CN108343626A - Big Megawatt fan performance test frock and the test method realized using the tooling - Google Patents

Big Megawatt fan performance test frock and the test method realized using the tooling Download PDF

Info

Publication number
CN108343626A
CN108343626A CN201810120722.9A CN201810120722A CN108343626A CN 108343626 A CN108343626 A CN 108343626A CN 201810120722 A CN201810120722 A CN 201810120722A CN 108343626 A CN108343626 A CN 108343626A
Authority
CN
China
Prior art keywords
big
megawatt fan
fan
test
connecting flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810120722.9A
Other languages
Chinese (zh)
Inventor
李德水
危志全
黄成彦
刘卫
陈艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MingYang Smart Energy Group Co Ltd
Original Assignee
MingYang Smart Energy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MingYang Smart Energy Group Co Ltd filed Critical MingYang Smart Energy Group Co Ltd
Priority to CN201810120722.9A priority Critical patent/CN108343626A/en
Publication of CN108343626A publication Critical patent/CN108343626A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04DNON-POSITIVE-DISPLACEMENT PUMPS
    • F04D27/00Control, e.g. regulation, of pumps, pumping installations or pumping systems specially adapted for elastic fluids
    • F04D27/001Testing thereof; Determination or simulation of flow characteristics; Stall or surge detection, e.g. condition monitoring

Abstract

The test method realized the invention discloses a kind of big Megawatt fan performance test frock and using the tooling, the tooling includes being configured with the first connecting flange of the first connection studs, it is configured with the second connecting flange of the second connection studs, rope, first connecting flange is connect by the first connection studs with the main shaft of big Megawatt fan, second connecting flange is connect by the second connection studs with the main shaft of small Megawatt fan, first connecting flange, second connecting flange is opposed in opposite directions, and both opposite one side is arranged with multiple lifting lugs, first connecting flange and the second connecting flange are attached in such a way that rope winds lifting lug, and the main shaft of big Megawatt fan, first connecting flange, second connecting flange, the main shaft of small Megawatt fan is same rotation centerline.The present invention can efficiently accomplish the performance test of big Megawatt fan.

Description

Big Megawatt fan performance test frock and the test method realized using the tooling
Technical field
The present invention relates to the technical fields of draught fan performance test, refer in particular to a kind of big Megawatt fan performance test frock And the test method realized using the tooling.
Background technology
Known in the industry, the performance for understanding, evaluation and analysis each parts of wind turbine usually carries out various testing experiments, surveys The purpose of examination is:It was found that various defects of the wind turbine in design, material and technique etc., through analyzing and improve, make wind turbine can Gradually increased by property, is finally reached scheduled reliability level, while can also be complete to improve the war preparedness of generating set Property, reduce maintenance cost provide safeguard, meet defined reliability quantification requirement to determine whether wind turbine meets, as power whether Reach target etc..Currently, wind turbine, towards ultra-compact, the direction of big MW class is developed, and the maintenance and replacement of fan are brought The big MW class such as inconvenience, especially offshore wind turbine requires the performance reliability of each parts of wind turbine also higher and higher.
For the reliability of guarantee fan performance, then wind turbine is tested for the property, in Wind turbines model machine R&D process, Such as in the case of no conventional complete machine full power trial (FPT) platform, it can not be surveyed by Partial Power to being tested after final assembly The method of examination carries out performance verification to Wind turbines to be particularly important, however then needs draught fan performance test by certain Bill is tested to carry out, therefore there is the demands for probing into big Megawatt fan test method, to ensure that fan test reaches pre- Phase purpose.
Invention content
It is an object of the invention to overcome big Megawatt fan centering relatively difficult, on the basis of time-consuming, for big Megawatt fan performance test problem, it is proposed that a kind of good economy performance, big Megawatt fan performance simple and reliable, easy to use Test fixture and the test method realized using the tooling.
To achieve the above object, technical solution provided by the present invention is as follows:
Big Megawatt fan performance test frock, the big Megawatt fan in the performance test, need to be configured with one The small Megawatt fan of platform drags it, and is by the tooling between the big Megawatt fan and small Megawatt fan It is flexibly connected;Wherein, the tooling includes the first connecting flange for being configured with the first connection studs, is configured with second The second connecting flange, the rope of studs are connected, first connecting flange passes through the first connection studs and big megawatt The main shaft connection of grade wind turbine, the main biography that second connecting flange passes through the second connection studs and small Megawatt fan Moving axis connects, and first connecting flange, the second connecting flange are opposed in opposite directions, and both opposite one side is arranged with Multiple lifting lugs, first connecting flange and the second connecting flange are attached in such a way that rope winds lifting lug, and described The main shaft of big Megawatt fan, the first connecting flange, the second connecting flange, small Megawatt fan main shaft be same Rotation centerline is dragged big Megawatt fan come the feature and working method of simulates blower fan by small Megawatt fan, is reached with this To the performance test to big Megawatt fan.
Whole-root rope only has head and the tail section to connect, and centre is not allow for other connectors.
The rope is nylon rope or hawser.
The test method realized using above-mentioned tooling mainly utilizes small Megawatt fan to be used when dragging motor, and big Megawatt fan is then run according to normal power generation mode, and big Megawatt fan is dragged come simulates blower fan by small Megawatt fan Feature and working method reach the performance test to big Megawatt fan with this;Wherein, connection two Fans test fixture by Then transition connection is carried out with rope, thus has the characteristics that flexible clutch, and two Fans form entire circuit so that Power circulates between two Fans, and the power attenuation of two Fans is then to be connected to plant-grid connection point by transformer It compensates;
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V, 50Hz, 1250A;C) 380V, 50Hz, 400A;Wherein, select 1250A access point be test main circuit power, select 315A and The access point of 400A is the power supply of wind turbine ancillary equipment electricity consumption;
In test, small Megawatt fan rotating speed is slowly increased to rated speed from zero, and big Megawatt fan is carried out with this Partial Power is tested, and tested wind turbine output power ability mainly according to small Megawatt fan, determine under corresponding rotating speed by dragging capabilities It is fixed;Wherein, the efficiency of the several critical components of the transmission chain of wind turbine is respectively:Gear-box >=0.96, generator >=0.95, frequency converter >=0.98, the efficiency of flexible clutch takes 1, and the transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big Megawatt fan exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test mistake Cheng Wei:The power generation mode of original frequency converter is revised as dragging operation mould by the frequency converter method of operation for changing small Megawatt fan Formula provides power initiation operation to the generator of small Megawatt fan, drags the transmission chain rotation of big Megawatt fan, checks big Rotating speed is stepped up after the transmission chain normal operation of Megawatt fan to rated speed, continues to run until the stipulated time, is completed empty Carry experiment process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, big MW class is given Torque reference is stepped up setting value, detects big Megawatt fan by fan frequency converter torque, control wind turbine to grid generation Gear-box, whether generator, frequency converter, lubricating system, master control system meet design requirement, and add in big Megawatt fan It carries under operational mode, efficiency test, vibration-testing, noise test these correlation test projects can be carried out, it is big by million to complete The performance test of watt grade wind turbine.
Compared with prior art, the present invention having the following advantages that and advantageous effect:
1, the present invention drags big Megawatt fan by small Megawatt fan, can as far as possible the feature of simulates blower fan and Working method reaches the test to big Megawatt fan with this, and can ensure that tested wind turbine will not be made during the test At damage, the big Megawatt fan model machine of no full power trial (FPT) platform is developed especially suitable.
2, the test fixture that the present invention uses is to carry out transition connection with rope (being specially nylon rope or high intensity hawser) (namely flexible connection), has the characteristics that flexible clutch, and wind can not be adjusted when can be effectively avoided in this way using rigid connection The position of machine and the requirement that merging precision cannot be met.
3, the present invention is connected using flexible structure, it is easier to which installation and implementation, operability is convenient, saves cost, and operate Person can be according to actual conditions, active control test process.
Description of the drawings
Fig. 1 is the structural schematic diagram of tooling of the present invention.
Fig. 2 is the structural schematic diagram of the first connecting flange.
Fig. 3 is the structural schematic diagram of the second connecting flange.
Fig. 4 is scheme of installation of the tooling of the present invention in big Megawatt fan performance test.
Fig. 5 is test loop schematic diagram.
Specific implementation mode
The present invention is further explained in the light of specific embodiments.
As shown in Figures 1 to 4, the big Megawatt fan performance test frock that the present embodiment is provided, including it is configured with First connecting flange 2 of one connection studs 1, the second connecting flange 4 and a rope for being configured with the second connection studs 3 Sub 5 (being specially nylon rope or high intensity hawser), wherein the big Megawatt fan 6 in the performance test, needs to configure There is a small Megawatt fan 7 to drag it, with the feature and working method of simulates blower fan, and the big Megawatt fan It is to be flexibly connected by the tooling between 6 and small Megawatt fan 7;First connecting flange 2 passes through the first connection Studs 1 is connect with the main shaft of big Megawatt fan 6, and second connecting flange 4 passes through the second connection studs 3 It being connect with the main shaft of small Megawatt fan 7, first connecting flange 2, the second connecting flange 4 are opposite opposed, and they The opposite one side of the two is arranged with multiple lifting lugs 8, and first connecting flange, 2 and second connecting flange 4 is restricted by one The mode that son 5 winds lifting lug 8 is attached, and 5 only head and the tail section of whole-root rope connects, and centre is not allow for other connectors, together The main shaft of the big Megawatt fans of Shi Suoshu 6, the main biography of the first connecting flange 2, the second connecting flange 4, small Megawatt fan 7 Moving axis is same rotation centerline.
It is the test method realized using the above-mentioned big Megawatt fan performance test frock of the present embodiment, this method master below If utilizing small Megawatt fan (example:3.0MW wind turbines) it uses when dragging motor, and big Megawatt fan (example:5.5MW wind turbines) It is then run according to normal power generation mode, big Megawatt fan is dragged come the feature of simulates blower fan and work by small Megawatt fan Mode reaches the performance test to big Megawatt fan with this;Wherein, the test fixture of two Fans of connection is due to being to use rope (being specially nylon rope or high intensity hawser) carries out transition connection (namely flexible connection), thus the spy with flexible clutch Point, and two Fans form entire circuit so that and power circulates between two Fans, and the power of two Fans damages Consumption is then to be connected to plant-grid connection point by transformer to compensate, as shown in Figure 5.
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V, 50Hz, 1250A;C) 380V, 50Hz, 400A;Wherein, the access point that 1250A can be selected is test main circuit power, selects 315A Access point with 400A is the power supply of wind turbine ancillary equipment electricity consumption.
In test, run according to the following table 1 mode, small Megawatt fan rotating speed is slowly increased to rated speed from zero, with this Carry out the Partial Power experiment of big Megawatt fan.
The 1 testing stand method of operation of table
Wherein, the efficiency of the several critical components of transmission chain of two Fans of setting is respectively:Gear-box >=0.96, generator >=0.95, frequency converter >=0.98;The transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big MW class Wind turbine exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test process is:It repaiies The power generation mode of original frequency converter is revised as dragging operational mode, to small by the frequency converter method of operation for changing small Megawatt fan The generator of Megawatt fan provides power initiation operation, drags the transmission chain rotation of big Megawatt fan, checks big MW class Rotating speed is stepped up after the transmission chain normal operation of wind turbine to rated speed, is continued to run until the stipulated time, is completed no-load test Process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, gives big Megawatt fan and become Torque reference is stepped up setting value, detects the gear of big Megawatt fan by frequency device torque, control wind turbine to grid generation Whether case, generator, frequency converter, lubricating system, master control system etc. meet design requirement, and load and transport in big Megawatt fan Under row pattern, the correlation tests project such as efficiency test, vibration-testing, noise test can be carried out, to complete big MW class wind The performance test of machine.The power test of certain xx type that specifically can be as shown in table 2 below, dragged wind turbine data power according to 1000kW is calculated, and Driving Fan input power is 1252kW.
Table 2xx type power calculations
Embodiment described above is only the preferred embodiments of the invention, and the implementation model of the present invention is not limited with this It encloses, therefore changes made by all shapes according to the present invention, principle, should all cover within the scope of the present invention.

Claims (4)

1. big Megawatt fan performance test frock, it is characterised in that:The big Megawatt fan in the performance test, needs It is dragged configured with a small Megawatt fan, and is to pass through between the big Megawatt fan and small Megawatt fan The tooling is flexibly connected;Wherein, the tooling includes the first connecting flange for being configured with the first connection studs, matches It is cased with the second connecting flange, the rope of the second connection studs, first connecting flange passes through the first connection studs It is connect with the main shaft of big Megawatt fan, second connecting flange passes through the second connection studs and small MW class wind The main shaft of machine connects, and first connecting flange, the second connecting flange are opposed in opposite directions, and both opposite one side Multiple lifting lugs, first connecting flange and the second connecting flange is arranged in such a way that rope winds lifting lug to be connected It connects, and the main biography of the main shaft of the big Megawatt fan, the first connecting flange, the second connecting flange, small Megawatt fan Moving axis is same rotation centerline, and big Megawatt fan is dragged come the feature of simulates blower fan and work side by small Megawatt fan Formula reaches the performance test to big Megawatt fan with this.
2. big Megawatt fan performance test frock according to claim 1, it is characterised in that:Whole-root rope only has head and the tail Section connects, and centre is not allow for other connectors.
3. big Megawatt fan performance test frock according to claim 1, it is characterised in that:The rope is nylon rope Or hawser.
4. the test method realized using big Megawatt fan performance test frock described in claim 1, it is characterised in that:It should Method is mainly using small Megawatt fan when dragging motor use, and big Megawatt fan is then transported according to normal power generation mode Row, is dragged big Megawatt fan come the feature and working method of simulates blower fan by small Megawatt fan, is reached to big by million with this The performance test of watt grade wind turbine;Wherein, the test fixture of two Fans of connection is due to being to carry out transition connection with rope, thus have The characteristics of flexible shaft coupling, and two Fans form entire circuit so that and power circulates between two Fans, and The power attenuation of two Fans is then to be connected to plant-grid connection point by transformer to compensate;
Before testing, 3 plant-grid connection points side by side need to be prepared, respectively:A) 380V, 50Hz, 315A;B) 380V, 50Hz, 1250A;C) 380V, 50Hz, 400A;Wherein, it is test main circuit power to select the access point of 1250A, selects 315A and 400A Access point be wind turbine ancillary equipment electricity consumption power supply;
In test, small Megawatt fan rotating speed is slowly increased to rated speed from zero, and the part of big Megawatt fan is carried out with this Power test, being tested wind turbine output power ability, mainly according to small Megawatt fan, dragging capabilities determine under corresponding rotating speed; Wherein, the efficiency of the several critical components of the transmission chain of wind turbine is respectively:Gear-box >=0.96, generator >=0.95, frequency converter >= 0.98, the efficiency of flexible clutch takes 1, and the transmission chain that small Megawatt fan dragging capabilities subtract two Fans is lost to obtain big by million Watt grade wind turbine exports measured power;Test process is broadly divided into no load test and load test two parts:1) no load test process For:The power generation mode of original frequency converter is revised as dragging operational mode by the frequency converter method of operation for changing small Megawatt fan, Power initiation operation is provided to the generator of small Megawatt fan, the transmission chain rotation of big Megawatt fan is dragged, checks big by million Rotating speed is stepped up after the transmission chain normal operation of watt grade wind turbine to rated speed, continues to run until the stipulated time, is completed unloaded Experiment process;2) load test:After the completion of no-load test, under big Megawatt fan rated speed, big MW class wind is given Torque reference is stepped up setting value, detects big Megawatt fan by machine frequency converter torque, control wind turbine to grid generation Whether gear-box, generator, frequency converter, lubricating system, master control system meet design requirement, and are loaded in big Megawatt fan Under operational mode, efficiency test, vibration-testing, noise test these correlation test projects can be carried out, to complete big megawatt The performance test of grade wind turbine.
CN201810120722.9A 2018-02-07 2018-02-07 Big Megawatt fan performance test frock and the test method realized using the tooling Pending CN108343626A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810120722.9A CN108343626A (en) 2018-02-07 2018-02-07 Big Megawatt fan performance test frock and the test method realized using the tooling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810120722.9A CN108343626A (en) 2018-02-07 2018-02-07 Big Megawatt fan performance test frock and the test method realized using the tooling

Publications (1)

Publication Number Publication Date
CN108343626A true CN108343626A (en) 2018-07-31

Family

ID=62959613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810120722.9A Pending CN108343626A (en) 2018-02-07 2018-02-07 Big Megawatt fan performance test frock and the test method realized using the tooling

Country Status (1)

Country Link
CN (1) CN108343626A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173472A (en) * 2019-05-15 2019-08-27 明阳智慧能源集团股份公司 The test bed hydraulic system of wind turbine gearbox flexible pin shaft and its control method
CN113790886A (en) * 2021-04-23 2021-12-14 重庆大学 Method for testing wind resistance power loss of gear system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509959A (en) * 2008-12-26 2009-08-19 大连天元电机有限公司 Low power frequency changer dragged 2MW electric generator test method
CN201396379Y (en) * 2009-04-30 2010-02-03 哈尔滨哈飞工业有限责任公司 Wind generating set experiment shaft coupling
WO2015096796A1 (en) * 2013-12-26 2015-07-02 深圳市配天智造装备股份有限公司 Speed reducer testing device
CN206246550U (en) * 2016-11-16 2017-06-13 重庆力宏精细化工有限公司 A kind of drive apparatus main spindle coupling device for bearing irregular torque
CN208169063U (en) * 2018-02-07 2018-11-30 明阳智慧能源集团股份公司 A kind of flexible frock of big MW class wind turbine group performance test

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101509959A (en) * 2008-12-26 2009-08-19 大连天元电机有限公司 Low power frequency changer dragged 2MW electric generator test method
CN201396379Y (en) * 2009-04-30 2010-02-03 哈尔滨哈飞工业有限责任公司 Wind generating set experiment shaft coupling
WO2015096796A1 (en) * 2013-12-26 2015-07-02 深圳市配天智造装备股份有限公司 Speed reducer testing device
CN206246550U (en) * 2016-11-16 2017-06-13 重庆力宏精细化工有限公司 A kind of drive apparatus main spindle coupling device for bearing irregular torque
CN208169063U (en) * 2018-02-07 2018-11-30 明阳智慧能源集团股份公司 A kind of flexible frock of big MW class wind turbine group performance test

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173472A (en) * 2019-05-15 2019-08-27 明阳智慧能源集团股份公司 The test bed hydraulic system of wind turbine gearbox flexible pin shaft and its control method
CN110173472B (en) * 2019-05-15 2024-03-26 明阳智慧能源集团股份公司 Hydraulic system of wind power gear box flexible pin shaft test bench and control method thereof
CN113790886A (en) * 2021-04-23 2021-12-14 重庆大学 Method for testing wind resistance power loss of gear system
CN113790886B (en) * 2021-04-23 2023-08-29 重庆大学 Wind resistance power loss testing method for gear system

Similar Documents

Publication Publication Date Title
WO2018000733A1 (en) System and method for hardware-in-the-loop test of subsynchronous resonance of double-fed fan
CN205262736U (en) Multistage planetary gear case combined test platform
CN108343626A (en) Big Megawatt fan performance test frock and the test method realized using the tooling
CN107767975B (en) Method for monitoring quality performance of weight-losing component of nuclear power plant and diagnosing fault
CN206235720U (en) A kind of LED drives test system
WO2021258649A1 (en) Comprehensive performance test and debugging experiment device for rotary drilling rig and experiment method
CN110109016A (en) New energy automobile motor test platform
CN110398380A (en) A kind of Electric Motor Wheel vehicle alternating current drive pilot system and method
CN111881736A (en) Rolling bearing early fault diagnosis method based on bandwidth Fourier decomposition
CN104697799A (en) Automatic load increase testing system and testing method for engine
CN103852255A (en) Typical transmission fault intelligent diagnosis method based on neural network wind generating set
WO2024002091A1 (en) Full-power test platform and method for tandem double-wind-wheel wind turbine generator set
CN107966616A (en) Motor vehicle electromagnetic Flied emission strength test method based on car body threedimensional model
CN208169063U (en) A kind of flexible frock of big MW class wind turbine group performance test
CN204740137U (en) Large -scale wind generating set work performance test device
Tudor et al. Locomotive Diesel Engine Test Stand with Energy Recovery in the Electrical Network
US20150013406A1 (en) System and method for removing dents from a wind turbine tower
CN211425862U (en) Starter load control system based on electric dynamometer
CN204882071U (en) Automatic derailleur performance test bench
CN206671454U (en) A kind of public test device of multi-functional different capacity inverter
CN111076938B (en) Control method of starter load control system based on electric dynamometer
CN104931265A (en) Large wind generating set work performance test device and test method thereof
CN204575328U (en) The test macro of checking engine PTO fan-out capability
CN114486242A (en) Aeroengine transmission system load spectrum and transmission efficiency measuring system
Zhang et al. Non-invasive condition monitoring and diagnostics techniques for wind turbines

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination