CN108385610A - A kind of Anti-Typhoon dykes and dams of seashore and its building method - Google Patents

A kind of Anti-Typhoon dykes and dams of seashore and its building method Download PDF

Info

Publication number
CN108385610A
CN108385610A CN201810073264.8A CN201810073264A CN108385610A CN 108385610 A CN108385610 A CN 108385610A CN 201810073264 A CN201810073264 A CN 201810073264A CN 108385610 A CN108385610 A CN 108385610A
Authority
CN
China
Prior art keywords
meters
seashore
dams
dykes
typhoon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810073264.8A
Other languages
Chinese (zh)
Inventor
李涛
高健
徐国梁
刘学应
杨东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Water Resources and Electric Power
Original Assignee
Zhejiang University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Water Resources and Electric Power filed Critical Zhejiang University of Water Resources and Electric Power
Priority to CN201810073264.8A priority Critical patent/CN108385610A/en
Publication of CN108385610A publication Critical patent/CN108385610A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use

Abstract

The invention discloses a kind of Anti-Typhoon dykes and dams of seashore and its building methods, including following construction procedure:A, excavation of foundation pit;B, Foundation treatment;C, foundation pit makes column;D, bar-mat reinforcement casting concrete is built;E, pouring for unrestrained body is kept off;F, pouring for wave circle pier is kept off;G, the protective layer of the unrestrained body of gear is poured;H, the construction of windbreak;I, the installation of wind-driven generator.The present invention provides a kind of Anti-Typhoon dykes and dams of seashore and its building methods, using the Anti-Typhoon dykes and dams of the seashore of reinforced concrete structure, and strengthen the anti-sea beat ability in surface, windbreak and wind-driven generator are added again, overall construction design is ingenious rationally, convenient for the maintenance in later stage, it can effectively improve the anti-sea beat ability of seashore dykes and dams by the construction method, it effectively prevent caving in for seashore dykes and dams, extend the service life of seashore dykes and dams, effectively convert wind energy into electric energy, the power of typhoon day typhoon is reduced to a certain extent, realize the anti-typhoon capacity of seashore dykes and dams.

Description

A kind of Anti-Typhoon dykes and dams of seashore and its building method
Technical field
The present invention relates to a kind of Anti-Typhoon dykes and dams of seashore and its building methods.
Background technology
Seashore dykes and dams refer to the dike for the damp wave resistance of gear coastwise built.Seashore dykes and dams are the important waterworks of project to enclose sea areas Object.Seashore dykes and dams are as wave resistance building, in addition to bearing wave action, while also to keep off tide.Seashore dykes and dams do not allow generally to get over Wave, crest elevation of levee are more demanding.
The Anti-Typhoon dykes and dams of seashore are then that Anti-Typhoon work(is added on the basis of considering seashore dykes and dams gear tide wave-resisting function Can, the novel seashore dykes and dams that the damp wave-resisting function of gear and Anti-Typhoon function are combined together have certain environmental protection ability, and And the intensity deficiency of existing dykes and dams is improved.
Invention content
Present invention aims at a kind of Anti-Typhoon dykes and dams of seashore and its block are provided for deficiency of the prior art The technical solution of building method changes the design of existing seashore dykes and dams, using the Anti-Typhoon dykes and dams of the seashore of reinforced concrete structure, and The anti-sea beat ability in surface is strengthened, and adds windbreak and wind-driven generator, overall construction design is ingenious rationally, is convenient for The maintenance in later stage can effectively improve the anti-sea beat ability of seashore dykes and dams by the construction method, effectively prevent seashore dike Dam caves in, and extends the service life of seashore dykes and dams, effectively converts wind energy into electric energy, reduce typhoon day to a certain extent The power of typhoon realizes the anti-typhoon capacity of seashore dykes and dams.
A kind of Anti-Typhoon dykes and dams of seashore and its building method, which is characterized in that include the following steps:
A, excavation of foundation pit
Exploration scene carries out foundation excavation to construction seashore, digs 10 to 20 meters of depths downwards, then use hook machine to seashore of constructing It carries out smooth, then measures unwrapping wire;
B, Foundation treatment
The rubble of one layer of 50cm thickness, the mixture of lime and flyash are laid in construction foundation pit, then with hook machine to this Metalling be compacted smooth, then with flyash hydration reaction occurs for the lime allowed between rubble,;
C, foundation pit makes column
3 meters of depths a diameter of 3 meters of holes is dug on foundation pit, be used in combination concrete reinforcement 10 meters to 20 meters height outside drilling and hole It is interior to pour cylinder vertically with concrete, a cylinder is built in this way every 15 meters;
D, bar-mat reinforcement casting concrete is built
Vertical 10 meters to the 20 meters high reinforcing bars in foundation pit, reinforcing bar is built into it is latticed, then with concreting dam body, Reach 10 meters to 20 meters;
E, pouring for unrestrained body is kept off
The gear wave body of dam body is poured with rock-fill concrete;
F, pouring for wave circle pier is kept off
On the inclined-plane of the unrestrained body of gear, columned bar-mat reinforcement is built with reinforcing bar, then with concreting at it is intermediate be hollow The cylinder of structure;
G, the protective layer of the unrestrained body of gear is poured
With polyurethane and loose broken granite with 3:100 ratio is mixed, and then pours 1 meter of thickness on the unrestrained body of gear Protective layer;
H, the construction of windbreak
20 meters of high reinforcing bars are holded up above dam body, reinforcing bar are built into latticed, then are molded, are poured with concreting Cast the windbreak of rectangular-shape;
I, the installation of wind-driven generator
On windbreak, front and back four air draft power generators are installed.
Further, in step f, a diameter of 1 meter of each gear wave circle pier, be highly 4 meters, in the horizontal direction every 0.5 meter pours in this way, in vertical direction, corresponding to pour gear wave circle pier every two meters, so pours four rows, then Between two rows of, a center line is taken, center line is drawn in the gap vertical direction that previous row's each two is kept off between wave circle pier, obtains The point of intersection is the center of circle, and gear wave circle pier is poured with armored concrete with this center of circle.
Further, in step i, the first length of blade of first row wind-driven generator and third air draft power generator is 10 Rice, the first tower height are 10 meters, and the second length of blade of second row wind-driven generator and the 4th air draft power generator is 30 meters, Second tower height is 30 meters, is 5 meters per the spacing between two rows wind-driven generator.
The present invention is by adopting the above-described technical solution, have the advantages that:
The smart structural design of the Anti-Typhoon dykes and dams of seashore of the present invention is reasonable, the dam of coastal area is made it is sturdy and durable, With the dam body of reinforced concrete structure so that dam body is firm, and has the cylinder goed deep into pit foundation inside dam body, ensure that The stabilization of structure pours protective layer on the unrestrained body of gear so that the unrestrained body of gear has preferably anti-unrestrained ability, is provided on the unrestrained body of gear Hollow gear wave justifies pier, and wave is disperseed to drain, and hollow gear wave is justified pier and can be saved by sea beat to when keeping off on wave circle pier The about dosage of concrete, it is cost-effective, windbreak is provided on dam body, typhoon when can cut down typhoon to a certain extent Power, the resource of the wind of coastal area is abundant, and wind-driven generator is provided with above windbreak, and a part for wind is moved It can be converted into electric energy, it is interim over typhoon day, the power of the typhoon of a part can be also cut down, the Anti-Typhoon of dam has been truly realized Ability.
The present invention changes the design of existing seashore dykes and dams, using the Anti-Typhoon dykes and dams of the seashore of reinforced concrete structure, and adds The strong anti-sea beat ability in surface, and windbreak and wind-driven generator are added, overall construction design is ingenious rationally, after being convenient for The maintenance of phase can effectively improve the anti-sea beat ability of seashore dykes and dams by the construction method, effectively prevent seashore dykes and dams Cave in, extend seashore dykes and dams service life, effectively convert wind energy into electric energy, reduce typhoon balcony to a certain extent The power of wind realizes the anti-typhoon capacity of seashore dykes and dams.
Description of the drawings
The invention will be further described below in conjunction with the accompanying drawings:
Fig. 1 is Anti-Typhoon dam configuration schematic diagram in the present invention;
Fig. 2 is pit foundation schematic diagram in the present invention;
Fig. 3 is the structural schematic diagram of pit foundation middle column body in the present invention;
In figure:1- construction seashores;2- foundation pits;3- cylinders;4- gear wave circle piers;5- dam bodys;The unrestrained body of 6- gears;7- windbreaks;8- Protective layer;The second blades of 9-;The first blades of 10-;The second pylons of 11-;The first pylons of 12-.
Specific implementation mode
As shown in Figure 1 to Figure 3, it is a kind of Anti-Typhoon dykes and dams of seashore of the present invention and its building method, includes the following steps:
A, excavation of foundation pit
Exploration scene carries out foundation excavation to construction seashore 1, digs 10 to 20 meters of depths downwards, then uses hook machine to construction sea Bank 1 carries out smooth, then measures unwrapping wire;
B, Foundation treatment
The rubble of one layer of 50cm thickness, the mixture of lime and flyash are laid in construction foundation pit 2, then with hook machine to this Metalling be compacted smooth, then with flyash hydration reaction occurs for the lime allowed between rubble;
C, foundation pit makes column
3 meters of depths a diameter of 3 meters of holes is dug on foundation pit 2, be used in combination concrete reinforcement 10 meters to 20 meters outside drilling and hole Cylinder 3 is poured vertically with concrete in height, and a cylinder 3 is built in this way every 15 meters;
D, bar-mat reinforcement casting concrete is built
Vertical 10 meters to the 20 meters high reinforcing bars in foundation pit 2, reinforcing bar is built into it is latticed, then with concreting dam body 5, reach 10 meters to 20 meters;
E, pouring for unrestrained body is kept off
The gear wave body 6 of dam body 5 is poured with rock-fill concrete;
F, pouring for wave circle pier is kept off
On the inclined-plane of the unrestrained body of gear 6, columned bar-mat reinforcement is built with reinforcing bar, then with concreting at it is intermediate be hollow The gear wave of structure justifies pier 4;
G, the protective layer of the unrestrained body of gear is poured
With polyurethane and loose broken granite with 3:100 ratio is mixed, and then pours 1 meter of thickness on gear wave body 6 The protective layer 8 of degree;
H, the construction of windbreak
20 meters of high reinforcing bars are holded up in the top of dam body 5, reinforcing bar are built into latticed, then are molded with concreting, It is cast into the windbreak 7 of rectangular-shape;
I, the installation of wind-driven generator
On windbreak, front and back four air draft power generators are installed.
Further, in step f, a diameter of 1 meter of each gear wave circle pier 4, be highly 4 meters, in the horizontal direction every 0.5 meter pours in this way, in vertical direction, corresponding to pour gear wave circle pier 4 every two meters, so pours four rows, then Between two rows of, a center line is taken, center line is drawn in the gap vertical direction that previous row's each two is kept off between wave circle pier 4, takes The point that must intersect is the center of circle, and gear wave circle pier 4 is poured with armored concrete with this center of circle.
Further, in step i, 10 length of the first blade of first row wind-driven generator and third air draft power generator is 10 meters, 12 height of the first pylon is 10 meters, and 9 length of the second blade of second row wind-driven generator and the 4th air draft power generator is 30 meters, 11 height of the second pylon is 30 meters, is 5 meters per the spacing between two rows wind-driven generator.
The smart structural design of the Anti-Typhoon dykes and dams of seashore of the present invention is reasonable, the dam of coastal area is made it is sturdy and durable, With the dam body of reinforced concrete structure so that dam body is firm, and has the cylinder goed deep into pit foundation inside dam body, ensure that The stabilization of structure pours protective layer on the unrestrained body of gear so that the unrestrained body of gear has preferably anti-unrestrained ability, is provided on the unrestrained body of gear Hollow gear wave justifies pier, and wave is disperseed to drain, and hollow gear wave is justified pier and can be saved by sea beat to when keeping off on wave circle pier The about dosage of concrete, it is cost-effective, windbreak is provided on dam body, typhoon when can cut down typhoon to a certain extent Power, the resource of the wind of coastal area is abundant, and wind-driven generator is provided with above windbreak, and a part for wind is moved It can be converted into electric energy, it is interim over typhoon day, the power of the typhoon of a part can be also cut down, the Anti-Typhoon of dam has been truly realized Ability.
The present invention changes the design of existing seashore dykes and dams, using the Anti-Typhoon dykes and dams of the seashore of reinforced concrete structure, and adds The strong anti-sea beat ability in surface, and windbreak and wind-driven generator are added, overall construction design is ingenious rationally, after being convenient for The maintenance of phase can effectively improve the anti-sea beat ability of seashore dykes and dams by the construction method, effectively prevent seashore dykes and dams Cave in, extend seashore dykes and dams service life, effectively convert wind energy into electric energy, reduce typhoon balcony to a certain extent The power of wind realizes the anti-typhoon capacity of seashore dykes and dams.
It these are only specific embodiments of the present invention, but the technical characteristic of the present invention is not limited thereto.It is any with this hair Based on bright, for the technique effect for realizing essentially identical, made ground simple change, equivalent replacement or modification etc. are all covered Among protection scope of the present invention.

Claims (3)

1. a kind of Anti-Typhoon dykes and dams of seashore and its building method, which is characterized in that include the following steps:
A, excavation of foundation pit
Exploration scene carries out foundation excavation to construction seashore, digs 10 to 20 meters of depths downwards, is then carried out to construction seashore with hook machine It is smooth, then measure unwrapping wire;
B, Foundation treatment
The rubble of one layer of 50cm thickness, the mixture of lime and flyash are laid in construction foundation pit, then with hook machine to the rubble Layer be compacted smooth, then with flyash hydration reaction occurs for the lime allowed between rubble,;
C, foundation pit makes column
3 meters of depths a diameter of 3 meters of holes is dug on foundation pit, be used in combination concrete reinforcement outside drilling and hole 10 meters to 20 meter Gao Nei use Concrete pours cylinder vertically, and a cylinder is built in this way every 15 meters;
D, bar-mat reinforcement casting concrete is built
Vertical 10 meters to the 20 meters high reinforcing bars in foundation pit, reinforcing bar are built into latticed, then with concreting dam body, are reached 10 meters to 20 meters;
E, pouring for unrestrained body is kept off
The gear wave body of dam body is poured with rock-fill concrete;
F, pouring for wave circle pier is kept off
On the inclined-plane of the unrestrained body of gear, columned bar-mat reinforcement is built with reinforcing bar, then with concreting at centre is hollow-core construction Gear wave justify pier;
G, the protective layer of the unrestrained body of gear is poured
With polyurethane and loose broken granite with 3:100 ratio is mixed, and the anti-of 1 meter of thickness is then poured on the unrestrained body of gear Sheath;
H, the construction of windbreak
20 meters of high reinforcing bars are holded up above dam body, reinforcing bar are built into latticed, then are molded, are cast into concreting The windbreak of rectangular-shape;
I, the installation of wind-driven generator
On windbreak, front and back four air draft power generators are installed.
2. the Anti-Typhoon dykes and dams of seashore according to claim 1 and its building method, it is characterised in that:In the step f, A diameter of 1 meter of each gear wave circle pier, is highly 4 meters, is poured in this way every 0.5 meter in the horizontal direction, vertical It is corresponding to pour gear wave circle pier every two meters on direction, four rows are so poured, then between every two rows, a center line is taken, preceding Center line is drawn in gap vertical direction between one row's each two gear wave circle pier, the point for obtaining intersection is the center of circle, is used with this center of circle Armored concrete pours gear wave circle pier.
3. the Anti-Typhoon dykes and dams of seashore according to claim 1 and its building method, it is characterised in that:In the step i, First length of blade of first row wind-driven generator and third air draft power generator is 10 meters, and the first tower height is 10 meters, the Second length of blade of two air draft power generators and the 4th air draft power generator be 30 meters, the second tower height be 30 meters, every two Spacing between air draft power generator is 5 meters.
CN201810073264.8A 2018-01-25 2018-01-25 A kind of Anti-Typhoon dykes and dams of seashore and its building method Pending CN108385610A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810073264.8A CN108385610A (en) 2018-01-25 2018-01-25 A kind of Anti-Typhoon dykes and dams of seashore and its building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810073264.8A CN108385610A (en) 2018-01-25 2018-01-25 A kind of Anti-Typhoon dykes and dams of seashore and its building method

Publications (1)

Publication Number Publication Date
CN108385610A true CN108385610A (en) 2018-08-10

Family

ID=63077215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810073264.8A Pending CN108385610A (en) 2018-01-25 2018-01-25 A kind of Anti-Typhoon dykes and dams of seashore and its building method

Country Status (1)

Country Link
CN (1) CN108385610A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1961150A (en) * 2003-11-19 2007-05-09 风力节能有限公司 Renewable energy resources
CN101198666A (en) * 2005-06-14 2008-06-11 巴斯福股份公司 Process for the production of a composite of stones and a plastic
WO2015054734A1 (en) * 2013-10-16 2015-04-23 Oceanlinx Ltd. Coastal protection and wave energy generation system
CN205857126U (en) * 2016-08-13 2017-01-04 海琴 Novel water conservancy dam configuration
CN106978796A (en) * 2016-01-18 2017-07-25 李星明 A kind of method of quick firm dam

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1961150A (en) * 2003-11-19 2007-05-09 风力节能有限公司 Renewable energy resources
CN101198666A (en) * 2005-06-14 2008-06-11 巴斯福股份公司 Process for the production of a composite of stones and a plastic
WO2015054734A1 (en) * 2013-10-16 2015-04-23 Oceanlinx Ltd. Coastal protection and wave energy generation system
CN106978796A (en) * 2016-01-18 2017-07-25 李星明 A kind of method of quick firm dam
CN205857126U (en) * 2016-08-13 2017-01-04 海琴 Novel water conservancy dam configuration

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
左其华: "《中国海岸工程进展》", 30 April 2014, 海洋出版社 *
陈虹: "《工程建设监理实用全书 上》", 31 May 1999, 中国建材工业出版社 *
隋良志等: "《建筑与装饰材料》", 30 September 2008, 天津大学出版社 *

Similar Documents

Publication Publication Date Title
CN108867688A (en) A kind of offshore wind turbine gravity type foundation and its installation method
CN204849680U (en) Novel ecological shore protection system
CN108867684A (en) Offshore wind turbine gravity caisson basis and its installation method
CN108798684B (en) A kind of method of completely decomposed fine sand stratum tunnel excavation
CN107489128A (en) A kind of protector for Hydraulic and Hydro-Power Engineering side slope
CN108677992A (en) Offshore wind turbine prestressing force gravity type foundation and its installation method
CN205475107U (en) Novel multi -functional reservoir dam structure
CN208763050U (en) Offshore wind turbine gravity caisson basis
CN113026795A (en) Water wind power tower consolidation rockfill column pier surrounding type foundation and construction method thereof
CN112411514A (en) Ecological wind-prevention and sand-fixation system for railway protection
CN105926660B (en) A kind of construction method on intertidal belt wind electric low pile cap basis
CN207933975U (en) A kind of high stability concrete structure for slope protection system
CN201582062U (en) Foundation structure of gravity type marine wind turbine group
CN112663616A (en) Cylindrical grouting equipment and construction method thereof
CN217325279U (en) Annual construction cofferdam type of hydropower station diversion tunnel inlet
CN208917861U (en) A kind of offshore wind turbine gravity type foundation
CN115387290B (en) Hydraulic and hydroelectric engineering overflow dam structure
CN108385610A (en) A kind of Anti-Typhoon dykes and dams of seashore and its building method
CN207211073U (en) A kind of river anti-impact spats
CN101649607A (en) Method for constructing ecological riverway slope
CN212077809U (en) Slope protection net is used in construction of rock-fill dam slope of falling into water side
CN205369167U (en) Back -up sand gravel material weir dam body is thrown to aquatic
CN108570964A (en) A kind of Ecological Retaining Wall and construction method based on bank slope supporting
CN105256763A (en) Diking method based on bamboo raft frame structure
CN204000745U (en) A kind of bulwark

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180810