CN108301441A - A kind of prefabricated underground pipe gallery box culvert - Google Patents
A kind of prefabricated underground pipe gallery box culvert Download PDFInfo
- Publication number
- CN108301441A CN108301441A CN201810356660.1A CN201810356660A CN108301441A CN 108301441 A CN108301441 A CN 108301441A CN 201810356660 A CN201810356660 A CN 201810356660A CN 108301441 A CN108301441 A CN 108301441A
- Authority
- CN
- China
- Prior art keywords
- plate
- partition board
- side plate
- link slot
- junction steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000005192 partition Methods 0.000 claims abstract description 41
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 22
- 239000010959 steel Substances 0.000 claims abstract description 22
- 239000003292 glue Substances 0.000 claims abstract description 13
- 229910052799 carbon Inorganic materials 0.000 claims description 4
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 claims description 3
- 229920002430 Fibre-reinforced plastic Polymers 0.000 claims description 3
- 239000011151 fibre-reinforced plastic Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 9
- 238000005265 energy consumption Methods 0.000 abstract description 3
- 230000011218 segmentation Effects 0.000 abstract description 3
- 238000003912 environmental pollution Methods 0.000 abstract description 2
- 230000018109 developmental process Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 6
- 230000002787 reinforcement Effects 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 4
- 238000005266 casting Methods 0.000 description 2
- 239000004744 fabric Substances 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 1
- 239000000835 fiber Substances 0.000 description 1
- 239000012634 fragment Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 230000003746 surface roughness Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Sewage (AREA)
Abstract
A kind of prefabricated underground pipe gallery box culvert, it is characterised in that:Including bottom plate, top plate, side plate and partition board, bottom plate and the upper surface of side plate and partition board are reserved with link slot respectively, it is embedded with junction steel plate below top plate and side plate and partition board, side plate and partition board are inserted into the link slot on bottom plate by following junction steel plate and use structure glue Nian Jie with bottom plate, and top plate is inserted into the link slot above side plate and partition board by following junction steel plate and uses structure glue Nian Jie with side plate and partition board.The present invention reserves link slot in bottom plate and the upper surface of side plate and partition board, it is embedded with junction steel plate below top plate and side plate and partition board, by junction steel plate and link slot grafting and it is bonded, realize that the fabricated construction of underground pipe gallery, the drawbacks of overcoming cast-in-place piping lane improve construction efficiency, it reduces environmental pollution, cost is reduced, energy consumption is saved, meets the industrialized development trend of construction industry.It solves the disadvantage that the prefabricated piping lane weight of segmentation is heavy, sectional dimension is big, not readily transportable and lifting, assembled piping lane is made to be easier to realize.
Description
Technical field
The present invention relates to underground pipe gallery more particularly to a kind of box culverts of novel fabricated underground pipe gallery.
Background technology
Currently, domestic underground pipe gallery is mostly based on cast-type, long construction period, is constructed into wasting manpower and material resources
This height, energy consumption are big, do not meet the requirement for the building pollution-free industry advocated in China.
Since underground pipe gallery section is tall and big, quality weight is not easy to be segmented prefabricated transport, and lifts and need bigger
Lifting equipment, be badly in need of developing a kind of novel fabricated pipe gallery that fragment is prefabricated.
Invention content
It is an object of the invention to overcome the shortcomings of cast-in-place pipe gallery, the difficulty of segmentation prefabricated transport and lifting is solved,
Develop it is a kind of it is easy to connect, be readily transported, be easy installation novel fabricated underground pipe gallery.
To achieve the above object, the present invention provides a kind of prefabricated underground pipe gallery box culvert, it is characterised in that:Packet
Include bottom plate, top plate, side plate and partition board, bottom plate and the upper surface of side plate and partition board be reserved with respectively link slot, top plate and side plate and every
Junction steel plate, side plate and partition board is embedded with below plate to be inserted into the link slot on bottom plate and using knot by following junction steel plate
Structure glue is Nian Jie with bottom plate, and top plate is inserted into the link slot above side plate and partition board by following junction steel plate and uses structure glue
It is Nian Jie with side plate and partition board.
The bottom plate, top plate, side plate and partition board side be embedded with hanging ring.
The outer carbon fibre reinforced polymer of the seam crossing of bottom plate, top plate and the side plate and partition board.
The present invention reserves link slot in bottom plate and the upper surface of side plate and partition board, is embedded with below top plate and side plate and partition board
Junction steel plate by junction steel plate and link slot grafting and is bonded, realizes the fabricated construction of underground pipe gallery, overcomes existing
The drawbacks of pouring piping lane improves construction efficiency, reduces environmental pollution, and reduces cost, saves energy consumption, meets the industrialized hair of construction industry
Exhibition trend.It solves the disadvantage that the prefabricated piping lane weight of segmentation is heavy, sectional dimension is big, not readily transportable and lifting, makes assembled pipe
Corridor is easier to realize.
Description of the drawings
Fig. 1 is component assembling schematic diagram;
Fig. 2 is floor diagram;
Fig. 3 is bottom plate sectional view;
Fig. 4 is top plate schematic diagram;
Fig. 5 is top plate sectional view;
Fig. 6 is side plate schematic diagram;
Fig. 7 is side plate sectional view;
Fig. 8 is partition board schematic diagram;
Fig. 9 is partition board sectional view;
Figure 10 is that schematic diagram is completed in component assembly.
Reference sign:
1 --- bottom plate;2 --- top plate;3 --- side plate;4 --- partition board
5 --- junction steel plate;6 --- link slot;7 --- carbon cloth
8 --- hanging ring.
Specific implementation mode
- Fig. 9 referring to Fig.1, bottom plate 1 reserve link slot 6 at the position being connect with side plate 3 and partition board 4, pre- on the outside of both sides
Bury hanging ring 8.The pre-buried junction steel plate 5 at the position being connect with side plate 3 and partition board 4 of top plate 2, the pre-buried hanging ring 8 on the outside of both sides.Side
Remain for the reserved link slot 6 being connect with top plate at the top of plate in advance, the pre-buried junction steel plate for being connect with bottom plate in bottom, both sides are pre-
Bury hanging ring 8.The construction of partition board is identical as side plate.Side plate and partition board are inserted by following junction steel plate in the link slot on bottom plate
And it is Nian Jie with bottom plate using structure glue, in the link slot that top plate is inserted by following junction steel plate above side plate and partition board and make
It is Nian Jie with side plate and partition board with structure glue.Carbon fibre reinforced polymer 7 outside the seam crossing of bottom plate, top plate and the side plate and partition board.
The present invention component manufacturing process be:Prefabricated panel 1, top plate 2, side plate 3 and partition board 4 in the factory.The system of bottom plate 1
It is to be laid with bar-mat reinforcement in template as process, junction steel plate 5 and component 8 is fixed on the corresponding position of bar-mat reinforcement, then is poured
Concrete simultaneously conserves.The manufacturing process of top plate 2 is that bar-mat reinforcement is laid in template, then by the mould used in component 8 and link slot 6
Plate is fixed on the corresponding position of bar-mat reinforcement, and casting concrete simultaneously conserves.The manufacturing process of side plate 3 is that reinforcing bar is laid in template
Net, then the template of junction steel plate 5, component 8 and link slot 6 is fixed on the corresponding position of bar-mat reinforcement, casting concrete is simultaneously
Maintenance.The manufacturing process of partition board 4 is the same as side plate 3.It, be in seam crossing in the making of bottom plate 1, top plate 2, side plate 3, partition board 4 is constituted
Section carry out surface roughness processing, be conducive to structure glue and component bonded.
Scene assembling sequence be:First bottom plate 1 is placed on construction location, is filled in the link slot 6 on 1 top of bottom plate
The pre-buried junction steel plate 5 of side plate 3 and 4 bottom of partition board is inserted into the link slot 6 on 1 top of bottom plate, makes structure glue by structure glue later
Spilling is paved with entire seam, plays the role of waterproof.Structure glue is filled in the link slot 6 at 4 top of side plate 3 and partition board again, it will
Pre-buried junction steel plate 5 is inserted into the link slot 6 at 4 top of side plate 3 and partition board in top plate 2, so that structure glue spilling is paved with and is entirely connect
Seam.Finally deposit of the seam crossing outer patch fiber cloth as joint strength between components completes the assembling of a box culvert at this time.
Claims (3)
1. a kind of prefabricated underground pipe gallery box culvert, it is characterised in that:Including bottom plate, top plate, side plate and partition board, bottom plate
Be reserved with respectively below link slot, top plate and side plate and partition board with the upper surface of side plate and partition board and be embedded with junction steel plate, side plate and
Partition board is inserted into the link slot on bottom plate by following junction steel plate and uses structure glue Nian Jie with bottom plate, and top plate passes through following
Junction steel plate be inserted into it is in the link slot above side plate and partition board and Nian Jie with side plate and partition board using structure glue.
2. a kind of prefabricated underground pipe gallery box culvert according to claim 1, it is characterised in that:The bottom
Plate, top plate, side plate and partition board side be embedded with hanging ring.
3. a kind of prefabricated underground pipe gallery box culvert according to claim 1, it is characterised in that:The bottom
The outer carbon fibre reinforced polymer of the seam crossing of plate, top plate and side plate and partition board.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810356660.1A CN108301441A (en) | 2018-04-20 | 2018-04-20 | A kind of prefabricated underground pipe gallery box culvert |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810356660.1A CN108301441A (en) | 2018-04-20 | 2018-04-20 | A kind of prefabricated underground pipe gallery box culvert |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108301441A true CN108301441A (en) | 2018-07-20 |
Family
ID=62847580
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810356660.1A Pending CN108301441A (en) | 2018-04-20 | 2018-04-20 | A kind of prefabricated underground pipe gallery box culvert |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108301441A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109723458A (en) * | 2018-12-29 | 2019-05-07 | 浙江万川装饰设计工程有限公司 | A kind of municipal tunnel |
CN110847053A (en) * | 2019-11-29 | 2020-02-28 | 中铁二院工程集团有限责任公司 | Construction method of vacuum magnetic suspension prefabricated assembly type pipeline beam |
CN110965579A (en) * | 2019-11-30 | 2020-04-07 | 四川鸥鹏建筑工程公司 | Double-bin spliced underground comprehensive pipe gallery |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105256837A (en) * | 2015-11-03 | 2016-01-20 | 深圳华瀚管廊物业服务有限公司 | Pipe gallery prefabricated member and assembled comprehensive pipe gallery |
CN105625471A (en) * | 2016-03-14 | 2016-06-01 | 青岛润国生态科技发展有限公司 | Prefabricated comprehensive pipe gallery |
CN105839666A (en) * | 2016-06-03 | 2016-08-10 | 长沙远大住宅工业集团股份有限公司 | Total-prefabricated superimposed assembly type underground pipe gallery and connecting node thereof |
CN206844147U (en) * | 2017-05-19 | 2018-01-05 | 西安交通大学 | Full prefabricated modular assembled pipe gallery |
CN208072464U (en) * | 2018-04-20 | 2018-11-09 | 长春工程学院 | A kind of prefabricated underground pipe gallery box culvert |
-
2018
- 2018-04-20 CN CN201810356660.1A patent/CN108301441A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105256837A (en) * | 2015-11-03 | 2016-01-20 | 深圳华瀚管廊物业服务有限公司 | Pipe gallery prefabricated member and assembled comprehensive pipe gallery |
CN105625471A (en) * | 2016-03-14 | 2016-06-01 | 青岛润国生态科技发展有限公司 | Prefabricated comprehensive pipe gallery |
CN105839666A (en) * | 2016-06-03 | 2016-08-10 | 长沙远大住宅工业集团股份有限公司 | Total-prefabricated superimposed assembly type underground pipe gallery and connecting node thereof |
CN206844147U (en) * | 2017-05-19 | 2018-01-05 | 西安交通大学 | Full prefabricated modular assembled pipe gallery |
CN208072464U (en) * | 2018-04-20 | 2018-11-09 | 长春工程学院 | A kind of prefabricated underground pipe gallery box culvert |
Non-Patent Citations (1)
Title |
---|
闫滨: "《病险水库除险加固技术》", 辽宁科学技术出版社, pages: 212 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109723458A (en) * | 2018-12-29 | 2019-05-07 | 浙江万川装饰设计工程有限公司 | A kind of municipal tunnel |
CN110847053A (en) * | 2019-11-29 | 2020-02-28 | 中铁二院工程集团有限责任公司 | Construction method of vacuum magnetic suspension prefabricated assembly type pipeline beam |
CN110965579A (en) * | 2019-11-30 | 2020-04-07 | 四川鸥鹏建筑工程公司 | Double-bin spliced underground comprehensive pipe gallery |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204531066U (en) | Assembly concrete-filled steel tube shear wall splits assembled syndeton | |
CN206052779U (en) | A kind of prefabricated pipe gallery splicing structure | |
CN105839666A (en) | Total-prefabricated superimposed assembly type underground pipe gallery and connecting node thereof | |
CN104727467A (en) | Assembly type concrete filled steel tube shear wall splitting and assembling connection structure and assembling connection method | |
CN205662947U (en) | Coincide assembled underground pipe gallery system | |
CN207348091U (en) | A kind of assembled pipe gallery | |
CN108301441A (en) | A kind of prefabricated underground pipe gallery box culvert | |
CN205742265U (en) | Complete prefabricated overlapping assembled underground pipe gallery and connection node thereof | |
CN108560586A (en) | Half prefabricated assembled pipe gallery and its construction method | |
CN103343503B (en) | Bridge-type prefabricated reinforced concrete trough slab wear resistant road surface structural system and construction method | |
CN208072464U (en) | A kind of prefabricated underground pipe gallery box culvert | |
CN105625466A (en) | Assembled prefabricated comprehensive pipe gallery | |
CN103334360B (en) | The dark beam slab wear-resistant pavement system of bridge-type prefabricated reinforced concrete and construction method thereof | |
CN205894280U (en) | Hollow superstructure beam -columns system's integral basement of coincide assembly | |
CN205369299U (en) | Pin -connected panel precast reinforced concrete piping lane | |
CN205894278U (en) | Solid superstructure beam -columns system's integral basement of coincide assembly | |
CN205116220U (en) | Pour cable pit after assembly of L type precast concrete spare | |
CN102003026A (en) | Combined hollow box body for cast-in-place energy-saving hollow floor | |
CN101994358A (en) | Combined hollow box body used for cast-in-place energy-saving hollow floor system | |
CN206554283U (en) | Prefabricated board connecting structure | |
CN210887303U (en) | Coincide assembled utility tunnel structure | |
CN103850163B (en) | Bridge-type steel plate pavement system and construction method thereof | |
CN204590360U (en) | A kind of cavity plate continuously | |
CN111535490B (en) | Fabricated floor and construction method thereof | |
CN218205192U (en) | Assembled light fiber cement prefabricated slab |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180720 |