CN108386327A CN201810385174.2A CN201810385174A CN108386327A CN 108386327 A CN108386327 A CN 108386327A CN 201810385174 A CN201810385174 A CN 201810385174A CN 108386327 A CN108386327 A CN 108386327A
Authority
CN
China
Prior art keywords
awning
cloth
stainless steel
sheet
wind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810385174.2A
Other languages
Chinese (zh)
Other versions
CN108386327B (en
Inventor
詹耀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MingYang Smart Energy Group Co Ltd
Original Assignee
MingYang Smart Energy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MingYang Smart Energy Group Co Ltd filed Critical MingYang Smart Energy Group Co Ltd
Priority to CN201810385174.2A priority Critical patent/CN108386327B/en
Publication of CN108386327A publication Critical patent/CN108386327A/en
Application granted granted Critical
Publication of CN108386327B publication Critical patent/CN108386327B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D80/00Details, components or accessories not provided for in groups F03D1/00 - F03D17/00
    • F03D80/50Maintenance or repair
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Tents Or Canopies (AREA)

Abstract

Top protection structure and its laying method after two sections are erect the invention discloses a kind of lifting of wind-power tower, including awning sheet, stainless steel paulin circle waterproof awning cloth, stretch rubber waterproof awning cloth, awning sheet is the circular enclosure to match at the top of shape size and the second section tower segments, stainless steel paulin circle waterproof awning cloth sews the internal layer in awning sheet, and there are multiple stainless steel Peng Quan in the came of stainless steel paulin circle waterproof awning cloth, use rope made of hemp one end strapped respectively in the hole of multiple stainless steel Peng Quan, stretching rubber waterproof awning cloth, vertically sewing is formed as straight-tube shape in the circumferential edges of awning sheet, and it is sewed with stretching rubber band in the internal layer for stretching rubber waterproof awning cloth, the stretching rubber waterproof awning cloth when being laid with is enable to be close to be attached to the circular outer wall surface at the top of the second section tower segments by the stretching rubber band in sewing.The protection questions such as rainwater-proof, anti-dust and anticorrosion of the present invention for wind power plant after two section tower segments of lifting have operability and realistic meaning.

Description

Top protection structure after two section of wind-power tower lifting setting and its laying method
Technical field
The present invention relates to the technical field of wind-power tower protection, refer in particular to after a kind of lifting of wind-power tower erects two sections Top protection structure and its laying method.
Background technology
Currently, the wind-power electricity generation project of domestic and international Devoting Major Efforts To Developing and construction green, however the erector of wind power generating set Journey project (including marine and land wind power generating set installing engineering project) erects two in lifting due to cause specific and saves towers Cylinder after need prolonged shutdowns for a period of time, and lifting stop work this period of time in, lifted setting two section towers by It is exposed at the top of it to be subject to inside the erosion to tower of the substances such as rainwater, dust, lead to the equipment inside tower and zero The corrosion and damage of component, cause certain property and economic loss.In order to avoid the generation of such loss phenomenon, need Protection is carried out after erectting two sections for tower lifting.For this purpose, preventing in the two section tower downtime of lifting in view of wind field The protections such as rainwater, anti-dust and anticorrosion need, and in view of being common to marine and land high-power such as 1.5MW-6.0MW Wind power generating set lifting erect two section towers after the protection of engineering downtime, now be badly in need of devise one kind can be effective The top protection structure after two sections is erect for wind-power tower lifting.
Invention content
The shortcomings that it is an object of the invention to overcome the prior art and deficiency, it is proposed that a kind of reliable wind-power tower lifting Top protection structure and its laying method after two sections are erect, the marine and land high-power wind such as 1.5MW-6.0MW is suitable for Top protection protection of the power generator group after two section tower segments are erect in lifting, this structure is for wind power plant in two section tower of lifting The protection questions such as rainwater-proof, anti-dust and anticorrosion after section have operability and realistic meaning.
To achieve the above object, technical solution provided by the present invention is:
The top protection structure after two sections is erect in wind-power tower lifting, includes awning sheet, stainless steel paulin circle rain-proof Tarpaulin stretches rubber waterproof awning cloth, wherein the awning sheet is to match at the top of shape size and the second section tower segments Circular enclosure, the stainless steel paulin circle waterproof awning cloth sew the internal layer in awning sheet, and in stainless steel paulin circle waterproof awning cloth Came has multiple stainless steel Peng Quan, uses rope made of hemp one end strapped respectively in the hole of multiple stainless steel Peng Quan, the stretching rubber Vertically sewing is formed as straight-tube shape to skin waterproof awning cloth in the circumferential edges of awning sheet, and is stretching rubber waterproof awning cloth Internal layer is sewed with stretching rubber band, enables the stretching rubber waterproof awning cloth when being laid with tight by the stretching rubber band in sewing The circular outer wall surface being attached at the top of the second section tower segments.
The awning sheet uses thickness to be sewed for the polyvinyl chloride plastic-coated canvas of 1-2mm, a diameter of 4.5-4.6m, material Matter parameter is:Tensile strength warp-wise >=2000N/50mm, broadwise >=1600N/50mm, warp-wise, broadwise tear resistance >=80N, Elongation at break≤30% of warp-wise, broadwise, anti-water penetration >=30KPa/min, temperature >=-25 DEG C of resisting cold, when having flame combustion Between≤10 seconds;The color of awning sheet is RAL5015, i.e. sky blue, the pvc coating on surface is answered uniformity, do not had Hole, caking, degumming, deadfold and open defect.
Stretching resistance >=950N of the stainless steel Peng Quan is slightly respectively with 1 meter long, rope in the hole of multiple stainless steel Peng Quan Rope made of hemp one end of 10-20mm is strapped.
The width for stretching rubber band is 200-300mm.
The awning sheet is sewn into straight-tube shape and stainless steel paulin circle waterproof awning cloth seam with rubber waterproof awning cloth is stretched Make the internal layer in awning sheet, all sewing tech all use bound edge sewing, and bound edge sewing answer it is straight, no run-bake-needle fault broken string, Without flotation line defect, sewing is connected firmly, and the back stitching number at starting and only needle is no less than 3 needles, and needle code is not less than 18 needles/100mm.
The laying method of the top protection structure after two sections is erect in above-mentioned wind-power tower lifting, is included the following steps:
1) it is slightly first diameter 10-20mm with 3 ropes, a length of 5 meters of rope made of hemp passes through the second section tower before waterproof awning cloth being installed The bolt hole of cylinder section upper flange surface is fixed, and specifically from the upper surface of bolt hole, wire rope handling, 3 ropes made of hemp are interconnected to " * " type down Rope made of hemp frame is fastened as knot at this " * " type rope made of hemp frame central intersection point, and the rope made of hemp must tense and fixation, this " * " type rope made of hemp Frame is the awning sheet covered for support top and bears weight of the rain water-harvesting on awning sheet, prevents from spreading If awning sheet be collapsed damage.
2) awning sheet is spread since the platform of the second section tower segments exports the flange on opposite towards both sides above and below If being fixed on the rope made of hemp other end on stainless steel paulin circle waterproof awning cloth when laying, wire rope handling is consolidated down from the upper surface of flange bolt hole It is scheduled on bolt hole, and side fixed edge to the movement of platform exit and fixes awning sheet;
3) it is laid with the stretching rubber waterproof awning cloth of awning sheet outer ring, awning sheet should be depended on and be close to by when laying On the outer circumferential walls surface of the second section tower segments, rubber waterproof awning cloth will be stretched and pushed toward the lower part of tower drum outer wall, to make drawing The outer circumferential walls surface stretched the stretching, extension of rubber waterproof awning cloth and be tightly attached at the top of the second section tower segments;
4) after the completion of the fixation and laying of entire awning sheet, the outlet of the second section tower segments platform can be opened Cover board is simultaneously climbed down from this safety, and shuts tower door, so far just completes the laying of entire top protection protection structure.
When fixing rope on the second section tower segments top platform and being laid with waterproof awning cloth operation, the tower of tower bottom is closed Tube door avoids the air inlet of tower door and stack effect that from may influencing and is laid with and fixes awning at the top of the second section tower segments Cloth, and the good upper and lower Outlet cover plate for often saving tower segments platform is closed, prevent object falling accident.
Compared with prior art, the present invention having the following advantages that and advantageous effect:
Offshore wind farm project and land Wind Power Project are needed due to cause specific after the section tower segments are erect in wind field lifting It stops work and lifts follow-up tower and host again for a period of time, prevent in the lifting the section tower segments downtime to carry out wind field The safeguard measures such as rainwater, anti-dust and anticorrosion.Therefore purposefully it is directed to marine and land high-power such as 1.5MW-6.0MW Engineering downtime protection of the wind power generating set after two section tower segments are erect in lifting, devises a kind of reliable wind-powered electricity generation The top protection structure after two sections and its laying method are erect in tower lifting, this structure be suitable for 1.5MW-6.0MW etc. it is marine and Top protection protection of the land high-power wind-driven generator group after two section tower segments are erect in lifting has rain-proof and dust-proof etc. The advantages that protection effect is good, and laying construction is easy, and the cost of material is low, and reusable, the two section towers erect for lifting Section due to its top it is exposed be subject to inside the erosion to tower of the substances such as rainwater, dust, avoid wind-powered electricity generation parts by The salt air corrosion and destruction of climatic environment advantageously promote green, the construction of clean marine and land wind power resources and health Development has positive social effect and economic implications.
Description of the drawings
Fig. 1 is the schematic diagram that structure of the invention is mounted at the top of the second section tower segments.
Fig. 2 is the A partial enlarged views of Fig. 1.
Fig. 3 is the design sketch that structure of the invention is mounted at the top of the second section tower segments.
Fig. 4 is the partial sectional view of structure of the invention.
Fig. 5 is the B partial enlarged views of Fig. 4.
Fig. 6 is the C partial enlarged views of Fig. 4.
Fig. 7 is 3 ropes made of hemp and (it is numb that 3 ropes made of hemp are interconnected to " * " type to the connection diagram of the second section atop a tower flange Rope support).
Fig. 8 is 3 ropes made of hemp and (it is numb that 3 ropes made of hemp are interconnected to " * " type to the connection effect figure of the second section atop a tower flange Rope support).
Specific implementation mode
The present invention is further explained in the light of specific embodiments.
Top protection structure after two section of wind-power tower lifting setting that the present embodiment is provided can be effectively used for sea turn The top protection protection of electric installing engineering and land installation wind energy project after two sections are erect in tower barrel of wind generating set lifting, is fitted The high-power wind-driven generator group (different tower diameter) marine and land for 1.5MW-6.0MW etc. erects two section towers in lifting Top protection protection after cylinder section.As shown in Figures 1 to 6, the top protection structure includes:Awning sheet 1, stainless steel paulin It encloses waterproof awning cloth 2, stretch 3 three parts of rubber waterproof awning cloth.Wherein, the awning sheet 1 be use thickness for 1-2mm, The polyvinyl chloride plastic-coated canvas of a diameter of 4.5-4.6m sews, and awning sheet 1 and stainless steel paulin circle waterproof awning cloth 2 and drawing It stretches rubber waterproof awning cloth 3 and is sewn into round, straight-tube shape protective roof structure jointly.The stainless steel paulin circle waterproof awning cloth 2 is seam The internal layer in awning sheet 1 is made, there are 36 stainless steel paulin circles 21 in the came of stainless steel paulin circle waterproof awning cloth 2, it is stainless Stretching resistance >=950N of steel paulin circle 21 with 1 meter long, rope is respectively slightly the rope made of hemp of 10-20mm in the hole of 36 stainless steel paulin circles 21 22 one end are strapped.Vertically sewing forms straight-tube shape to the stretching rubber waterproof awning cloth 3 in the circumferential edges of awning sheet 1, and And it is sewed with the stretching rubber band 31 that width is 200-300mm in the internal layer for stretching rubber waterproof awning cloth 3, it stretches rubber band 31 and has There are certain retractility and elasticity, rubber waterproof awning cloth 3 is stretched when being laid with can be close to be attached to 4 top of the second section tower segments Circular outer wall surface.The awning sheet 1 is sewn into straight-tube shape and stainless steel paulin circle rain-proof with rubber waterproof awning cloth 3 is stretched Tarpaulin 2 sews the internal layer in awning sheet 1, and all sewing tech all use bound edge sewing, does not allow to use other sewing works Skill and connection type, bound edge sewing answer it is straight, no run-bake-needle fault broken string, without flotation line the defects of, sewing is connected firmly.At starting and only needle Back stitching number be no less than 3 needles, needle code is not less than 18 needles/100mm.In addition, the material parameters of polyvinyl chloride plastic-coated canvas are:It stretches Intensity >=2000N/50mm (warp-wise), >=1600N/50mm (broadwise), tear resistance >=80N (warp-wise, broadwise), elongation at break There are flaming combustion time≤10 second in≤30% (warp-wise, broadwise), anti-water penetration >=30KPa/min, temperature >=-25 DEG C of resisting cold.It applies The color for moulding canvas is RAL5015 (sky blue), and the pvc coating on plastic-coated canvas surface answers uniformity, without hole, The defects of caking, degumming, deadfold and breakage.
It is the laying method of the above-mentioned top protection structure of the present embodiment below, specially:
1) before installing waterproof awning cloth, first be slightly diameter 10-20mm with 3 ropes, a length of 5 meters of rope made of hemp 5 passes through the second section The bolt hole of tower segments upper flange surface 41 is fixed (from the upper surface of bolt hole wire rope handling down), and 3 ropes made of hemp 5 are interconnected to " * " type Rope made of hemp frame is fastened as knot, and the rope made of hemp 5 must be tensed and be fixed at this " * " type rope made of hemp frame central intersection point as shown in Figure 7 and Figure 8 Securely.This " * " type rope made of hemp frame is the awning sheet covered for support top and bears rain water-harvesting in awning sheet On weight, prevent be laid with awning sheet be collapsed damage.
2) awning sheet is spread since the platform of the second section tower segments exports the flange on opposite towards both sides above and below If being fixed on the rope made of hemp other end of " stainless steel paulin circle waterproof awning cloth " when laying, wire rope handling is solid down from the upper surface of flange bolt hole It is scheduled on bolt hole, side fixed edge is to the movement of platform exit and fixes awning sheet.
3) this awning sheet should be depended in " the stretching rubber waterproof awning cloth " for being laid with awning sheet outer ring and tightly It is attached to the outer circumferential walls surface of the second section tower segments, when laying, which can borrow hand or waddy etc., " will stretch rubber waterproof awning cloth " toward tower The lower part of drum outer wall pushes, to make this " stretching rubber waterproof awning cloth " stretching, extension and to be tightly attached to outside the circumference of the second section atop a tower Wall surface is laid with shown in the result is shown in Figure 1 completed.
4) after the completion of the fixation and laying of entire awning sheet, the Outlet cover plate of the second section tower barrel platform can just be opened And climbed down from this safety, and shut tower door.So far the laying of entire top protection protection structure is just completed.
Remarks:When fixing rope on the second section atop a tower platform and being laid with waterproof awning cloth operation, tower bottom is closed Tower door, avoid the air inlet of tower door and stack effect that from may influencing and be laid with and fixed awning in the second section atop a tower Cloth, and close the good Outlet cover plate up and down for often saving tower barrel platform prevents object and the accidents such as falls.
Embodiment described above is only the preferred embodiments of the invention, and but not intended to limit the scope of the present invention, therefore Change made by all shapes according to the present invention, principle, should all cover within the scope of the present invention.

Claims (7)

1. the top protection structure after two sections is erect in wind-power tower lifting, it is characterised in that:Include awning sheet, stainless steel Paulin circle waterproof awning cloth stretches rubber waterproof awning cloth, wherein the awning sheet is at the top of shape size and the second section tower segments The circular enclosure to match, the stainless steel paulin circle waterproof awning cloth sew the internal layer in awning sheet, and anti-in stainless steel Peng Quan The came of canopy cloth has multiple stainless steel Peng Quan, uses rope made of hemp one end strapped respectively in the hole of multiple stainless steel Peng Quan, institute Stating stretching rubber waterproof awning cloth, vertically sewing is formed as straight-tube shape in the circumferential edges of awning sheet, and anti-stretching rubber The internal layer of canopy cloth is sewed with stretching rubber band, makes to stretch rubber awning when being laid with by the stretching rubber band in sewing Cloth can be close to be attached to the circular outer wall surface at the top of the second section tower segments.
2. the top protection structure after two sections is erect in wind-power tower lifting according to claim 1, it is characterised in that:It is described Awning sheet uses thickness to be sewed for the polyvinyl chloride plastic-coated canvas of 1-2mm, a diameter of 4.5-4.6m, and material parameters are:It draws Stretch intensity warp-wise >=2000N/50mm, broadwise >=1600N/50mm, warp-wise, broadwise tear resistance >=80N, warp-wise, broadwise There are flaming combustion time≤10 second in elongation at break≤30%, anti-water penetration >=30KPa/min, temperature >=-25 DEG C of resisting cold;It is anti- The color of canopy sheet is RAL5015, i.e. sky blue, the pvc coating on surface answers uniformity, without hole, knot Block, degumming, deadfold and open defect.
3. the top protection structure after two sections is erect in wind-power tower lifting according to claim 1, it is characterised in that:It is described Stretching resistance >=950N of stainless steel Peng Quan with 1 meter long, rope is respectively slightly the fiber crops of 10-20mm in the hole of multiple stainless steel Peng Quan Rope one end is strapped.
4. the top protection structure after two sections is erect in wind-power tower lifting according to claim 1, it is characterised in that:It is described The width for stretching rubber band is 200-300mm.
5. the top protection structure after two sections is erect in wind-power tower lifting according to claim 1, it is characterised in that:It is described Awning sheet is sewn into straight-tube shape and the sewing of stainless steel paulin circle waterproof awning cloth in waterproof awning cloth with rubber waterproof awning cloth is stretched The internal layer of cover, all sewing tech all use bound edge sewing, and bound edge sewing answers straight, no run-bake-needle fault broken string, without flotation line defect, seam System is connected firmly, and the back stitching number at starting and only needle is no less than 3 needles, and needle code is not less than 18 needles/100mm.
6. the laying method of the top protection structure after two sections is erect in wind-power tower lifting described in claim 1, which is characterized in that Include the following steps:
1) it is slightly first diameter 10-20mm with 3 ropes, a length of 5 meters of rope made of hemp passes through the second section tower segments before waterproof awning cloth being installed The bolt hole of upper flange surface is fixed, and specifically from the upper surface of bolt hole, wire rope handling, 3 ropes made of hemp are interconnected to " * " type rope made of hemp down Frame is fastened as knot at this " * " type rope made of hemp frame central intersection point, and the rope made of hemp must tense and fixation, this " * " type rope made of hemp frame is For support top covering awning sheet and bear weight of the rain water-harvesting on awning sheet, prevent be laid with Awning sheet is collapsed damage.
2) awning sheet is laid with since the platform of the second section tower segments exports the flange on opposite towards both sides above and below, is spread If when will be fixed on the rope made of hemp other end on stainless steel paulin circle waterproof awning cloth, from the upper surface of flange bolt hole, wire rope handling is fixed on down On bolt hole, and side fixed edge to the movement of platform exit and fixes awning sheet;
3) it is laid with the stretching rubber waterproof awning cloth of awning sheet outer ring, awning sheet should be depended on and be tightly attached to the by when laying The outer circumferential walls surface of two section tower segments will stretch rubber waterproof awning cloth and be pushed toward the lower part of tower drum outer wall, to make stretching rubber The outer circumferential walls surface that skin waterproof awning cloth is stretched and is tightly attached at the top of the second section tower segments;
4) after the completion of the fixation and laying of entire awning sheet, the Outlet cover plate of the second section tower segments platform can be opened And climbed down from this safety, and tower door is shut, so far just complete the laying of entire top protection protection structure.
7. the laying method of the top protection structure after two sections is erect in wind-power tower lifting according to claim 6, special Sign is:When fixing rope on the second section tower segments top platform and being laid with waterproof awning cloth operation, the tower of tower bottom is closed Tube door avoids the air inlet of tower door and stack effect that from may influencing and is laid with and fixes awning at the top of the second section tower segments Cloth, and the good upper and lower Outlet cover plate for often saving tower segments platform is closed, prevent object falling accident.
CN201810385174.2A 2018-04-26 2018-04-26 Top protection structure for wind power tower after hoisting and erecting two sections and laying method thereof Active CN108386327B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810385174.2A CN108386327B (en) 2018-04-26 2018-04-26 Top protection structure for wind power tower after hoisting and erecting two sections and laying method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810385174.2A CN108386327B (en) 2018-04-26 2018-04-26 Top protection structure for wind power tower after hoisting and erecting two sections and laying method thereof

Publications (2)

Publication Number Publication Date
CN108386327A true CN108386327A (en) 2018-08-10
CN108386327B CN108386327B (en) 2024-03-26

Family

ID=63065576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810385174.2A Active CN108386327B (en) 2018-04-26 2018-04-26 Top protection structure for wind power tower after hoisting and erecting two sections and laying method thereof

Country Status (1)

Country Link
CN (1) CN108386327B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109756798A (en) * 2018-12-24 2019-05-14 广州奥丁诺科技有限公司 A kind of universal water-tight device based on outdoor loudspeaker
EP4177420A1 (en) * 2021-11-08 2023-05-10 Christin Jensen Covering device

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1502357A (en) * 1975-09-29 1978-03-01 Maiken F Umbrella tent
US6051812A (en) * 1998-11-16 2000-04-18 Walker; Lawrence Snow and ice melting blanket device
US20040178650A1 (en) * 2003-03-10 2004-09-16 Edscha Lkw-Schiebeverdecke Gmbh Covering for utility vehicle superstructures
CN202157919U (en) * 2011-07-22 2012-03-07 邓允河 Rainproof and dustproof tower column of vertical wind power generator
CN202493388U (en) * 2012-04-09 2012-10-17 南车株洲电力机车研究所有限公司 Wind driven generator unit engine room protecting device
DE102013002886B3 (en) * 2013-02-19 2014-03-27 Gerhard Lehmann Device for driving on tower and/or tower-like structures e.g. wind turbines, has tubular connection profile with setting profile whose ends are provided with self-powered trolley, and guide roller that guides setting profile
WO2015039777A1 (en) * 2013-09-20 2015-03-26 Nordex Energy Gmbh Variable protective roof
CN204877805U (en) * 2015-07-29 2015-12-16 华北电力大学 A removable fraction wind generating set tower section of thick bamboo
CN205277708U (en) * 2015-12-30 2016-06-01 江苏金风科技有限公司 Top sealed cowling of a section tower section of thick bamboo at bottom of offshore wind power generation unit
CN208310966U (en) * 2018-04-26 2019-01-01 明阳智慧能源集团股份公司 The top protection structure after two sections is erect in a kind of lifting of wind-power tower

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1502357A (en) * 1975-09-29 1978-03-01 Maiken F Umbrella tent
US6051812A (en) * 1998-11-16 2000-04-18 Walker; Lawrence Snow and ice melting blanket device
US20040178650A1 (en) * 2003-03-10 2004-09-16 Edscha Lkw-Schiebeverdecke Gmbh Covering for utility vehicle superstructures
CN202157919U (en) * 2011-07-22 2012-03-07 邓允河 Rainproof and dustproof tower column of vertical wind power generator
CN202493388U (en) * 2012-04-09 2012-10-17 南车株洲电力机车研究所有限公司 Wind driven generator unit engine room protecting device
DE102013002886B3 (en) * 2013-02-19 2014-03-27 Gerhard Lehmann Device for driving on tower and/or tower-like structures e.g. wind turbines, has tubular connection profile with setting profile whose ends are provided with self-powered trolley, and guide roller that guides setting profile
WO2015039777A1 (en) * 2013-09-20 2015-03-26 Nordex Energy Gmbh Variable protective roof
CN204877805U (en) * 2015-07-29 2015-12-16 华北电力大学 A removable fraction wind generating set tower section of thick bamboo
CN205277708U (en) * 2015-12-30 2016-06-01 江苏金风科技有限公司 Top sealed cowling of a section tower section of thick bamboo at bottom of offshore wind power generation unit
CN208310966U (en) * 2018-04-26 2019-01-01 明阳智慧能源集团股份公司 The top protection structure after two sections is erect in a kind of lifting of wind-power tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109756798A (en) * 2018-12-24 2019-05-14 广州奥丁诺科技有限公司 A kind of universal water-tight device based on outdoor loudspeaker
EP4177420A1 (en) * 2021-11-08 2023-05-10 Christin Jensen Covering device

Also Published As

Publication number Publication date
CN108386327B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
CN208310966U (en) The top protection structure after two sections is erect in a kind of lifting of wind-power tower
CN108386327A (en) Top protection structure after two section of wind-power tower lifting setting and its laying method
CN107843456A (en) A kind of float type water source sampling device for environment measuring
CN208470081U (en) Marine concentrating type floats wind power platform
CN205077972U (en) Tendril climbing device is prevented to circuit
CN104410349B (en) Intelligent sail type over-water floating solar power station
CN103636534B (en) Fish barriering and escape preventing device suitable for riverway type reservoir and management and maintenance method thereof
CN209652971U (en) A kind of compound bucket foundation Anti-scouring device of offshore wind farm
CN108064781A (en) A kind of electric hydraulic elevation type aquaculture net cage based on compound bucket foundation
CN205945592U (en) Showy formula photovoltaic power plant on water
CN206845396U (en) A kind of offshore wind energy plant
JP6894406B2 (en) How to install the rain pit in the tank pit and the rain pit in the tank pit
CN209093714U (en) The adjustable funnel of dry-type air-core reactor total incapsulation process for protecting technology
CN210517738U (en) Cable trench cover plate
CN213235335U (en) Wind driven generator cabin type-following rainproof cover
CN208619085U (en) A kind of oilfield downhole operation clean manufacturing macromolecule software platform
CN209143866U (en) A kind of high reliability ocean engineering collection fresh water equipment
CN207399111U (en) solar panel supporting structure
CN206596452U (en) Umbrella curtain and multifunction protection canopy
CN109537622A (en) A kind of compound bucket foundation Anti-scouring device of offshore wind farm
CN206156339U (en) A sealing device , tower shell ring section and a tower section of thick bamboo for column is hollow
CN211470187U (en) Modified asphalt cold winding belt winding device
CN113924973B (en) Folding laver cultivation device
CN204919547U (en) Outer anchor head steel strand wires protection device of anchor rope
CN204850672U (en) Portable simple and easy construction canopy

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant