CN108277750A - The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section - Google Patents

The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section Download PDF

Info

Publication number
CN108277750A
CN108277750A CN201810228531.4A CN201810228531A CN108277750A CN 108277750 A CN108277750 A CN 108277750A CN 201810228531 A CN201810228531 A CN 201810228531A CN 108277750 A CN108277750 A CN 108277750A
Authority
CN
China
Prior art keywords
pile
template
box culvert
fixed
truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810228531.4A
Other languages
Chinese (zh)
Other versions
CN108277750B (en
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Jiangrun Technology Co Ltd
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201810228531.4A priority Critical patent/CN108277750B/en
Publication of CN108277750A publication Critical patent/CN108277750A/en
Application granted granted Critical
Publication of CN108277750B publication Critical patent/CN108277750B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)

Abstract

The present invention relates to a kind of porous cast-in-place box culvert construct methods of high roadbed deep soft foundation pile formula big cross section, it is characterised in that work progress is including excavating high roadbed deep soft foundation pile formula carrying system, the modular assembling Integral Steel sheet pile support system of regularization and being based on the porous cast-in-place box culvert construct technology of regularization Slidable template system big cross section after first precompressed.The present invention improves construction efficiency, applied to can obtain preferable technical economic benefit in Practical Project.

Description

The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section
Technical field
The present invention relates to a kind of porous cast-in-place box culvert construct methods of high roadbed deep soft foundation pile formula big cross section, belong to basis Engineering construction field is suitable for the cast-in-place box culvert construct of pile formula big cross section.
Background technology
With flourishing for China's expressway construction cause, more and more newly-built high speed project input construction, old Technique, aging method have been unable to meet the construction requirement of Modern High-Speed highway construction, therefore logical for big cross section multiple box culvert at present Frequently with cast-in-place method, the porous cast-in-place box culvert of big cross section has the good characteristics such as good integrity, durability be strong, in many highways It is used in engineering.China's Coastal Areas is dispersed with more deep soft foundation, is frequently encountered in highway construction various Soft base.Soft base has the characteristics that high-moisture percentage, high-compressibility, intensity is low and bad hydraulic permeability, in subgrade construction, if place It manages bad, easily causes that subgrade settlement is excessive, in turn results in destabilization of roadbed, the difference of pavement cracking and abutment and subgrade settlement And phenomena such as causing bumping at bridge-head.Therefore to the construction technology for the porous cast-in-place box culvert of big cross section of constructing on high roadbed deep soft foundation More stringent requirements are proposed.
Invention content
It is an object of the invention to be directed to deep soft foundation area box culvert construct process, a kind of elder generation is provided After precompressed excavate high roadbed deep soft foundation pile formula carrying system, the modular assembling Integral Steel sheet pile support system of regularization with And the method based on the porous cast-in-place box culvert construct technology of regularization Slidable template system big cross section.
In order to achieve the above technical purposes, present invention employs following technical schemes:
The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section, which is characterized in that including following step Suddenly:
Step 1 after excavation of foundation pit, sets the pile for prestressed pipe (1) with pile cover (2), and pile cover (2) bottom is solid using bolt Fixed anti-bias armlet (4) and the anti-detachment rib (3) of reinforcement;
Step 2 is laid with bed course, construction bearing platform (7) on pile for prestressed pipe (1);
Step 3 is laid with steel wire grid (6) and blotter (5), formation pile formula reinforcement cushion on cushion cap (7);
Step 4 excavates box culvert basis, and steel sheet pile (8) of constructing on pile formula reinforcement cushion is constructed on steel sheet pile (8) Shaped steel Guan Liang (9) and steel wale (10), steel wale (10) between construct type steel support fixed with high-strength bolt (11) (13) supporting is carried out;
Step 5, construction band is fitted into the thin plate loose tool (14) of rib (15), thin plate loose tool (14) on pile formula reinforcement cushion Corner junction setting corner connection sheet (28) be fixed;
The built-in fitting for fixing outboard template (18) and inner side template (17) is arranged in step 6 on thin plate loose tool (14) (16), outboard template (18) is lifted to fixed position;
Step 7 is laid with billet (19) on the pile formula reinforcement cushion on the outside of thin plate loose tool (14), installs supporting beam (21), it lifts on sub-truss (22) to supporting beam (21) and is set up;
Step 8 installs universal wheel (20) under the supporting beam (21) of sub-truss (22) bottom, and by sub-truss (22) it is moved to designated position with universal wheel;
Step 9, erection construction platform billet (24), and with sub-truss (22) at the top of using fixing bolt (23) into Row is fixed;
Step 10, truss hoisting beam (25) are weldingly fixed on operation platform billet to design position, and by its both sides (24) on;
Step 11 will lift straining beam (26) and will be fixed by bolts to designated position, and with outboard template (18);
Step 12, assembled inner side template (17), is then hoisted to design position and fixation;
Step 13, inner side template (17) and outboard template (18) carry out pouring coagulation by the slip scaffold set up Native (27) construction;
Step 14 after the completion of waiting for concrete curing, removes slip scaffold.
The porous cast-in-place box culvert of big cross section uses band pile cover (2) prestressed pipe using excavation construction after first precompressed, deep soft foundation Stake (1) forms pile formula reinforcement cushion with steel wire grid (6) blotter (5), and prefabricated pile cover (2) is socketed anti-bias using bottom belt Armlet (4) and the high strong ties for reinforcing anti-detachment rib (3) realization stake top and cover board.
The modular assembling Integral Steel sheet pile support system of regularization, including steel sheet pile (8) by steel wale (10) and Shaped steel Guan Liang (9) is linked as steel sheet pile module units, realizes quickly bolt and dismounting by high-strength bolt (11), Guan Liang foundation pit side is set Band silk mandril connecting pin (12) is set, support system is collectively formed with support (13) in steel sheet pile (8).
Regularization Slidable template system for the porous cast-in-place box culvert construct of big cross section, which is characterized in that described fixed Type Slidable template system includes thin plate loose tool (14), outboard template (18), inner side template (17) and slip scaffold, Thin plate loose tool (14) is equipped with the built-in fitting (16) for fixing outboard template (18) and inner side template (17), outboard template (18) Between straining beam (26) is fixedly connected by top, slip scaffold is by billet (19), universal wheel (20), supporting beam (21), sub-truss (22), fixing bolt (23), operation platform billet (24) and girder truss (25), billet (19) are set to On pile formula reinforcement cushion on the outside of thin plate loose tool (14), universal wheel (20) is set to supporting beam (21) bottom, sub-truss (22) It is erected in supporting beam (21);It is fixed by fixing bolt (23) and girder truss (25) at the top of sub-truss (22), girder truss (25) operation platform billet (24) is set on.
The invention has the characteristics that and advantageous effect:
(1) the prefabricated pile cover of the invention using bottom belt is socketed anti-bias armlet and reinforces anti-detachment rib realization stake top and cover board High strong ties, it is ensured that Construction quality and safety is reliable.
(2) the invention steel sheet pile is linked as steel sheet pile module units by steel wale and shaped steel Guan Liang, and is linked as with support Support system enhances the stability of supporting construction, it is ensured that work progress safety.
(3) the sliding pouring construction of unit or merogenesis is realized box culvert construct by the way that slip scaffold is arranged in the invention, Construction efficiency is improved, construction speed is accelerated.
Description of the drawings
Fig. 1 overall structure diagrams
Fig. 2 thin plate loose tool structure charts
Fig. 3 operation platform billets overlap joint figure
In figure:1- pile for prestressed pipe;2- pile covers;3- reinforces anti-detachment rib;The anti-bias retaining walls of 4-;5- blotters;6- steel wires Barrier;7- cushion caps;8- steel sheet piles;9- shaped steel Guan Liangs;10- steel wales;11- high-strength bolts;12- band silk mandrils connecting pin;13- Support;14- thin plate fetal membranes;15- is fitted into rib;16- built-in fittings;17- inner side templates;18- outboard templates;19- billets;20- ten thousand To wheel;21- supporting beams;22- sub-trusses;23- fixing bolts;24- operation platform billets;25- girder trusses;26- is to straining beam; 27- cast-in-place concretes;28- corner connection sheets.
Specific implementation mode
Invention is further described in detail below in conjunction with the accompanying drawings and by embodiment, which is not limited to following Embodiment.
Fig. 1 is overall structure diagram, and Fig. 2 is thin plate loose tool structure chart, and Fig. 3 is operation platform billet overlap joint figure, ginseng According to shown in Fig. 1-3.
The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section, work progress are opened after using first precompressed Dig high roadbed deep soft foundation pile formula carrying system, the modular assembling Integral Steel sheet pile support system of regularization and based on fixed The porous cast-in-place box culvert construct technology of type Slidable template system big cross section.
The porous cast-in-place box culvert of big cross section uses band 2 pile for prestressed pipe 1 of pile cover using excavation construction after first precompressed, deep soft foundation Pile formula reinforcement cushion is formed with 6 blotter 5 of steel wire grid, prefabricated pile cover 2 is socketed anti-bias armlet 4 using bottom belt and reinforces Anti-detachment rib 3 realizes the high strong ties of stake top and cover board.
Steel sheet pile 8 is linked as steel sheet pile module units by steel wale 10 and shaped steel Guan Liang 9, is realized by high-strength bolt 11 Quickly bolt and dismounting, Guan Liang foundation pit side setting band silk mandril connecting pin 12, prop is collectively formed with support 13 in steel sheet pile 8 System.
For the regularization Slidable template system of the porous cast-in-place box culvert construct of big cross section, including it is thin plate loose tool 14, outer Side template 18, inner side template 17 and slip scaffold, thin plate loose tool 14 are equipped with for fixing outboard template 18 and interior side form The built-in fitting 16 of plate 17 is fixedly connected with straining beam 26 by top between outboard template 18, and slip scaffold is by billet 19, universal wheel 20, supporting beam 21, sub-truss 22, fixing bolt 23, operation platform billet 24 and girder truss 25, billet 19 are set on the pile formula reinforcement cushion in 14 outside of thin plate loose tool, and universal wheel 20 is set to 21 bottom of supporting beam, and sub-truss 22 is taken In supporting beam 21;22 top of sub-truss is fixed by fixing bolt 23 and girder truss 25, and facility work is flat on girder truss 25 Platform billet 24.
The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section, which is characterized in that including following step Suddenly:
Step 1 after excavation of foundation pit, sets the pile for prestressed pipe 1 with pile cover 2,2 bottom of pile cover is fixed by bolts anti-bias Armlet 4 and reinforce anti-detachment rib 3;
Step 2 is laid with bed course, construction bearing platform 7 on pile for prestressed pipe 1;
Step 3 is laid with steel wire grid 6 and blotter 5 on cushion cap 7, forms pile formula reinforcement cushion;
Step 4 excavates box culvert basis, steel sheet pile 8 of constructing on pile formula reinforcement cushion, shaped steel of constructing on steel sheet pile 8 Guan Liang 9 and steel wale 10 are fixed with high-strength bolt 11, and type steel support 13 of constructing between steel wale 10 carries out supporting;
Step 5, construction band is fitted into the thin plate loose tool 14 of rib 15, the corner of thin plate loose tool 14 on pile formula reinforcement cushion Junction setting corner connection sheet 28 is fixed;
The built-in fitting 16 for fixing outboard template 18 and inner side template 17 is arranged on thin plate loose tool 14, hangs for step 6 Outboard template 18 is filled to fixed position;Outboard template 18 and inner side template 17 use modular assembling regularization template.
Step 7 is laid with billet 19 on the pile formula reinforcement cushion in 14 outside of thin plate loose tool, installs supporting beam 21, hang On dress sub-truss 22 to supporting beam 21 and set up;
Step 8, the installation universal wheels 20 of supporting beam 21 times in 22 bottom of sub-truss, and by sub-truss 22 with universal Wheel is moved to designated position;
Step 9, erection construction platform billet 24, and be fixed using fixing bolt 23 with 22 top of sub-truss;
Step 10, truss hoisting beam 25 are weldingly fixed on to design position, and by its both sides on operation platform billet 24;
Step 11 will lift straining beam 26 and will be fixed by bolts to designated position, and with outboard template 18;
Then step 12, assembled inner side template 17 are hoisted to design position and fixation;
Step 13, inner side template 17 and outboard template 18 carry out casting concrete 27 by the slip scaffold set up Construction;
Step 14 after the completion of waiting for concrete curing, removes slip scaffold.

Claims (2)

1. the porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section, which is characterized in that include the following steps:
Step 1 after excavation of foundation pit, sets the pile for prestressed pipe (1) with pile cover (2), pile cover (2) bottom is fixed by bolts anti- It is partial to and side with arm (4) and reinforces anti-detachment rib (3);
Step 2 is laid with bed course, construction bearing platform (7) on pile for prestressed pipe (1);
Step 3 is laid with steel wire grid (6) and blotter (5), formation pile formula reinforcement cushion on cushion cap (7);
Step 4 excavates box culvert basis, steel sheet pile (8) of constructing on pile formula reinforcement cushion, shaped steel of constructing on steel sheet pile (8) Guan Liang (9) and steel wale (10), it is fixed with high-strength bolt (11), construct between steel wale (10) type steel support (13) into Row supporting;
Step 5, construction band is fitted into the thin plate loose tool (14) of rib (15) on pile formula reinforcement cushion, and thin plate loose tool (14) turns Angle junction setting corner connection sheet (28) is fixed;
The built-in fitting for fixing outboard template (18) and inner side template (17) is arranged in step 6 on thin plate loose tool (14) (16), outboard template (18) is lifted to fixed position;
Step 7, is laid with billet (19) on the pile formula reinforcement cushion on the outside of thin plate loose tool (14), installation supporting beam (21), On lifting sub-truss (22) to supporting beam (21) and set up;
Step 8 installs universal wheel (20) under the supporting beam (21) of sub-truss (22) bottom, and sub-truss (22) is used Universal wheel is moved to designated position;
Step 9, erection construction platform billet (24), and consolidated using fixing bolt (23) at the top of sub-truss (22) It is fixed;
Step 10, truss hoisting beam (25) are weldingly fixed on to design position, and by its both sides on operation platform billet (24);
Step 11 will lift straining beam (26) and will be fixed by bolts to designated position, and with outboard template (18);
Step 12, assembled inner side template (17), is then hoisted to design position and fixation;
Step 13, inner side template (17) and outboard template (18) carry out casting concrete by the slip scaffold set up (27) it constructs;
Step 14 after the completion of waiting for concrete curing, removes slip scaffold.
2. construction method according to claim 1, which is characterized in that outboard template (18) and inner side template (17) are using single First formula assembling regularization template.
CN201810228531.4A 2018-03-20 2018-03-20 Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert Active CN108277750B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810228531.4A CN108277750B (en) 2018-03-20 2018-03-20 Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810228531.4A CN108277750B (en) 2018-03-20 2018-03-20 Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert

Publications (2)

Publication Number Publication Date
CN108277750A true CN108277750A (en) 2018-07-13
CN108277750B CN108277750B (en) 2020-08-14

Family

ID=62809931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810228531.4A Active CN108277750B (en) 2018-03-20 2018-03-20 Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert

Country Status (1)

Country Link
CN (1) CN108277750B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777835A (en) * 2019-10-31 2020-02-11 安徽省路港工程有限责任公司 Construction method of steel pipe pile supporting pile foundation bearing platform formwork system
CN115418983A (en) * 2022-09-27 2022-12-02 中铁十四局集团有限公司 Construction method for prefabricated box culvert in highway-railway combined large-section shield tunnel
CN116122190A (en) * 2023-04-13 2023-05-16 山西建投建筑产业有限公司 Construction structure and construction process for assembled integral multi-cabin drainage box culvert

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203514315U (en) * 2013-08-06 2014-04-02 江苏翔森建设工程有限公司 Reinforced connecting structure between pile and pile cap
CN103821160A (en) * 2014-01-28 2014-05-28 中铁二院工程集团有限责任公司 Soft soil foundation combined pile net structure
CN105625202A (en) * 2016-03-18 2016-06-01 杭州江润科技有限公司 Construction method of large-cross-section, porous, super-long and cast-in-place box culvert
CN107268573A (en) * 2017-07-18 2017-10-20 深圳市工勘岩土集团有限公司 The composite construction of soft soil foundation
CN107542096A (en) * 2017-08-29 2018-01-05 中国建筑第八工程局有限公司 The supporting construction of dam body between a kind of Adjacent Pit

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203514315U (en) * 2013-08-06 2014-04-02 江苏翔森建设工程有限公司 Reinforced connecting structure between pile and pile cap
CN103821160A (en) * 2014-01-28 2014-05-28 中铁二院工程集团有限责任公司 Soft soil foundation combined pile net structure
CN105625202A (en) * 2016-03-18 2016-06-01 杭州江润科技有限公司 Construction method of large-cross-section, porous, super-long and cast-in-place box culvert
CN107268573A (en) * 2017-07-18 2017-10-20 深圳市工勘岩土集团有限公司 The composite construction of soft soil foundation
CN107542096A (en) * 2017-08-29 2018-01-05 中国建筑第八工程局有限公司 The supporting construction of dam body between a kind of Adjacent Pit

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777835A (en) * 2019-10-31 2020-02-11 安徽省路港工程有限责任公司 Construction method of steel pipe pile supporting pile foundation bearing platform formwork system
CN110777835B (en) * 2019-10-31 2021-04-27 安徽省路港工程有限责任公司 Construction method of steel pipe pile supporting pile foundation bearing platform formwork system
CN115418983A (en) * 2022-09-27 2022-12-02 中铁十四局集团有限公司 Construction method for prefabricated box culvert in highway-railway combined large-section shield tunnel
CN116122190A (en) * 2023-04-13 2023-05-16 山西建投建筑产业有限公司 Construction structure and construction process for assembled integral multi-cabin drainage box culvert

Also Published As

Publication number Publication date
CN108277750B (en) 2020-08-14

Similar Documents

Publication Publication Date Title
CN106223360B (en) Using the open cut cast in place and precast construction subway station construction method of stake supporting system
CN100441779C (en) Bridge construction method for air prefabrication and translation in place
CN108277750A (en) The porous cast-in-place box culvert construct method of high roadbed deep soft foundation pile formula big cross section
CN102031756A (en) Support assembly and construction method of cast-in-place box girder
CN108999097B (en) Modification structure and construction method of existing bridge abutment in bridge jacking
CN107476337A (en) The prefabricated side wall assembling and construction method in open cut subway assembled station
CN108396630A (en) The big box-beam structure of precast concrete with the connection of wet seam direction across bridge
CN112942147A (en) Bridge pile active underpinning method
CN107100083A (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method
CN104532754A (en) Prestress concrete box girder end sealing formwork construction method
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN110439000B (en) Underground structure internal transportation system based on plate lower sliding chute and construction method
CN111719436A (en) Construction system and construction method for urban railway cast-in-place box girder support in soft foundation area
CN111236089A (en) Uneven jacking system and uneven jacking construction method for existing bridge superstructure
CN110820519A (en) Tunnel arch bridge convenient for rapid construction and construction method thereof
CN111254843A (en) Bridge pile foundation uplifting structure and construction method thereof
CN108999427B (en) Support structure for moving load during building migration in place and construction method thereof
CN107988921A (en) Single-point continuous pushing construction method for overpass bridge over railway and highway
CN211872669U (en) Uneven jacking system of current bridge superstructure
CN108487072B (en) Across Business Line railway cast-in-place frame bridge rapid constructing method in one kind
CN102691267A (en) High pier construction method for external whole operation platform
CN210737607U (en) A hang braced system for reverse construction method beam slab construction
CN209779640U (en) foundation pit supporting pile top crown beam construction structure
CN108360685B (en) Monoblock type jack-up construction method
CN115748483A (en) Pile-pier-beam integrated bridge fabrication machine construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant