CN108317334A - A kind of high-temperature medium plugging pipelines device - Google Patents

A kind of high-temperature medium plugging pipelines device Download PDF

Info

Publication number
CN108317334A
CN108317334A CN201810114521.8A CN201810114521A CN108317334A CN 108317334 A CN108317334 A CN 108317334A CN 201810114521 A CN201810114521 A CN 201810114521A CN 108317334 A CN108317334 A CN 108317334A
Authority
CN
China
Prior art keywords
inspection
closure
camber
plugging
walking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810114521.8A
Other languages
Chinese (zh)
Inventor
张桂华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810114521.8A priority Critical patent/CN108317334A/en
Publication of CN108317334A publication Critical patent/CN108317334A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L55/00Devices or appurtenances for use in, or in connection with, pipes or pipe systems
    • F16L55/16Devices for covering leaks in pipes or hoses, e.g. hose-menders
    • F16L55/168Devices for covering leaks in pipes or hoses, e.g. hose-menders from outside the pipe
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D5/00Protection or supervision of installations
    • F17D5/02Preventing, monitoring, or locating loss

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Pipe Accessories (AREA)

Abstract

The present invention provides a kind of high-temperature medium plugging pipelines device, including the walking mechanism on the end fixed pedestal of pressure piping is arranged, the inspection mechanism being arranged in the walking mechanism, be arranged in the walking mechanism and with the matched plugging mechanism of inspection mechanism, the cooling mechanism being arranged in walking mechanism, and the control mechanism for controlling walking mechanism, inspection mechanism, cooling mechanism and plugging mechanism is set in the walking mechanism;The present invention can not only realize online closure, and leak holes side wall slag can will not be caused to fall when being handled using tool, to the contamination phenomenon to pipeline internal medium;Simultaneously can it is permanent or it is semipermanent pipeline is repaired, avoid when carrying out general overhaul, again to the repairerment of pipeline, it only needs to carry out automatic detecting, can temporarily it be cooled down when there is high temperature leakage simultaneously, hazardous environment caused by avoiding temperature excessively high.

Description

A kind of high-temperature medium plugging pipelines device
Technical field
The present invention relates to pipeline leakage plugging device technical fields, and in particular to a kind of high-temperature medium plugging pipelines dress It sets.
Background technology
Pressure pipeline refers to all pipelines for bearing internal pressure or external pressure, however for pressure piping, it is not only required to bear Very high pressure, and work steady in a long-term is needed, but since working environment badly makes it inevitably will appear leakage Phenomenon, most safe and most safe mode exactly close bearing pipe, are then repairing, but it can seriously affect work Industry produces or resident living, it is therefore desirable to which a kind of plugging device that can be repaired online exists various in the prior art The plugging device and mode of various kinds, but its be also only carried out temporary closure, and and be not implemented closure steady in a long-term, Or plugging effect is bad, and since Hand scarf is in the process there are will produce unnecessary pollution at plugging hole, in turn The tool for necessarily limiting plugging device to the unnecessary pollution of pipeline is caused to use.
Invention content
In view of this, purpose provided by the invention is in view of the deficiencies of the prior art, a kind of high-temperature medium pipe is provided Road plugging device can not only realize online closure, and can will not cause leak holes when being handled using tool Side wall slag is fallen, to the contamination phenomenon to pipeline internal medium;Simultaneously can it is permanent or it is semipermanent pipeline is repaired, keep away Exempt from when carrying out general overhaul, again to the repairerment of pipeline, it is only necessary to carry out inspection, while high temperature leakage can occurring When, cooled down temporarily, hazardous environment caused by avoiding temperature excessively high.
To solve above-mentioned purpose, the technical solution used in the present invention is:
A kind of high-temperature medium plugging pipelines device, including the vehicle with walking machine that is arranged on the end fixed pedestal of pressure piping Structure, the inspection mechanism being arranged in the walking mechanism are arranged in the walking mechanism and are matched with the inspection mechanism Plugging mechanism, and be arranged in the walking mechanism for controlling the control of walking mechanism, inspection mechanism and plugging mechanism Mechanism;
The walking mechanism includes the walking track being connected with the fixed pedestal of pressure piping, is arranged on the walking track Walking dolly, be arranged in the walking dolly lower part and the matched multiple driving wheels of walking track, with the driving Matched driving motor is taken turns, the cooling mechanism on the walking dolly is set, and is arranged on the walking dolly The control mechanism.
The inspection mechanism includes inspection support telescopic arm, and the inspection being arranged in the inspection support telescopic arm upper end is lateral Inspection electric rotating machine is arranged in the inspection transversal stretching boom end in telescopic rod, setting, and setting is defeated in the inspection electric rotating machine The first driving wheel in the inspection driving motor output shaft is arranged in inspection driving motor on shaft, is driven with the inspection The two inspection guide grooves that dynamic electric machine casing is connected are arranged with the two matched camber inspection guide rails of inspection guide groove described Camber inspection guide rail upper surface and with the matched first camber drive rack of first driving wheel, setting patrolled in the camber The limited block at guide rail both ends is examined, and the air-flow detection module being arranged on the camber inspection guide rail lower surface.
First driving wheel is spur gear or helical gear.
The air-flow detection module includes the camber detection plate being arranged on the arc inspection guide rail, is arranged in the arc Multiple pressure sensors in type detection plate, and the airflow plate in the pressure sensor upper end is set.
The plugging mechanism includes the closure support telescopic arm being arranged on the walking dolly, and setting is in closure branch The closure transversal stretching bar for supportting telescopic arm upper end is arranged in the closure steering motor for blocking transversal stretching boom end, setting Closure on the closure steering motor output end bridges block, is arranged in the two closure guide grooves blocked on bridge joint block, if It sets between the two closure guide grooves and positioned at the closure driving motor for blocking and bridging on block, setting is in closure driving The second driving wheel on the output shaft of motor matches camber with the closure guide groove and blocks guide rail, and setting is sealed in the camber Stifled guide rail upper surface and with the matched second camber drive rack of the second driving wheel, be arranged and blocked on guide rail in the camber Support plate is blocked, and the plugging module being arranged in the closure support plate.
The plugging module includes the plugging hole being arranged in the closure support plate, and the envelope on the plugging hole is arranged The first solenoid valve on the closure pipe is arranged in plugging, is arranged in the closure support plate and is carried out with the closure pipe The closure working track of cooperation is arranged the operation base station on the closure working track, is arranged in the closure working track End and the operation telescopic rod being connected with the operation base station, are arranged the operation support telescopic arm on the operation base station, Operation cross-brace arm in the operation support telescopic arm upper end is set, the behaviour in the operation cross-brace arm end is set Rotate motor, is arranged the operation panel on the operation rotary electric machine output shaft, be arranged on the operation panel multiple and The operation boss being circumferentially distributed, and be arranged it is multiple it is described operation boss on the first operating units, the second operating unit, Third operating unit and the 4th operating unit.
The side setting of the operation boss and the matched sealing ring in the closure pipe upper end.
First operating unit includes the first operation telescopic rod being arranged on operation boss, and setting is in first behaviour The electromagnetic clamp for making telescopic rod end, is arranged the inner seal on the electromagnetic clamp, be arranged on the electromagnetic clamp with it is described The matched conductive plug of inner seal.
Second operating unit includes the second operation telescopic rod being arranged on the operation boss, and setting is described the The drill bit on the drilling motor output shaft is arranged in the drilling motor of two operation telescopic rod ends, and setting is in punching electricity On machine and with the matched first negative pressure suction nozzle of the drill bit, the first negative pressure suction nozzle be arranged it is micro- on the operation panel Type Negative pressure machine matches.
The third operating unit includes that the third being arranged on the operation boss operates telescopic rod, and setting is described the The screw tap on the tapping motor output shaft is arranged in the tapping motor of three operation telescopic rod ends, and setting is in tapping electricity On machine and with the matched second negative pressure suction nozzle of the screw tap, the second negative pressure suction nozzle be arranged it is micro- on the operation panel Type Negative pressure machine matches.
4th operating unit includes the 4th operation telescopic rod being arranged on the operation boss, and setting is described the The sealed electric-motor of four operation telescopic rod ends, is arranged the permanent magnetism screwdriver on the sealed electric-motor output shaft, is arranged described Seal plug on permanent magnetism screwdriver.
The inner seal includes sealing bar, and the sucker in the sealing bar lower end is arranged, and is arranged in the sealing bar The memorial alloy obturating cup of upper end, is arranged the sealing ring in memorial alloy obturating cup side, and setting is sealed in the memorial alloy Bowl in heater strip, the heater strip and be arranged it is described sealing boom end electrically conductive socket be connected, setting in the sealing Boom end is used for and the matched bloom of the electromagnetic clamp.
The control mechanism includes protecting crust, the computer being arranged in protecting crust, the electricity being connected with the computer Source.
The cooling mechanism includes that the storehouse that cools down on walking dolly is arranged, and the compressed tanks in the cooling storehouse are arranged, if The solenoid valve in the compressed tanks exit is set, be connected with the solenoid valve and is located at multiple sprays on the walking dolly Mouth, the multiple temperature sensors being arranged on the walking dolly, the solenoid valve and multiple temperature sensors are and institute State Computer signal interconnection.
It is arranged in the closure support plate, and multi-layer sealed circle is set around the plugging hole.
The camber blocks guide rail and is more than pressure pipeline cross section with the circular radius distance value where camber inspection guide rail The circular radius distance value of outer wall.
It is semi arch or major arc that the camber, which blocks guide rail and the arc of the formation of camber inspection guide rail,.
The thread surface setting graphite grazing coating of the seal plug is wound with sealing belt.
A kind of application method of high-temperature medium plugging pipelines device:
S1:After checking all parts normal operation, inspection support telescopic arm is stretched out, then carries out inspection transversal stretching bar It is expanded to bearing pipe central upper portion, is turned to camber inspection guide rail at a wherein limited block by the first driving wheel, so The inspection to half pipeline surface is realized by the walking of walking dolly afterwards, by camber inspection guide rail after completing to half inspection It turns at another limited block, is then returned by walking dolly and inspection is carried out to the other half pipeline surface;
S2:When air-flow detection module detects pressure sensor there are when pressure during inspection, walking dolly can then stop It only walks, is then slowly being moved forward and backward, and camber inspection guide rail is slowly moved back and forth, and is implicitly present in The phenomenon that gas leakage, and the location information of corresponding pressure sensor is fed back into control mechanism, and inspection mechanism is stored, together When detect when the temperature is excessively high when temperature sensor, then signal can be passed to computer, and solenoid valve is controlled by computer, By the gas discharge in compressed tanks, to cooling down at leakage, until temperature is restored to normal temperature state, then to stop operation;
S3:According to the range data of gas leakage coordinate information and leak holes that inspection mechanism obtains, itself is judged by control mechanism Whether the tool of carrying can directly be constructed, and use sequence;
When detect meet plugging mechanism opereating specification when, by adjusting block support telescopic arm height, then according to gas leakage Coordinate information adjustment blocks the angle of steering motor, then drives the second camber drive rack row by the rotation of the second driving wheel It walks, to adjust plugging hole to gas leakage coordinate position, then by blocking support telescopic arm, blocking the mutual of transversal stretching bar Coordination downwards compresses leak holes, closes the first solenoid valve by control mechanism at this time, realizes temporarily sealing;
S4:It will be operated during base station pushes at plugging hole by operating telescopic rod, operation support telescopic arm stretches out upwards, And operation cross-brace arm is protruding so that the working position of the work of operation panel when rotated can be aligned in leak holes Then first operating unit is aligned and blocks pipe by heart position first, and realize operation boss and block the fixing seal of pipe upper end, Then the first solenoid valve is opened, is put into inner seal in pressure pipeline across leak holes by the first operation telescopic rod, After inner seal is fixed, heater strip is heated by conductive plug, so that memorial alloy obturating cup is realized It restores, and gluing, sealing is realized by sealing ring and inner wall of the pipe;
S5:Then electromagnetic clamp is unclamped, and cuts off conductive plug power supply, and the first operation telescopic rod is resetted, is then shut off First solenoid valve, and lifting operation support telescopic arm, then rotate operation panel so that the second operation telescopic rod alignment envelope Plugging, and moved downward by operating support telescopic arm, and be sealed by operating boss to blocking pipe, then open first Solenoid valve, and reaming is carried out to pressure-bearing tube wall downwards under the drive of the second operation telescopic rod, and will by the first negative pressure suction nozzle Abrasive dust siphons away, and after expanding treatment, the second operation telescopic rod is resetted;
S6:Lifting operation support telescopic arm, then rotates operation panel so that and third operates telescopic rod alignment and blocks pipe, Then it is moved downward by operating support telescopic arm, and is sealed by operating boss to blocking pipe, then grasped by third Make moving downward for telescopic rod and tapping is carried out to leak holes, and is siphoned away abrasive dust by the second negative suction head, it, will after tapping Third operation telescopic rod is resetted;
S7:Lifting operation support telescopic arm, then rotates operation panel so that and the 4th operation telescopic rod alignment blocks pipe, Then it is moved downward by operating support telescopic arm, and is sealed by operating boss to blocking pipe, then pass through the 4th behaviour Make moving downward for telescopic rod leak holes are fixed and tighten, realizes sealing.
Further, it in S3, when detecting that leak holes are too small, then can be sent out on one side to operation maintenance personnel by control mechanism Aperture and the location data signal of leak holes are sent, and completes the action of temporarily sealing;
Operation maintenance personnel chooses the drill bit of corresponding model, machine tap, blocks screw, go to scene after receiving data-signal, After reaching scene, instruction is sent out by smart mobile phone APP so that plugging mechanism, which releases temporarily sealing action and realizes, to be resetted, and It, will by operation maintenance personnel so that the present apparatus runs the position to the end of pipeline closest to operation maintenance personnel under the drive of walking dolly Drill bit is mounted on the second operating unit, and machine tap is arranged on third operating unit, will be blocked screw and is arranged the 4th On operating unit;
After accomplishing the setting up, operation maintenance personnel makes the present apparatus resume operation by cell phone application, then first carry out S5 the step of, It carries out being punching difference lies in it with S5;Then in the sealing for entering step S4 progress inner seals;Then entering Tapping is carried out in S6, is then being entered S7 steps, is being completed sealing blocking.
Further, it in S3, when detecting that leak holes are excessive, then can be sent out on one side to operation maintenance personnel by control mechanism Aperture and the location data signal for sending leak holes then proceed by S4 steps, realize temporarily sealing;
Operation maintenance personnel chooses the drill bit of corresponding model, machine tap, blocks screw, go to scene after receiving data-signal, After reaching scene, instruction is sent out by smart mobile phone APP so that plugging mechanism, which releases temporarily sealing action and realizes, to be resetted, and It, will by operation maintenance personnel so that the present apparatus runs the position to the end of pipeline closest to operation maintenance personnel under the drive of walking dolly Drill bit is mounted on the second operating unit, and machine tap is arranged on third operating unit, will be blocked screw and is arranged the 4th On operating unit, S5 steps are then entered back into.
Further, in S6, the first solenoid valve is closed, then lifting operation support telescopic arm, then operation panel is carried out Rotation so that the first operation telescopic rod alignment blocks pipe, is then moved downward by operating support telescopic arm, and convex by operating Platform is sealed to blocking pipe, opens the first solenoid valve, then moving downward by the first operation telescopic rod, by the first operation The electromagnetic clamp of telescopic rod end is mutually fixed with inner seal end, is then firmly pulled upwardly so that memorial alloy obturating cup Deformation is generated, and then pulls out leak holes, then so that closing the first solenoid valve;
In S7, after operation boss is sealed closure pipe, the first solenoid valve is opened.
Further, graphite encapsulation layer is arranged in seal plug surface in S7.
The present invention is directed to and leak point is only capable of carrying out temporary closure in the prior art, and cannot be sealed steadily in the long term It is stifled, and staff is needed to carry out emphasis inspection to emphasis pipeline;And what is occurred fails to be blocked steadily in the long term, Huo Zhefeng It is stifled ineffective, and due to, there are will produce unnecessary pollution at plugging hole, being in turn resulted in pipeline during online processing Unnecessary pollution, the tool for necessarily limiting plugging device uses, therefore the present invention provides a kind of high-temperature medium pipe Road plugging device can not only realize online closure, and can will not cause leak holes when being handled using tool Side wall slag is fallen, to the contamination phenomenon to pipeline internal medium;Simultaneously can it is permanent or it is semipermanent pipeline is repaired, keep away Exempt from when carrying out general overhaul, again to the repairerment of pipeline, it is only necessary to carry out automatic detecting, while can be let out there is high temperature When dew, cooled down temporarily, hazardous environment caused by avoiding temperature excessively high;It is in pipeline or the danger for needing progress emphasis inspection Region channel sides and the position setting walking track for being less than pipeline bottom surface, and walking dolly is set on walking track, and Inspection mechanism, plugging mechanism, cooling mechanism and control mechanism are set on walking dolly, and control row is coordinated by control mechanism Mechanism, inspection mechanism, cooling mechanism and plugging mechanism are walked, to orderly realization inspection and closure and the adjusting of environment.
In addition, the walking mechanism used includes the walking track being connected with the fixed pedestal of pressure piping, the row of use It is conventional I shape track either swallowtail track or groove steel rail to walk track, using multiple driving wheels and track phase of walking Cooperation so that it can not only realize walking, can also realize clampings, avoid occurring falling during operation closure or injustice Steady phenomenon, and the phenomenon that be not in skidding in traveling process to ensure, it is arranged on the one side for track of walking wherein Rubbing surface may also set up rack certainly, corresponding driving wheel is changed to gear, and then obtain good antiskid effect, and can Ensure the precision of driving, and the driving motor used is stepper motor, the signal pulse that can be sent out according to control mechanism, Come obtain the speed of traveling with the location of, and control mechanism is set on walking dolly, walking dolly can not only be increased Quality, but also the stability of structure can be improved;Cool down on walking dolly in addition, the cooling mechanism used includes setting Compressed tanks can be arranged in storehouse wherein, can provide a good environmental protection to compressed tanks, avoid directly heated make At destabilizing factor, preferred selection setting compressed nitrogen in the compressed tanks of use, it is also an option that setting compressed helium or The inert gases such as argon gas, and in the solenoid valve of compressed tanks exit setting, the unlatching of compressed tanks can be controlled, realizes the need of cooling It wants, in order to realize the uniformity of cooling, multiple nozzles is set on the upper surface of walking dolly, by metal or low temperature resistant Pipeline is connected to, and in order to realize preferably control solenoid valve keying, multiple temperature sensors are set on walking dolly, To realize quick detection so that then cool down when temperature is more than threshold value, can then stop cooling down when less than threshold value, for the dress The normal operation set provides good working environment.
In addition, the inspection mechanism used includes inspection support telescopic arm, it is vertically arranged on walking dolly, realizes inspection Comprehensive inspection of the mechanism to conduit upper side and lower side, and the inspection transversal stretching bar being arranged, can realize is needing When carrying out inspection, then air-flow detection module can be pushed to pipeline to be inspected to realize the inspection to pipeline;In inspection cross To the end set inspection electric rotating machine of telescopic rod, it can realize in upper side and downside inspection, its air-flow is detected Module is overturn to be fitted close with pipe surface with this, the inspection driving electricity being arranged on the output shaft of inspection electric rotating machine Machine, and setting and the two inspection guide grooves that the first driving wheel is coordinated thereon on the shell of inspection driving motor, and patrolled two It examines and camber inspection guide rail is set on guide groove, and in order to ensure the stability of operation, the inspection guide groove used is dovetail groove, T-slot Or arc groove, it can realize that the emphasis of certain surface is patrolled in the rotation of camber inspection guide rail, realization by the rotation of the first driving wheel Depending on, or for evading to obstacle on the way, and in order to realize accurately change in displacement, the setting and first in the upper surface of guide rail The matched first camber drive rack of driving wheel, and in order to avoid excess of stroke phenomenon occurs, set at the both ends of camber inspection guide rail Set limited block;And in order to ensure the effect of detection, air-flow detection module is set on camber inspection guide rail lower surface.
In addition, the air-flow detection module used includes the camber detection plate being arranged on the arc inspection guide rail, and Multiple pressure sensors are set thereon, and in order to ensure the precision of pressure sensor, in pressure sensor upper end, air-flow is set Plate, due to being both provided with airflow plate on each pressure sensor, and area is smaller, can find, there are when gas leakage, to pass through Walking dolly is moved forward and backward, and the first driving wheel is moved forward and backward, and can be obtained the elaborate position and hole size of leak holes, is follow-up Work provides accurate position coordinate parameters;And in order to ensure the stable of the first driving wheel and the first camber drive rack, Helical gear is preferably used, the structures such as spur gear can also be used certainly.
In addition, the plugging mechanism used includes the closure support telescopic arm being arranged on the walking dolly, realize up and down Height is adjusted, and lateral adjustments to pipeline can be realized by blocking transversal stretching bar, and is blocking the setting of transversal stretching boom end Closure steering motor, can realize when being overhauled to different location, the phenomenon that plugging plate can be bonded with pipe surface;And it adopts The closure blocked on steering motor output end bridges block, closure driving motor can be arranged on it, and be arranged at both ends Guide groove is blocked, T-slot or circular arc type groove, the camber being arranged on it can also be used for dovetail groove in the closure guide groove used certainly Closure guide rail, and the second driving wheel being arranged on the output shaft for blocking driving motor, can realize arc by way of rotation Type blocks movement of the guide rail along arc surface, and plugging module is arranged on blocking support plate in order to realize to block.
In addition, in order to ensure the effect of closure, plugging hole is set on blocking support plate, and is arranged on plugging hole and blocks Preferably plugging hole is arranged in the centre position for blocking support plate for pipe, and setting blocks pipe on it, and in order to ensure to block The first solenoid valve is arranged in being smoothed out for operation on it, is arranged on blocking support plate and manages matched closure work with closure Track, the closure working track used is swallowtail track or I shape track, it is ensured that the stability run on it, on it Setting operation base station, and operate the position that base station realizes operation base station by being arranged in the operation telescopic rod for blocking working track end Variation is set, to realize the progress of closure, and the setting operation support telescopic arm on operation base station, is achived up and down, and in order to Lateral position adjustment is realized, in operation support arm upper end setting operation cross-brace arm, and in the end of operation cross-brace arm Operation panel is set, and is distributed on operation panel and circumferentially and multiple operation boss is set, the operation boss used for round platform, and Polytetrafluorethylecoatings coatings are set on it, and to realize and block the good sealing property of pipe, and the first operation being arranged on it is single Member is realized and inner seal is placed in pressure pipeline, and inner sealing is carried out, and the second operating unit is for realizing to leakage The reaming in hole can also be used and frustrates head and polish, is polished into circular hole certainly, and it is circle prepared by hard alloy material to use Column bulb-shaped frustrates head, and then can be can be repaired to hole on the basis of original hole, to by triangle, rectangle Or irregular circular hole is polished into the circular hole of rule, since crackle power being disperseed so that the trend of pressure piping split It is limited, avoids the phenomenon that continuing to crack;Then tapping is carried out on circular hole by the way of tapping, and is passed through Abrasive dust is sucked out Negative pressure machine;After tapping, by can be directly placed at inner seal wherein, it can also pass through first Operating unit pulls it, then by the 4th operating unit by closeouts, that is, bolt directly tightens, and realizes lock sealing.
The present invention can obtain the substantially aperture of leak holes by airflow plate, and then be obtained in the present invention by control mechanism Plugging mechanism whether can construct, then can be in inner seal when the aperture of acquisition, the plugging mechanism can not be implemented When carrying out inner sealing, alarm can be sent out to staff, remind it to select mating tool to carry out punching or reaming, then Tapping is in the mode blocked;It when aperture is too small, then can first be punched after closure, due to the air-flow of pressure pipeline Enable abrasive dust therein as leak holes exclude, therefore do not have abrasive dust and enter in pressure pipeline, then puts wherein again Inner seal is set, is then carrying out tapping, closeouts sealing;Enter dangerous pipeline to reduce operating personnel as far as possible Range can carry out the sealing of punching voluntarily, and the sealing means of the present invention are semipermanent or permanent sealing, ensure that sealing Effect.
Description of the drawings
Fig. 1 is the overall structure diagram of the present invention;
Fig. 2 is the structural schematic diagram of walking mechanism of the present invention;
Fig. 3 is the side structure schematic diagram of inspection mechanism of the present invention;
Fig. 4 is the present invention looks up structural representation of camber detection plate of the present invention;
Fig. 5 is the structural schematic diagram that plugging mechanism of the present invention removes plugging module;
Fig. 6 is the positive structural schematic diagram of plugging mechanism of the present invention;
Fig. 7 is the side structure schematic diagram of plugging module of the present invention;
Fig. 8 is the structural schematic diagram of operation panel of the present invention;
Fig. 9 is the structural schematic diagram at present invention closure support plate;
Figure 10 is the structural schematic diagram of the first operating unit of the invention;
Figure 11 is the structural schematic diagram of the second operating unit of the invention;
Figure 12 is the structural schematic diagram of third operating unit of the present invention;
Figure 13 is the structural schematic diagram of the 4th operating unit of the invention;
Figure 14 is the structural schematic diagram at cooling mechanism of the present invention.
Specific implementation mode
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention Attached drawing 1-14, the technical solution of the embodiment of the present invention is clearly and completely described.Obviously, described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on described the embodiment of the present invention, this field is common The every other embodiment that technical staff is obtained, shall fall within the protection scope of the present invention.
Embodiment one
A kind of high-temperature medium plugging pipelines device, including the vehicle with walking machine that is arranged on the end fixed pedestal of pressure piping 1 Structure 7, the inspection mechanism 3 being arranged in the walking mechanism 7, be arranged in the walking mechanism 7 and with 3 phase of inspection mechanism The plugging mechanism 4 of cooperation, and be arranged in the walking mechanism 7 for controlling walking mechanism 7, inspection mechanism 3 and stopple plugging machine The control mechanism of structure 4;
The walking mechanism 7 includes the walking track 2 being connected with the fixed pedestal of pressure piping 1, is arranged in the walking rail Walking dolly 71 on road 2 is arranged in 71 lower part of the walking dolly and 2 matched multiple driving wheels of the walking track 76, with 76 matched driving motor 75 of the driving wheel, the cooling mechanism on the walking dolly is set, and setting exists The control mechanism on the walking dolly 71.
The inspection mechanism 3 includes inspection support telescopic arm 301, is arranged in 301 upper end of inspection support telescopic arm Inspection transversal stretching bar 302, setting are arranged in 302 end set inspection electric rotating machine 303 of the inspection transversal stretching bar in institute The inspection driving motor 304 on 303 output shaft of inspection electric rotating machine is stated, is arranged on 304 output shaft of inspection driving motor The first driving wheel 310, two inspection guide grooves 305 being connected with 304 shell of inspection driving motor lead with two inspections 305 matched camber inspection guide rail 306 of slot, setting drive in 306 upper surface of camber inspection guide rail and with described first 310 matched first camber drive racks are taken turns, the limited block 309 at 306 both ends of camber inspection guide rail is set, and Air-flow detection module on 309 lower surface of camber inspection guide rail is set.
The air-flow detection module includes the camber detection plate 311 being arranged on the arc inspection guide rail 306, and setting exists Multiple pressure sensors 307 in the camber detection plate 311, and the air-flow in 307 upper end of the pressure sensor is set Plate 308.
The plugging mechanism includes the closure support telescopic arm 401 being arranged on the walking dolly 71, is arranged described The envelope in 402 end of closure transversal stretching bar is arranged in the closure transversal stretching bar 402 for blocking 401 upper end of support telescopic arm Stifled steering motor 403, the closure being arranged on closure 403 output end of steering motor bridge block 404, are arranged in the closure Two bridged on block 404 block guide groove 406, are arranged between the two closure guide grooves 406 and bridge block 404 positioned at the closure On closure driving motor 405, the second driving wheel 406 on the output shaft for blocking driving motor 405 is set, and it is described It blocks guide groove 407 and matches camber closure guide rail 408, setting blocks 408 upper surface of guide rail in the camber and driven with second 406 matched second camber drive racks are taken turns, is arranged and blocks the closure support plate 409 on guide rail 408 in the camber, and Plugging module in the closure support plate 409 is set.
The plugging module includes the plugging hole 423 being arranged in the closure support plate 409, is arranged in the plugging hole Closure pipe 5 on 423, be arranged it is described closure pipe 5 on the first solenoid valve 415, be arranged in the closure support plate 409 and The operation base station on the closure working track 416 is arranged in the closure working track 416 coordinated with the closure pipe 5 411, it is arranged in the operation telescopic rod 410 for blocking 416 end of working track and being connected with the operation base station 411, if The operation support telescopic arm 412 on the operation base station 411 is set, the behaviour in 412 upper end of operation support telescopic arm is set Make cross-brace arm 402, the operation rotary electric machine 418 in 402 end of operation cross-brace arm is set, is arranged in the behaviour The operation panel 413 to rotate on 418 output shaft of motor, be arranged on the operation panel 413 multiple and the behaviour being circumferentially distributed Make boss 414, and be arranged on multiple operation boss 414 the first operating units 419, the second operating unit 420, the Three operating units 421 and the 4th operating unit 422.
First operating unit 419 includes the first operation telescopic rod 4191 being arranged on operation boss 414, and setting exists The electromagnetic clamp 4192 of the first operation telescopic rod, 4191 end, is arranged the inner seal on the electromagnetic clamp 4192, if Set on the electromagnetic clamp 4192 with the matched conductive plug of the inner seal 4194.
Second operating unit 420 includes the second operation telescopic rod 4201 being arranged on the operation boss 414, if The drilling motor 4202 in the second operation telescopic rod end is set, the drill bit on 4202 output shaft of the drilling motor is set 4203, be arranged on the drilling motor 4202 and with 4203 matched first negative pressure suction nozzle 4204 of the drill bit, described the One negative pressure suction nozzle 4204 is matched with the Minitype negative pressure machine 423 being arranged on the operation panel 413.
The third operating unit 421 includes the third operation telescopic rod 4211 being arranged on the operation boss 414, if The tapping motor 4212 for operating telescopic rod end in the third is set, the screw tap on 4212 output shaft of tapping motor is set 4213, be arranged on the tapping motor 4212 and with 4213 matched second negative pressure suction nozzle 4214 of the screw tap, described the Two negative pressure suction nozzles 4214 are matched with the Minitype negative pressure machine 423 being arranged on the operation panel 413.
4th operating unit 422 includes the 4th operation telescopic rod 4221 being arranged on the operation boss 414, if The sealed electric-motor 4222 in the 4th operation telescopic rod end is set, the permanent magnetism screw on the sealed electric-motor output shaft is set The seal plug 4223 on the permanent magnetism screwdriver 4224 is arranged in knife 4224.
The inner seal includes sealing bar 4196, and the sucker 4197 in 4196 lower end of the sealing bar is arranged, setting Memorial alloy obturating cup 4193 in 4196 upper end of the sealing bar, is arranged the sealing in 4193 side of memorial alloy obturating cup The heater strip 4198 in the memorial alloy obturating cup 4193 is arranged in circle, and the heater strip 4198 is with setting in the sealing The electrically conductive socket 4199 of 4196 end of bar is connected, and setting is used to match with the electromagnetic clamp 4192 in the sealing boom end Bloom 4195.
The control mechanism includes protecting crust 73, the computer 72 being arranged in protecting crust 73, with 72 phase of the computer The power supply 74 of connection.
First driving wheel 310 is spur gear.
The cooling mechanism includes that the storehouse 11 that cools down is arranged on walking dolly 71, and the compression in the cooling storehouse 11 is arranged Tank 12, is arranged the solenoid valve 10 in 12 exit of the compressed tanks, is connected with the solenoid valve 10 and small positioned at the walking Multiple nozzles 8 on vehicle 71, the multiple temperature sensors 9 being arranged on the walking dolly 71, the solenoid valve 10 and multiple The temperature sensor 9 is interconnected with 72 signal of the computer.
The first camber drive rack in the embodiment is the arc-shaped rack coordinated with the first driving wheel, is mainly The accuracy when movement of realization camber inspection guide rail, can also be not provided with, but precision is bad, need manually to carry out field side auxiliary;And The second camber drive rack being arranged similarly, is preferably coordinated, realize more accurately also for guide rail is blocked with camber It is mobile;And the power supply being arranged can be the electric rail mode of the power supply of lithium battery or electric car, can also directly use the side of disk line Formula;The sealing ring of setting is the flexible graphite gasket or teflon gasket of high temperature resistant and corrosion;In this embodiment Electromagnetic clamp is the electromagnet of internal setting and sealing bar matching ends.
Embodiment two
Its with embodiment one difference lies in:The side setting of the operation boss 414 is matched with 5 upper ends of the closure pipe Sealing ring.
It is arranged in the closure support plate 409, and multi-layer sealed circle 417 is set around the plugging hole 423.
The camber blocks guide rail 306 and is more than pressure pipeline 1 with the circular radius distance value where camber inspection guide rail 408 The circular radius distance value of cross section outer wall.
It is semi arch that the camber, which blocks guide rail 306 and the arc of the formation of camber inspection guide rail 408,.
Graphite grazing coating is arranged in the thread surface of the seal plug 4223.
Embodiment three
Its with embodiment one difference lies in:First driving wheel 310 is helical gear.
The thread surface setting of the seal plug 4223 is wound with sealing belt.
Example IV
A kind of application method of high-temperature medium plugging pipelines device:
S1:After checking all parts normal operation, inspection support telescopic arm is stretched out, then carries out inspection transversal stretching bar It is expanded to bearing pipe central upper portion, is turned to camber inspection guide rail at a wherein limited block by the first driving wheel, so The inspection to half pipeline surface is realized by the walking of walking dolly afterwards, by camber inspection guide rail after completing to half inspection It turns at another limited block, is then returned by walking dolly and inspection is carried out to the other half pipeline surface;
S2:When air-flow detection module detects pressure sensor there are when pressure during inspection, walking dolly can then stop It only walks, is then slowly being moved forward and backward, and camber inspection guide rail is slowly moved back and forth, and is implicitly present in The phenomenon that gas leakage, and the location information of corresponding pressure sensor is fed back into control mechanism, and inspection mechanism is stored, together When detect when the temperature is excessively high when temperature sensor, then signal can be passed to computer, and solenoid valve is controlled by computer, By the gas discharge in compressed tanks, to cooling down at leakage, until temperature is restored to normal temperature state, then to stop operation;
S3:According to the range data of gas leakage coordinate information and leak holes that inspection mechanism obtains, itself is judged by control mechanism Whether the tool of carrying can directly be constructed, and use sequence;
When detect meet plugging mechanism opereating specification when, by adjusting block support telescopic arm height, then according to gas leakage Coordinate information adjustment blocks the angle of steering motor, then drives the second camber drive rack row by the rotation of the second driving wheel It walks, to adjust plugging hole to gas leakage coordinate position, then by blocking support telescopic arm, blocking the mutual of transversal stretching bar Coordination downwards compresses leak holes, closes the first solenoid valve by control mechanism at this time, realizes temporarily sealing;
S4:It will be operated during base station pushes at plugging hole by operating telescopic rod, operation support telescopic arm stretches out upwards, And operation cross-brace arm is protruding so that the working position of the work of operation panel when rotated can be aligned in leak holes Then first operating unit is aligned and blocks pipe by heart position first, and realize operation boss and block the fixing seal of pipe upper end, Then the first solenoid valve is opened, is put into inner seal in pressure pipeline across leak holes by the first operation telescopic rod, After inner seal is fixed, heater strip is heated by conductive plug, so that memorial alloy obturating cup is realized It restores, and gluing, sealing is realized by sealing ring and inner wall of the pipe;
S5:Then electromagnetic clamp is unclamped, and cuts off conductive plug power supply, and the first operation telescopic rod is resetted, is then shut off First solenoid valve, and lifting operation support telescopic arm, then rotate operation panel so that the second operation telescopic rod alignment envelope Plugging, and moved downward by operating support telescopic arm, and be sealed by operating boss to blocking pipe, then open first Solenoid valve, and reaming is carried out to pressure-bearing tube wall downwards under the drive of the second operation telescopic rod, and will by the first negative pressure suction nozzle Abrasive dust siphons away, and after expanding treatment, the second operation telescopic rod is resetted;
S6:Lifting operation support telescopic arm, then rotates operation panel so that and third operates telescopic rod alignment and blocks pipe, Then it is moved downward by operating support telescopic arm, and is sealed by operating boss to blocking pipe, then grasped by third Make moving downward for telescopic rod and tapping is carried out to leak holes, and is siphoned away abrasive dust by the second negative suction head, it, will after tapping Third operation telescopic rod is resetted;
S7:Lifting operation support telescopic arm, then rotates operation panel so that and the 4th operation telescopic rod alignment blocks pipe, Then it is moved downward by operating support telescopic arm, and is sealed by operating boss to blocking pipe, then pass through the 4th behaviour Make moving downward for telescopic rod leak holes are fixed and tighten, realizes sealing.
Embodiment five
Its with embodiment one difference lies in:Further, in S3, when detecting that leak holes are too small, then it can pass through control Mechanism sends aperture and the location data signal of leak holes to operation maintenance personnel on one side, and completes the action of temporarily sealing;
Operation maintenance personnel chooses the drill bit of corresponding model, machine tap, blocks screw, go to scene after receiving data-signal, After reaching scene, instruction is sent out by smart mobile phone APP so that plugging mechanism, which releases temporarily sealing action and realizes, to be resetted, and It, will by operation maintenance personnel so that the present apparatus runs the position to the end of pipeline closest to operation maintenance personnel under the drive of walking dolly Drill bit is mounted on the second operating unit, and machine tap is arranged on third operating unit, will be blocked screw and is arranged the 4th On operating unit;
After accomplishing the setting up, operation maintenance personnel makes the present apparatus resume operation by cell phone application, then first carry out S5 the step of, It carries out being punching difference lies in it with S5;Then in the sealing for entering step S4 progress inner seals;Then entering Tapping is carried out in S6, is then being entered S7 steps, is being completed sealing blocking.
Further, it in S3, when detecting that leak holes are excessive, then can be sent out on one side to operation maintenance personnel by control mechanism Aperture and the location data signal for sending leak holes then proceed by S4 steps, realize temporarily sealing;
Operation maintenance personnel chooses the drill bit of corresponding model, machine tap, blocks screw, go to scene after receiving data-signal, After reaching scene, instruction is sent out by smart mobile phone APP so that plugging mechanism, which releases temporarily sealing action and realizes, to be resetted, and It, will by operation maintenance personnel so that the present apparatus runs the position to the end of pipeline closest to operation maintenance personnel under the drive of walking dolly Drill bit is mounted on the second operating unit, and machine tap is arranged on third operating unit, will be blocked screw and is arranged the 4th On operating unit, S5 steps are then entered back into.
Further, in S6, the first solenoid valve is closed, then lifting operation support telescopic arm, then operation panel is carried out Rotation so that the first operation telescopic rod alignment blocks pipe, is then moved downward by operating support telescopic arm, and convex by operating Platform is sealed to blocking pipe, opens the first solenoid valve, then moving downward by the first operation telescopic rod, by the first operation The electromagnetic clamp of telescopic rod end is mutually fixed with inner seal end, is then firmly pulled upwardly so that memorial alloy obturating cup Deformation is generated, and then pulls out leak holes, then so that closing the first solenoid valve;
In S7, after operation boss is sealed closure pipe, the first solenoid valve is opened.
Further, graphite encapsulation layer is arranged in seal plug surface in S7.
The above is the preferred embodiment of the present invention, it is noted that for those skilled in the art For, without departing from the principles of the present invention, it can also make several improvements and retouch, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (10)

1. a kind of high-temperature medium plugging pipelines device, it is characterised in that:Including being arranged base is fixed in the end of pressure piping Walking mechanism on seat, the inspection mechanism being arranged in the walking mechanism are arranged in the walking mechanism and are patrolled with described The matched plugging mechanism of mechanism is examined, and is arranged in the walking mechanism for controlling walking mechanism, inspection mechanism and envelope The control mechanism of stifled mechanism;
The walking mechanism includes the walking track being connected with the fixed pedestal of pressure piping, is arranged on the walking track Walking dolly, be arranged in the walking dolly lower part and the matched multiple driving wheels of walking track, with the driving Matched driving motor is taken turns, the cooling mechanism on the walking dolly is set, and is arranged on the walking dolly The control mechanism.
2. high-temperature medium plugging pipelines device as described in claim 1, it is characterised in that:The inspection mechanism includes patrolling Support telescopic arm is examined, the inspection transversal stretching bar in the inspection support telescopic arm upper end is set, and setting is in inspection transverse direction Inspection electric rotating machine is arranged in telescopic rod end, and the inspection driving motor on the inspection electric rotating machine output shaft is arranged, and is arranged The first driving wheel in the inspection driving motor output shaft, two inspections being connected with the inspection driving motor shell are led Slot, and two matched camber inspection guide rails of inspection guide groove, setting the camber inspection guide rail upper surface and with it is described The limited block at the camber inspection guide rail both ends is arranged in the matched first camber drive rack of first driving wheel, and Air-flow detection module on the camber inspection guide rail lower surface is set.
3. high-temperature medium plugging pipelines device as claimed in claim 2, it is characterised in that:The air-flow detection module packet The camber detection plate being arranged on the arc inspection guide rail is included, multiple pressure sensings in the camber detection plate are set Device, and the airflow plate in the pressure sensor upper end is set.
4. high-temperature medium plugging pipelines device as claimed in claim 3, it is characterised in that:The plugging mechanism includes setting The closure support telescopic arm on the walking dolly is set, the closure transversal stretching in the closure support telescopic arm upper end is set Bar is arranged in the closure steering motor for blocking transversal stretching boom end, is arranged on the closure steering motor output end Closure bridge block, be arranged and block two on bridge joint block described and block guide grooves, be arranged between the two closure guide grooves and position In the closure driving motor blocked on bridge joint block, second be arranged on the output shaft for blocking driving motor drives Wheel matches camber with the closure guide groove and blocks guide rail, and setting blocks guide rail upper surface in the camber and driven with second Matched second camber drive rack is taken turns, is arranged and blocks the closure support plate on guide rail in the camber, and be arranged in institute State the plugging module blocked in support plate.
5. high-temperature medium plugging pipelines device as claimed in claim 4, it is characterised in that:The plugging module includes setting The plugging hole in the closure support plate is set, the closure pipe being arranged on the plugging hole is arranged on the closure pipe First solenoid valve, the closure working track for being arranged in the closure support plate and being coordinated with the closure pipe, setting exist Operation base station on the closure working track is arranged in the closure working track end and is connected with the operation base station Operation telescopic rod, be arranged it is described operation base station on operation support telescopic arm, be arranged on the operation support telescopic arm The operation cross-brace arm at end is arranged the operation rotary electric machine in the operation cross-brace arm end, is arranged in the operation Operation panel on rotary electric machine output shaft, be arranged on the operation panel multiple and the operation boss being circumferentially distributed, and The first operating unit, the second operating unit, third operating unit and the 4th operation being arranged on multiple operation boss are single Member.
6. high-temperature medium plugging pipelines device as claimed in claim 5, it is characterised in that:The first operating unit packet The first operation telescopic rod being arranged on operation boss is included, the electromagnetic clamp in the first operation telescopic rod end, setting are set Inner seal on the electromagnetic clamp is arranged on the electromagnetic clamp matched conductive slotting with the inner seal Head.
7. high-temperature medium plugging pipelines device as claimed in claim 6, it is characterised in that:The second operating unit packet The second operation telescopic rod being arranged on the operation boss is included, the punching electricity in the second operation telescopic rod end is set Machine, is arranged the drill bit on the drilling motor output shaft, and setting is on the drilling motor and matched with the drill bit First negative pressure suction nozzle, the first negative pressure suction nozzle are matched with the Minitype negative pressure machine being arranged on the operation panel.
8. high-temperature medium plugging pipelines device as claimed in claim 7, it is characterised in that:The third operating unit packet It includes the third being arranged on the operation boss and operates telescopic rod, the tapping electricity that telescopic rod end is operated in the third is set Machine, is arranged the screw tap on the tapping motor output shaft, and setting is on the tapping motor and matched with the screw tap Second negative pressure suction nozzle, the second negative pressure suction nozzle are matched with the Minitype negative pressure machine being arranged on the operation panel.
9. high-temperature medium plugging pipelines device as claimed in claim 8, it is characterised in that:The camber block guide rail with Circular radius distance value where camber inspection guide rail is more than the circular radius distance value of pressure pipeline cross section outer wall.
10. high-temperature medium plugging pipelines device as claimed in claim 9, it is characterised in that:The cooling mechanism includes The storehouse that cools down on walking dolly is set, the compressed tanks in the cooling storehouse are set, the electricity in the compressed tanks exit is set Magnet valve is connected with the solenoid valve and is located at multiple nozzles on the walking dolly, is arranged on the walking dolly Multiple temperature sensors, the solenoid valve and multiple temperature sensors are interconnected with the Computer signal.
CN201810114521.8A 2018-02-05 2018-02-05 A kind of high-temperature medium plugging pipelines device Withdrawn CN108317334A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810114521.8A CN108317334A (en) 2018-02-05 2018-02-05 A kind of high-temperature medium plugging pipelines device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810114521.8A CN108317334A (en) 2018-02-05 2018-02-05 A kind of high-temperature medium plugging pipelines device

Publications (1)

Publication Number Publication Date
CN108317334A true CN108317334A (en) 2018-07-24

Family

ID=62901990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810114521.8A Withdrawn CN108317334A (en) 2018-02-05 2018-02-05 A kind of high-temperature medium plugging pipelines device

Country Status (1)

Country Link
CN (1) CN108317334A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460483A (en) * 2020-10-21 2021-03-09 英诺维尔智能科技(苏州)有限公司 Pipeline switch structure in sterilization system
CN113340519A (en) * 2021-04-27 2021-09-03 郑志扬 High-stability monocrystalline silicon differential pressure sensor
CN115727220A (en) * 2023-01-09 2023-03-03 山东石油化工学院 Temporary plugging device for petroleum transportation pipeline

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2752583Y (en) * 2004-11-04 2006-01-18 万宏伟 Equipment for making urgent repair on perforating on plastic composite gas pipe with steel skeleton
CN201851837U (en) * 2010-11-18 2011-06-01 中国石油天然气集团公司 Device for repairing, reinforcing and/or preventing crack of in-service pipeline
CN103650059A (en) * 2011-07-13 2014-03-19 韩国电力技术株式会社 Apparatus and method for inspecting pipelines
CN104514943A (en) * 2013-09-30 2015-04-15 宝山钢铁股份有限公司 Method for repairing pressure pipeline burying defects
CN204345165U (en) * 2014-12-28 2015-05-20 漯河职业技术学院 A kind of harmful gas pipe leakage emergency treatment plant
CN204756297U (en) * 2015-06-11 2015-11-11 娄颖 Petroleum pipeline repairs device with detecting
CN206290903U (en) * 2016-12-18 2017-06-30 广东元和鑫龙游艇制造有限公司 A kind of pipeline maintenance device for plugging easy to use
CN206504041U (en) * 2017-01-20 2017-09-19 中国石油化工股份有限公司 The dual-purpose equipment of plugging holes of pipeline
CN107314190A (en) * 2017-08-04 2017-11-03 中国石油大学(北京) Pipeline rehabilitation device
CN107387938A (en) * 2017-07-05 2017-11-24 佛山杰致信息科技有限公司 pipeline rehabilitation robot
CN206831048U (en) * 2017-05-10 2018-01-02 浙江海洋大学 A kind of sea-bottom oil-gas pipeline leaks real-time automatic sealing package leakage device

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2752583Y (en) * 2004-11-04 2006-01-18 万宏伟 Equipment for making urgent repair on perforating on plastic composite gas pipe with steel skeleton
CN201851837U (en) * 2010-11-18 2011-06-01 中国石油天然气集团公司 Device for repairing, reinforcing and/or preventing crack of in-service pipeline
CN103650059A (en) * 2011-07-13 2014-03-19 韩国电力技术株式会社 Apparatus and method for inspecting pipelines
CN104514943A (en) * 2013-09-30 2015-04-15 宝山钢铁股份有限公司 Method for repairing pressure pipeline burying defects
CN204345165U (en) * 2014-12-28 2015-05-20 漯河职业技术学院 A kind of harmful gas pipe leakage emergency treatment plant
CN204756297U (en) * 2015-06-11 2015-11-11 娄颖 Petroleum pipeline repairs device with detecting
CN206290903U (en) * 2016-12-18 2017-06-30 广东元和鑫龙游艇制造有限公司 A kind of pipeline maintenance device for plugging easy to use
CN206504041U (en) * 2017-01-20 2017-09-19 中国石油化工股份有限公司 The dual-purpose equipment of plugging holes of pipeline
CN206831048U (en) * 2017-05-10 2018-01-02 浙江海洋大学 A kind of sea-bottom oil-gas pipeline leaks real-time automatic sealing package leakage device
CN107387938A (en) * 2017-07-05 2017-11-24 佛山杰致信息科技有限公司 pipeline rehabilitation robot
CN107314190A (en) * 2017-08-04 2017-11-03 中国石油大学(北京) Pipeline rehabilitation device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460483A (en) * 2020-10-21 2021-03-09 英诺维尔智能科技(苏州)有限公司 Pipeline switch structure in sterilization system
CN113340519A (en) * 2021-04-27 2021-09-03 郑志扬 High-stability monocrystalline silicon differential pressure sensor
CN113340519B (en) * 2021-04-27 2022-07-19 安徽允昊物联网科技有限公司 High-stability monocrystalline silicon differential pressure sensor
CN115727220A (en) * 2023-01-09 2023-03-03 山东石油化工学院 Temporary plugging device for petroleum transportation pipeline

Similar Documents

Publication Publication Date Title
CN108398217A (en) Plugging device is monitored automatically at a kind of pressure-bearing pipeline leakage
CN206854736U (en) Pipe cutting machine people
CN108317334A (en) A kind of high-temperature medium plugging pipelines device
CN107489854B (en) A kind of contactless magnetic adsorption wall climbing robot adapting to complicated wall surface operation
CN108332061A (en) A kind of pressure pipeline leakage emergency treatment device
CN108374942A (en) A kind of pressure-bearing pipeline plugging device
CN203765395U (en) Automatic polishing machine for flange faces of rotators
US5669547A (en) Apparatus and method for supplying inert gas to a welding location
CN104977215B (en) Steel pipe air pressure resistance automatic checkout equipment
CN108680312B (en) Detection mechanism for automatically detecting product air tightness on production line and application of detection mechanism
CN107812962A (en) A kind of machine tool chief axis with annular spray formula cooling device
WO2024113600A1 (en) Gas impurity detection apparatus for electronic-grade fluorine gas preparation
CN107013018A (en) A kind of high-rise outer rendering robot
CN210719570U (en) Airtight detector of blast pipe based on PLC control
CN103143480B (en) A kind of rear axle housing glue spreader
CN108361467B (en) A kind of method for blocking of pressure-bearing pipeline
CN111633307B (en) Welding device
CN106077949A (en) A kind of based on the laser welding packaging device under the conditions of atmosphere protection
CN208596016U (en) The testing agency of products air tightness on a kind of automatic detection production line
CN205175633U (en) A sealed frock that is used for water heater inner bag welding seam to hunt leak
CN204053477U (en) Large-scale steel structure robot automatic charging welding grinding and polishing detection system
CN115890430A (en) High-precision vertical grinding machine with automatic positioning and aligning functions
KR102552198B1 (en) Welding Bead Automatic Grinding System of ICT and IoT and Method Thereof
CN209716806U (en) A kind of package seal checker of steel drum welding line of barrel body
CN209559438U (en) The air-tightness detection tool of PUN type water pump

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180724