CN108343626A - Big Megawatt fan performance test frock and the test method realized using the tooling - Google Patents
Big Megawatt fan performance test frock and the test method realized using the tooling Download PDFInfo
- Publication number
- CN108343626A CN108343626A CN201810120722.9A CN201810120722A CN108343626A CN 108343626 A CN108343626 A CN 108343626A CN 201810120722 A CN201810120722 A CN 201810120722A CN 108343626 A CN108343626 A CN 108343626A
- Authority
- CN
- China
- Prior art keywords
- big
- megawatt fan
- fan
- test
- connecting flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F04—POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
- F04D—NON-POSITIVE-DISPLACEMENT PUMPS
- F04D27/00—Control, e.g. regulation, of pumps, pumping installations or pumping systems specially adapted for elastic fluids
- F04D27/001—Testing thereof; Determination or simulation of flow characteristics; Stall or surge detection, e.g. condition monitoring
Abstract
The test method realized the invention discloses a kind of big Megawatt fan performance test frock and using the tooling, the tooling includes being configured with the first connecting flange of the first connection studs, it is configured with the second connecting flange of the second connection studs, rope, first connecting flange is connect by the first connection studs with the main shaft of big Megawatt fan, second connecting flange is connect by the second connection studs with the main shaft of small Megawatt fan, first connecting flange, second connecting flange is opposed in opposite directions, and both opposite one side is arranged with multiple lifting lugs, first connecting flange and the second connecting flange are attached in such a way that rope winds lifting lug, and the main shaft of big Megawatt fan, first connecting flange, second connecting flange, the main shaft of small Megawatt fan is same rotation centerline.The present invention can efficiently accomplish the performance test of big Megawatt fan.
Description
Technical field
The present invention relates to the technical fields of draught fan performance test, refer in particular to a kind of big Megawatt fan performance test frock
And the test method realized using the tooling.
Background technology
Known in the industry, the performance for understanding, evaluation and analysis each parts of wind turbine usually carries out various testing experiments, surveys
The purpose of examination is:It was found that various defects of the wind turbine in design, material and technique etc., through analyzing and improve, make wind turbine can
Gradually increased by property, is finally reached scheduled reliability level, while can also be complete to improve the war preparedness of generating set
Property, reduce maintenance cost provide safeguard, meet defined reliability quantification requirement to determine whether wind turbine meets, as power whether
Reach target etc..Currently, wind turbine, towards ultra-compact, the direction of big MW class is developed, and the maintenance and replacement of fan are brought
The big MW class such as inconvenience, especially offshore wind turbine requires the performance reliability of each parts of wind turbine also higher and higher.
For the reliability of guarantee fan performance, then wind turbine is tested for the property, in Wind turbines model machine R&D process,
Such as in the case of no conventional complete machine full power trial (FPT) platform, it can not be surveyed by Partial Power to being tested after final assembly
The method of examination carries out performance verification to Wind turbines to be particularly important, however then needs draught fan performance test by certain
Bill is tested to carry out, therefore there is the demands for probing into big Megawatt fan test method, to ensure that fan test reaches pre-
Phase purpose.
Invention content
It is an object of the invention to overcome big Megawatt fan centering relatively difficult, on the basis of time-consuming, for big
Megawatt fan performance test problem, it is proposed that a kind of good economy performance, big Megawatt fan performance simple and reliable, easy to use
Test fixture and the test method realized using the tooling.
To achieve the above object, technical solution provided by the present invention is as follows:
Big Megawatt fan performance test frock, the big Megawatt fan in the performance test, need to be configured with one
The small Megawatt fan of platform drags it, and is by the tooling between the big Megawatt fan and small Megawatt fan
It is flexibly connected;Wherein, the tooling includes the first connecting flange for being configured with the first connection studs, is configured with second
The second connecting flange, the rope of studs are connected, first connecting flange passes through the first connection studs and big megawatt
The main shaft connection of grade wind turbine, the main biography that second connecting flange passes through the second connection studs and small Megawatt fan
Moving axis connects, and first connecting flange, the second connecting flange are opposed in opposite directions, and both opposite one side is arranged with
Multiple lifting lugs, first connecting flange and the second connecting flange are attached in such a way that rope winds lifting lug, and described
The main shaft of big Megawatt fan, the first connecting flange, the second connecting flange, small Megawatt fan main shaft be same
Rotation centerline is dragged big Megawatt fan come the feature and working method of simulates blower fan by small Megawatt fan, is reached with this
To the performance test to big Megawatt fan.
Whole-root rope only has head and the tail section to connect, and centre is not allow for other connectors.
The rope is nylon rope or hawser.
The test method realized using above-mentioned tooling mainly utilizes small Megawatt fan to be used when dragging motor, and big
Megawatt fan is then run according to normal power generation mode, and big Megawatt fan is dragged come simulates blower fan by small Megawatt fan
Feature and working method reach the performance test to big Megawatt fan with this;Wherein, connection two Fans test fixture by
Then transition connection is carried out with rope, thus has the characteristics that flexible clutch, and two Fans form entire circuit so that
Power circulates between two Fans, and the power attenuation of two Fans is then to be connected to plant-grid connection point by transformer
It compensates;
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V,
50Hz, 1250A;C) 380V, 50Hz, 400A;Wherein, select 1250A access point be test main circuit power, select 315A and
The access point of 400A is the power supply of wind turbine ancillary equipment electricity consumption;
In test, small Megawatt fan rotating speed is slowly increased to rated speed from zero, and big Megawatt fan is carried out with this
Partial Power is tested, and tested wind turbine output power ability mainly according to small Megawatt fan, determine under corresponding rotating speed by dragging capabilities
It is fixed;Wherein, the efficiency of the several critical components of the transmission chain of wind turbine is respectively:Gear-box >=0.96, generator >=0.95, frequency converter
>=0.98, the efficiency of flexible clutch takes 1, and the transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big
Megawatt fan exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test mistake
Cheng Wei:The power generation mode of original frequency converter is revised as dragging operation mould by the frequency converter method of operation for changing small Megawatt fan
Formula provides power initiation operation to the generator of small Megawatt fan, drags the transmission chain rotation of big Megawatt fan, checks big
Rotating speed is stepped up after the transmission chain normal operation of Megawatt fan to rated speed, continues to run until the stipulated time, is completed empty
Carry experiment process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, big MW class is given
Torque reference is stepped up setting value, detects big Megawatt fan by fan frequency converter torque, control wind turbine to grid generation
Gear-box, whether generator, frequency converter, lubricating system, master control system meet design requirement, and add in big Megawatt fan
It carries under operational mode, efficiency test, vibration-testing, noise test these correlation test projects can be carried out, it is big by million to complete
The performance test of watt grade wind turbine.
Compared with prior art, the present invention having the following advantages that and advantageous effect:
1, the present invention drags big Megawatt fan by small Megawatt fan, can as far as possible the feature of simulates blower fan and
Working method reaches the test to big Megawatt fan with this, and can ensure that tested wind turbine will not be made during the test
At damage, the big Megawatt fan model machine of no full power trial (FPT) platform is developed especially suitable.
2, the test fixture that the present invention uses is to carry out transition connection with rope (being specially nylon rope or high intensity hawser)
(namely flexible connection), has the characteristics that flexible clutch, and wind can not be adjusted when can be effectively avoided in this way using rigid connection
The position of machine and the requirement that merging precision cannot be met.
3, the present invention is connected using flexible structure, it is easier to which installation and implementation, operability is convenient, saves cost, and operate
Person can be according to actual conditions, active control test process.
Description of the drawings
Fig. 1 is the structural schematic diagram of tooling of the present invention.
Fig. 2 is the structural schematic diagram of the first connecting flange.
Fig. 3 is the structural schematic diagram of the second connecting flange.
Fig. 4 is scheme of installation of the tooling of the present invention in big Megawatt fan performance test.
Fig. 5 is test loop schematic diagram.
Specific implementation mode
The present invention is further explained in the light of specific embodiments.
As shown in Figures 1 to 4, the big Megawatt fan performance test frock that the present embodiment is provided, including it is configured with
First connecting flange 2 of one connection studs 1, the second connecting flange 4 and a rope for being configured with the second connection studs 3
Sub 5 (being specially nylon rope or high intensity hawser), wherein the big Megawatt fan 6 in the performance test, needs to configure
There is a small Megawatt fan 7 to drag it, with the feature and working method of simulates blower fan, and the big Megawatt fan
It is to be flexibly connected by the tooling between 6 and small Megawatt fan 7;First connecting flange 2 passes through the first connection
Studs 1 is connect with the main shaft of big Megawatt fan 6, and second connecting flange 4 passes through the second connection studs 3
It being connect with the main shaft of small Megawatt fan 7, first connecting flange 2, the second connecting flange 4 are opposite opposed, and they
The opposite one side of the two is arranged with multiple lifting lugs 8, and first connecting flange, 2 and second connecting flange 4 is restricted by one
The mode that son 5 winds lifting lug 8 is attached, and 5 only head and the tail section of whole-root rope connects, and centre is not allow for other connectors, together
The main shaft of the big Megawatt fans of Shi Suoshu 6, the main biography of the first connecting flange 2, the second connecting flange 4, small Megawatt fan 7
Moving axis is same rotation centerline.
It is the test method realized using the above-mentioned big Megawatt fan performance test frock of the present embodiment, this method master below
If utilizing small Megawatt fan (example:3.0MW wind turbines) it uses when dragging motor, and big Megawatt fan (example:5.5MW wind turbines)
It is then run according to normal power generation mode, big Megawatt fan is dragged come the feature of simulates blower fan and work by small Megawatt fan
Mode reaches the performance test to big Megawatt fan with this;Wherein, the test fixture of two Fans of connection is due to being to use rope
(being specially nylon rope or high intensity hawser) carries out transition connection (namely flexible connection), thus the spy with flexible clutch
Point, and two Fans form entire circuit so that and power circulates between two Fans, and the power of two Fans damages
Consumption is then to be connected to plant-grid connection point by transformer to compensate, as shown in Figure 5.
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V,
50Hz, 1250A;C) 380V, 50Hz, 400A;Wherein, the access point that 1250A can be selected is test main circuit power, selects 315A
Access point with 400A is the power supply of wind turbine ancillary equipment electricity consumption.
In test, run according to the following table 1 mode, small Megawatt fan rotating speed is slowly increased to rated speed from zero, with this
Carry out the Partial Power experiment of big Megawatt fan.
The 1 testing stand method of operation of table
Wherein, the efficiency of the several critical components of transmission chain of two Fans of setting is respectively:Gear-box >=0.96, generator
>=0.95, frequency converter >=0.98;The transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big MW class
Wind turbine exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test process is:It repaiies
The power generation mode of original frequency converter is revised as dragging operational mode, to small by the frequency converter method of operation for changing small Megawatt fan
The generator of Megawatt fan provides power initiation operation, drags the transmission chain rotation of big Megawatt fan, checks big MW class
Rotating speed is stepped up after the transmission chain normal operation of wind turbine to rated speed, is continued to run until the stipulated time, is completed no-load test
Process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, gives big Megawatt fan and become
Torque reference is stepped up setting value, detects the gear of big Megawatt fan by frequency device torque, control wind turbine to grid generation
Whether case, generator, frequency converter, lubricating system, master control system etc. meet design requirement, and load and transport in big Megawatt fan
Under row pattern, the correlation tests project such as efficiency test, vibration-testing, noise test can be carried out, to complete big MW class wind
The performance test of machine.The power test of certain xx type that specifically can be as shown in table 2 below, dragged wind turbine data power according to
1000kW is calculated, and Driving Fan input power is 1252kW.
Table 2xx type power calculations
Embodiment described above is only the preferred embodiments of the invention, and the implementation model of the present invention is not limited with this
It encloses, therefore changes made by all shapes according to the present invention, principle, should all cover within the scope of the present invention.
Claims (4)
1. big Megawatt fan performance test frock, it is characterised in that:The big Megawatt fan in the performance test, needs
It is dragged configured with a small Megawatt fan, and is to pass through between the big Megawatt fan and small Megawatt fan
The tooling is flexibly connected;Wherein, the tooling includes the first connecting flange for being configured with the first connection studs, matches
It is cased with the second connecting flange, the rope of the second connection studs, first connecting flange passes through the first connection studs
It is connect with the main shaft of big Megawatt fan, second connecting flange passes through the second connection studs and small MW class wind
The main shaft of machine connects, and first connecting flange, the second connecting flange are opposed in opposite directions, and both opposite one side
Multiple lifting lugs, first connecting flange and the second connecting flange is arranged in such a way that rope winds lifting lug to be connected
It connects, and the main biography of the main shaft of the big Megawatt fan, the first connecting flange, the second connecting flange, small Megawatt fan
Moving axis is same rotation centerline, and big Megawatt fan is dragged come the feature of simulates blower fan and work side by small Megawatt fan
Formula reaches the performance test to big Megawatt fan with this.
2. big Megawatt fan performance test frock according to claim 1, it is characterised in that:Whole-root rope only has head and the tail
Section connects, and centre is not allow for other connectors.
3. big Megawatt fan performance test frock according to claim 1, it is characterised in that:The rope is nylon rope
Or hawser.
4. the test method realized using big Megawatt fan performance test frock described in claim 1, it is characterised in that:It should
Method is mainly using small Megawatt fan when dragging motor use, and big Megawatt fan is then transported according to normal power generation mode
Row, is dragged big Megawatt fan come the feature and working method of simulates blower fan by small Megawatt fan, is reached to big by million with this
The performance test of watt grade wind turbine;Wherein, the test fixture of two Fans of connection is due to being to carry out transition connection with rope, thus have
The characteristics of flexible shaft coupling, and two Fans form entire circuit so that and power circulates between two Fans, and
The power attenuation of two Fans is then to be connected to plant-grid connection point by transformer to compensate;
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V, 50Hz,
1250A;C) 380V, 50Hz, 400A;Wherein, it is test main circuit power to select the access point of 1250A, selects 315A and 400A
Access point be wind turbine ancillary equipment electricity consumption power supply;
In test, small Megawatt fan rotating speed is slowly increased to rated speed from zero, and the part of big Megawatt fan is carried out with this
Power test, being tested wind turbine output power ability, mainly according to small Megawatt fan, dragging capabilities determine under corresponding rotating speed;
Wherein, the efficiency of the several critical components of the transmission chain of wind turbine is respectively:Gear-box >=0.96, generator >=0.95, frequency converter >=
0.98, the efficiency of flexible clutch takes 1, and the transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big by million
Watt grade wind turbine exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test process
For:The power generation mode of original frequency converter is revised as dragging operational mode by the frequency converter method of operation for changing small Megawatt fan,
Power initiation operation is provided to the generator of small Megawatt fan, the transmission chain rotation of big Megawatt fan is dragged, checks big by million
Rotating speed is stepped up after the transmission chain normal operation of watt grade wind turbine to rated speed, continues to run until the stipulated time, is completed unloaded
Experiment process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, big MW class wind is given
Torque reference is stepped up setting value, detects big Megawatt fan by machine frequency converter torque, control wind turbine to grid generation
Whether gear-box, generator, frequency converter, lubricating system, master control system meet design requirement, and are loaded in big Megawatt fan
Under operational mode, efficiency test, vibration-testing, noise test these correlation test projects can be carried out, to complete big megawatt
The performance test of grade wind turbine.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810120722.9A CN108343626A (en) | 2018-02-07 | 2018-02-07 | Big Megawatt fan performance test frock and the test method realized using the tooling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810120722.9A CN108343626A (en) | 2018-02-07 | 2018-02-07 | Big Megawatt fan performance test frock and the test method realized using the tooling |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108343626A true CN108343626A (en) | 2018-07-31 |
Family
ID=62959613
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810120722.9A Pending CN108343626A (en) | 2018-02-07 | 2018-02-07 | Big Megawatt fan performance test frock and the test method realized using the tooling |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108343626A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110173472A (en) * | 2019-05-15 | 2019-08-27 | 明阳智慧能源集团股份公司 | The test bed hydraulic system of wind turbine gearbox flexible pin shaft and its control method |
CN113790886A (en) * | 2021-04-23 | 2021-12-14 | 重庆大学 | Method for testing wind resistance power loss of gear system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101509959A (en) * | 2008-12-26 | 2009-08-19 | 大连天元电机有限公司 | Low power frequency changer dragged 2MW electric generator test method |
CN201396379Y (en) * | 2009-04-30 | 2010-02-03 | 哈尔滨哈飞工业有限责任公司 | Wind generating set experiment shaft coupling |
WO2015096796A1 (en) * | 2013-12-26 | 2015-07-02 | 深圳市配天智造装备股份有限公司 | Speed reducer testing device |
CN206246550U (en) * | 2016-11-16 | 2017-06-13 | 重庆力宏精细化工有限公司 | A kind of drive apparatus main spindle coupling device for bearing irregular torque |
CN208169063U (en) * | 2018-02-07 | 2018-11-30 | 明阳智慧能源集团股份公司 | A kind of flexible frock of big MW class wind turbine group performance test |
-
2018
- 2018-02-07 CN CN201810120722.9A patent/CN108343626A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101509959A (en) * | 2008-12-26 | 2009-08-19 | 大连天元电机有限公司 | Low power frequency changer dragged 2MW electric generator test method |
CN201396379Y (en) * | 2009-04-30 | 2010-02-03 | 哈尔滨哈飞工业有限责任公司 | Wind generating set experiment shaft coupling |
WO2015096796A1 (en) * | 2013-12-26 | 2015-07-02 | 深圳市配天智造装备股份有限公司 | Speed reducer testing device |
CN206246550U (en) * | 2016-11-16 | 2017-06-13 | 重庆力宏精细化工有限公司 | A kind of drive apparatus main spindle coupling device for bearing irregular torque |
CN208169063U (en) * | 2018-02-07 | 2018-11-30 | 明阳智慧能源集团股份公司 | A kind of flexible frock of big MW class wind turbine group performance test |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110173472A (en) * | 2019-05-15 | 2019-08-27 | 明阳智慧能源集团股份公司 | The test bed hydraulic system of wind turbine gearbox flexible pin shaft and its control method |
CN110173472B (en) * | 2019-05-15 | 2024-03-26 | 明阳智慧能源集团股份公司 | Hydraulic system of wind power gear box flexible pin shaft test bench and control method thereof |
CN113790886A (en) * | 2021-04-23 | 2021-12-14 | 重庆大学 | Method for testing wind resistance power loss of gear system |
CN113790886B (en) * | 2021-04-23 | 2023-08-29 | 重庆大学 | Wind resistance power loss testing method for gear system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018000733A1 (en) | System and method for hardware-in-the-loop test of subsynchronous resonance of double-fed fan | |
CN205262736U (en) | Multistage planetary gear case combined test platform | |
CN108343626A (en) | Big Megawatt fan performance test frock and the test method realized using the tooling | |
CN107767975B (en) | Method for monitoring quality performance of weight-losing component of nuclear power plant and diagnosing fault | |
CN206235720U (en) | A kind of LED drives test system | |
WO2021258649A1 (en) | Comprehensive performance test and debugging experiment device for rotary drilling rig and experiment method | |
CN110109016A (en) | New energy automobile motor test platform | |
CN110398380A (en) | A kind of Electric Motor Wheel vehicle alternating current drive pilot system and method | |
CN111881736A (en) | Rolling bearing early fault diagnosis method based on bandwidth Fourier decomposition | |
CN104697799A (en) | Automatic load increase testing system and testing method for engine | |
CN103852255A (en) | Typical transmission fault intelligent diagnosis method based on neural network wind generating set | |
WO2024002091A1 (en) | Full-power test platform and method for tandem double-wind-wheel wind turbine generator set | |
CN107966616A (en) | Motor vehicle electromagnetic Flied emission strength test method based on car body threedimensional model | |
CN208169063U (en) | A kind of flexible frock of big MW class wind turbine group performance test | |
CN204740137U (en) | Large -scale wind generating set work performance test device | |
Tudor et al. | Locomotive Diesel Engine Test Stand with Energy Recovery in the Electrical Network | |
US20150013406A1 (en) | System and method for removing dents from a wind turbine tower | |
CN211425862U (en) | Starter load control system based on electric dynamometer | |
CN204882071U (en) | Automatic derailleur performance test bench | |
CN206671454U (en) | A kind of public test device of multi-functional different capacity inverter | |
CN111076938B (en) | Control method of starter load control system based on electric dynamometer | |
CN104931265A (en) | Large wind generating set work performance test device and test method thereof | |
CN204575328U (en) | The test macro of checking engine PTO fan-out capability | |
CN114486242A (en) | Aeroengine transmission system load spectrum and transmission efficiency measuring system | |
Zhang et al. | Non-invasive condition monitoring and diagnostics techniques for wind turbines |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |