CN108280623A - 一种基于bim在电力管道拉管中应用的方法 - Google Patents
一种基于bim在电力管道拉管中应用的方法 Download PDFInfo
- Publication number
- CN108280623A CN108280623A CN201711427460.2A CN201711427460A CN108280623A CN 108280623 A CN108280623 A CN 108280623A CN 201711427460 A CN201711427460 A CN 201711427460A CN 108280623 A CN108280623 A CN 108280623A
- Authority
- CN
- China
- Prior art keywords
- bim
- power pipe
- trombone slide
- pipe
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T17/00—Three dimensional [3D] modelling, e.g. data description of 3D objects
- G06T17/05—Geographic models
Abstract
本发明实施例提供了一种基于BIM在电力管道拉管中应用的方法,主要包括以下流程:获取地形、地貌和地下情况→建立三维地形、地貌模型:将获取的地形、地貌和地下情况转化成三维的BIM模型→建立电力管道模型→数据信息辅助→施工应用;本发明的目的在于将BIM技术应用到电力管道拉管中,利用其强大的数据计算、三维可视、模拟等功能,选定合理的拉管路径,制定施工方案,同时给予现场以三维可视化的交底。解决了电力管道施工过程中易导致地下管线破坏,造成的经济损失、人员安全和环境影响的问题。
Description
技术领域
本发明属于建筑工程技术领域,具体涉及一种基于BIM在电力管道拉管中应用的方法。
背景技术
电力管道施工过程中遇到市政主干道、国家保护区域及开挖难以实现的区域,基本采用拉管施工工艺,每年由于拉管施工而造成地下管线破坏以及市政道路下沉的情况很多,其中被破坏的地下管线大多由燃气、电力、给水、通讯管线组成,给公共安全、居民的生活造成了很大的影响,也造成了巨大的经济损失。
发明内容
本发明的目的在于将BIM技术应用到电力管道拉管中,利用其强大的数据计算、三维可视、模拟等功能,选定合理的拉管路径,制定施工方案,同时给予现场以三维可视化的交底。解决上述背景技术中提出的电力管道施工过程中易导致地下管线破坏,造成的经济损失、人员安全和环境影响的问题。
为实现上述目的,本发明提供了一种基于BIM在电力管道拉管中应用的方法,包括以下步骤:
步骤一,利用BIM建模技术,扫描还原现场的地形地貌,与规划部门联系取得拉管区域的地下管线图,结合地勘报告,结合后建立三维的数据模型,按地下管线的安全特性,考虑其安全区域,以及地质特点,在不造成原有地面下沉的情况下,考虑其深度、穿越地质区域;
步骤二,确保上述要求后,建立电力管道初步模型,通过BIM软件计算拉管的弯曲弧度,拉管过程中各管道承受的拉力、土体压力,通过反复的调整电力管道方案,选定最终满足计算的路径,调整三维模型;
步骤三,利用BIM软件生成工程量明细表,制定采购计划,按计算得出的数据,选择电力管道材质,同时生成平、剖面图,制定施工方案。
优选的,在施工过程中结合模型,实时掌握拉管施工过程中地下的动态。
本发明使操作人员实时了解施工信息和工艺要求,提高了项目的施工水平,确保了施工过程中的安全、质量要求,减少了对周围环境的破坏,控制了施工成本,提高了与现场的沟通。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
本发明实施例提供了一种基于BIM在电力管道拉管中应用的方法,其具体实施方式如下:
1)获取地形、地貌和地下情况:利用BIM建模技术,扫描还原现场的地形地貌,与规划部门联系取得拉管区域的地下管线图,结合地勘报告,结合后建立三维的数据模型;
2)建立三维地形、地貌模型:将获取的地形、地貌和地下情况转化成三维的BIM模型;
3)建立电力管道模型:按地下管线的安全特性,考虑其安全区域,以及根据地质特点,在不造成原有地面下沉的情况下,考虑其深度、穿越地质区域。确保上述要求后,建立电力管道初步模型,通过BIM软件计算拉管的弯曲弧度,拉管过程中各管道承受的拉力、土体压力,通过反复的调整电力管道方案,选定最终满足计算的路径,调整三维模型;
4)数据信息辅助:利用BIM软件生成工程量明细表,制定采购计划,按计算得出的数据,选择电力管道材质,同时生成平、剖面图,制定施工方案;
5)施工应用:在拉管施工过程中,给工程施工人员以三维可视化交底,实时掌握拉管施工过程中地下的动态。
需要说明的是,在本文中,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括一个……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。
以上所述仅是本发明的具体实施方式,使本领域技术人员能够理解或实现本发明。对这些实施例的多种修改对本领域的技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。
Claims (2)
1.一种基于BIM在电力管道拉管中应用的方法,其特征在于,包括以下步骤:
步骤一,利用BIM建模技术,扫描还原现场的地形地貌,与规划部门联系取得拉管区域的地下管线图,结合地勘报告,结合后建立三维的数据模型,按地下管线的安全特性,考虑其安全区域,以及地质特点,在不造成原有地面下沉的情况下,考虑其深度、穿越地质区域。
步骤二,确保上述要求后,建立电力管道初步模型,通过BIM软件计算拉管的弯曲弧度,拉管过程中各管道承受的拉力、土体压力,通过反复的调整电力管道方案,选定最终满足计算的路径,调整三维模型。
步骤三,利用BIM软件生成工程量明细表,制定采购计划,按计算得出的数据,选择电力管道材质,同时生成平、剖面图,制定施工方案。
2.根据权利要求1所述的一种基于BIM在电力管道拉管中应用的方法,其特征在于,在施工过程中结合模型,操作人员实时掌握拉管施工过程中地下的动态。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711427460.2A CN108280623B (zh) | 2017-12-26 | 2017-12-26 | 一种基于bim在电力管道拉管中应用的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711427460.2A CN108280623B (zh) | 2017-12-26 | 2017-12-26 | 一种基于bim在电力管道拉管中应用的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108280623A true CN108280623A (zh) | 2018-07-13 |
CN108280623B CN108280623B (zh) | 2021-08-03 |
Family
ID=62802322
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711427460.2A Active CN108280623B (zh) | 2017-12-26 | 2017-12-26 | 一种基于bim在电力管道拉管中应用的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108280623B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111931316A (zh) * | 2020-05-26 | 2020-11-13 | 中建八局天津建设工程有限公司 | 一种模块化装配式机房设备及管线施工方法 |
US11120171B2 (en) | 2019-09-13 | 2021-09-14 | Mccormick Systems Llc. | System and method for construction cost estimation for non-computer aided design (CAD) files |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101440895A (zh) * | 2008-12-30 | 2009-05-27 | 浙江尤尼克管业有限公司 | 一种非开挖拖拉管施工的回填装置及方法 |
CN202206072U (zh) * | 2011-08-31 | 2012-04-25 | 广东威恒输变电工程有限公司 | 电缆管道疏通装置 |
US20140353965A1 (en) * | 2012-05-11 | 2014-12-04 | Higashio Mech Co., Ltd. | Pipe joint |
-
2017
- 2017-12-26 CN CN201711427460.2A patent/CN108280623B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101440895A (zh) * | 2008-12-30 | 2009-05-27 | 浙江尤尼克管业有限公司 | 一种非开挖拖拉管施工的回填装置及方法 |
CN202206072U (zh) * | 2011-08-31 | 2012-04-25 | 广东威恒输变电工程有限公司 | 电缆管道疏通装置 |
US20140353965A1 (en) * | 2012-05-11 | 2014-12-04 | Higashio Mech Co., Ltd. | Pipe joint |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11120171B2 (en) | 2019-09-13 | 2021-09-14 | Mccormick Systems Llc. | System and method for construction cost estimation for non-computer aided design (CAD) files |
CN111931316A (zh) * | 2020-05-26 | 2020-11-13 | 中建八局天津建设工程有限公司 | 一种模块化装配式机房设备及管线施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108280623B (zh) | 2021-08-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Merwade et al. | Geospatial representation of river channels | |
CN110532719A (zh) | 一种施工场地土方量计算方法及装置 | |
CN108280623A (zh) | 一种基于bim在电力管道拉管中应用的方法 | |
CN112231818B (zh) | 一种基于bim的山地城市三维地质建模方法 | |
CN105184862B (zh) | 一种三维地层模型动态构建方法 | |
Makasis et al. | Impact of simplifications on numerical modelling of the shallow subsurface at city-scale and implications for shallow geothermal potential | |
Zhen et al. | Integration of engineering geological investigation data and construction of a 3D geological structure model in the Xiong’an new area | |
Campbell et al. | 3D geological models and their hydrogeological applications: supporting urban development: a case study in Glasgow-Clyde, UK | |
Tonini et al. | 3D geo-mapping based on surface data for preliminary study of underground works: A case study in Val Topina (Central Italy) | |
Deutsch | Reservoir modeling with publicly available software | |
CN105760609B (zh) | 一种长输管道站场模型的建模方法及建模系统 | |
JP6449180B2 (ja) | 三次元画像表示システム、三次元画像表示装置、三次元画像表示方法及びプラント設備の三次元画像表示システム | |
Macfarlane | Nature empowered: Hydraulic models and the engineering of Niagara Falls | |
Taranchuk | The integrated program complex of the composer of geological models. The concept, solutions | |
CN116246015A (zh) | 一种含采空区的矿山三维精确模型的建模方法 | |
Paris et al. | Synthesizing Geologically Coherent Cave Networks | |
Wu et al. | A three-dimensional model and its potential application to spring protection | |
Křivánek | Magnetometric prospection of various types of large ditched enclosures in Bohemia | |
CN106446369A (zh) | 基于catia的地下洞室群施工交互仿真方法 | |
Merritt et al. | Integrated geoscience data, maps and 3D models for the City of Glasgow, UK | |
Si-jie et al. | Research on modeling method of 3D geological entity model based on BIM | |
Chiang et al. | Terrain synthesis: An interactive approach | |
Du et al. | Incremental growth of a shallow hydraulic fracture at a waste remediation site, Oakbrook, Illinois from inversion of elevation changes | |
MARIAN | GENERATION OF DIGITAL ELEVATION MODEL BASED ON A CONTOUR MAP AND ITS SUBSEQUENT USE. | |
Paliou et al. | “The Whole is More than the Sum of its Parts”-Geospatial Data Integration, Visualisation and Analysis at the Roman Site of Ammaia (Marvão, Portugal) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |