CN108385723A - A kind of construction method of prefabricated piping lane deformation joint connection structure - Google Patents

A kind of construction method of prefabricated piping lane deformation joint connection structure Download PDF

Info

Publication number
CN108385723A
CN108385723A CN201810251925.1A CN201810251925A CN108385723A CN 108385723 A CN108385723 A CN 108385723A CN 201810251925 A CN201810251925 A CN 201810251925A CN 108385723 A CN108385723 A CN 108385723A
Authority
CN
China
Prior art keywords
piping lane
deformation joint
nailing
waterproof roll
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810251925.1A
Other languages
Chinese (zh)
Inventor
刘义博
王雨
夏庆秋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201810251925.1A priority Critical patent/CN108385723A/en
Publication of CN108385723A publication Critical patent/CN108385723A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Building Environments (AREA)

Abstract

The invention discloses a kind of construction method of prefabricated piping lane deformation joint connection structure, construction procedure is:First prefabricated piping lane, then held out against using jack, the slip casting cementation of fissures, deformation joint is sealed using waterproof roll nailing, then cement protective layer is arranged in outer wall deformation joint.The construction method construction is simple, efficient of the present invention need to only use mating tool operation that can be easily accomplished, time saving, laborsaving, disposably install successfully, the excavation for reducing earth volume, shortening the duration thus greatly reduces construction cost, and ensure that construction quality.

Description

A kind of construction method of prefabricated piping lane deformation joint connection structure
Technical field
The invention belongs to pipe gallery technical field of construction in municipal works, and in particular to a kind of prefabricated piping lane deformation joint company The construction method of binding structure.
Background technology
Currently, prefabricated piping lane deformation joint connection structure has been used for municipal administration now as a kind of novel piping lane construction method Pipe gallery technical field of construction in engineering.Prefabricated piping lane is compared with cast-in-place piping lane is constructed:Earthwork excavated volume is small, and short time limit subtracts Few noise pollution, piping lane section concrete maintenance quality is high, and connection method generally uses buried water strip, welding waterstop.And Buried water strip needs to use sweat soldering, and sweat soldering power consumption, consumptive material are uneconomical, and speed of application is slow, and technological requirement is high, construction Dangerous, welding quality is also difficult to ensure.The construction method for how improving prefabricated piping lane deformation joint connection structure is anxious at this stage It need to solve the problems, such as.
Invention content
The present invention provides a kind of construction method of prefabricated piping lane deformation joint connection structure, is held out against using jack, and slip casting fills Seam, the sealing of waterproof roll nailing, entire constructing operation are convenient, convenient.
The specific technical solution of the present invention is:A kind of construction method of prefabricated piping lane deformation joint connection structure, construction procedure It is as follows:
1) it is required according to detail design, it is prefabricated with certain specification size piping lane section in pre-fabricated factory;In prefabricated piping lane section Four reserving hole channels are reserved on four angles of cross section, are prepared for subsequent steel strand tension;
2) before constructing, rubber ring is installed on the reserved location for being inserted into piping lane section, then by prefabricated piping lane adjacent two-by-two Section is held out against by jack, the steel strand wires in four reserving hole channels of tensioning and slurry seal anchoring;
3) start the seam construction of piping lane inner wall deformation:Top, side wall first at piping lane inner wall deformation seam, bottom high pressure Slip casting machine slip casting, with quick grout off;It paves waterproof roll in deformation joint, waterproof roll both ends are positioned over advance indwelling Groove in, fixed with method of powder actuated shot, in nailing groove with nailing sealing compound sealing after, the waterproof that paves above pre-groove volume Material;
4) start piping lane outer wall deformation joint construction:It is noted with high-pressure grout injector in the top of piping lane outer wall, side wall deformation joint Slurry, with quick grout off;It paves waterproof roll in deformation joint, waterproof roll both ends are positioned over the groove of advance indwelling In, it is fixed, is sealed with nailing sealing compound in nailing groove, pave waterproof roll above pre-groove with method of powder actuated shot;
5) cement protective layer is set in the deformation joint of piping lane outer wall, cement protective layer is covered on waterproof roll as guarantor Sheath.
Further, top, side wall, bottom of the step 3) at piping lane inner wall deformation seam are noted with high-pressure grout injector Before slurry, temporary baffle is set, removes temporary baffle after slip casting grouting behind shaft or drift lining material has certain intensity, is sealed with quick cement It is stifled.
Further, the step 3) 4) in nailing fix waterproof roll, nailing fixed point away from coil edge 20mm at, Nailing pitch of nails is 500-800mm, and nail is long to be more than 30mm.
Further, the step step 3) 4) in, nailing needs complexed metal gasket and thermoplasticity circular washer by waterproof Layer is fixed in substrate surface, and metal gasket diameter is more than 20mm, double more than 100mm with diameter at reserved groove nailing position Waterproof roll piece sealing is glued in face reaction.
Further, the waterproof roll uses cps waterproof rolls.
Compared with prior art, beneficial effects of the present invention are:
1) present invention in prefabricated piping lane section size it is small, it is light-weight be readily transported, store facilitate, will not be made because of transportation problem At damage;
2) live sweat soldering is can completely avoid in the method for the present invention construction, reduces the input of manpower and materials, also avoids The construction problem caused by welding quality;
3) construction method step of the invention is simple, and mounting process is simple, does not need huge tool equipment, time saving, laborsaving, It disposably installs successfully, and greatly reduces construction cost, ensure construction quality, improve the safety coefficient of construction personnel.
Description of the drawings
Fig. 1 is single prefabricated piping lane section schematic diagram in the present invention.
Fig. 2 is piping lane top plate, side wall side structure connection diagram.
Fig. 3 is thin portion structure enlargement diagram in Fig. 2.
Fig. 4 is piping lane bottom plate side structure connection diagram.
Fig. 5 is thin portion structure enlargement diagram in Fig. 4.
In figure:1, waterproof roll;2, nailing sealing compound;3, nailing;4, metal gasket;5, thermoplasticity circular washer washer;6、 Rubber ring;7, slurry;8, reserving hole channel.
Specific implementation mode
The method of the present invention is further described through with specific embodiment with reference to the accompanying drawings of the specification.
Embodiment 1
As shown in Figure 1, Figure 4, Figure 5, construction method of the prefabricated piping lane at piping lane inner wall deformation seam is:
Step 1) is required according to detail design, prefabricated with certain specification size piping lane section in pre-fabricated factory;In prefabricated pipe Four reserving hole channels 8 are reserved on four angles of corridor section cross section, are prepared for subsequent steel strand tension.
Before step 2) construction, rubber ring 6 is installed on the reserved location for being inserted into piping lane section, it then will be adjacent prefabricated two-by-two Piping lane section is held out against by jack, the steel strand wires in four reserving hole channels 8 of tensioning and slurry seal anchoring.
3) start the seam construction of piping lane inner wall deformation:
Before top, side wall, bottom high-pressure grout injector slip casting first at piping lane inner wall deformation seam, interim gear is set Plate removes temporary baffle, with quick grout off after slip casting grouting behind shaft or drift lining material has certain intensity;With quick grout off The groove of deformation joint improves groove structural strength, while levelling for the covering of top waterproof roll.
It paves waterproof roll 1 in deformation joint, waterproof roll both ends are positioned in the groove of advance indwelling, use method of powder actuated shot Fixed, with after nailing sealing compound sealing 2 in 3 groove of nailing, pave one layer of waterproof roll 1 again above pre-groove, by nailing Sealing compound 2 is wrapped up.
When above-mentioned step 3) nailing fixes waterproof roll 1,3 fixed point of nailing is located away from coil edge 20mm, the nail of nailing 3 It is more than 30mm away from for 500-800mm, nail is long.Nailing needs complexed metal gasket 4 and thermoplasticity circular washer 5 that waterproof layer is secured simultaneously Be fixed in substrate surface;4 diameter of metal gasket is more than 20mm, at reserved groove nailing position with diameter more than 100mm's Waterproof roll piece sealing is glued in two-sided reaction.
Waterproof roll 1 uses cps waterproof rolls in the present embodiment.Strength grade of concrete in the present embodiment is more than C40, concrete strength is more than 25Mpa when demoulding, and manufacture concrete strength is not less than design strength;Reserving hole channel position degree of skewness ± 3mm, Aperture deviation ± 1mm.
Embodiment 2
As shown in Figure 1, Figure 2, Figure 3 shows, prefabricated piping lane is in the construction method of piping lane outer wall deformation joint:
Step 1) is required according to detail design, prefabricated with certain specification size piping lane section in pre-fabricated factory;In prefabricated pipe Four reserving hole channels 8 are reserved on four angles of corridor section cross section, are prepared for subsequent steel strand tension.
Before step 2) construction, rubber ring 6 is installed on the reserved location for being inserted into piping lane section, it then will be adjacent prefabricated two-by-two Piping lane section is held out against by jack, the steel strand wires in four reserving hole channels 8 of tensioning and slurry seal anchoring.
Step 3) starts piping lane outer wall deformation joint construction:In the top of piping lane outer wall, side wall deformation joint high-pressure slip-casting Machine slip casting, with quick grout off;With the groove of quick grout off deformation joint, groove structural strength is improved, is simultaneously The covering of top waterproof roll is levelling.
It paves waterproof roll 1 in deformation joint, 1 both ends of waterproof roll is positioned in the groove of advance indwelling, nailing is used Method is fixed, and seals 2 with nailing sealing compound in 3 groove of nailing, pave one layer of waterproof roll 1 again above pre-groove.
Cement protective layer is arranged in the deformation joint of piping lane outer wall in step 4), and cement protective layer is covered on waterproof roll 1 As protective layer, prevent weathering and external condition from corroding.
When above-mentioned step 3) nailing fixes waterproof roll 1,3 fixed point of nailing away from coil edge 20mm at, 3 pitch of nails of nailing For 500-800mm, nail is long to be more than 30mm.Nailing needs complexed metal gasket 4 and thermoplasticity circular washer 5 that waterproof layer is firm simultaneously It is fixed in substrate surface;4 diameter of metal gasket is more than 20mm, double more than 100mm with diameter at reserved groove nailing position Waterproof roll piece sealing is glued in face reaction.
Waterproof roll 1 uses cps waterproof rolls in the present embodiment.Strength grade of concrete in the present embodiment is more than C40, concrete strength is more than 25Mpa when demoulding, and manufacture concrete strength is not less than design strength;Reserving hole channel position degree of skewness ± 3mm, Aperture deviation ± 1mm.
It is construction method construction is simple of the invention, efficient in conjunction with the above embodiments, need to only mating tool be used to grasp Work can be easily accomplished, time saving, laborsaving, disposably install the excavation for successfully reducing earth volume, shorten the duration to significantly Construction cost is reduced, and ensure that construction quality.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of construction method of prefabricated piping lane deformation joint connection structure, characterized in that steps are as follows:
1) it is required according to detail design, it is prefabricated with certain specification size piping lane section in pre-fabricated factory;It is transversal in prefabricated piping lane section Four reserving hole channels (8) are reserved on four angles in face, are prepared for subsequent steel strand tension;
2) before constructing, the installation rubber ring (6) on the reserved location for being inserted into piping lane section, then by prefabricated piping lane section adjacent two-by-two It is held out against by jack, the steel strand wires in four reserving hole channels (8) of tensioning and slurry seal anchoring;
3) start the seam construction of piping lane inner wall deformation:Top, side wall first at piping lane inner wall deformation seam, bottom high-pressure slip-casting Machine slip casting, with quick grout off;It paves waterproof roll (1) in deformation joint, waterproof roll (1) both ends are positioned over to be stayed in advance It in the groove set, is fixed with method of powder actuated shot, with after nailing sealing compound (2) sealing in nailing (3) groove, is paved above pre-groove Waterproof roll (1);
4) start piping lane outer wall deformation joint construction:In the top of piping lane outer wall, the high-pressure grout injector slip casting of side wall deformation joint, use Quick grout off;It paving waterproof roll (1) in deformation joint, waterproof roll (1) both ends are positioned in the groove of advance indwelling, It is fixed, is sealed with nailing sealing compound (2) in nailing (3) groove, pave waterproof roll (1) above pre-groove with method of powder actuated shot;
5) cement protective layer is set in the deformation joint of piping lane outer wall, cement protective layer is covered on waterproof roll (1) as guarantor Sheath.
2. a kind of construction method of prefabricated piping lane deformation joint connection structure according to claim 1, characterized in that described Before top of the step 3) at piping lane inner wall deformation seam, side wall, bottom high-pressure grout injector slip casting, temporary baffle is set, note is worked as Slurry grouting behind shaft or drift lining material removes temporary baffle after having certain intensity, with quick grout off.
3. a kind of construction method of prefabricated piping lane deformation joint connection structure according to claim 1, characterized in that described Step 3) 4) in nailing fix waterproof roll (1), nailing (3) fixed point away from coil edge 20mm locate, nailing pitch of nails be 500- 800mm, nail is long to be more than 30mm.
4. a kind of construction method of prefabricated piping lane deformation joint connection structure according to claim 1, characterized in that described Step step 3) 4) in, nailing (3) needs complexed metal gasket (4) and thermoplasticity circular washer (5) that waterproof layer is fixed on base's table On face, metal gasket (4) diameter is more than 20mm, and at reserved groove nailing position, the two-sided reaction with diameter more than 100mm is viscous anti- Water web sheet seals.
5. a kind of construction method of prefabricated piping lane deformation joint connection structure according to claim 1, characterized in that described Waterproof roll (1) uses cps waterproof rolls.
CN201810251925.1A 2018-03-26 2018-03-26 A kind of construction method of prefabricated piping lane deformation joint connection structure Pending CN108385723A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810251925.1A CN108385723A (en) 2018-03-26 2018-03-26 A kind of construction method of prefabricated piping lane deformation joint connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810251925.1A CN108385723A (en) 2018-03-26 2018-03-26 A kind of construction method of prefabricated piping lane deformation joint connection structure

Publications (1)

Publication Number Publication Date
CN108385723A true CN108385723A (en) 2018-08-10

Family

ID=63072215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810251925.1A Pending CN108385723A (en) 2018-03-26 2018-03-26 A kind of construction method of prefabricated piping lane deformation joint connection structure

Country Status (1)

Country Link
CN (1) CN108385723A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962565A (en) * 2020-08-18 2020-11-20 中国五冶集团有限公司 Waterproof structure for deformation joint of pipe gallery and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000074322A (en) * 1999-05-20 2000-12-15 이계철 Waterproofing structure at joints between precast concrete segment block using a waterproofing seat
CN202672360U (en) * 2012-03-20 2013-01-16 叶长青 Waterproof coiled material mouth-closing structure
CN106149764A (en) * 2016-08-23 2016-11-23 四川佳世特橡胶有限公司 A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN206034502U (en) * 2016-08-23 2017-03-22 四川佳世特橡胶有限公司 Prefabricated utility tunnel bell and spigot waterproof construction of assembling
CN106760263A (en) * 2016-12-22 2017-05-31 安徽水安建设集团股份有限公司 A kind of deformation joint of roof slope covering plate structure
CN107386322A (en) * 2017-07-31 2017-11-24 广西路桥工程集团有限公司 A kind of prefabricated installation pipe gallery
CN107489167A (en) * 2017-09-05 2017-12-19 中国建筑第八工程局有限公司 A kind of underground pipe gallery socket joint deformation joint structure and its construction method
CN107700556A (en) * 2017-09-28 2018-02-16 中国建筑第八工程局有限公司 Underground pipe gallery water-proof system and its construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000074322A (en) * 1999-05-20 2000-12-15 이계철 Waterproofing structure at joints between precast concrete segment block using a waterproofing seat
CN202672360U (en) * 2012-03-20 2013-01-16 叶长青 Waterproof coiled material mouth-closing structure
CN106149764A (en) * 2016-08-23 2016-11-23 四川佳世特橡胶有限公司 A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN206034502U (en) * 2016-08-23 2017-03-22 四川佳世特橡胶有限公司 Prefabricated utility tunnel bell and spigot waterproof construction of assembling
CN106760263A (en) * 2016-12-22 2017-05-31 安徽水安建设集团股份有限公司 A kind of deformation joint of roof slope covering plate structure
CN107386322A (en) * 2017-07-31 2017-11-24 广西路桥工程集团有限公司 A kind of prefabricated installation pipe gallery
CN107489167A (en) * 2017-09-05 2017-12-19 中国建筑第八工程局有限公司 A kind of underground pipe gallery socket joint deformation joint structure and its construction method
CN107700556A (en) * 2017-09-28 2018-02-16 中国建筑第八工程局有限公司 Underground pipe gallery water-proof system and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
何小英: "西部地区地下综合管廊防水施工技术探讨", 《中国建筑防水》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111962565A (en) * 2020-08-18 2020-11-20 中国五冶集团有限公司 Waterproof structure for deformation joint of pipe gallery and construction method

Similar Documents

Publication Publication Date Title
CN204343312U (en) Plugging device of precipitation well in foundation pit
CN105041337B (en) The seam splicing construction and waterproof method of a kind of Tunnel Boring tunnel lining segment
CN108442412A (en) Deformation joint seepage waterproof construction method
CN109440951B (en) Waterproof structure for joint of new and old concrete structures and construction process
CN105019919B (en) Tunnel and its construction method for transmitting fluid
CN102561405A (en) Opening treatment method for pipe-roofing continuous perforation
CN105862928A (en) Post-cast strip outer wall in-advance water stopping treatment structure and construction process thereof
CN112376620A (en) Waterproof treatment method for side wall of underground building structure by reverse construction joint
CN110805212A (en) Construction method for roof flashing
CN114482135A (en) Advanced water stop structure of basement exterior wall post-cast strip and construction method
CN102912945B (en) Roof compound seepage-proofing steam exhausting hole detail treatment technology
CN109339118A (en) A kind of basement bottom board leakage-resistant device and construction method
CN108385723A (en) A kind of construction method of prefabricated piping lane deformation joint connection structure
CN110552378A (en) Underground space roof subsides post-cast strip and seals structure in advance
CN110080181B (en) Hydraulic tunnel grouting structure and arrangement method thereof
CN202401561U (en) Multifunctional environment-friendly movable water channel
CN110080796B (en) Tunnel segment repairing process
CN210508385U (en) Shear force wall bushing reinforced structure
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN211312769U (en) Connecting member of plastic pipe and concrete prefabricated inspection well
CN112211230A (en) Steel plate mortar brick composite structure and method for repairing leakage of concrete structure by using same
CN108521097A (en) A kind of prefabricated tunnel of electric power and its installation method
CN205839811U (en) A kind of post-cast strip exterior wall advanced water-stopping processes structure
CN104963364A (en) Disposing method for topdown structural slab lower side wall construction joint
CN103924694A (en) Leakage repairing treatment method for waterproof concrete expansion joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180810