CN106149764A - A kind of precast assembly pipe gallery bell and spigot waterproof construction - Google Patents

A kind of precast assembly pipe gallery bell and spigot waterproof construction Download PDF

Info

Publication number
CN106149764A
CN106149764A CN201610707908.5A CN201610707908A CN106149764A CN 106149764 A CN106149764 A CN 106149764A CN 201610707908 A CN201610707908 A CN 201610707908A CN 106149764 A CN106149764 A CN 106149764A
Authority
CN
China
Prior art keywords
waterproof
pipe gallery
self
seam
spigot
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610707908.5A
Other languages
Chinese (zh)
Other versions
CN106149764B (en
Inventor
严林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN JUST RUBBER CO Ltd
Original Assignee
SICHUAN JUST RUBBER CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN JUST RUBBER CO Ltd filed Critical SICHUAN JUST RUBBER CO Ltd
Priority to CN201610707908.5A priority Critical patent/CN106149764B/en
Publication of CN106149764A publication Critical patent/CN106149764A/en
Application granted granted Critical
Publication of CN106149764B publication Critical patent/CN106149764B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种预制拼装综合管廊承插口防水结构,包括由管廊插口与管廊承口构成的接缝,在所述接缝处,至接缝外侧至接缝内侧,依次设置有由1.5‑3.0mm厚的PCM防水卷材、JS‑211型双组份密封胶、聚乙烯泡沫填充板、EPDM楔形密封圈、遇水膨胀弹性橡胶体、聚乙烯泡沫填充板、JS‑211型双组份密封胶、1.5‑2.0mm厚的EPⅡR自粘防水胶带构成的防水构造体。本构造多道防水设防,外侧PCM自粘聚合物改性沥青防水卷材除有防水功能外,还可以防植物根茎穿刺,保护外缝;双组份密封胶嵌缝起防水、防渗作用;内侧EPIIR自粘防水胶带除防水、防渗外,还可以起到防昆虫、鼠咬的作用,主要起保护内缝的作用,通过上述的多道防水,该防水构造使用寿命长,可达100年。

The invention discloses a prefabricated and assembled comprehensive pipe gallery socket socket waterproof structure, which comprises a joint formed by a pipe gallery socket and a pipe gallery socket. At the joint, from the outside to the inside of the joint, there are sequentially arranged Composed of 1.5-3.0mm thick PCM waterproof membrane, JS-211 two-component sealant, polyethylene foam filling board, EPDM wedge-shaped sealing ring, water-swellable elastic rubber body, polyethylene foam filling board, JS-211 type A waterproof structure composed of two-component sealant and 1.5-2.0mm thick EPIIR self-adhesive waterproof tape. This structure has multiple waterproof fortifications, and the outer PCM self-adhesive polymer modified bitumen waterproof membrane not only has the waterproof function, but also can prevent plant roots from puncturing and protect the outer seams; the two-component sealant caulking plays the role of waterproof and anti-seepage; In addition to waterproofing and anti-seepage, the inner EPIIR self-adhesive waterproof tape can also play the role of preventing insects and rats from biting. year.

Description

一种预制拼装综合管廊承插口防水结构A prefabricated and assembled comprehensive pipe gallery socket socket waterproof structure

技术领域technical field

本发明涉及预制拼装综合管廊,尤其一种预制拼装综合管廊插口防水结构。The invention relates to a prefabricated and assembled comprehensive pipe gallery, in particular to a waterproof structure for an outlet of a prefabricated and assembled comprehensive pipe gallery.

背景技术Background technique

城市综合管廊,也称为共同沟、综合管沟,是在市政道路下建造一个地下廊道,将电力、通讯、热力和给排水等各种市政管线一并纳入其中,并设置专门的检修口、投料口等的设施装备。城市综合管廊统一建设管理,省去管线自身独立的构筑物和土方开挖,可以有效集约化的利用空间资源。The urban comprehensive pipe corridor, also known as the common ditch and the comprehensive pipe ditch, is an underground corridor built under the municipal road, which incorporates various municipal pipelines such as electricity, communication, heat, water supply and drainage, and sets up special maintenance Facilities and equipment such as mouth and feeding port. The unified construction and management of the urban comprehensive pipeline corridor saves the independent structures and earthwork excavation of the pipeline itself, which can effectively and intensively use space resources.

不同形式的地下综合管廊,其断面形式、容纳管线种类、造价、维修及管理均有所不同。目前,已建成或正在建设的部分地下综合管廊,绝大部分采用现浇式或者是在工厂里采用离心或振捣浇筑成一个整体运送到施工现场的方式。这两种方法都存在一定的不足:现场浇筑箱涵施工周期长、劳动强度大、效率低,受天气、现场条件影响大,对周围环境容易产生较大的污染、施工质量也不稳定,成本高;工厂化生产的整体箱涵,管廊成型时间长,工艺步骤繁琐,施工成本高,运输、吊装困难,尤其是大型的箱涵,生产设备和吊装设备投入巨大,而超大规格的箱涵难有生产设备也无法制造。Different forms of underground comprehensive utility corridors have different cross-sectional forms, types of pipelines accommodated, cost, maintenance and management. At present, most of the underground comprehensive pipe galleries that have been built or are under construction are cast-in-place or centrifugally or vibrated in the factory to form a whole and transported to the construction site. These two methods have certain shortcomings: the construction period of pouring on-site box culvert is long, the labor intensity is high, the efficiency is low, it is greatly affected by the weather and site conditions, it is easy to cause relatively large pollution to the surrounding environment, the construction quality is also unstable, and the cost High; for the overall box culvert produced in factory, it takes a long time to form the pipe gallery, the process steps are cumbersome, the construction cost is high, and the transportation and hoisting are difficult. Especially for large box culverts, the investment in production equipment and hoisting equipment is huge. Difficult to have production equipment also can't manufacture.

因此,预制拼装综合管廊应运而生,预制拼装综合管廊制造简单,片状构件运输,吊装方便,工厂化生产,质量可控,综合成本低,相对于混凝土板状构件组装施工周期可大大提前,且基本不影响道路通行,适用范围广,经济环保。由于采用装配式结构,箱涵的规格尺寸可以制造到超大尺寸,不再受限于制造和运输等外部条件,解决了现有现浇、整体预制技术中存在的问题。但是由于是预制拼装是拼装片状安装方式,片状结构搭接处的防水问题尤为突出,现有管廊结构在震动及其他原因造成的变形时管廊承插口处容易漏水而影响使用功能。Therefore, the prefabricated and assembled comprehensive pipe gallery came into being. The prefabricated and assembled comprehensive pipe gallery is simple to manufacture, the sheet-shaped components are transported and hoisted conveniently, the factory production, the quality is controllable, and the comprehensive cost is low. Compared with the concrete plate-shaped components, the construction period can be greatly reduced It is ahead of time, and basically does not affect road traffic, has a wide range of applications, and is economical and environmentally friendly. Due to the prefabricated structure, the specification and size of the box culvert can be manufactured to a super large size, and it is no longer limited by external conditions such as manufacturing and transportation, which solves the problems existing in the existing cast-in-place and overall prefabrication technology. However, due to the prefabricated and assembled sheet-like installation method, the waterproof problem of the overlapping joints of the sheet structures is particularly prominent. When the existing pipe gallery structure is deformed due to vibration and other reasons, water is prone to leak at the socket of the pipe gallery and affect the use function.

中国专利公开号:CN105525632A公开了一种装配式预制综合管廊承插口防水构造,该结构在前一节承口和后一管节插口之间采用5道防水构造设计。所述的5道防水构造包括:遇水膨胀止水条1、遇水膨胀止水条2、在两道遇水膨胀止水条之间注入弹性防水材料、遇水膨胀止水条1外缝隙处灌入弹性防水材料、外侧接缝处粘贴防水卷材。该技术方案有一定的先进性,但不足的是整个接缝处全部用防水材料填充,制作相对繁琐,成本略高,有必要改进。Chinese Patent Publication No.: CN105525632A discloses an assembled prefabricated comprehensive pipe gallery socket socket waterproof structure, the structure adopts five waterproof structure designs between the socket of the previous section and the socket of the next pipe section. The five waterproof structures include: water-expandable water-stop strip 1, water-expandable water-stop strip 2, elastic waterproof material injected between the two water-expandable water-stop strips, water-expandable water-stop strip 1 outer gap The elastic waterproof material is poured into the joint, and the waterproof membrane is pasted on the outer seam. This technical solution has a certain degree of advancement, but the disadvantage is that the entire seam is filled with waterproof materials, the production is relatively cumbersome, and the cost is slightly high, so it is necessary to improve.

发明内容Contents of the invention

基于上述所述,本发明的目的是提供一种新型结构的管廊承插口防水结构,以改进现有防水构造的不足,优化其结构,使其更具有创新性、实用性、经济性。Based on the above, the purpose of the present invention is to provide a new type of waterproof structure for the socket of the pipe gallery to improve the shortcomings of the existing waterproof structure, optimize its structure, and make it more innovative, practical and economical.

本发明是通过如下技术方案实现的:The present invention is achieved through the following technical solutions:

一种预制拼装综合管廊承插口防水结构,包括由管廊插口与管廊承口构成的接缝,创新之处在于,在所述接缝处设置有由PCM防水卷材,双组份密封胶,聚乙烯泡沫填充板,EPDM楔形密封圈,遇水膨胀弹性橡胶体,自粘防水胶带构成的防水构造体。A prefabricated and assembled comprehensive pipe gallery socket waterproof structure, including the joint formed by the pipe gallery socket and the pipe gallery socket. The waterproof structure is composed of glue, polyethylene foam filling board, EPDM wedge-shaped sealing ring, water-swellable elastic rubber body, and self-adhesive waterproof tape.

进一步地,还包括注浆孔管,所述注浆孔管设置在管廊插口上,其开口方向朝向管廊插口的内侧。Further, the grouting hole tube is also included, and the grouting hole tube is arranged on the socket of the pipe gallery, and its opening direction faces the inner side of the socket of the pipe gallery.

进一步地,所述双组份密封胶为JS-211型双组分密封胶,所述自粘防水胶带为EPⅡR型自粘防水胶带。Further, the two-component sealant is JS-211 type two-component sealant, and the self-adhesive waterproof tape is EPIIR self-adhesive waterproof tape.

进一步地,所述的EPDM楔形密封圈为双唇楔形密封圈的一种。Further, the EPDM wedge seal ring is a kind of double-lip wedge seal ring.

进一步地,所述EPDM楔形密封圈张口方向朝向接缝的外侧。Further, the opening direction of the EPDM wedge-shaped sealing ring is toward the outside of the seam.

进一步地,在所述接缝处,至接缝外侧至接缝内侧,依次设置有由PCM防水卷材、双组份密封胶、聚乙烯泡沫填充板、EPDM楔形密封圈、遇水膨胀弹性橡胶体、聚乙烯泡沫填充板、双组份密封胶、EPⅡR自粘防水胶带构成的防水构造体。Further, at the seam, from the outside of the seam to the inside of the seam, PCM waterproof membrane, two-component sealant, polyethylene foam filling board, EPDM wedge-shaped sealing ring, water-swellable elastic rubber Body, polyethylene foam filling board, two-component sealant, EPIIR self-adhesive waterproof tape is a waterproof structure.

进一步地,所述PCM防水卷材设置在接缝的外侧,所述EPⅡR自粘防水胶带设置在接缝的内侧。Further, the PCM waterproof membrane is arranged on the outside of the seam, and the EPIIR self-adhesive waterproof tape is arranged on the inside of the seam.

进一步地,所述PCM防水卷材的设置厚度为1.5~3.0mm,所述EPⅡR自粘防水胶带的设置厚度为1.5~2.0mm。Further, the thickness of the PCM waterproof membrane is 1.5-3.0 mm, and the thickness of the EPIIR self-adhesive waterproof tape is 1.5-2.0 mm.

与现有技术相比,本发明的有益效果在于:Compared with prior art, the beneficial effect of the present invention is:

1、EPDM楔型密封圈采用双唇口设计,其楔形设计安装阻力小,可有效的将单唇口的阻力分摊到2个唇口上,更加利于安装,密封效果更久,时间更长;此外,两个密封唇口的设计也解决了在装配一个密封唇口时容易发生移动翻滚的现象,双唇楔形密封圈唇口高度的尺寸设计比钢筋混泥土顶管的插口高出10-20%,有效的利用了将橡胶弹性密封功能,可起到了高度永久密封的作用。1. The EPDM wedge-shaped sealing ring adopts a double-lip design, and its wedge-shaped design has low installation resistance, which can effectively distribute the resistance of a single lip to two lips, which is more convenient for installation, and the sealing effect is longer and the time is longer; in addition , The design of the two sealing lips also solves the phenomenon that it is easy to move and roll when assembling a sealing lip. The lip height of the double-lip wedge sealing ring is designed to be 10-20% higher than the socket of the reinforced concrete jacking pipe , effective use of the rubber elastic sealing function, can play a highly permanent sealing role.

2、本构造多道防水设防,外侧PCM自粘聚合物改性沥青防水卷材除有防水功能外,还可以防植物根茎穿刺,保护外缝;双组份密封胶嵌缝起防水、防渗作用;内侧EPIIR自粘防水胶带除防水、防渗外,还可以起到防昆虫、鼠咬的作用,主要起保护内缝的作用,通过上述的多道防水,该防水构造使用寿命长,可达100年。2. This structure has multiple waterproof fortifications. The outer PCM self-adhesive polymer modified asphalt waterproof membrane can not only waterproof, but also prevent plant roots from puncturing and protect the outer seam; the two-component sealant caulking is waterproof and anti-seepage Function; In addition to waterproofing and anti-seepage, the inner EPIIR self-adhesive waterproof tape can also play the role of preventing insects and rats from biting, mainly protecting the inner seam. Through the above-mentioned multiple waterproofing, the waterproof structure has a long service life and can Up to 100 years.

附图说明Description of drawings

图1是本发明实施例示意图。Fig. 1 is a schematic diagram of an embodiment of the present invention.

具体实施方式detailed description

下面结合附图及具体实施方式对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.

如图1所示,本发明公开了一种预制拼装综合管廊承插口防水结构,下述实施例给出一个优选实施例。As shown in Fig. 1, the present invention discloses a waterproof structure for socket sockets of prefabricated and assembled integrated pipe galleries, and the following example provides a preferred embodiment.

一种预制拼装综合管廊承插口防水结构,包括由管廊插口与管廊承口构成的接缝,其中,插口深度为100-130mm,接口转角度1.5~2.5度。在所述接缝处,至接缝外侧至接缝内侧,依次设置有由PCM防水卷材1、JS-211型双组份密封胶2、聚乙烯泡沫填充板3、EPDM楔形密封圈4、遇水膨胀弹性橡胶体5、聚乙烯泡沫填充板3、双组份密封胶2、EPⅡR自粘防水胶带6构成的防水构造体;其中,PCM防水卷材的设置厚度为1.5~3.0mm,所述EPⅡR自粘防水胶带的设置厚度为1.5~2.0mm。A prefabricated and assembled comprehensive pipe gallery socket waterproof structure, including the joint formed by the pipe gallery socket and the pipe gallery socket, wherein the depth of the socket is 100-130mm, and the joint rotation angle is 1.5-2.5 degrees. At the seam, from the outside of the seam to the inside of the seam, PCM waterproof membrane 1, JS-211 type two-component sealant 2, polyethylene foam filling board 3, EPDM wedge-shaped sealing ring 4, The water-swellable elastic rubber body 5, the polyethylene foam filling board 3, the two-component sealant 2, and the EPIIR self-adhesive waterproof tape 6 constitute a waterproof structure; among them, the thickness of the PCM waterproof membrane is 1.5~3.0mm, and the The setting thickness of the EPIIR self-adhesive waterproof tape is 1.5~2.0mm.

在本实施例中,还包括注浆孔管7,所述注浆孔管7设置在管廊插口上,其开口方向朝向管廊插口的内侧。注浆孔管7一方面可以做管节接缝处防水试压用,测试管节内外胶条防水密封性能;另一方面可以作为后期堵漏的预留通道。如果管廊使用阶段出现变形沉降过大,可能造成局部渗漏后,可以进行注胶、注浆封装补救。In this embodiment, a grouting hole pipe 7 is also included, and the grouting hole pipe 7 is arranged on the socket of the pipe gallery, and its opening direction is toward the inside of the socket of the pipe gallery. On the one hand, the grouting hole pipe 7 can be used as a waterproof pressure test at the joint of the pipe joint to test the waterproof and sealing performance of the inner and outer rubber strips of the pipe joint; on the other hand, it can be used as a reserved channel for later plugging. If the deformation and settlement of the pipe gallery are too large during the use stage, which may cause local leakage, glue injection and grouting packaging can be carried out for remediation.

在本实施例中,JS-211型双组份密封胶是我公司在现有双组份密封胶的基础上改良的一种密封胶,配方组成为:液体聚硫橡胶100份、聚硐增粘树脂10份、纳米碳酸氢钙80份、酚酫树脂5份、聚乙二醇8份、液体硫磺1.5份、防老剂4010NA4.5份、抗霉菌剂3.5份、液体氯化石蜡(阻燃剂)4.5份。In this example, the JS-211 two-component sealant is a sealant improved by our company on the basis of the existing two-component sealant. The formula is composed of: 100 parts of liquid polysulfide rubber, polysulfide 10 parts of viscose resin, 80 parts of nano-calcium bicarbonate, 5 parts of phenolic resin, 8 parts of polyethylene glycol, 1.5 parts of liquid sulfur, 4.5 parts of anti-aging agent 4010NA, 3.5 parts of anti-mold agent, liquid chlorinated paraffin (flame retardant agent) 4.5 parts.

在本实施例中,EPⅡR自粘防水胶带6是我公司在现有防水胶带的技基础上改良的一种防水胶带,配方组成为:三元乙丙橡胶100份、235碳黑120份、超细滑石粉50份、300号石蜡油50份、硫化剂1.5份、促进剂2.3份、防老剂3.5份、防霉菌剂2.5份、抗氧化剂2.2份、阻燃剂1.8份、丁基橡㬵100份、白油30份、酚酫树脂10份、聚乙烯醇20份。In this example, EPIIR self-adhesive waterproof tape 6 is a waterproof tape improved by our company on the basis of the existing waterproof tape technology. The formula is composed of: 100 parts of EPDM rubber, 120 parts of 235 carbon black, 50 parts of fine talcum powder, 50 parts of No. 300 paraffin oil, 1.5 parts of vulcanizing agent, 2.3 parts of accelerator, 3.5 parts of anti-aging agent, 2.5 parts of anti-mold agent, 2.2 parts of antioxidant, 1.8 parts of flame retardant, 100 parts of butyl rubber 30 parts of white oil, 10 parts of phenolic resin, and 20 parts of polyvinyl alcohol.

本构造多道防水设防,外侧PCM自粘聚合物改性沥青防水卷材除有防水功能外,还可以防植物根茎穿刺,保护外缝;双组份密封胶嵌缝起防水、防渗作用;内侧EPIIR自粘防水胶带除防水、防渗外,还可以起到防昆虫、鼠咬的作用,主要起保护内缝的作用,通过上述的多道防水,该防水构造使用寿命长,可达100年。This structure has multiple waterproofing fortifications, and the outer PCM self-adhesive polymer modified bitumen waterproofing membrane not only has the waterproof function, but also can prevent plant roots from puncturing and protect the outer seams; the two-component sealant caulking plays the role of waterproofing and anti-seepage; In addition to waterproofing and anti-seepage, the inner EPIIR self-adhesive waterproof tape can also play the role of preventing insects and rats from biting. year.

以上描述是对本发明的解释,不是对本发明的限定,本发明所限定的范围参见权利要求,在不违背本发明基本构思的情况下,本发明可以作其它形式的修改。The above description is an explanation of the present invention, not a limitation of the present invention. For the limited scope of the present invention, refer to the claims. The present invention can be modified in other forms without violating the basic concept of the present invention.

Claims (8)

1. a precast assembly pipe gallery bell and spigot waterproof construction, including the seam being made up of with piping lane bellmouth piping lane socket, It is characterized in that, being provided with by PCM waterproof roll, double-component fluid sealant at described seam crossing, polyethylene fills plate, EPDM Wedge-type seal circle, water-swellable elastic rubbery body, the water proof structure body that self-adhesion adhesive waterproof tape is constituted.
2. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 1, it is characterised in that also include Injected hole pipe, described injected hole pipe is arranged on piping lane socket, and its opening direction is towards the inner side of piping lane socket.
3. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 1 any one, its feature exists In described double-component fluid sealant is JS-211 type bi-component fluid sealant, and described self-adhesion adhesive waterproof tape is EP II R type self-adhesion marine glue Band.
4. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 1, it is characterised in that described EPDM wedge-type seal circle is lips wedge-type seal circles.
5. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 1, it is characterised in that described EPDM wedge-type seal circle is dehisced the outside towards seam for the direction.
6. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 1 ~ 4 any one, its feature Be, at described seam crossing, to inside seam to seam, be disposed with by PCM waterproof roll, double-component fluid sealant, Polyethylene filling plate, EPDM wedge-type seal circle, water-swellable elastic rubbery body, polyethylene filling plate, double-component are close The water proof structure body that sealing, EP II R self-adhesion adhesive waterproof tape are constituted.
7. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 6, it is characterised in that described PCM waterproof roll is arranged on the outside of seam, and described EP II R self-adhesion adhesive waterproof tape is arranged on the inner side of seam.
8. a kind of precast assembly pipe gallery bell and spigot waterproof construction according to claim 6, it is characterised in that described The thickness that arranges of PCM waterproof roll is 1.5 ~ 3.0mm, and the thickness that arranges of described EP II R self-adhesion adhesive waterproof tape is 1.5 ~ 2.0mm.
CN201610707908.5A 2016-08-23 2016-08-23 A kind of precast assembly pipe gallery bell and spigot waterproof construction Active CN106149764B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610707908.5A CN106149764B (en) 2016-08-23 2016-08-23 A kind of precast assembly pipe gallery bell and spigot waterproof construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610707908.5A CN106149764B (en) 2016-08-23 2016-08-23 A kind of precast assembly pipe gallery bell and spigot waterproof construction

Publications (2)

Publication Number Publication Date
CN106149764A true CN106149764A (en) 2016-11-23
CN106149764B CN106149764B (en) 2018-06-01

Family

ID=57342583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610707908.5A Active CN106149764B (en) 2016-08-23 2016-08-23 A kind of precast assembly pipe gallery bell and spigot waterproof construction

Country Status (1)

Country Link
CN (1) CN106149764B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836278A (en) * 2017-01-22 2017-06-13 中交第公路勘察设计研究院有限公司 The construction method of corrugated steel pipe gallery
CN107386322A (en) * 2017-07-31 2017-11-24 广西路桥工程集团有限公司 A kind of prefabricated installation pipe gallery
CN107859065A (en) * 2017-11-03 2018-03-30 湖南大学 A kind of ultra-high performance concrete precast assembly pipe gallery and construction method
CN107859075A (en) * 2017-12-14 2018-03-30 成都市第三建筑工程公司 A kind of prefabricated pipe gallery joint waterproof structure and its construction method
CN108193707A (en) * 2017-12-22 2018-06-22 成都市市政工程设计研究院 A kind of comprehensive pipe gallery structure
CN108316347A (en) * 2018-03-09 2018-07-24 中冶京诚工程技术有限公司 Partition waterproof assembly type underground comprehensive pipe gallery and waterproof method thereof
CN108385723A (en) * 2018-03-26 2018-08-10 中国十七冶集团有限公司 A kind of construction method of prefabricated piping lane deformation joint connection structure
CN108411939A (en) * 2018-03-16 2018-08-17 通号建设集团有限公司 The spliced prefabricated pipe gallery of one kind and its construction method
CN108867699A (en) * 2018-09-25 2018-11-23 四川沃特尔管业有限公司 A kind of interface structure of pipe gallery
CN108867697A (en) * 2018-08-31 2018-11-23 江苏金贸科技发展有限公司 A kind of concrete prefabricated piping lane with antiseep preset structure
CN110284519A (en) * 2019-06-17 2019-09-27 湖北建科国际工程有限公司 A kind of pipe gallery assembling structure and pipe gallery
CN110978256A (en) * 2019-12-20 2020-04-10 辽宁衍水水工水泥制品集团有限公司 Method for vertically producing precast concrete box culvert
CN112144578A (en) * 2020-10-29 2020-12-29 中国十九冶集团有限公司 Socket structure for prefabricated assembled pipe gallery and construction method
CN112343084A (en) * 2021-01-11 2021-02-09 沈阳建筑大学 Waterproof underground pipe gallery
CN112359880A (en) * 2020-11-26 2021-02-12 中铁第四勘察设计院集团有限公司 Assembled underground structure seam connection structure
CN112726666A (en) * 2020-12-30 2021-04-30 中国二十冶集团有限公司 Pipe gallery and pipe gallery construction method
CN114232691A (en) * 2022-01-19 2022-03-25 上海市政工程设计研究总院(集团)有限公司 Prefabricated inspection well and assembling method thereof
CN114960750A (en) * 2022-07-13 2022-08-30 中建二局第一建筑工程有限公司 Anti-seismic waterproof prefabricated pipe gallery and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090132071A (en) * 2008-06-20 2009-12-30 박정규 Waterproof member, waterproof structure using the same, waterproof method
CN105525632A (en) * 2016-02-05 2016-04-27 青岛润国生态科技发展有限公司 Waterproof structure for bellmouths and sockets of fabricated prefabricated composite pipe gallery
CN105625471A (en) * 2016-03-14 2016-06-01 青岛润国生态科技发展有限公司 Prefabricated comprehensive pipe gallery
CN105780808A (en) * 2016-03-14 2016-07-20 青岛润国生态科技发展有限公司 Assembly type precast comprehensive pipe gallery
CN206034502U (en) * 2016-08-23 2017-03-22 四川佳世特橡胶有限公司 Prefabricated utility tunnel bell and spigot waterproof construction of assembling

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090132071A (en) * 2008-06-20 2009-12-30 박정규 Waterproof member, waterproof structure using the same, waterproof method
CN105525632A (en) * 2016-02-05 2016-04-27 青岛润国生态科技发展有限公司 Waterproof structure for bellmouths and sockets of fabricated prefabricated composite pipe gallery
CN105625471A (en) * 2016-03-14 2016-06-01 青岛润国生态科技发展有限公司 Prefabricated comprehensive pipe gallery
CN105780808A (en) * 2016-03-14 2016-07-20 青岛润国生态科技发展有限公司 Assembly type precast comprehensive pipe gallery
CN206034502U (en) * 2016-08-23 2017-03-22 四川佳世特橡胶有限公司 Prefabricated utility tunnel bell and spigot waterproof construction of assembling

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836278A (en) * 2017-01-22 2017-06-13 中交第公路勘察设计研究院有限公司 The construction method of corrugated steel pipe gallery
CN107386322A (en) * 2017-07-31 2017-11-24 广西路桥工程集团有限公司 A kind of prefabricated installation pipe gallery
CN107859065A (en) * 2017-11-03 2018-03-30 湖南大学 A kind of ultra-high performance concrete precast assembly pipe gallery and construction method
CN107859075A (en) * 2017-12-14 2018-03-30 成都市第三建筑工程公司 A kind of prefabricated pipe gallery joint waterproof structure and its construction method
CN108193707A (en) * 2017-12-22 2018-06-22 成都市市政工程设计研究院 A kind of comprehensive pipe gallery structure
CN108316347A (en) * 2018-03-09 2018-07-24 中冶京诚工程技术有限公司 Partition waterproof assembly type underground comprehensive pipe gallery and waterproof method thereof
CN108411939A (en) * 2018-03-16 2018-08-17 通号建设集团有限公司 The spliced prefabricated pipe gallery of one kind and its construction method
CN108385723A (en) * 2018-03-26 2018-08-10 中国十七冶集团有限公司 A kind of construction method of prefabricated piping lane deformation joint connection structure
CN108867697A (en) * 2018-08-31 2018-11-23 江苏金贸科技发展有限公司 A kind of concrete prefabricated piping lane with antiseep preset structure
CN108867699A (en) * 2018-09-25 2018-11-23 四川沃特尔管业有限公司 A kind of interface structure of pipe gallery
CN110284519A (en) * 2019-06-17 2019-09-27 湖北建科国际工程有限公司 A kind of pipe gallery assembling structure and pipe gallery
CN110978256A (en) * 2019-12-20 2020-04-10 辽宁衍水水工水泥制品集团有限公司 Method for vertically producing precast concrete box culvert
CN112144578A (en) * 2020-10-29 2020-12-29 中国十九冶集团有限公司 Socket structure for prefabricated assembled pipe gallery and construction method
CN112359880A (en) * 2020-11-26 2021-02-12 中铁第四勘察设计院集团有限公司 Assembled underground structure seam connection structure
CN112726666A (en) * 2020-12-30 2021-04-30 中国二十冶集团有限公司 Pipe gallery and pipe gallery construction method
CN112343084A (en) * 2021-01-11 2021-02-09 沈阳建筑大学 Waterproof underground pipe gallery
CN114232691A (en) * 2022-01-19 2022-03-25 上海市政工程设计研究总院(集团)有限公司 Prefabricated inspection well and assembling method thereof
CN114960750A (en) * 2022-07-13 2022-08-30 中建二局第一建筑工程有限公司 Anti-seismic waterproof prefabricated pipe gallery and construction method thereof

Also Published As

Publication number Publication date
CN106149764B (en) 2018-06-01

Similar Documents

Publication Publication Date Title
CN106149764B (en) A kind of precast assembly pipe gallery bell and spigot waterproof construction
CN204477513U (en) A kind of push pipe starts portal water sealing structure
CN105041337B (en) The seam splicing construction and waterproof method of a kind of Tunnel Boring tunnel lining segment
CN205000976U (en) A shield structure segment lining structure for deep drainage tunnel
CN204716291U (en) Dewatering installation is drawn in tunnel pressure release
CN207700220U (en) A kind of waterproof construction of pipe gallery outer wall
CN109026079B (en) Tunnel joint waterproof structure and waterproof construction method
CN107989068A (en) A kind of waterproof construction of pipe gallery outer wall
CN106049551B (en) Utility tunnel boss seal structure
CN206143804U (en) Prefabricated socket joint formula waterproof construction of assembling utility tunnel tube coupling
CN108756953B (en) Waterproof and drainage system with secondary lining shield tunnel
CN113513048A (en) Station house underground passage leakage-proof structure and construction process
CN206034502U (en) Prefabricated utility tunnel bell and spigot waterproof construction of assembling
CN203948784U (en) Jacking pipe joints joint waterproofing structure
CN207111105U (en) Tunnel ring seam water seepage treatment structure
CN106368239A (en) Water stop structure arranged at position of expansion joint of urban underground comprehensive pipe rack and construction method of water stop structure
CN210462146U (en) Circular pipeline repairing structure
CN110953416A (en) Pipe joint sealing method for socket type reinforced concrete drain pipe
CN107355234B (en) Anti-seepage, anti-corrosion, durable confluence regulation and storage type deep tunnel
CN211447035U (en) Piping lane lateral wall movement joint waterproof construction
CN207633358U (en) A kind of prefabricated assembled pipe gallery jointing construction
CN111719664A (en) An Assembled Rain and Sewage Diversion Interchange Inspection Well
CN217762498U (en) Municipal administration water supply and drainage pipeline connection structure
CN205242454U (en) Underground concrete structure expansion joint administration structure
CN204691791U (en) The waterproof construction of rectangular top pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20161123

Contract record no.: X2025980046911

Denomination of invention: A prefabricated assembled integrated utility tunnel spigot and socket waterproof structure

Granted publication date: 20180601

License type: Common License

Record date: 20251222