CN108252217A - A kind of special constructing device of bridge - Google Patents

A kind of special constructing device of bridge Download PDF

Info

Publication number
CN108252217A
CN108252217A CN201710393419.1A CN201710393419A CN108252217A CN 108252217 A CN108252217 A CN 108252217A CN 201710393419 A CN201710393419 A CN 201710393419A CN 108252217 A CN108252217 A CN 108252217A
Authority
CN
China
Prior art keywords
slippage slot
slot
bar
sliding
tight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710393419.1A
Other languages
Chinese (zh)
Inventor
陈光才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Lin Ji Electromechanical Technology Co Ltd
Original Assignee
Foshan Lin Ji Electromechanical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Lin Ji Electromechanical Technology Co Ltd filed Critical Foshan Lin Ji Electromechanical Technology Co Ltd
Priority to CN201710393419.1A priority Critical patent/CN108252217A/en
Publication of CN108252217A publication Critical patent/CN108252217A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The invention discloses a kind of special constructing devices of bridge, including pedestal, pedestal upper side is equipped with clamping device and the sliding dispatching device for being arranged on clamping device front and rear sides and being correspondingly arranged, pedestal between clamping device and rear side sliding dispatching device is equipped with frame, the first slippage slot and the second slippage slot that left and right is correspondingly arranged are equipped in each sliding dispatching device, plate is equipped between first slippage slot and the second slippage slot, supporting member is equipped in first slippage slot and the second slippage slot, the supporting member of the left and right sides is internally provided with the tapered wheel being oppositely arranged, with being connected in the pedestal of clamping device bottom equipped with the first slid chamber in clamping device, first slid chamber is internally provided with sliding component, the left and right sides is correspondingly provided with elongated slot at the top of clamping device, sliding component is internally provided with the second slid chamber;The configuration of the present invention is simple, it is easy to operate, improve jewel hole accuracy and stability.

Description

A kind of special constructing device of bridge
Technical field
The present invention relates to bridge technology field, specifically a kind of special constructing device of bridge.
Background technology
Adaptation to local conditions is needed during bridge construction, according to scene actual conditions by construction material be processed again into One step uses.Tubing jewel hole is one of frequently problem in bridge construction, and since construction environment is mixed and disorderly, tubing is consolidated Fixed particularly significant, it is askew that fixed shakiness can bore eyelet.Presently mainly people's Manual press is fixed, and stability is poor, partly certainly The machine volume of dynamic jewel hole is larger, and it is inconvenient to carry, and typically single head is fixed, and jewel hole is inevitable in the process or can shake Dynamic, in addition traditional to beat drill configuration single, it is impossible to voluntarily be adjusted according to tubing specification.
Invention content
The technical problems to be solved by the invention are to provide a kind of special constructing device of bridge, can solve above-mentioned present The problems in technology.
The present invention is achieved through the following technical solutions:The special constructing device of a kind of bridge of the present invention, including seat Body, the pedestal upper side are equipped with clamping device and are arranged on the clamping device front and rear sides and the sliding tune being correspondingly arranged Device is spent, the pedestal between the clamping device and the rear side sliding dispatching device is equipped with frame, each cunning It moves in dispatching device and is equipped with left and right the first slippage slot and the second slippage slot that are correspondingly arranged, first slippage slot and described the Plate is equipped between two slippage slots, supporting member is equipped in first slippage slot and second slippage slot, the left and right sides The supporting member is internally provided with the tapered wheel being oppositely arranged, the interior pedestal with the clamping device bottom of the clamping device It is inside connected equipped with the first slid chamber, first slid chamber is internally provided with sliding component, the clamping device top left and right sides Elongated slot is correspondingly provided with, the sliding component is internally provided with the second slid chamber, and the second slid chamber rear wall, which is internally provided with, leads shifting slot, Described lead moves the tight lock spiral bar that slot is internally provided with the setting that stretches up and down, and the tight lock spiral bar, which is equipped with, leads shifting block, described to lead Second slid chamber moved above slot is internally provided with front and back end and is propped up with what inner wall before and after second slid chamber was fixedly connected Block, the block left side of propping up slide with the second slid chamber inner left wall and the block right side of propping up with described second It is equipped between inner wall on the right side of chamber and leads shifting bar, it is each described to lead the tight lock for moving and being slid on bar and being connected with the setting that stretches up and down Bar, the section that stretches at the top of the tight locking bar are reached by elongated slot outside the upper side of the clamping device, each the tight locking bar bottom Stretch tip and it is described lead move before block between hinge be connected with catch bar, the first slid chamber inner bottom wall is equipped with top The first air pressure pushing meanss that portion is fixedly connected with the sliding component bottom faces, the pedestal bottom are provided with wheel chamber, the wheel Intracavitary operating is connected with traveling wheel, and there are four the traveling wheel settings, and enclosure device is provided at the top of the pedestal.
Further technical solution, the tapered wheel upside is reached outside the upper side of the sliding dispatching device, described Bottom is equipped with the first electricity and makes a connection in plate, and the first electricity favourable turn left and right sides, which is connected with to stretch towards the left and right sides respectively, to be set The the first spiral bar put, the first spiral bar in first slippage slot are matched with the first slippage slot inner left wall operating It closes and connects, the first spiral bar in second slippage slot connects with the right side inner wall operating cooperation in second slippage slot It connects, the first spiral bar in first slippage slot connects with the supporting member spiral line cooperation in first slippage slot It connects, the first spiral bar in second slippage slot connects with the supporting member spiral line cooperation in second slippage slot It connects, the plate inner top is combined with the left and right sides and stretches respectively into first slippage slot and second slippage slot setting The second spiral bar, the second spiral bar of the left and right sides lead to wears the supporting member and with it is described it is tapered wheel left and right sliding cooperation It connecting, the tip that stretches on the left of the second spiral bar is connected with the first slippage slot inner left wall operating, and described second Stretch tip and the second electricity favourable turn mating connection on the right side of spiral bar, and the second electricity favourable turn outer surface is set to second sliding In slot right side and it is fixedly connected.
Further technical solution, the first spiral bar in first slippage slot in second slippage slot The first spiral bar spiral line is disposed opposite to each other.
The operating mating connection of slot inner bottom wall, institute are moved in further technical solution, the tight lock spiral bar bottom with described lead It states at the top of tight lock spiral bar and tight lock electricity favourable turn mating connection, the tight lock electricity favourable turn outer surface is set to described lead in shifting slot and pushes up In wall and it is fixedly connected.
Further technical solution, the tight locking bar outside the clamping device upper side are internally provided with tight lock slippage slot, The tight lock slippage slot is internally provided with spring part and tightly locks slipping block, and the tight lock slipping block leads to the tight lock for wearing the left and right sides It the face of bar opposite side and is oppositely arranged, the tight lock slipping block opposite flank of the left and right sides is internally provided with tight locked groove.
Further technical solution, the frame include controlling the roofbolt being correspondingly arranged and be fixed at the top of the roofbolt Top beam, the face of roofbolt opposite side described in two groups is internally provided with first and leads shifting slot, and described first shifting is led in roofbolt described in two groups Sliding is connected with lifting lever between slot, and lifting lever bottom centre position is equipped with drilling machine, the lifting lever top and institute It states and is connected with the second air pressure pushing meanss between top beam bottom.
Further technical solution, the enclosure device include enclosing lid and window, and the window is arranged on described Enclosing covers top, and the enclosing lid right end is connect by hinge with the pedestal side wall, and the enclosing lid left side top is fixed Draw piece is provided with, the enclosing lid left side is fixedly installed locked groove, and the pedestal left side top is fixedly installed and the lock The matched latch fitting of slot.
The beneficial effects of the invention are as follows:
1. by sliding left and right is all provided in dispatching device and is correspondingly arranged the first slippage slot and the second slippage slot, the first slippage slot And second set plate between slippage slot, supporting member is all provided in the first slippage slot and the second slippage slot, tapered wheel upside reaches cunning It moves outside the upper side of dispatching device, bottom sets the first electric favourable turn, the first electric left and right sides mating connection court respectively that makes a connection in plate The left and right sides stretches the first spiral bar of setting, and the first spiral bar and the first slippage slot inner left wall in the first slippage slot operate It is connected, the right side inner wall operating in the first spiral bar and the second slippage slot in the second slippage slot is connected, and first slides The supporting member spiral line moved in the first spiral bar and the first slippage slot in slot is connected, the first spiral in the second slippage slot Supporting member spiral line in bar and the second slippage slot is connected, and the plate inner top cooperation left and right sides is respectively to the first slippage slot With the second spiral bar of the setting that stretches in the second slippage slot, the second spiral bar of the left and right sides, which leads to, to be worn supporting member and takes turns a left side with tapered Right sliding is connected, and stretch tip and the operating mating connection of the first slippage slot inner left wall on the left of the second spiral bar, the second spiral shell Stretch tip and the second electricity favourable turn mating connection on the right side of shape bar, and the second electricity favourable turn outer surface is set in the second slippage slot right side And be fixedly connected, so as to fulfill the back-and-forth motion of jewel hole is automatically controlled, facilitate and adjust jewel hole position, improve working efficiency and brill Eye quality.
2. by setting the first slid chamber with being connected in the pedestal of clamping device bottom in clamping device, the first slid chamber Inside sets sliding component, and left and right sides correspondence sets elongated slot at the top of clamping device, and the second slid chamber, the second slid chamber are set inside sliding component It is set inside rear wall and leads shifting slot, led and move the tight lock spiral bar that the setting that stretches up and down is set inside slot, tightly lock to set on spiral bar and lead shifting block, It leads and sets front and back end inside the second slid chamber moved above slot and prop up block with what inner wall before and after the second slid chamber was fixedly connected, prop up block It left side and the second slid chamber inner left wall and props up and is all provided with leading shifting bar between inner wall on the right side of block right side and the second slid chamber, Each to lead the tight locking bar for moving on bar and sliding the setting that stretches above and below mating connection, the section that stretches at the top of tight locking bar reaches folder by elongated slot Be fixedly mounted with outside the upper side put, each tight locking bar bottom stretch tip and leading move before block between equal hinge mating connection catch bars, First slid chamber inner bottom wall sets the first air pressure pushing meanss that top is fixedly connected with sliding component bottom faces, so as to fulfill according to not The tubing of same specification size automatically adjusts, and tightly lock is highly and width, satisfaction are fixed for tubing card of different size and specifications It is fixed, improve device functionality and jewel hole quality.
3. the roofbolt that left and right is correspondingly arranged and the top beam being fixed at the top of roofbolt, two groups of roofbolt phases are included by frame First is set inside the face of offside and leads shifting slot, first in two groups of roofbolts, which leads to move between slot, slides mating connection lifting lever, lifting lever Bottom interposition installs drilling machine, and be connected the second air pressure pushing meanss at the top of lifting lever between top beam bottom, so as to fulfill Jewel hole work is lifted, improves working efficiency.
4. the configuration of the present invention is simple, easy to operate, it is tight that adjusting can be carried out automatically controlling for tubing of different size and specifications Lock, while can realize the jewel hole position of automatic control and adjustment tubing, improve accuracy and stability, prevent eyelet from training off with And tubing generates happening for vibration, while can automatically control tubing before tight lock by the sliding dispatching device of front and rear setting It is mobile, while there is the stability for propping up tubing, raising tubing jewel hole and movement in jewel hole.
Description of the drawings
For ease of explanation, the present invention is described in detail by following specific embodiment and attached drawing.
Fig. 1 is a kind of special constructing device vertical view of bridge of the present invention;
Fig. 2 is the structure diagram of A-A in Fig. 1 of the present invention;
Fig. 3 is the structure diagram of B-B in Fig. 1 of the present invention;
Fig. 4 is pedestal bottom plan view of the present invention.
Specific embodiment
As shown in Figure 1, Figure 2, Figure 3 and Figure 4, the special constructing device of a kind of bridge of the invention, including pedestal 5, the seat 5 upper side of body is equipped with clamping device 7 and is arranged on 7 front and rear sides of clamping device and the sliding dispatching device being correspondingly arranged 6, the pedestal 5 between the clamping device 7 and the rear side sliding dispatching device 6 is equipped with frame 8, each sliding The first slippage slot 64 and the second slippage slot 61 that left and right is correspondingly arranged, 64 He of the first slippage slot are equipped in dispatching device 6 Plate 62 is equipped between second slippage slot 61, is equipped with and props up in first slippage slot 64 and second slippage slot 61 Part 63, the supporting member 63 of the left and right sides are internally provided with the tapered wheel 631 being oppositely arranged, in the clamping device 7 with it is described It is connected in the pedestal 5 of 7 bottom of clamping device equipped with the first slid chamber 71, first slid chamber 71 is internally provided with sliding Part 73, the 7 top left and right sides of clamping device are correspondingly provided with elongated slot 72, and the sliding component 73 is internally provided with the second slid chamber 731,731 rear wall of the second slid chamber, which is internally provided with to lead, moves slot 734, it is described lead to move slot 734 and be internally provided with stretch and set up and down The tight lock spiral bar 7341 put, the tight lock spiral bar 7341, which is equipped with to lead, moves block 7342, and described lead moves the described of 734 top of slot Second slid chamber 731 is internally provided with front and back end and props up block 733, institute with what inner wall before and after second slid chamber 731 was fixedly connected It states and props up 733 left side of block and 731 inner left wall of the second slid chamber and described prop up 733 right side of block and described second It is equipped with to lead between 731 right side inner wall of slid chamber and moves bar 732, each described lead moves on bar 732 that sliding is connected with up and down Stretch the tight locking bar 735 of setting, and tight 735 top of the locking bar section that stretches reaches the upside of the clamping device 7 by elongated slot 72 Outside face, each tight 735 bottom of locking bar stretch tip and it is described lead to move between 7342 front of block hinge and be connected with push away Lever 736,71 inner bottom wall of the first slid chamber are equipped with the first air pressure that top is fixedly connected with 73 bottom faces of sliding component Pushing meanss 74,5 bottom of pedestal is provided with wheel chamber 52, is operated in the wheel cavity 52 and be connected with traveling wheel 51, described There are four the settings of traveling wheel 51, and 5 top of pedestal is provided with enclosure device.
Wherein, 631 upsides of the tapered wheel are reached outside the upper side of the sliding dispatching device 6, in the plate 62 Bottom is equipped with the first electricity and makes a connection 65, and 65 left and right sides of the first electricity favourable turn is connected with to stretch setting respectively towards the left and right sides The first spiral bar 641, the first spiral bar 641 in first slippage slot 64 in 64 left side of the first slippage slot Wall operating is connected, the first spiral bar 641 in second slippage slot 61 and the right side in second slippage slot 61 Side inner wall operating is connected, in the first spiral bar 641 and first slippage slot 64 in first slippage slot 64 63 spiral line of the supporting member be connected, the first spiral bar 641 and described second in second slippage slot 61 63 spiral line of the supporting member in slippage slot 61 is connected, and 62 inner top of plate is combined with the left and right sides respectively to institute State the second spiral bar 67 of the setting that stretches in the first slippage slot 64 and second slippage slot 61, second spiral shell of the left and right sides Shape bar 67 is logical to be worn the supporting member 63 and is connected with tapered 631 or so the sliding of wheel, 67 left side of the second spiral bar Tip and 64 inner left wall of the first slippage slot of stretching operating are connected, 67 right side of the second spiral bar stretch tip with Second electricity favourable turn 66 be connected, it is described second electricity favourable turn 66 outer surfaces be set to the 61 right side of the second slippage slot in and admittedly Fixed connection so as to fulfill the back-and-forth motion of jewel hole is automatically controlled, facilitates and adjusts jewel hole position, improves working efficiency and jewel hole product Matter.
Wherein, the first spiral bar 641 in first slippage slot 64 with it is described in second slippage slot 61 First spiral bar, 641 spiral line is disposed opposite to each other, so as to fulfill 63 phase of supporting member in the first slippage slot 64 and the second slippage slot 61 Pair and be moved away from work.
Wherein, the operating mating connection of 734 inner bottom wall of slot, the tight lock are moved in tight 7341 bottom of lock spiral bar with described lead The top of spiral bar 7341 is connected with tight lock electricity favourable turn 7343, and 7343 outer surfaces of the tight lock electricity favourable turn, which are set to, described leads shifting It in 734 inner roof wall of slot and is fixedly connected, moves block 7342 so as to fulfill being led by tightly locking 7343 control of electricity favourable turn catch bar 736 is driven to draw It moves tight locking bar 735 and is slid along 732 inward-outward direction of shifting bar is led.
Wherein, the tight locking bar 735 outside 7 upper side of clamping device is internally provided with tight lock slippage slot 7351, described Tight lock slippage slot 7351 is internally provided with spring part 7352 and tight lock slipping block 7353, and the tight lock slipping block 7353 is logical to wear left and right two It the face of tight 735 opposite side of locking bar of side and is oppositely arranged, in 7353 opposite flank of the tight lock slipping block of the left and right sides Portion is equipped with tight locked groove 7354, is tightly locked so as to fulfill stability.
Wherein, the frame 8 includes the roofbolt 81 that left and right is correspondingly arranged and the top beam being fixed at the top of the roofbolt 81 82, the face of 81 opposite side of roofbolt described in two groups, which is internally provided with first, leads and moves slot 811, described first leading in roofbolt 81 described in two groups Sliding is connected with lifting lever 83 between moving slot 811, and the 83 bottom centre position of lifting lever is equipped with drilling machine 831, described It falls between 83 top of bar and 82 bottom of the top beam and is connected with the second air pressure pushing meanss 84, so as to fulfill lifting borer Make.
Wherein, the enclosure device includes enclosing lid 501 and window 502, and the window 502 is arranged on the enclosing 501 upper top of lid, 501 right end of enclosing lid are connect by hinge 504 with 5 side wall of pedestal, 501 left side of enclosing lid Top is fixedly installed draw piece 503, and 501 left side of enclosing lid is fixedly installed locked groove 505,5 left side top of pedestal It is fixedly installed and the 505 matched latch fitting 506 of locked groove.
During original state, lead and move block 7342 positioned at the top position led in shifting slot 734, at this point, the tight lock of the left and right sides Bar 735 is made the tight locking bar 735 in left side offset with 731 inner left wall of the second slid chamber by the pushing of left and right sides catch bar 736 It connects, the tight locking bar 735 on right side is made to be abutted against with 731 right side inner wall of the second slid chamber, meanwhile, the tight locking bar 735 in left side is located at left side Left-most position in elongated slot 72, the tight locking bar 735 in right side are located at the right-most position in left and right sides elongated slot 72, at this point, for maximum Unlocked state.
When needing jewel hole, pushed up first by lifting lever 83 being driven to lead shifting slot 811 along first second air pressure pushing meanss 84 Portion direction moves up, until lifting lever 83, which is moved to first, leads the top position moved in slot 811, then passes through control first Electricity favourable turn 65 drives the 641 positive and negative operating of the first spiral bar of the left and right sides, is driven respectively by the first spiral bar 641 of the left and right sides Supporting member 63 in first slippage slot 64 and the second slippage slot 61 moves left and right, at this point, the cone in left and right sides supporting member 63 Type wheel 631 relatively or contrarily moves respectively along the second spiral bar 67 in the first slippage slot 64 and the second slippage slot 61, so as to Meet for tubing of different size and specifications roll and prop up, then tubing is placed on to the sliding dispatching device of front and rear sides In 6, the second electricity favourable turn 66 slid by front and rear sides in dispatching device 6 drives the 67 positive and negative operating of the second spiral bar simultaneously, by Second spiral bar 67 drives the 631 positive and negative operating of tapered wheel in the supporting member 63 of the left and right sides simultaneously, and is driven and managed by tapered wheel 631 Material, which is moved forward and backward, adjusts jewel hole position, is then driven on sliding component 73 by the first air pressure pushing meanss 74 in clamping device 7 Lower movement, until making the tight directly to the left relative position locked slipping block 7353 and be moved to tubing in the tight locking bar 735 in left side, simultaneously The tight lock slipping block 7353 in the tight locking bar 735 in right side is made to be moved to the directly to the right relative position of tubing, at this point, by tightly locking electricity Favourable turn 7343 drives tight lock spiral bar 7341 to operate, and is led by tightly locking the drive of spiral bar 7341 and moves block 7342 and move 734 bottom of slot along leading Direction slides, and tight locking bar 735 is driven to move bar 732 towards propping up 733 side of block along leading at this point, leading the catch bar 736 moved on block 7342 Relative sliding, until the tight locked groove 7354 that the left and right sides is tightly locked in slipping block 7353 offsets respectively with outer wall at left and right sides of tubing It connects, at this point, continuing to control tight 7343 operating of lock electricity favourable turn, the tight lock slipping block 7353 in the left and right sides is made to overcome the top pressure of spring part 7352 Power slides respectively towards corresponding tight lock in slippage slot 7351, until the left and right sides tightly locks slipping block 7353 and is slid onto corresponding tightly lock sliding During most inner side position in slot 7351, tight lock is completed at this time, and 83 edge of lifting lever is driven finally by the second air pressure pushing meanss 84 First leads the 811 bottom direction sliding of shifting slot, at this point, drilling machine 831 is driven to be moved towards tubing top exterior walls for lifting lever 83 until completion Jewel hole.
The beneficial effects of the invention are as follows:
1. by sliding left and right is all provided in dispatching device and is correspondingly arranged the first slippage slot and the second slippage slot, the first slippage slot And second set plate between slippage slot, supporting member is all provided in the first slippage slot and the second slippage slot, tapered wheel upside reaches cunning It moves outside the upper side of dispatching device, bottom sets the first electric favourable turn, the first electric left and right sides mating connection court respectively that makes a connection in plate The left and right sides stretches the first spiral bar of setting, and the first spiral bar and the first slippage slot inner left wall in the first slippage slot operate It is connected, the right side inner wall operating in the first spiral bar and the second slippage slot in the second slippage slot is connected, and first slides The supporting member spiral line moved in the first spiral bar and the first slippage slot in slot is connected, the first spiral in the second slippage slot Supporting member spiral line in bar and the second slippage slot is connected, and the plate inner top cooperation left and right sides is respectively to the first slippage slot With the second spiral bar of the setting that stretches in the second slippage slot, the second spiral bar of the left and right sides, which leads to, to be worn supporting member and takes turns a left side with tapered Right sliding is connected, and stretch tip and the operating mating connection of the first slippage slot inner left wall on the left of the second spiral bar, the second spiral shell Stretch tip and the second electricity favourable turn mating connection on the right side of shape bar, and the second electricity favourable turn outer surface is set in the second slippage slot right side And be fixedly connected, so as to fulfill the back-and-forth motion of jewel hole is automatically controlled, facilitate and adjust jewel hole position, improve working efficiency and brill Eye quality.
2. by setting the first slid chamber with being connected in the pedestal of clamping device bottom in clamping device, the first slid chamber Inside sets sliding component, and left and right sides correspondence sets elongated slot at the top of clamping device, and the second slid chamber, the second slid chamber are set inside sliding component It is set inside rear wall and leads shifting slot, led and move the tight lock spiral bar that the setting that stretches up and down is set inside slot, tightly lock to set on spiral bar and lead shifting block, It leads and sets front and back end inside the second slid chamber moved above slot and prop up block with what inner wall before and after the second slid chamber was fixedly connected, prop up block It left side and the second slid chamber inner left wall and props up and is all provided with leading shifting bar between inner wall on the right side of block right side and the second slid chamber, Each to lead the tight locking bar for moving on bar and sliding the setting that stretches above and below mating connection, the section that stretches at the top of tight locking bar reaches folder by elongated slot Be fixedly mounted with outside the upper side put, each tight locking bar bottom stretch tip and leading move before block between equal hinge mating connection catch bars, First slid chamber inner bottom wall sets the first air pressure pushing meanss that top is fixedly connected with sliding component bottom faces, so as to fulfill according to not The tubing of same specification size automatically adjusts, and tightly lock is highly and width, satisfaction are fixed for tubing card of different size and specifications It is fixed, improve device functionality and jewel hole quality.
3. the roofbolt that left and right is correspondingly arranged and the top beam being fixed at the top of roofbolt, two groups of roofbolt phases are included by frame First is set inside the face of offside and leads shifting slot, first in two groups of roofbolts, which leads to move between slot, slides mating connection lifting lever, lifting lever Bottom interposition installs drilling machine, and be connected the second air pressure pushing meanss at the top of lifting lever between top beam bottom, so as to fulfill Jewel hole work is lifted, improves working efficiency.
4. the configuration of the present invention is simple, easy to operate, it is tight that adjusting can be carried out automatically controlling for tubing of different size and specifications Lock, while can realize the jewel hole position of automatic control and adjustment tubing, improve accuracy and stability, prevent eyelet from training off with And tubing generates happening for vibration, while can automatically control tubing before tight lock by the sliding dispatching device of front and rear setting It is mobile, while there is the stability for propping up tubing, raising tubing jewel hole and movement in jewel hole.
The above description is merely a specific embodiment, but protection scope of the present invention is not limited thereto, any The change or replacement expected without creative work, should be covered by the protection scope of the present invention.Therefore, it is of the invention Protection domain should be determined by the scope of protection defined in the claims.

Claims (7)

1. a kind of special constructing device of bridge, including pedestal, it is characterised in that:Pedestal upper side is equipped with clamping device and setting In clamping device front and rear sides and the sliding dispatching device that is correspondingly arranged, the seat between clamping device and rear side sliding dispatching device Body is equipped with frame, and each slide is equipped with the first slippage slot and the second slippage slot that left and right is correspondingly arranged in dispatching device, the Plate is equipped between one slippage slot and the second slippage slot, supporting member, left and right two are equipped in the first slippage slot and the second slippage slot The supporting member of side is internally provided with the tapered wheel being oppositely arranged, and is equipped in clamping device with being connected in the pedestal of clamping device bottom First slid chamber, the first slid chamber are internally provided with sliding component, and the left and right sides is correspondingly provided with elongated slot at the top of clamping device, in sliding component Portion is equipped with the second slid chamber, and the second slid chamber rear wall, which is internally provided with, leads shifting slot, leads shifting slot and is internally provided with the setting that stretches up and down Tight lock spiral bar, tight spiral bar of locking lead the second slid chamber moved above slot and are internally provided with front and back end and second equipped with shifting block is led What inner wall was fixedly connected before and after slid chamber props up block, props up block left side and the second slid chamber inner left wall and props up on the right side of block It is equipped between inner wall on the right side of face and the second slid chamber and leads shifting bar, each lead to move on bar to slide to be connected with to stretch up and down setting The tight locking bar put, the section that stretches at the top of tight locking bar are reached by elongated slot outside the upper side of clamping device, and each tightly locking bar bottom stretches Hinge is connected with catch bar between tip and leading is moved before block, and the first slid chamber inner bottom wall is equipped with top and sliding component bottom The first air pressure pushing meanss that portion face is fixedly connected, pedestal bottom are provided with wheel chamber, and wheel intracavitary operating is connected with traveling wheel, There are four traveling wheel settings, and enclosure device is provided at the top of pedestal.
2. a kind of special constructing device of bridge according to claim 1, it is characterised in that:The tapered wheel upside reaches Outside the upper side of the sliding dispatching device, bottom is equipped with the first electricity and makes a connection in the plate, the first electricity favourable turn left and right two Side is connected with the first spiral bar of the setting that stretches respectively towards the left and right sides, first spiral in first slippage slot The operating of bar and the first slippage slot inner left wall is connected, the first spiral bar in second slippage slot with it is described Right side inner wall operating in second slippage slot is connected, the first spiral bar and described first in first slippage slot The supporting member spiral line in slippage slot is connected, the first spiral bar and described second in second slippage slot The supporting member spiral line in slippage slot is connected, and the plate inner top is combined with the left and right sides respectively to described first Stretch the second spiral bar of setting in slippage slot and second slippage slot, the second spiral bar of the left and right sides lead to wear it is described It supporting member and is connected with the tapered wheel left and right sliding, stretch tip and the described first sliding on the left of the second spiral bar The operating of slot inner left wall is connected, and stretch tip and the second electricity favourable turn mating connection on the right side of the second spiral bar, and described the Two electricity favourable turn outer surfaces are set in the second slippage slot right side and are fixedly connected.
3. a kind of special constructing device of bridge according to claim 2, it is characterised in that:Institute in first slippage slot The first spiral bar is stated to be disposed opposite to each other with the first spiral bar spiral line in second slippage slot.
4. a kind of special constructing device of bridge according to claim 1, it is characterised in that:It is described it is tight lock spiral bar bottom with Described lead moves the operating mating connection of slot inner bottom wall, is connected at the top of the tight lock spiral bar with tight electricity favourable turn of locking, the tight lock Electricity favourable turn outer surface is set to described lead and moves in slot inner roof wall and be fixedly connected.
5. a kind of special constructing device of bridge according to claim 1, it is characterised in that:Outside the clamping device upper side The tight locking bar be internally provided with tight lock slippage slot, the tight lock slippage slot is internally provided with spring part and tightly locks slipping block, described Tight lock slipping block leads to the face for the tight locking bar opposite side for wearing the left and right sides and is oppositely arranged, the tight lock sliding of the left and right sides Block opposite flank is internally provided with tight locked groove.
6. a kind of special constructing device of bridge according to claim 1, it is characterised in that:The frame includes left and right and corresponds to The roofbolt of setting and the top beam being fixed at the top of the roofbolt, the face of roofbolt opposite side described in two groups are internally provided with first and lead shifting Slot, described in two groups in roofbolt described first lead move slot between sliding be connected with lifting lever, among the lifting lever bottom Position is equipped with drilling machine, and the second air pressure pushing meanss are connected between the top beam bottom at the top of the lifting lever.
7. a kind of special constructing device of bridge according to claim 1, it is characterised in that:The enclosure device includes enclosing Lid and window, the window are arranged on the enclosing and cover top, and the enclosing lid right end passes through hinge and the pedestal Side wall connects, and the enclosing lid left side top is fixedly installed draw piece, and the enclosing lid left side is fixedly installed locked groove, described Pedestal left side top is fixedly installed and the matched latch fitting of the locked groove.
CN201710393419.1A 2017-05-27 2017-05-27 A kind of special constructing device of bridge Withdrawn CN108252217A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710393419.1A CN108252217A (en) 2017-05-27 2017-05-27 A kind of special constructing device of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710393419.1A CN108252217A (en) 2017-05-27 2017-05-27 A kind of special constructing device of bridge

Publications (1)

Publication Number Publication Date
CN108252217A true CN108252217A (en) 2018-07-06

Family

ID=62721877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710393419.1A Withdrawn CN108252217A (en) 2017-05-27 2017-05-27 A kind of special constructing device of bridge

Country Status (1)

Country Link
CN (1) CN108252217A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204094408U (en) * 2014-08-29 2015-01-14 天津曹氏锅炉有限公司 A kind of steel pipe seaming device
CN205271302U (en) * 2015-11-19 2016-06-01 长春捷柯技术开发有限公司 Pipe seam welding jig
CN205927698U (en) * 2016-05-30 2017-02-08 浙江蓝能燃气设备有限公司 Rotary rolling wheel frame of interior throwing steel bottle

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204094408U (en) * 2014-08-29 2015-01-14 天津曹氏锅炉有限公司 A kind of steel pipe seaming device
CN205271302U (en) * 2015-11-19 2016-06-01 长春捷柯技术开发有限公司 Pipe seam welding jig
CN205927698U (en) * 2016-05-30 2017-02-08 浙江蓝能燃气设备有限公司 Rotary rolling wheel frame of interior throwing steel bottle

Similar Documents

Publication Publication Date Title
CN107127598B (en) A kind of perforating device suitable for different-diameter size steel pipe
CN106956016B (en) A kind of equidistant perforating device of building board
CN106994524B (en) A kind of bridge construction device
CN110254080A (en) A kind of Household children drawing board
CN107685163B (en) A kind of adjustable plate punching equipment
CN108252217A (en) A kind of special constructing device of bridge
CN107816035B (en) A kind of tamping unit of Phase of Electric Power Projects
CN108067653B (en) A kind of perforating device of the steel pipe suitable for different-diameter
CN107052397A (en) A kind of convenient bridge construction device
CN107086444B (en) A kind of vertical electric power distributing cabinet
CN107069524B (en) A kind of vertical electric power distributing cabinet of automatic control
CN107842186A (en) One kind finishing sturdy device of land used brick wall brick
CN107175410B (en) A kind of laser engraving machine
CN107654054B (en) A kind of finishing brick bat compaction apparatus
CN107583926A (en) A kind of vessel cleaning equipment
CN108058239A (en) A kind of follow-on environment-friendly sheet processing unit (plant)
CN107069456A (en) A kind of power distribution cabinet device
CN107511411B (en) A kind of metallic plate flattening device
CN108380926B (en) A kind of letter box arrangement
CN107780939B (en) A kind of mining apparatus
CN107685171B (en) A kind of building board perforating device
CN108444844B (en) A kind of communication equipment test device
CN108189600B (en) A kind of modified engraving machine
CN108104446A (en) A kind of brick bat sturdy device of follow-on finishing
CN109237227A (en) A kind of Contiuum type heat engine heat pump assembly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180706