CN108360473A - The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating - Google Patents

The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating Download PDF

Info

Publication number
CN108360473A
CN108360473A CN201810131029.1A CN201810131029A CN108360473A CN 108360473 A CN108360473 A CN 108360473A CN 201810131029 A CN201810131029 A CN 201810131029A CN 108360473 A CN108360473 A CN 108360473A
Authority
CN
China
Prior art keywords
bank
choose
chosen
sides
energy dissipating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810131029.1A
Other languages
Chinese (zh)
Inventor
夏鹏飞
霍倩倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yangling Vocational and Technical College
Original Assignee
Yangling Vocational and Technical College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yangling Vocational and Technical College filed Critical Yangling Vocational and Technical College
Priority to CN201810131029.1A priority Critical patent/CN108360473A/en
Publication of CN108360473A publication Critical patent/CN108360473A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/06Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention is that bank construction method is chosen in a kind of three-dimensional scatter energy dissipating, can increase the aerial aeration effect of water body, increase the overboard region area of overflow, is reduced into water discharge per unit width, and effect of energy dissipation is improved, and decrease washes away riverbed.The technical solution adopted by the present invention is:Step 1:The conventional wide continuous outlet point midway for choosing bank is lifted certain altitude upwards, and it is connected with straight line with choosing bank initial position midpoint and choose bank outlet port both sides endpoint, makes to choose bank interior central area and forms a upward sphenoid structure;Step 2:Choose bank initial position midpoint in the plane with choose bank outlet both sides endpoint linearly connect, it is in triangular shape to make the structure in the plane, this at two straight line choose projection on bank in anti-arc and form an arc, choose bank initial position midpoint and be connected by the camber line with bank terminal position both sides endpoint is chosen;Step 3:Bank both sides abutment wall will be chosen simultaneously to cancel.

Description

The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating
One, technical field:
The present invention relates to belong to flood-discharge energy-dissipating field in hydraulic and hydroelectric engineering, and in particular to bank construction is chosen in a kind of three-dimensional scatter energy dissipating Method.
Two, background technology:
In hydraulic and hydroelectric engineering, is limited sometimes by terrain or for from the aspect of to construction investment, there is one kind to let out Water buildings jet bucket axis is in nearly orthogonal with river center line(The two angle is 70 ° ~ 110 °)The case where(Such as Fig. 1 institutes Show), good dispersion energy dissipating should be realized in such cases, and is needed to limit and chosen the flip shot distance of bank overflow to ensure not wash away River opposite bank bank slope.
It is followed from the perspective of energy dissipating, in engineering and is dispensed into water to increase effective upstream face product as much as possible to realize The principle of energy dispersive, there are commonly inclined cutouts of the narrow slit type of longitudinal stretching overflow and overflow extending transversely etc. effectively to disappear It can work.However, slit-type energy dissipation be mainly by the narrow effect of the beam to jet bucket use flowing water body in it is longitudinal with stand to drawing It stretches, this will certainly increase sater professionals to be unfavorable for the erosion control of opposite bank bank slope;Although and chamferring bank has certain lateral expansion Effect is dissipated, but it is more faint to the influence for reducing the farthest drop point of overflow.
Three, invention content
Bank construction method is chosen in a kind of three-dimensional scatter energy dissipating of present invention offer, to prevent water area from not washing away river opposite bank bank slope.
To achieve the above object, the technical solution adopted by the present invention is:
The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating, it is characterised in that:The construction procedure is:
Step 1:The conventional wide continuous outlet point midway for choosing bank is lifted certain altitude upwards, and it is originated with bank is chosen Position midpoint and choose bank outlet port both sides endpoint and be connected with straight line, make to choose bank interior central area formed one it is prominent upwards The sphenoid structure risen;
Step 2:Choose bank initial position midpoint in the plane with choose bank outlet both sides endpoint linearly connect, to make the structure Be in triangular shape in the plane, this at two straight line choose projection on bank in anti-arc and form an arc, choose bank initial position midpoint and choose bank Terminal position both sides endpoint is connected by the camber line;
Step 3:Bank both sides abutment wall will be chosen simultaneously to cancel.
Sphenoid end height h=(1.1~2.0)h0, h0To choose the depth of water in bank, when river is wider, center can be made to choose flowing water Amount appropriateness increases, and h can use smaller value at this time;Conversely, when positioned at Narrow Valleys, h can be taken higher value, to reduce overflow most It is remote choose away from.
When river relative narrower, make arctan(h/L)≥(π/180)θ, wherein θ are that can be protected with what angle indicated Card choose bank have farthest choose away from choose angle, take 40 °, L is the floor projection length for choosing bank ogee section.
Compared with prior art, the invention has the advantages that and effect:
The present invention makes water body realize the dispersion of diversification after the flip shot of flood releasing structure end is gone out, and can shorten overflow of growing It chooses away from the erosion damage to weaken water body for river opposite bank bank slope, and largely interior in a limited space can realize water The high degree of dispersion of body increases the overboard region area of overflow, reduces into water discharge per unit width to increase the aerial aeration effect of water body, Effect of energy dissipation is improved, decrease washes away riverbed.
Four, it illustrates
Fig. 1 discharge structures and river nearly orthogonal typical layout;
Fig. 2 is that the present invention chooses bank structural schematic diagram;
Fig. 3 is the structural model figure of the present invention;
Fig. 4 is the vertical view of Fig. 2;
Fig. 5 is the side view of Fig. 2;
Fig. 6, which is that routine is wide, continuously chooses bank vertical view;
Fig. 7, which is that routine is wide, continuously chooses bank side view;
Fig. 8 " three-dimensional scatter energy dissipating " structure typical flow pattern one;
Fig. 9 " three-dimensional scatter energy dissipating " structure typical flow pattern two;
Figure 10 chooses bank overflow drop point canonical schema;A routinely chooses bank;B three-dimensional scatters choose bank.
Five, specific implementation mode
It is limited with reference to specific embodiment technical scheme of the present invention is further:
The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating(Referring to Fig. 2 and Fig. 7), the construction procedure is:
Step 1:The conventional wide continuous outlet point midway for choosing bank is lifted certain altitude upwards, and it is originated with bank is chosen Position midpoint and choose bank outlet port both sides endpoint and be connected with straight line, make to choose bank interior central area formed one it is prominent upwards The sphenoid structure risen;
Step 2:Choose bank initial position midpoint in the plane with choose bank outlet both sides endpoint linearly connect, to make the structure Be in triangular shape in the plane, this at two straight line choose projection on bank in anti-arc and form an arc, choose bank initial position midpoint and choose bank Terminal position both sides endpoint is connected by the camber line;
Step 3:Simultaneously to increase the horizontal proliferation effect for choosing bank, bank both sides abutment wall will be chosen and cancelled.
The present invention chooses bank separation beam corporeity, the transversely acting that flow of growing is applied by wedge structure so that go out The trend of oriented two side diffusion of tongue of carrying water, it is lateral by intermediate wedge structure further as the reason chosen bank side wall and be cancelled Notch flip shot that the part water body of effect occurs from side due to the cancellation of abutment wall and go out, to substantially increase flow Horizontal proliferation so that the water length that enters that flow enters downstream river course is significantly increased, and greatly reduces water and flows into water discharge per unit width; Simultaneously because the presence of intermediate wedge structure so that flow has different flip shot angles upwards vertical, to make overflow in centre Closely, the remote inner concavity in both sides enters water form, and by numerical computations, it is as shown in Figure 8 and Figure 9 to choose bank typical flow pattern for this.
Influence the major parameter that overflow enters water form(Referring to Fig. 2-Fig. 5)Be sphenoid end height h, h size it is direct Be related to overflow of growing laterally and longitudinal assignment of traffic ratio, the h the big, choose bank midline position water flow it is smaller and two Side water flow is bigger, and upstream area depression is deeper for overflow drop point center, and vice versa(It is typical that difference chooses bank overflow drop point Schematic diagram is shown in Figure 10);It can make both sides water flow excessive if h is excessive and enter water discharge per unit width to increase both sides.In order to make Flow disperse as far as possible and realize well shorten overflow longitudinally choose away from purpose, general h=(1.1~2.0)h0, h0To choose bank The interior depth of water, but orographic condition can also have an impact h, when river is wider, center can be made to choose streamflow and moderately increased, h can at this time Take smaller value;Conversely, when positioned at Narrow Valleys, h can be taken higher value, farthest be chosen to reduce overflow away from concrete numerical value needs It just can determine that according to river width.
In addition, when river relative narrower, arctan can be made(h/L)≥(π/180)θ, wherein θ are to be indicated with angle Can ensure choose bank have farthest choose away from choose angle, generally take 40 °, so as to effectively shorten overflow it is farthest choose away from.

Claims (3)

1. the construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating, it is characterised in that:The construction procedure is:
Step 1:The conventional wide continuous outlet point midway for choosing bank is lifted certain altitude upwards, and it is originated with bank is chosen Position midpoint and choose bank outlet port both sides endpoint and be connected with straight line, make to choose bank interior central area formed one it is prominent upwards The sphenoid structure risen;
Step 2:Choose bank initial position midpoint in the plane with choose bank outlet both sides endpoint linearly connect, to make the structure Be in triangular shape in the plane, this at two straight line choose projection on bank in anti-arc and form an arc, choose bank initial position midpoint and choose bank Terminal position both sides endpoint is connected by the camber line;
Step 3:Bank both sides abutment wall will be chosen simultaneously to cancel.
2. the construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating according to claim 1, it is characterised in that:Sphenoid end Height h=(1.1~2.0)h0, h0To choose the depth of water in bank, when river is wider, make center choose streamflow moderately increase, at this time h take compared with Small value;Conversely, when positioned at Narrow Valleys, h is taken into higher value, to reduce overflow farthest choose away from.
3. the construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating according to claim 1, it is characterised in that:When river is opposite When relatively narrow, make arctan(h/L)≥(π/180)θ, wherein θ be with angle indicate can ensure to choose bank have it is farthest choose away from Choose angle, take 40 °, L chooses the floor projection length of bank ogee section.
CN201810131029.1A 2018-02-09 2018-02-09 The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating Pending CN108360473A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810131029.1A CN108360473A (en) 2018-02-09 2018-02-09 The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810131029.1A CN108360473A (en) 2018-02-09 2018-02-09 The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating

Publications (1)

Publication Number Publication Date
CN108360473A true CN108360473A (en) 2018-08-03

Family

ID=63005410

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810131029.1A Pending CN108360473A (en) 2018-02-09 2018-02-09 The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating

Country Status (1)

Country Link
CN (1) CN108360473A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110747830A (en) * 2019-10-22 2020-02-04 四川大学 Reverse tongue-shaped flip bucket

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189024A (en) * 1995-01-09 1996-07-23 Nippon Concrete Ind Co Ltd Method for constructing apron of dam
CN202440803U (en) * 2012-02-13 2012-09-19 中国水电顾问集团成都勘测设计研究院 Air-entraining structure for flood releasing building
CN103276703B (en) * 2013-06-14 2015-03-11 西北农林科技大学 Folded-line shape diversion pier of spillway
CN205035778U (en) * 2015-09-14 2016-02-17 珠江水利委员会珠江水利科学研究院 Flip trajectory bucket worker
CN205077460U (en) * 2015-09-09 2016-03-09 珠江水利委员会珠江水利科学研究院 A class bank is chosen to differential type
CN106930249A (en) * 2017-04-17 2017-07-07 四川大学 A kind of taper volute chamber rotational flow silo flood discharging tunnel system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189024A (en) * 1995-01-09 1996-07-23 Nippon Concrete Ind Co Ltd Method for constructing apron of dam
CN202440803U (en) * 2012-02-13 2012-09-19 中国水电顾问集团成都勘测设计研究院 Air-entraining structure for flood releasing building
CN103276703B (en) * 2013-06-14 2015-03-11 西北农林科技大学 Folded-line shape diversion pier of spillway
CN205077460U (en) * 2015-09-09 2016-03-09 珠江水利委员会珠江水利科学研究院 A class bank is chosen to differential type
CN205035778U (en) * 2015-09-14 2016-02-17 珠江水利委员会珠江水利科学研究院 Flip trajectory bucket worker
CN106930249A (en) * 2017-04-17 2017-07-07 四川大学 A kind of taper volute chamber rotational flow silo flood discharging tunnel system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110747830A (en) * 2019-10-22 2020-02-04 四川大学 Reverse tongue-shaped flip bucket

Similar Documents

Publication Publication Date Title
CN104775393A (en) Deformed inverse step rectifying energy dissipation method and stilling basin
CN106436659A (en) Special-shaped step energy dissipater
CN106498909B (en) For spillway on bank or the defrlector bucket of flood discharge hole outlet
CN108360473A (en) The construction method of bank is chosen in a kind of three-dimensional scatter energy dissipating
CN111501682A (en) Flood discharge orifice multilayer asymmetric arrangement method suitable for high arch dam
CN114059501B (en) Method for estimating flow distribution after water entering after surface deep hole water tongue air collision
CN101864754B (en) Inclined flip bucket for spillway or flood discharge hole outlet
CN108005039A (en) It is a kind of to be arranged at the energy dissipating construction for letting out groove
CN103669301A (en) High-low ridge stilling pool achieving double-layer disperse energy dissipation
CN206971181U (en) A kind of multichannel bank stiling basin of dispersible energy dissipating
CN106894399B (en) Structure and method for adjusting flood discharge water flow distribution
CN104563067A (en) Method for eliminating deviation of water jet of water tongue shock wave of slot sill and auto-correcting deviation slot sill
CN108517842A (en) Asymmetric aeration method suitable for curving spillway
CN208009378U (en) A kind of longitudinal direction formula High-low Bucket Energy Dissipation Building straggly
CN111979989B (en) Tweezer-shaped water tongue transverse collision energy dissipater
CN205077460U (en) A class bank is chosen to differential type
CN114718028A (en) Double-layer dispersed energy dissipation device for water flow energy dissipation
CN213389967U (en) Energy dissipation dam for river and lake water body
CN209412796U (en) A kind of energy dissipation by hydraulic jump structure extending to stilling pond suitable for flaring gate pier
CN210597232U (en) Flip bucket based auxiliary energy dissipation building block
CN112796284A (en) Choose face mixed flow energy dissipation type
CN206408597U (en) The tail pier and gate pier component of spillway
CN110747830A (en) Reverse tongue-shaped flip bucket
CN203603126U (en) Double-layer dispersion energy dissipation high-and-low sill stilling pool
CN219100252U (en) Combined type drainage ditch force dissipating structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803