CN108266004A - A kind of drawer type walking construction shed and its construction method - Google Patents

A kind of drawer type walking construction shed and its construction method Download PDF

Info

Publication number
CN108266004A
CN108266004A CN201810053766.4A CN201810053766A CN108266004A CN 108266004 A CN108266004 A CN 108266004A CN 201810053766 A CN201810053766 A CN 201810053766A CN 108266004 A CN108266004 A CN 108266004A
Authority
CN
China
Prior art keywords
construction
canopy
area
drawer type
shed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810053766.4A
Other languages
Chinese (zh)
Other versions
CN108266004B (en
Inventor
谢燕青
张铭
孔德志
黄轶
徐亭
曹喜华
褚伟青
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN201810053766.4A priority Critical patent/CN108266004B/en
Publication of CN108266004A publication Critical patent/CN108266004A/en
Application granted granted Critical
Publication of CN108266004B publication Critical patent/CN108266004B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/1205Small buildings erected in the open air
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34336Structures movable as a whole, e.g. mobile home structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/28Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Tents Or Canopies (AREA)

Abstract

The invention discloses a kind of drawer type walking construction shed and its construction methods, the construction shed includes the Nei Peng for being located at strip construction area width direction both sides and outer canopy, Nei Peng can be moved with outer canopy respectively along the length direction of strip construction area, interior canopy is set to the inside composition drawer type composite construction of outer canopy, the inside upper part of Nei Peng and outer canopy is respectively equipped with can be along the driving of the axial movement of interior canopy or outer canopy, and the driving of the outer canopy is located at the top of the interior canopy.Nei Peng and outer canopy form a drawer type composite construction, Nei Peng and outer canopy can be moved forward successively, close region to be onstructed, ensure that enclosed environment can be with the movement carried out to carry out position of construction, it constructs suitable for long line, had not only kept the green construction superiority of construction shed, but also can guarantee that enclosed environment can be with the movement carried out to carry out position of construction, and the use coverage rate of the raising construction shed of maximum possible, achieve the purpose that make green all standing along subway work.

Description

A kind of drawer type walking construction shed and its construction method
Technical field
The invention belongs to subway work technical field more particularly to a kind of drawer type walking construction shed and its construction methods.
Background technology
Now, construction shed dust control and noise absorption is in foreign countries using widely, and especially in Japan and other countries, construction shed is not only It is used in during the underground constructions such as subway station, it is also relatively common in Superstructure Construction.Project makes more during building Seal treatment is carried out to foundation pit or building body with light steel frame and canvas closed net, has achieved the purpose that civilized green construction. At home underground space construction especially constructing metro tunnel when also begin to attempt to construct using the mode of closure construction canopy Scene with surrounding enviroment completely cut off, to avoid brought in underground construction especially earth excavation and concrete construction dirt, sound, Light pollution.
But most domestic closure construction canopy there is no and construction form connected effect, be merely possible to a kind of construction Additional stability maintenance device, is disagreed with the original intention of green construction.It is green as society is higher and higher to the requirement for building civilized construction The breakthrough of construction new model is sought by comprehensive deeply universal and unit in charge of construction itself of color job specfication, and closure construction canopy is the general trend of events Become.And subway is due to the particularity of its full underground construction, construction shed can play its maximum function.And, it would be highly desirable to one kind can fit Answer subway strip, long linear building feature construction shed.
Invention content
The purpose of the present invention is to provide a kind of drawer type walking construction shed and its construction methods, have both kept the green of construction shed Color constructs superiority, and can guarantee that enclosed environment can be with the movement carried out to carry out position of construction, and maximum possible carries The use coverage rate of high construction shed achievees the purpose that make green all standing along subway work.
In order to solve the above technical problems, the present invention provides following technical solution:
A kind of drawer type is walked construction shed, including be located at the Nei Peng of strip construction area width direction both sides with it is outer Canopy, the Nei Peng can be moved with outer canopy respectively along the length direction of strip construction area, and the interior canopy is set to described The inside composition drawer type composite construction of outer canopy, the inside upper part of the interior canopy and the outer canopy be respectively equipped with can along interior canopy or The driving of the axial movement of the outer canopy of person, the driving of the outer canopy are located at the top of the interior canopy.
Preferably, in above-mentioned drawer type walking construction shed, two side bottoms of the Nei Peng and outer canopy are respectively arranged in On respective ground rail, the Nei Peng is able to move along respective ground rail with outer canopy, the Nei Peng and outer canopy It is respectively equipped with the guide wheel to match with corresponding ground rail, the corresponding ground rail of the interior canopy is located at strip construction area The both sides of width direction, the corresponding ground rail of the outer canopy are located at the outside of the corresponding ground rail of the interior canopy.
Preferably, in above-mentioned drawer type walking construction shed, the Nei Peng and the upper inside of the both sides of outer canopy are distinguished Equipped with Crane Rail, the both ends of the driving are respectively arranged on corresponding Crane Rail and can be along corresponding Crane Rails Mobile, the both ends of the driving are respectively equipped with the guide wheel to match with corresponding Crane Rail.
Preferably, in above-mentioned drawer type walking construction shed, the Nei Peng includes several doors being connected with outer canopy Formula steelframe and the top roof truss being set to above portal frame, top roof truss weld assembled truss, door using round steel Formula steelframe includes the lateral column braces at the top of two root posts and connection two root posts, and the correspondence column of adjacent portal frame leads to Cross longitudinal column braces connection.
Preferably, in above-mentioned drawer type walking construction shed, the outer canopy uses modularization making, and type of attachment is adopted It is connected with high-strength bolt, convenient for dismounting and mounting dress, transport and recycling, the outer canopy of required length can be formed.It is likewise, described Interior canopy uses modularization making, and type of attachment is connected using high-strength bolt, can convenient for dismounting and mounting dress, transport and recycling With canopy in length needed for formation.
Preferably, in above-mentioned drawer type walking construction shed, bracket, ox are equipped on the inside of the Nei Peng and the column of outer canopy The length direction of leg upper edge strip construction area is equipped with Crane Rail, and the both ends of the driving are respectively arranged in corresponding driving It can move on track and along corresponding Crane Rail, the both ends of the driving are respectively equipped with and corresponding Crane Rail phase The guide wheel matched.
Preferably, in above-mentioned drawer type walking construction shed, if strip construction area one is divided into along its length Dry area, is followed successively by 1st area to N areas, and N is natural number, and the length of the interior canopy is 1.2-1.6 times of the length in each area, described outer The length of canopy is 2.2-2.6 times of the length in each area, and the whole maximum coverage range of the Nei Peng and outer canopy are more than 4 Area.
The invention also discloses a kind of construction methods of drawer type walking construction shed as described above, include the following steps:
Step 1, strip construction area is divided into several areas along its length, is followed successively by 1st area to N areas, wherein N is nature Number installs drawer type walking construction shed so that outer canopy covers 1st area, 2nd area, and it is whole that interior canopy covers 2nd area on strip construction area With the part in 1st area, in set the driving of canopy and the driving of outer canopy preferentially construct 1st area;
Step 2, the construction of 1st area is treated to certain phase, and when 2nd area start construction, interior canopy is protruding so that interior canopy covers 3rd area, Continue construct 1st area and 2nd area;
Step 3, treat that certain phase, interior canopy is stretched out to greatest extent for the construction of 2nd area so that interior canopy covers 4th area, so as to 3rd area are able to start closed operation;
Step 4, after the completion of 1st area for most starting construction, outer canopy is moved towards Nei Peng directions so that Nei Peng and outer canopy 2nd area and 3rd area that driving transport power is constructed after concentrating on;
Step 5, it as above rolls and constructs forward, interior canopy preferentially forward extends out, and covers new subregion and new subregion is opened Beginning closed operation, and outer canopy can also follow the movement of interior canopy to collapse after constructing in the region that it is covered so that interior canopy can be after It is continuous to stretch out, until the construction of entire strip construction area finishes.
Preferably, in the construction method of above-mentioned drawer type walking construction shed, in step 1, in strip construction area The step of drawer type walking construction shed is installed on domain, including:
Step 11, first construction ground track;
Step 12, first canopy installs outer canopy again in installation;
Step 13, bracket is welded on inside and outside canopy column, after Crane Rail is layed on bracket, is installed on Crane Rail Driving;
Step 14, the metope affiliated facility of rolling screen door and inside and outside canopy is installed.
Preferably, in the construction method of above-mentioned drawer type walking construction shed, in step 1, after step 5, also Including:All after construction, first manipulation construction shed is stopped locked on ground rail, will driving, rolling screen door and inside and outside canopy Metope affiliated facility removed, outer canopy is first then torn open, then tear interior canopy open using top-down dismounting mode.
By techniques disclosed above scheme it is found that compared with prior art, beneficial effects of the present invention are as follows:
(1) drawer type walking construction shed provided by the invention, can ensure closure construction, solve what is generated in work progress The pollution such as sound, light, dirt leads to the problem of surrounding enviroment baneful influence, while the environment closed can prevent the poles such as rain, snow, wind Hold influence of the bad weather to construction, it is also ensured that the duration to carry on construction work at night shortens the construction period to greatest extent.
(2) drawer type walking construction shed provided by the invention, an original construction shed is changed into two construction sheds:It is interior Canopy and outer canopy, Nei Peng and outer canopy form a drawer type composite construction, and Nei Peng and outer canopy are moved forward, closed to be onstructed successively Region can guarantee that enclosed environment with construction can be more applicable for long line carrying out the movement of position and construct;Interior canopy and Working driving is carried on outer canopy respectively, the driving of the outer canopy is located at the top of the interior canopy, can between driving It runs simultaneously, so as to accelerate construction progress;The Nei Peng can be respectively along the length of strip construction area with outer canopy Direction is moved, and can not be moved to another construction bid section from a construction bid section by dismantling the form installed again, not only be saved A large amount of time and expense have been saved, can more keep up with allegro subway work, has expanded the applicable model of construction shed to greatest extent It encloses and using coverage rate.
(3) construction method of drawer type walking construction shed provided by the invention, first, two rows of set Nei Peng and outer canopy First construction bid section i.e. 1st area of the preferential construction of the capacity of vehicle;Since Nei Peng and outer canopy form a drawer type composite construction and interior Canopy and outer canopy can move freely, and interior canopy preferentially forward extends out, and cover new subregion and new subregion is enabled to start closed operation, And outer canopy can also follow interior canopy movement to collapse after constructing in the region that it is covered so that interior canopy can continue to stretch out, until Entire strip construction area construction finishes, and the mode for the cross construction that as above stretches is more suitable for strip foundation pit construction;And not It needs that another construction bid section can be moved to from a construction bid section by dismantling the form installed again, not only saves big The time of amount and expense, can more keep up with allegro subway work, have expanded the scope of application of construction shed to greatest extent and have made Use coverage rate.
Description of the drawings
Fig. 1 is the facade structures schematic diagram of the drawer type walking construction shed of one embodiment of the invention.
Fig. 2 is the planar structure schematic diagram of the drawer type walking construction shed of one embodiment of the invention.
Fig. 3~Fig. 6 is the construction process figure of drawer type walking construction shed in one embodiment of the invention.
In figure:1. outer canopy;Canopy in 2.;3. ground rail;4. driving;5. bracket;6. Crane Rail;7. foundation pit;8. roller shutter Door.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and right Claim, advantages and features of the invention will become apparent from.To this hair be described in detail by cited embodiment combination attached drawing below Bright technology contents and feature.Need in addition it illustrate, attached drawing uses very simplified form and uses non-accurate ratio Example, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.For sake of convenience, described below " on ", " under " the upper and lower direction with attached drawing is consistent, but this can't be the limitation of technical solution of the present invention.
It please refers to Fig.1 to Fig. 6, present embodiment discloses a kind of drawer type walking construction sheds, are applied including being located at strip The interior canopy 2 of work peak width direction both sides and outer canopy 1, the interior canopy 2 can be respectively along strip construction areas with outer canopy 1 Length direction moves, and the interior canopy 2 is set to the inside composition drawer type composite construction of the outer canopy 1, the interior canopy 2 and described The inside upper part of outer canopy 1 be respectively equipped with can along the driving 4 of the axial movement of interior canopy 2 or outer canopy 1, the outer canopy 1 it is described Driving 4 is located at the top of the interior canopy 2.
The present invention changes its structural system on the basis of traditional construction canopy, and an original construction shed is changed into two A construction shed:Interior canopy 2 and outer canopy 1, interior canopy 2 and outer canopy 1 form a drawer type composite construction, are more applicable for long line construction; Working driving 4 is carried on interior canopy 2 and outer canopy 1 respectively, the driving 4 of the outer canopy 1 is located at the top of the interior canopy 2, It can put into operation simultaneously between driving 4, so as to accelerate construction progress;The interior canopy 2 can be respectively along length with outer canopy 1 The length direction movement of strip construction area can not be moved to by dismantling the form installed again from a construction bid section another A construction bid section, not only saves a large amount of time and expense, can more keep up with allegro subway work, expand to greatest extent The scope of application of construction shed and use coverage rate.In addition, drawer type walking construction shed can ensure closure construction, construction is solved The pollution such as sound, light, dirt for generating in the process leads to the problem of baneful influence to surrounding enviroment;The environment of closing can prevent rain, Influence of the exceedingly odious weather such as snow, wind to construction, it is also ensured that the duration to carry on construction work at night shortens work to greatest extent Phase.
In order to enable the interior canopy 2 can be moved with outer canopy 1 respectively along the length direction of strip construction area, preferably , in above-mentioned drawer type walking construction shed, two side bottoms of the interior canopy 2 and outer canopy 1 are respectively arranged in respective ground On track 3, the interior canopy 2 is able to move along respective ground rail 3 with outer canopy 1, and the interior canopy 2 is distinguished with outer canopy 1 Equipped with the guide wheel to match with corresponding ground rail 3, the interior 2 corresponding ground rail 3 of canopy is located at strip construction area The both sides of width direction, the outer 1 corresponding ground rail 3 of canopy are located at the outside of the interior 2 corresponding ground rail 3 of canopy.
Preferably, in above-mentioned drawer type walking construction shed, the interior canopy 2 and the upper inside point of the both sides of outer canopy 1 Not She You Crane Rail 6, the both ends of the driving 4 are respectively arranged on corresponding Crane Rail 6 and can be along corresponding row Track road 6 moves, and the both ends of the driving 4 are respectively equipped with the guide wheel to match with corresponding Crane Rail 6.Crane Rail 6, no But driving 4 can be supported, and the movement for driving 4 provides guiding.Driving is respectively provided on the interior canopy 2 and outer canopy 1 The guide wheel driving mechanism of guide wheel.
Preferably, in above-mentioned drawer type walking construction shed, the interior canopy 2 and outer canopy 1 are connected including several Portal frame and the top roof truss being set to above portal frame, top roof truss weld assembled truss using round steel, Portal frame includes the lateral column braces at the top of two root posts and connection two root posts, the correspondence column of adjacent portal frame It is connected by longitudinal column braces.The column uses H profile steel or round steel, and lateral column braces and lateral column braces are using circle Steel.
Preferably, in above-mentioned drawer type walking construction shed, the outer canopy 1 uses modularization making, and type of attachment is equal It is connected using high-strength bolt, convenient for dismounting and mounting dress, transport and recycling, the outer canopy 1 of required length can be formed.Likewise, The interior canopy 2 uses modularization making, and type of attachment is connected using high-strength bolt, makes convenient for dismounting and mounting dress, transport and cycle With, can be formed needed for length interior canopy 2.
In order to which Crane Rail 6 and driving 4 is given to provide stable support, it is preferred that in above-mentioned drawer type walking construction shed In, bracket 5 is equipped on the inside of the interior canopy 2 and the column of outer canopy 1, the length direction of 5 upper edge strip construction area of bracket is equipped with Crane Rail 6, the both ends of the driving 4 are respectively arranged on corresponding Crane Rail 6 and can be along corresponding Crane Rails 6 It is mobile.
Preferably, in above-mentioned drawer type walking construction shed, if strip construction area one is divided into along its length Dry area i.e. construction bid section, is followed successively by 1st area to N areas, N is natural number, and the length of the interior canopy 2 is the 1.2- of the length in each area 1.6 times, the length of the outer canopy 1 is 2.2-2.6 times of the length in each area, and the whole maximum of the interior canopy 2 and outer canopy 1 is covered Lid range is more than 4 areas.Above-mentioned design can both enable two drivings 4 to construct simultaneously same area, can also construct respectively Different areas so as to improve the utilization rate of driving 4, significantly improves construction efficiency, reduces the duration.
Preferably, in above-mentioned drawer type walking construction shed, the both ends of the interior canopy 2 and outer canopy 1 are respectively equipped with for people The rolling screen door 8 of member's goods and materials disengaging.
Please continue to refer to Fig. 1 to Fig. 6, the construction method of drawer type walking construction shed as described above includes the following steps:
Step 1, strip construction area is divided into several areas along its length to construct bid section, is followed successively by 1st area to N areas, Wherein N is natural number, drawer type walking construction shed is installed on strip construction area so that outer canopy 1 covers 1st area, 2nd area, interior Canopy 2 covers that 2nd area are whole and the part in 1st area, preferential 1st area of construction of the driving 4 of canopy 2 and the driving 4 of outer canopy 1 in set;
Step 2, the construction of 1st area is treated to certain phase, when 2nd area start construction, interior canopy 2 is protruding so that the interior covering of canopy 23 Area continues construct 1st area and 2nd area;
Step 3, treat that certain phase, interior canopy 2 is stretched out to greatest extent for the construction of 2nd area so that interior canopy 2 covers 4th area, from And 3rd area are able to start closed operation;
Step 4, most start construction 1st area after the completion of, outer canopy 1 move towards interior 2 direction of canopy so that interior canopy 2 and outside 2nd area and 3rd area that 4 transport power of driving of canopy 1 is constructed after concentrating on;
Step 5, it as above rolls and constructs forward, interior canopy 2 preferentially forward extends out, and covers new subregion and new subregion is opened Beginning closed operation, and outer canopy 1 can also follow the interior movement of canopy 2 to collapse after constructing in the region that it is covered so that interior canopy 2 can Continue to stretch out, until the construction of entire strip construction area finishes.
First construction bid section i.e. 1 of the preferential construction of capacity that the present invention passes through two drivings 4 of canopy in set 2 and outer canopy 1 Area;Since interior canopy 2 and outer canopy 1 form a drawer type composite construction and interior canopy 2 and outer canopy 1 can move freely, interior canopy 2 can be with It preferentially forward extends out, covers new subregion and new subregion is enabled to start closed operation, and outer canopy 1 is constructed in the region that it is covered After the movement of interior canopy 2 can also be followed to collapse so that interior canopy 2 can continue to stretch out, until entire strip construction area is constructed It finishes, the mode for the cross construction that as above stretches is more suitable for strip foundation pit 7 and constructs;And it does not need to by dismantling the shape installed again Formula can be moved to another construction bid section from a construction bid section, not only save a large amount of time and expense, more can be with Upper allegro subway work, has expanded the scope of application of construction shed and using coverage rate to greatest extent.
Preferably, in the construction method of above-mentioned drawer type walking construction shed, in step 1, in strip construction area The step of drawer type walking construction shed is installed on domain, including:
Step 11, first construction ground track 3.
Step 12, first canopy 2 installs outer canopy 1 again in installation.
Step 13, bracket 5 is welded on 1 column of inside and outside canopy, after Crane Rail 6 is layed on bracket 5, in Crane Rail 6 Upper installation driving 4,4 included drive systems of driving a vehicle.
Step 14, the metope affiliated facility of rolling screen door 8 and inside and outside canopy 1 is installed.
After installation is complete, before construction usage, preparation of construction work is carried out, to carry out full side to drawer type walking construction shed The inspection debugging of position.The preparation of construction work includes the following contents:
To the deviation of guide rail and guide wheel, the levelness of guide rail, the spacing of two closed slides carries out repetition measurement;
Differential settlement mark is done on column, convenient for later long-term reinspection differential settlement;
In the case where interior canopy 2 and outer canopy 1 are static, experiment 4 performances of driving.
It is required for carrying out more than preparation of construction work later it should be noted that installing or moving to finish each time Make, to ensure the available and security performance of construction shed.
Preferably, in the construction method of above-mentioned drawer type walking construction shed, in step 1, after step 5, also Including:On strip construction area dismantle drawer type walking construction shed the step of, that is, step 6, all construction after, first grasp Control construction shed is stopped on ground rail 3 it is locked, by driving 4, rolling screen door 8 and interior canopy 2, outer canopy 1 metope affiliated facility into Row is removed, and then first tears outer canopy 1 open, then tear interior canopy 2 open using top-down dismounting mode.Also drawer type walking construction shed is just said Disassembly and installation sequence is opposite.
In conclusion the present invention can keep the green construction superiority of construction shed and enclosed environment can be with The movement carried out to carry out position of construction, and the use coverage rate of the raising construction shed of maximum possible, reaching makes subway work The purpose of green all standing along the line.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (10)

  1. The construction shed 1. a kind of drawer type is walked, which is characterized in that including being located at strip construction area width direction both sides Nei Peng and outer canopy, the Nei Peng can be moved with outer canopy respectively along the length direction of strip construction area, and the interior canopy is set The inside composition drawer type composite construction of the outer canopy is placed in, the inside upper part of the interior canopy and the outer canopy is respectively equipped with can Along the driving of the axial movement of interior canopy or outer canopy, the driving of the outer canopy is located at the top of the interior canopy.
  2. The construction shed 2. drawer type as described in claim 1 is walked, which is characterized in that two side bottoms point of the Nei Peng and outer canopy It is not installed on respective ground rail, the Nei Peng is able to move along respective ground rail with outer canopy, described interior Canopy and outer canopy are respectively equipped with the guide wheel to match with corresponding ground rail, and the corresponding ground rail of the interior canopy is located at strip The both sides of construction area width direction, the corresponding ground rail of the outer canopy are located at the outer of the corresponding ground rail of the interior canopy Side.
  3. The construction shed 3. drawer type as described in claim 1 is walked, which is characterized in that the Nei Peng and the inside of the both sides of outer canopy Upside is respectively equipped with Crane Rail, and the both ends of the driving are respectively arranged on corresponding Crane Rail and can be along corresponding Crane Rail moves.
  4. The construction shed 4. drawer type as described in claim 1 is walked, which is characterized in that the Nei Peng includes several phases with outer canopy The portal frame of connection and the top roof truss being set to above portal frame, top roof truss are welded assembled using round steel Truss, portal frame include the lateral column braces at the top of two root posts and connection two root posts, pair of adjacent portal frame Column is answered to be connected by longitudinal column braces.
  5. The construction shed 5. drawer type as claimed in claim 4 is walked, which is characterized in that the outer canopy uses modularization making, even It connects form to connect using high-strength bolt, convenient for dismounting and mounting dress, transport and recycling.
  6. The construction shed 6. drawer type as claimed in claim 4 is walked, which is characterized in that set on the inside of the Nei Peng and the column of outer canopy There is bracket, the length direction of bracket upper edge strip construction area is equipped with Crane Rail, and the both ends of the driving are respectively arranged in It can move on corresponding Crane Rail and along corresponding Crane Rail, the both ends of the driving are respectively equipped with and corresponding row The guide wheel that track road matches.
  7. The construction shed 7. drawer type as described in claim 1 is walked, which is characterized in that by strip construction area one along length side To several areas are divided into, 1st area is followed successively by N areas, and N is natural number, and the length of the interior canopy is the 1.2-1.6 of the length in each area Times, the length of the outer canopy is 2.2-2.6 times of the length in each area, and the whole maximum coverage range of the Nei Peng and outer canopy More than 4 areas.
  8. 8. a kind of construction method of the drawer type walking construction shed in 1-7 such as claim as described in any one, which is characterized in that Include the following steps:
    Step 1, strip construction area being divided into several areas along its length, is followed successively by 1st area to N areas, wherein N is natural number, Drawer type walking construction shed is installed on strip construction area so that outer canopy covers 1st area, 2nd area, and interior canopy covers 2nd area entirety and 1 The part in area, in set the driving of canopy and the driving of outer canopy preferentially construct 1st area;
    Step 2, the construction of 1st area is treated to certain phase, when 2nd area start construction, interior canopy is protruding so that interior canopy covers 3rd area, continues Construct 1st area and 2nd area;
    Step 3, treat that certain phase, interior canopy is stretched out to greatest extent for the construction of 2nd area so that interior canopy covers 4th area, so as to 3rd area It is able to start closed operation;
    Step 4, after the completion of 1st area for most starting construction, outer canopy is moved towards Nei Peng directions so that the driving of Nei Peng and outer canopy 2nd area and 3rd area that transport power is constructed after concentrating on;
    Step 5, it as above rolls and constructs forward, interior canopy preferentially forward extends out, and covers new subregion and new subregion is enabled to start to seal Operation is closed, and outer canopy can also follow interior canopy movement to collapse after constructing in the region that it is covered so that interior canopy can continue to stretch Go out, until the construction of entire strip construction area finishes.
  9. 9. the construction method of drawer type walking construction shed as claimed in claim 8, which is characterized in that in step 1, in strip The step of drawer type walking construction shed is installed on shape construction area, including:
    Step 11, first construction ground track;
    Step 12, first canopy installs outer canopy again in installation;
    Step 13, bracket is welded on inside and outside canopy column, and after Crane Rail is layed on bracket, row is installed on Crane Rail Vehicle;
    Step 14, the metope affiliated facility of rolling screen door and inside and outside canopy is installed.
  10. 10. the construction method of drawer type walking construction shed as claimed in claim 8, which is characterized in that after step 5, also Including:All after construction, first manipulation construction shed is stopped locked on ground rail, will driving, rolling screen door and inside and outside canopy Metope affiliated facility removed, outer canopy is first then torn open, then tear interior canopy open using top-down dismounting mode.
CN201810053766.4A 2018-01-19 2018-01-19 Drawer type walking construction shed and construction method thereof Active CN108266004B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810053766.4A CN108266004B (en) 2018-01-19 2018-01-19 Drawer type walking construction shed and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810053766.4A CN108266004B (en) 2018-01-19 2018-01-19 Drawer type walking construction shed and construction method thereof

Publications (2)

Publication Number Publication Date
CN108266004A true CN108266004A (en) 2018-07-10
CN108266004B CN108266004B (en) 2023-10-31

Family

ID=62776085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810053766.4A Active CN108266004B (en) 2018-01-19 2018-01-19 Drawer type walking construction shed and construction method thereof

Country Status (1)

Country Link
CN (1) CN108266004B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108824121A (en) * 2018-07-20 2018-11-16 四川瑞通工程建设集团有限公司 A kind of rainy day asphalt pavement construction method
CN113775207A (en) * 2021-09-22 2021-12-10 张国锋 Temporary door type passage design and construction method for building

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202347442U (en) * 2011-12-02 2012-07-25 中铁七局集团郑州工程有限公司 Protective shed for precast beam reinforcement cage binding operation
US20120266929A1 (en) * 2011-04-25 2012-10-25 Johnson Outdoors Inc. Insulated liner and tent having insulated liner
CN205713167U (en) * 2016-06-15 2016-11-23 中国电建集团铁路建设有限公司 A kind of packaged type rain shade for main structure of subway station construction
CN205777634U (en) * 2016-06-29 2016-12-07 郑州市第一建筑工程集团有限公司 Telescopic moving formula protection canopy
CN207847164U (en) * 2018-01-19 2018-09-11 上海建工四建集团有限公司 A kind of drawer type walking construction shed

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120266929A1 (en) * 2011-04-25 2012-10-25 Johnson Outdoors Inc. Insulated liner and tent having insulated liner
CN202347442U (en) * 2011-12-02 2012-07-25 中铁七局集团郑州工程有限公司 Protective shed for precast beam reinforcement cage binding operation
CN205713167U (en) * 2016-06-15 2016-11-23 中国电建集团铁路建设有限公司 A kind of packaged type rain shade for main structure of subway station construction
CN205777634U (en) * 2016-06-29 2016-12-07 郑州市第一建筑工程集团有限公司 Telescopic moving formula protection canopy
CN207847164U (en) * 2018-01-19 2018-09-11 上海建工四建集团有限公司 A kind of drawer type walking construction shed

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108824121A (en) * 2018-07-20 2018-11-16 四川瑞通工程建设集团有限公司 A kind of rainy day asphalt pavement construction method
CN113775207A (en) * 2021-09-22 2021-12-10 张国锋 Temporary door type passage design and construction method for building
CN113775207B (en) * 2021-09-22 2022-09-23 张国锋 Temporary door type passage design and construction method for building

Also Published As

Publication number Publication date
CN108266004B (en) 2023-10-31

Similar Documents

Publication Publication Date Title
CN109025388B (en) Construction device and construction method of movable expanded openable canopy
CN102383712B (en) Built-in sunshade hollow glass product
CN103422570B (en) Open-close type hut product
CN207847164U (en) A kind of drawer type walking construction shed
JPH11513761A (en) Cable-supported opening / closing daylighting roof for stadium, arena and other structures, and method of constructing the same
CN108266004A (en) A kind of drawer type walking construction shed and its construction method
CN107178226A (en) The whole self-propelled totally-enclosed green construction enclosing of formula and its construction method
CN203701601U (en) Building maintenance shed
CN209585718U (en) A kind of multi-functional foundation pit protection canopy
CN206917351U (en) The whole self-propelled totally-enclosed green construction enclosing of formula
CN106567552A (en) Dynamic closed construction method of subway station using fast folding shelters
CN205891817U (en) Building rubbish pond device that all steel system is closed and ceiling can open and shut
CN104060860A (en) Sectional telescopic rainproof shed and application method for prefabricating concrete T beam
CN210147306U (en) Foldable movable windproof cover for welding penstock
CN107060410A (en) A kind of Full-automatic folding garage
CN208897847U (en) One kind pushing and pulling closed atomizing refuse depot entirely
CN106437000A (en) Turnover sliding combined type roofing structure capable of being opened and closed
CN202899384U (en) Suspended roof structural system for slide construction and opening and closing
CN207211786U (en) Portable suitable for metro station construction covers canopy
CN206900371U (en) Rail traffic platform door pillar combines and the platform door system using column combination
CN103437287B (en) Be applied to the whole opening box girder section assembling method of bridge construction
CN206273957U (en) The fast folding for being capable of achieving the construction of subway station Dynamic Closed covers canopy group
CN207228069U (en) Rectangle aqueduct construction telescoping steel form
CN206733273U (en) Movable folding type steam curing cover
CN108910369A (en) One kind pushing and pulling closed atomizing refuse depot and its construction method entirely

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant