CN108330773A CN201711294690.6A CN201711294690A CN108330773A CN 108330773 A CN108330773 A CN 108330773A CN 201711294690 A CN201711294690 A CN 201711294690A CN 108330773 A CN108330773 A CN 108330773A
Authority
CN
China
Prior art keywords
hole
face layer
rubber
elastic plastic
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711294690.6A
Other languages
Chinese (zh)
Other versions
CN108330773B (en
Inventor
王建中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinsheng Construction Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711294690.6A priority Critical patent/CN108330773B/en
Publication of CN108330773A publication Critical patent/CN108330773A/en
Application granted granted Critical
Publication of CN108330773B publication Critical patent/CN108330773B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C13/00Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
    • E01C13/06Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003
    • E01C13/065Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003 at least one in situ layer consisting of or including bitumen, rubber or plastics
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention provides a kind of plastic cement race track, including face layer, base, bottom, soil horizon, the face layer is internally provided with several first through hole, the face layer includes polyurethane particles face layer successively from top to bottom, first Elastic plastic-rubber face layer, second Elastic plastic-rubber face layer, the base is internally provided with several the second through-holes, the base includes rubber substrate successively from top to bottom, land plaster base, waterproof matrix, several drainpipes are installed above the bottom, the bottom is internally provided with several third through-holes, the bottom includes antidetonation layer successively from top to bottom, mixed mud layer and adhesive linkage, the third through-hole is connected with soil horizon, the first through hole, second through-hole, drainpipe, third through-hole is connected.A kind of plastic cement race track of the present invention has the characteristics that good permeability, infiltration power is strong, elasticity is good, wearability is strong, damping property is good, extends service life, durable, improves use quality, reduces use cost.

Description

A kind of plastic cement race track
【Technical field】
The present invention relates to runway technology field, more particularly to a kind of plastic cement race track.
【Background technology】
As the leisure time of the development of productivity level, the raising of living standards of the people, people is also more and more, sport Movement is one of people's spare time favorite activity, and therefore, sports equipment science, hommization is directly related to sporter's Personal safety.
Plastic cement race track is indispensable critical facility in modern track and field place, compared with traditional soil property runway, tool Have good elasticity, skid resistance, wearability, a shock absorption, place nursing is easy, in bright gay color, it is beautiful and tidy the advantages that.Currently, Existing plastic cement race track ventilating water seepage is poor, and runway is easy ponding, and summer will appear sultry sense in the movement of air-locked runway Feel, and poor flexibility, wearability be not strong, damping property is bad, influences the use of runway.
【Invention content】
It is an object of the invention to overcome above-mentioned the deficiencies in the prior art, provide a kind of plastic cement race track, have good permeability, The feature that the power that seeps water is strong, elasticity is good, wearability is strong, damping property is good, extends service life, durable, improves using matter Amount reduces use cost.
To achieve the above object, the present invention proposes a kind of plastic cement race track, including face layer, base, bottom, soil horizon, institute The face layer stated is internally provided with several first through hole, and face layer includes polyurethane particles face layer, the successively from top to bottom One Elastic plastic-rubber face layer, the second Elastic plastic-rubber face layer, the lower section of second Elastic plastic-rubber face layer are equipped with base, the base Layer is internally provided with several the second through-holes, and the base includes rubber substrate, land plaster base, waterproof successively from top to bottom The lower section of base, the waterproof matrix is equipped with bottom, and several drainpipes, the bottom are equipped with above the bottom Layer is internally provided with several third through-holes, and the bottom includes antidetonation layer, mixed mud layer and adhesive linkage successively from top to bottom, The lower section of the adhesive linkage is equipped with soil horizon, and the third through-hole is connected with soil horizon, the first through hole, second Through-hole, drainpipe, third through-hole are connected.
Preferably, the inner wall of the first through hole is equipped with seal groove, the inner wall of the seal groove is equipped with several Drainage trough straight down, the lower end of the drainage trough are connect with the second through-hole.
Preferably, the polyurethane particles face layer is equipped with several polyurethane particles, the two neighboring poly- ammonia It is bonded by polyurethane adhesive between ester particle, the upper surface of polyurethane particles face layer is equipped with wearing layer, described The upper surface of wearing layer is equipped with several wear ribs outwardly protruded, and stiffener is equipped between adjacent two wear ribs, The wear rib is identical as the length of stiffener.
Preferably, the elasticity of the first Elastic plastic-rubber face layer is more than the elasticity of the second Elastic plastic-rubber face layer, it is described The first Elastic plastic-rubber be equipped with several first Elastic plastic-rubber items, the is equipped between adjacent two first Elastic plastic-rubbers article One movable span, second Elastic plastic-rubber face layer are equipped with several the second Elastic plastic-rubber items, adjacent two second bullets Property plastic strip between be equipped with the second movable span.
Preferably, the length of the first Elastic plastic-rubber item is more than the length of the second Elastic plastic-rubber item, described the One Elastic plastic-rubber item and the second Elastic plastic-rubber item are memory plastic strip.
Preferably, the first through hole, the second through-hole, the diameter of third through-hole are identical, the first through hole, Two through-holes, third through-hole a diameter of 1mm, 1.5mm, 2mm, 2.5mm, 3mm in it is one or more.
Preferably, the inner wall of the drainpipe is smooth inner wall, the inner wall of the drainpipe is equipped with anti-tongue layer.
Preferably, the thickness of the face layer is less than the thickness of base, the thickness of the base is less than the thickness of bottom The overall thickness of degree, face layer, base and bottom is 20mm-30mm.
Beneficial effects of the present invention:The present invention inside face layer, base and bottom by being arranged several through-holes, by through-hole It is arranged to several different sizes, meets the gas permeability of runway under varying environment;The seal groove being equipped in first through hole prevents water Stream is run helter-skelter, and drainage trough takes advantage of a situation flow toward flowing down, and improves using effect;In polyurethane particles face layer setting wearing layer, wearing layer Wear rib and stiffener is arranged in surface, ensures the flatness of runway surface, increases the wearability of the strength and enhancing runway of runway; In polyurethane particles face, the first memory elasticity plastic cement and the second memory elasticity plastic cement of different elastic force is arranged in the lower section of layer, resists not With impact force suffered under motion state, enhance impact resistance;The thickness of bottom is set as most thick, enhances the stability of substrate, Service life is extended, it is durable, use quality is improved, use cost is reduced.
The feature and advantage of the present invention will be described in detail by embodiment combination attached drawing.
【Description of the drawings】
Fig. 1 is a kind of internal structure schematic diagram of plastic cement race track of the present invention;
Fig. 2 is the three-dimensional structure diagram of first through hole;
Fig. 3 is a kind of left view of plastic cement race track of the present invention.
In figure:The faces 1- layer, 2- bases, 3- bottoms, 4- soil horizons, 5- drainpipes, 11- first through hole, 12- polyurethane particles Face layer, the first Elastic plastic-rubbers of 13- face layer, the second Elastic plastic-rubbers of 14- face layer, 15- wearing layers, the second through-holes of 21-, 22- rubber-baseds Layer, 23- land plasters base, 24- waterproof matrixs, 31- third through-holes, 32- antidetonations layer, 33- mixed muds layer, 34- adhesive linkages, 51- Anti- tongue layer, 111- seal grooves, 112- drainage troughs, 121- polyurethane particles, the first Elastic plastic-rubbers of 131- item, the first activities of 132- Hole, the second Elastic plastic-rubbers of 141- item, the second movable spans of 142-, 151- wear ribs, 152- stiffeners.
【Specific implementation mode】
In order to make the objectives, technical solutions and advantages of the present invention clearer, below by accompanying drawings and embodiments, to this Invention is further elaborated.However, it should be understood that the specific embodiments described herein are merely illustrative of the present invention, The range being not intended to restrict the invention.In addition, in the following description, descriptions of well-known structures and technologies are omitted, to keep away Exempt from unnecessarily to obscure idea of the invention.
Refering to fig. 1 to Fig. 3, the present invention provides a kind of plastic cement race track, including face layer 1, base 2, bottom 3, soil horizon 4, institute The face layer 1 stated is internally provided with several first through hole 11, and face layer 1 includes polyurethane particles face layer successively from top to bottom 12, the 13, second Elastic plastic-rubber face of the first Elastic plastic-rubber face layer layer 14, the lower section of second Elastic plastic-rubber face layer 14 is equipped with base Layer 2, the base 2 is internally provided with several the second through-holes 21, and the base 2 includes rubber substrate successively from top to bottom 22, the lower section of land plaster base 23, waterproof matrix 24, the waterproof matrix 24 is equipped with bottom 3, the top of the bottom 3 Several drainpipes 5 are installed, the bottom 3 is internally provided with several third through-holes 31, and the bottom 3 is from top to bottom Include antidetonation layer 32, mixed mud layer 33 and adhesive linkage 34 successively, the lower section of the adhesive linkage 34 is equipped with soil horizon 4, described Third through-hole 31 is connected with soil horizon 4, and the first through hole 11, the second through-hole 21, drainpipe 5, third through-hole 31 are connected It is logical;The inner wall of the first through hole 11 is equipped with seal groove 111, the inner wall of the seal groove 111 be equipped with several vertically to Under drainage trough 112, the lower end of the drainage trough 112 is connect with the second through-hole 21;The polyurethane particles face layer 12 is set There are several polyurethane particles 121, is bonded by polyurethane adhesive between the two neighboring polyurethane particles 121, institute The upper surface for the polyurethane particles face layer 12 stated is equipped with wearing layer 15, and the upper surface of the wearing layer 15 is equipped with several outward The wear rib 151 of protrusion, is equipped with stiffener 152 between adjacent two wear ribs 151, the wear rib 151 with plus The length of strong item 152 is identical;The elasticity of the first Elastic plastic-rubber face layer 13 is more than the elasticity of the second Elastic plastic-rubber face layer 14, First Elastic plastic-rubber 13 is equipped with several first Elastic plastic-rubber items 131, the adjacent two first Elastic plastic-rubber items The first movable span 132 is equipped between 131, second Elastic plastic-rubber face layer 14 is equipped with several the second Elastic plastic-rubber items 141, The second movable span 142 is equipped between the adjacent two second Elastic plastic-rubber items 141;The first Elastic plastic-rubber item 131 Length be more than the second Elastic plastic-rubber item 141 length, the first Elastic plastic-rubber item 131 and the second Elastic plastic-rubber item 141 To remember plastic strip;Identical, the described first through hole of the first through hole 11, the second through-hole 21, the diameter of third through-hole 31 11, one or more in a diameter of 1mm, 1.5mm, 2mm, 2.5mm, 3mm of the second through-hole 21, third through-hole 31, it is described The inner wall of drainpipe 5 is smooth inner wall, and the inner wall of the drainpipe 5 is equipped with anti-tongue layer 51;The thickness of the face layer 1 is less than The thickness of base 2, the thickness of the base 2 are less than the thickness of bottom 3, face layer 1, base 2 and bottom 3 overall thickness For 20mm-30mm.
By using above-mentioned technical proposal, the present invention inside face layer 1 by being arranged several first through hole 11, first It is equipped with seal groove 111 in through-hole 11, is equipped with drainage trough 112 in seal groove 111, several the second through-holes is set inside base 2 21, several drainpipes 5 are set above bottom 3, several third through-holes 31 are set inside bottom 3, drainage trough 112, the Two through-holes 21, drainpipe 5, third through-hole 31 communicate, and air is by drainage trough 112, the second through-hole 21, drainpipe 5, third through-hole 31 carry out convection current exchanges, on rainy day or when needing to clean runway, first through hole 11, the second through-hole 21, third through-hole Multiple sizes of 32 settings meet the infiltration of different flow sizes, and the excessive influence of flow is avoided to use, the setting of 5 inner wall of drainpipe Anti- tongue layer 51 reduces moss and is attached to 5 inner wall of drainpipe, influences the drain function of drainpipe;By in polyurethane particles face layer 12 Wearing layer 15 is set, the wear rib 151 and stiffener 152 that several are outwardly protruded are set on wearing layer 15, increase surface Strength and enhancing surface wearability, the setting identical with 152 length of stiffener of wear rib 151 ensure that the flat of surface Property, meet the match request in especially flat place;In polyurethane particles face, the first bullet of different elasticity is arranged in the lower section of layer 12 Property plastic coat 13 and the second Elastic plastic-rubber face layer 14, resist impact force suffered under different motion state, enhance impact resistance; In the first Elastic plastic-rubber face, the first Elastic plastic-rubber item 131 is arranged in layer 13, and the is equipped between adjacent two first Elastic plastic-rubbers article 131 One movable span 132, in the second Elastic plastic-rubber face, the second Elastic plastic-rubber item 141, adjacent two second Elastic plastic-rubber items are arranged in layer 14 It is equipped with the second movable span 142 between 141, enhances the elasticity of the present invention, the first movable span 132 and the second movable span 142 are set Plastic strip is set when avoiding movement because of elastic volume increases mutual crimp, the first Elastic plastic-rubber item 131 of extension and the second bullet Property plastic strip 141 service life, by the first Elastic plastic-rubber item 131 and the second Elastic plastic-rubber item 141 be set as memory plastic strip, Improve run-up effect when movement;Land plaster base 23 is set in base 2, mixed mud layer 33, two intensity enhancings are arranged in bottom 3 The setting of layer substantially increases stability, and the waterproof matrix 24 and antidetonation layer 32 that are equipped with enhance water proofing property and shock resistance. Good permeability of the present invention, the feature that infiltration power is strong, elasticity is good, wearability is strong, damping property is good, extend service life, prolonged resistance to With improving use quality, reduce use cost.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention Any modification, equivalent replacement or improvement etc., should all be included in the protection scope of the present invention made by within refreshing and principle.

Claims (8)

1. a kind of plastic cement race track, it is characterised in that:Including face layer (1), base (2), bottom (3), soil horizon (4), the face Layer (1) is internally provided with several first through hole (11), and face layer (1) includes polyurethane particles face layer successively from top to bottom (12), the first Elastic plastic-rubber face layer (13), the second Elastic plastic-rubber face layer (14), the second Elastic plastic-rubber face layer (14) under Side is equipped with base (2), and the base (2) is internally provided with several the second through-holes (21), and the base (2) is from top to bottom Include successively rubber substrate (22), land plaster base (23), waterproof matrix (24), the lower section of the waterproof matrix (24) is equipped with Bottom (3) is equipped with several drainpipes (5) above the bottom (3), and being internally provided with for the bottom (3) is several A third through-hole (31), the bottom (3) include antidetonation layer (32), mixed mud layer (33) and adhesive linkage successively from top to bottom (34), the lower section of the adhesive linkage (34) is equipped with soil horizon (4), and the third through-hole (31) is connected with soil horizon (4), The first through hole (11), the second through-hole (21), drainpipe (5), third through-hole (31) are connected.
2. a kind of plastic cement race track as described in claim 1, it is characterised in that:The inner wall of the first through hole (11) is equipped with close The inner wall of sealing groove (111), the seal groove (111) is equipped with several drainage troughs (112) straight down, the drainage trough (112) lower end is connect with the second through-hole (21).
3. a kind of plastic cement race track as described in claim 1, it is characterised in that:The polyurethane particles face layer (12) is if be equipped with A polyurethane particles (121) are done, are bonded by polyurethane adhesive between the two neighboring polyurethane particles (121), institute The upper surface for the polyurethane particles face layer (12) stated is equipped with wearing layer (15), and the upper surface of the wearing layer (15) is equipped with several A wear rib (151) outwardly protruded is equipped with stiffener (152) between adjacent two wear ribs (151), and described is resistance to Abrasive stick (151) is identical as the length of stiffener (152).
4. a kind of plastic cement race track as described in claim 1, it is characterised in that:The bullet of the first Elastic plastic-rubber face layer (13) Property be more than the second Elastic plastic-rubber face layer (14) elasticity, first Elastic plastic-rubber (13) be equipped with several first Elastic plastic-rubbers Item (131) is equipped with the first movable span (132), second bullet between the adjacent two first Elastic plastic-rubber items (131) Property plastic coat (14) be equipped with several the second Elastic plastic-rubber items (141), the adjacent two second Elastic plastic-rubber items (141) Between be equipped with the second movable span (142).
5. a kind of plastic cement race track as described in claim 1, it is characterised in that:The length of the first Elastic plastic-rubber item (131) Degree is more than the length of the second Elastic plastic-rubber item (141), the first Elastic plastic-rubber item (131) and the second Elastic plastic-rubber item (141) it is memory plastic strip.
6. a kind of plastic cement race track as described in claim 1, it is characterised in that:The first through hole (11), the second through-hole (21), the diameter of third through-hole (31) is identical, the first through hole (11), the second through-hole (21), third through-hole (31) it is straight Diameter is one or more in 1mm, 1.5mm, 2mm, 2.5mm, 3mm.
7. a kind of plastic cement race track as described in claim 1, it is characterised in that:The inner wall of the drainpipe (5) is in smooth The inner wall of wall, the drainpipe (5) is equipped with anti-tongue layer (51).
8. a kind of plastic cement race track as described in claim 1, it is characterised in that:The thickness of the face layer (1) is less than base (2) Thickness, the thickness of the base (2) is less than the thickness of bottom (3), face layer (1), base (2) and bottom (3) Overall thickness is 20mm-30mm.
CN201711294690.6A 2017-12-08 2017-12-08 Plastic course Active CN108330773B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711294690.6A CN108330773B (en) 2017-12-08 2017-12-08 Plastic course

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711294690.6A CN108330773B (en) 2017-12-08 2017-12-08 Plastic course

Publications (2)

Publication Number Publication Date
CN108330773A true CN108330773A (en) 2018-07-27
CN108330773B CN108330773B (en) 2023-07-21

Family

ID=62922506

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711294690.6A Active CN108330773B (en) 2017-12-08 2017-12-08 Plastic course

Country Status (1)

Country Link
CN (1) CN108330773B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101792997A (en) * 2010-03-31 2010-08-04 成都建筑工程集团总公司 Mixed type plastic track construction method
CN203890834U (en) * 2014-03-26 2014-10-22 广东伟佳体育设施有限公司 Water-permeable polyurethane plastic track
CN205276092U (en) * 2015-12-30 2016-06-01 广州市柏奥体育场地设施工程有限公司 Mixed type plastic course
CN205662810U (en) * 2016-06-02 2016-10-26 南京禾邦体育场地工程有限公司 Ventilative type plastic course
CN106189236A (en) * 2016-08-08 2016-12-07 杭州耀恩环保科技有限公司 A kind of novel environment friendly runway
CN106555372A (en) * 2017-01-22 2017-04-05 海绵城市道路材料(深圳)有限公司 A kind of porous pavement is mated formation plate and porous pavement paving structure
CN207958907U (en) * 2017-12-08 2018-10-12 浙江锦圣市政园林有限公司 A kind of plastic cement race track

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101792997A (en) * 2010-03-31 2010-08-04 成都建筑工程集团总公司 Mixed type plastic track construction method
CN203890834U (en) * 2014-03-26 2014-10-22 广东伟佳体育设施有限公司 Water-permeable polyurethane plastic track
CN205276092U (en) * 2015-12-30 2016-06-01 广州市柏奥体育场地设施工程有限公司 Mixed type plastic course
CN205662810U (en) * 2016-06-02 2016-10-26 南京禾邦体育场地工程有限公司 Ventilative type plastic course
CN106189236A (en) * 2016-08-08 2016-12-07 杭州耀恩环保科技有限公司 A kind of novel environment friendly runway
CN106555372A (en) * 2017-01-22 2017-04-05 海绵城市道路材料(深圳)有限公司 A kind of porous pavement is mated formation plate and porous pavement paving structure
CN207958907U (en) * 2017-12-08 2018-10-12 浙江锦圣市政园林有限公司 A kind of plastic cement race track

Also Published As

Publication number Publication date
CN108330773B (en) 2023-07-21

Similar Documents

Publication Publication Date Title
CN207958907U (en) A kind of plastic cement race track
CN206858995U (en) A kind of plastic cement race track layer structure
CN207987675U (en) A kind of plastic cement race track of long lifespan
CN202500069U (en) Ecological permeable concrete terrace
CN206692986U (en) A kind of fluorescent antislip plastic cement race track
CN108330773A (en) A kind of plastic cement race track
CN204640993U (en) A kind of netted TPU composite membrane of waterproof of good heat insulating
CN207862721U (en) A kind of plastic cement race track that ventilating water seepage power is strong
CN208917629U (en) Plastic cement race track
CN206680834U (en) A kind of plastic cement race track
CN214061126U (en) Wear-resisting environmental protection water-based plastic course material layer
CN109554983A (en) A kind of vapor-permeable type plastic cement race track
CN208425856U (en) A kind of plastic cement doormat with absorption umbrella flowing water function
CN208618217U (en) A kind of vapor-permeable type plastic cement race track
CN108004873A (en) A kind of good plastic cement race track of effect that seeps water
CN207484222U (en) A kind of aqueous elastic acrylic acid court
CN207194390U (en) Moistureproof muting pad
CN208701453U (en) A kind of prefabricated profiled rubber track
CN205399937U (en) Terrace with high -build anti -slipping type coating
CN206560085U (en) A kind of waterproof footwear
CN206971044U (en) A kind of children special-purpose protects terrace
CN217852321U (en) High-flatness anti-fatigue ground mat
CN219280404U (en) Plastic course that air permeability is good and anti-skidding effect is good
CN208533306U (en) Vapor-permeable type plastic cement race track
CN205295861U (en) Plastic course lamellar structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20230613

Address after: 311199 No. 464, Tangqi Road, Building 13, Tangqi Jiayuan, Tangqi Town, Linping District, Hangzhou City, Zhejiang Province

Applicant after: Zhejiang Jinsheng Construction Co.,Ltd.

Address before: Room 402, Unit 1, Building 28, Shuixie Huadu, Xinyuan Community, Tangqi Town, Yuhang District, Hangzhou City, Zhejiang Province, 310000

Applicant before: Wang Jianzhong

GR01 Patent grant
GR01 Patent grant