental implants and prosthesis, and related methods
Weigl et al. Advanced biomaterials used for a new telescopic retainer for removable dentures: ceramic vs. electroplated gold copings: part II. Clinical effects
US20130209961A1 (en) Dental Implant Assembly, Implant, and Prosthesis to Replace a Nonfunctional Natural Tooth and Related Methods
CN106725946A (en) The method for prefabricating and application method of a kind of Dental implant surgery provisional prosthesis
Fabbri et al. The full-mouth mock-up: a dynamic diagnostic approach (DDA) to test function and esthetics in complex rehabilitations with increased vertical dimension of occlusion
CN111658195A (en) Multifunctional tray for dental implantation double-scanning matching and jaw position recording and use method
CN108403244A (en) The screw of planting body superstructure-cemented retention analogy method and fixing device
Ghodsi et al. Oral rehabilitation of a patient with amelogenesis imperfecta using removable overlay denture: a clinical report
CN102499770B (en) Manufacturing method of upper structure of screw-retained implant
CN112386344B (en) Elastic veneered bridge and preparation method thereof
Smielak " No-preparation" and Minimally Invasive Veneers in Clinical Practice: Part 1.
Watson et al. Implant complications and failures: the single-tooth restoration
Cofar et al. Contemporary Planning Tools for Restoration of Congenitally Missing Maxillary Lateral Incisors
EP2816967A2 (en) Dental implant assembly, implant, prosthesis to replace a nonfunctional natural tooth, integrated support device for providing temporary primary stability to dental implants and prosthesis, and related methods
CN206355158U (en) Reinforced screw retained plants supporting dummy
CN218515822U (en) A record base station for planting implant occlusion record
CN115531015B (en) Manufacturing method of dentition gap orthodontic adjusting guide plate
Hegenbarth Use of the Procera CAD/CAM System for Metal-free Crowns on Single-Tooth Implants.
Chio et al. Restoration of two implants using custom abutments and transverse screw-retained zirconia crowns
RU2331387C1 (en) Method of restoration of group of frontal teeth of upper jaw using reinforcing framework-contour elements when eliminating defects of tooth replacement with metal-ceramic crowns
US20230112706A1 (en) Prosthetic tooth or denture base
Abrol et al. Prosthodontic management of sub-total maxillectomy: A case report
KR20100136670A (en) Implants pfm frame manufacfuring method
RU2693220C1 (en) Method of direct dental implantation
Wöhrle et al. CONTEMPORARY MAXILLARY IMPLANT-SUPPORTED FULL-ARCH RESTORATIONS COMBINING ESTHETICS AND PASSIVE FIT.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817