CN108233252A - A kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform - Google Patents
A kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform Download PDFInfo
- Publication number
- CN108233252A CN108233252A CN201711228544.3A CN201711228544A CN108233252A CN 108233252 A CN108233252 A CN 108233252A CN 201711228544 A CN201711228544 A CN 201711228544A CN 108233252 A CN108233252 A CN 108233252A
- Authority
- CN
- China
- Prior art keywords
- tooling
- rack
- fixedly connected
- sliding rail
- cutter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Pressure Welding/Diffusion-Bonding (AREA)
- Machine Tool Units (AREA)
Abstract
A kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform, including:Rack, control circuit, hydraulic pump pre-install tooling, are arranged on right over the sliding rail of top;Top sliding rail, is fixedly connected with rack;Lower slide track, is fixedly connected with rack;Tooling is lifted platform, is arranged on the front of lower slide track, is fixedly connected with rack;Tooling recycles platform, is arranged on the dead astern of lower slide track, is fixedly connected with rack;Shipment track is arranged on top sliding rail dead astern, is fixedly connected with rack;Caulking gun rivets Pre-Cutter-Type Anti-Vibration Hammer simultaneously from the left and right sides, is arranged on above the sliding rail of top in the rack of the left and right sides, connects with hydraulic pump, be electrically connected with control circuit;The control circuit is electrically connected with hydraulic pump.Can be with synchronous riveting Pre-Cutter-Type Anti-Vibration Hammer both sides tup, and pipeline system processing can be carried out, production efficiency is accelerated, improves the safety coefficient in production process.
Description
Technical field
The present invention relates to electric power utensil manufacture fields, and in particular to a kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform.
Background technology
Damper is in use, by wire clip body upper end connecting wire, and axis occurs on conducting wire for wire clip body in order to prevent
It to play and overturns, someone provides a kind of structure, and after setting preformed armor rods on wire clip body, the preformed armor rods are helically
Wire clip body is fastened on conducting wire by type, and such structure compares traditional structure, there is better fastening effect.But due to
Wire clip body surface is more smooth, and wire clip body does not have baffle in preformed armor rods both sides, and preformed armor rods also exist to a certain extent
Axial direction, radial slippage, there are the hidden danger of damper play.During manufacturing at present, tup riveting generally use is efficient
High texture presses form, but presses and easily limited by product structure form;And it is easy to operate it is flexible hammer riveting efficiency it is low
Under, riveting quality is also very different.
Chinese publication CN205304187U, publication date on June 8th, 2016, innovation and creation it is entitled a kind of anti-
Vibration hammer tup riveting tool discloses a kind of anti-vibration hammer riveting tool, is related to electric armour clamp field, including pedestal, opens counterbore
Two pieces of tablets and bolt of lower base connection, lower end be inserted into two pieces of tablets between gap movable bearing support, be welded on consolidating on tablet
Determine bearing;Open the straight slot that section is semicircle in the movable bearing support side opposite with the two vertical plates of hold-down support;The straight slot
Section radius and the steel strand wires diameter of damper match;The two vertical plates height of the movable bearing support and hold-down support is more than anti-
The length of vibration hammer tup lower ending opening, thickness are less than the width of anti-vibration hammer lower ending opening.The utility model makes the hammer that presses
It is no longer limited during head by the structure type of hypophysis, under the premise of riveting quality is ensured, saves the working time, reduce labour
Intensity substantially increases production efficiency.
But for its shortcoming for that cannot carry out automated production, whole process is required for manual operation.
Invention content
The present invention be directed to the riveting of existing Pre-Cutter-Type Anti-Vibration Hammer, platform is cumbersome needs to consume a large amount of manpowers, relates to one kind
Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform quickly and automation riveting Pre-Cutter-Type Anti-Vibration Hammer can increase speed of production.
A kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform, including:Rack, control circuit, hydraulic pump pre-install tooling, are used for
Dispose the semi-finished product to be riveted of steel strand wires and anti-vibration hammer composition, be arranged on right over top sliding rail, with riveting gun, on
Portion's sliding rail and lower slide track cooperating;Top sliding rail pre-installs tooling for carrying, is fixed with rack
Connection;Lower slide track pre-installs tooling for back transfer, is arranged on the underface of top sliding rail, consolidates with rack
Fixed connection;Tooling is lifted platform, for the pre-installation tooling carried on lower slide track to be raised to top sliding rail, setting
In the front of lower slide track, it is fixedly connected with rack;Tooling recycles platform, is slid on the sliding rail of top for recycling
The pre-installation tooling of tail end is arranged on the dead astern of lower slide track, is fixedly connected with rack to lower slide track;Shipment
Track for the Pre-Cutter-Type Anti-Vibration Hammer that riveting is completed to be removed from pre-installation tooling, is arranged on top sliding rail dead astern,
It is fixedly connected with rack;At least two caulking guns rivet Pre-Cutter-Type Anti-Vibration Hammer simultaneously from the left and right sides, are arranged on top and slide rail
Above road in the rack of the left and right sides, connect with hydraulic pump, be electrically connected with control circuit;The control circuit and hydraulic pump electricity
Connection.
Preferably, the rack is additionally provided with upper limit device, the upper limit device includes:At least two
Block movable plate is arranged on the pre-installation tooling on the sliding rail of top below frame top bottom alignment, through frame top,
It is sequentially connected with vertical translation hydraulic unit driver;Vertical translation hydraulic unit driver is arranged on frame top center, with activity
Plate is sequentially connected, and is connected with hydraulic pump;Several base pressure sensors, may be contained within movable plate bottom, with control circuit electricity
Connection.
Upper limit device can be when pre-installation tooling enters operating position, to the semi-finished product placed in pre-installation tooling
It is limited, places anti-vibration hammer in riveting process and be in distortion state, steel strand wires generate bending etc due to rivet force
The problem of.
Preferably, the rack, further includes:At least two top tooling shifters, are arranged on top sliding rail
Front on horizontal plane, the horizontal distance of top tooling shifter are more than tooling and are lifted platform width, connected with hydraulic pump;At least two
A lower part tooling shifter is arranged on dead astern on lower slide track horizontal plane, and the horizontal distance of lower part tooling shifter should
More than the width of tooling recycling platform, connected with hydraulic pump;At least two caulking gun horizontal position adjustment devices, respectively with being arranged on machine
Caulking gun at left and right sides of frame is fixedly connected, and is fixedly connected with rack, is connected with hydraulic pump.
Top tooling shifter can allow is raised to the pre-installation tooling of top sliding rail backward by tooling lifting platform
It pushes, when the pre-installation tooling being lifted enters top sliding rail and in orbit and the tooling that finishes of riveting enters
Tooling recycles platform;Top tooling shifter retraction, tooling lifting platform decline, and wait for next pre-installation into tooling lifting platform
Tooling;When pre-installation tooling enters right over tooling recycling platform, it is placed in the Pre-Cutter-Type Anti-Vibration Hammer finished product pre-installed in tooling
Into shipment track, tooling recycling platform carries pre-installation tooling and drops to lower slide track, and lower part tooling shifter pushes pre-
Mounting tool is moved along.
Preferably, the pre-installation tooling, including:Base frame, front are undercut type, are used among base frame equipped with groove
Steel strand wires positioning tables, hook shelves and tup positioning table are disposed, and top sliding rail cooperating, with disposing steel strand wires
Positioning table and tup positioning table are spirally connected, and are fixedly connected with hook shelves;Steel strand wires positioning table is faced in concave, and top is set
Arc groove is equipped with for disposing steel strand wires, middle part recessed portion is equipped with screw hole, and steel strand wires positioning table is spirally connected with base frame;At least two
A tup positioning table is arranged on left side tup positioning table and is arranged on left side steel strand wires positioning table with a left side, and right side is symmetrically installed, and is passed through
The screw hole among tup positioning table is arranged on to be spirally connected with base frame;Shelves are linked up with, place to the rear on base frame central axes are arranged on, the bottom of with
Platform is fixedly connected.
Preferably, the shipment track, top is provided with arc adapting table, and arc adapting table front end is equipped with protrusion,
Arc adapting table bottom is equipped with supporting rod;Arc adapting table rear is fixedly connected with oblique track, and oblique track is used for shipment, with
Rack is fixedly connected.
The substantial effect of the present invention is can be with synchronous riveting Pre-Cutter-Type Anti-Vibration Hammer both sides tup, and can carry out assembly line
Formula is processed, and is accelerated production efficiency, is improved the safety coefficient in production process.
Description of the drawings
Fig. 1 pre-installation toolings are overlooked and schematic elevation view;
Fig. 2 rivets platform front schematic view;
Fig. 3 rivets platform side schematic view;
In figure:1st, tup positioning table, 2, steel strand wires positioning table, 3, hook shelves, 4, base frame, 5, vertical translation hydraulic-driven
Device, 6, rack, 7, movable plate, 8, caulking gun, 9, pre-installation tooling, 10, top sliding rail, 11, lower slide track, 12,
Tooling is lifted platform, and 13, tooling recycling platform, 14, lower part tooling shifter, 15, top tooling shifter, 16, shipment track.
Specific embodiment
Below by specific embodiment, and with reference to attached drawing, technical scheme of the present invention is described in further detail.
Embodiment 1
As shown in Figure 1, Figure 2 and Figure 3, a kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform, including:Rack 6, control circuit,
Hydraulic pump pre-installs tooling 9, for the semi-finished product to be riveted that steel strand wires and anti-vibration hammer is disposed to form, is arranged on top cunning
Right over dynamic rail road 10, with 11 cooperating of riveting gun, top sliding rail 10 and lower slide track;Top sliding rail
10, tooling 9 is pre-installed for carrying, is fixedly connected with rack 6;Lower slide track 11 pre-installs tooling for back transfer
9, the underface of top sliding rail 10 is arranged on, is fixedly connected with rack 6;Tooling is lifted platform 12, for lower slide rail
The pre-installation tooling 9 carried on road 11 is raised to top sliding rail 10, is arranged on the front of lower slide track 11, with machine
Frame 6 is fixedly connected;Tooling recycles platform 13, for recycling the pre-installation tooling 9 that tail end is slid on top sliding rail 10 under
Portion's sliding rail 11 is arranged on the dead astern of lower slide track 11, is fixedly connected with rack 6;Shipment track 16, for riveting
The Pre-Cutter-Type Anti-Vibration Hammer for connecing completion is removed from pre-installation tooling 9, is arranged on 10 dead astern of top sliding rail, solid with rack 6
Fixed connection;At least two caulking guns 8, Pre-Cutter-Type Anti-Vibration Hammer is riveted from the left and right sides simultaneously, is arranged on top sliding rail 10
In the rack 6 of the side left and right sides, connect with hydraulic pump, be electrically connected with control circuit;The control circuit is electrically connected with hydraulic pump
It connects.
The rack 6 is additionally provided with upper limit device, and the upper limit device includes:At least two pieces of movable plates
7, the pre-installation tooling 9 being arranged on 6 top base of rack alignment lower section top sliding rail 10, through 6 top of rack, with
Vertical translation hydraulic unit driver 5 is sequentially connected;Vertical translation hydraulic unit driver 5 is arranged on 6 top center of rack, with work
Movable plate 7 is sequentially connected, and is connected with hydraulic pump;Several base pressure sensors may be contained within 7 bottom of movable plate, with control electricity
Road is electrically connected.
Upper limit device can when pre-installing tooling 9 and entering operating position, to placed in pre-installation tooling 9 half into
Product are limited, and are placed anti-vibration hammer in riveting process and are in distortion state, steel strand wires generate bending due to rivet force
The problem of class.
The rack 6, further includes:It is horizontal to be arranged on top sliding rail 10 at least two top tooling shifters 15
Front on face, the horizontal distance of top tooling shifter 15 are more than tooling and are lifted 12 width of platform, connected with hydraulic pump;At least two
A lower part tooling shifter 14 is arranged on dead astern on 11 horizontal plane of lower slide track, the level of lower part tooling shifter 14
Distance should be greater than the width of tooling recycling platform 13, be connected with hydraulic pump;At least two caulking guns, 8 horizontal position adjustment device, respectively
It is fixedly connected with the caulking gun 8 for being arranged on 6 left and right sides of rack, is fixedly connected with rack 6, is connected with hydraulic pump.
Top tooling shifter 15 can allow is raised to the pre-installation work of top sliding rail 10 by tooling lifting platform 12
It fills 9 to push backward, when the pre-installation tooling 9 being lifted enters top sliding rail 10 and in orbit and riveting finishes
Tooling enter tooling recycling platform 13;Top tooling shifter 15 bounces back, and tooling lifting platform 12 declines, and waits for next into work
The pre-installation tooling 9 of dress lifting platform 12;When pre-installing tooling 9 into tooling recycling 13 surface of platform, it is placed in pre-installation work
It fills the Pre-Cutter-Type Anti-Vibration Hammer finished product on 9 and enters shipment track 16, tooling recycling platform 13 carries pre-installation tooling 9 and drops to lower part cunning
Dynamic rail road 11, lower part tooling shifter 14 push pre-installation tooling 9 to be moved along.
The pre-installation tooling 9, including:Base frame 4, front are undercut type, and groove is equipped among base frame 4 for disposing steel
Twisted wire positioning table 2, hook shelves 3 and tup positioning table 1, and 10 cooperating of top sliding rail, with disposing steel strand wires
Positioning table 2 and tup positioning table 1 are spirally connected, and are fixedly connected with hook shelves 3;Steel strand wires positioning table 2 is faced in concave, top
Portion is provided with arc groove for disposing steel strand wires, and middle part recessed portion is equipped with screw hole, and steel strand wires positioning table 2 is spirally connected with base frame 4;
At least two tup positioning tables 1 are arranged on left side tup positioning table 1 and are arranged on left side steel strand wires positioning table 2 with a left side, and right side is symmetrical
Installation is spirally connected by being arranged on the screw hole among tup positioning table 1 with base frame 4;Shelves 3 are linked up with, are arranged on 4 central axes of base frame
Upper place to the rear, is fixedly connected with base frame 4.
The shipment track 16, top are provided with arc adapting table, and arc adapting table front end is equipped with protrusion, and arc is accepted
Platform bottom is equipped with supporting rod;Arc adapting table rear is fixedly connected with oblique track, and oblique track is used for shipment, solid with rack 6
Fixed connection.
Claims (5)
1. a kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform, including:Rack, control circuit and hydraulic pump, which is characterized in that also wrap
It includes:
Tooling is pre-installed, for the semi-finished product to be riveted that steel strand wires and anti-vibration hammer is disposed to form, top is arranged on and slides rail
Right over road, with riveting gun, top sliding rail and lower slide track cooperating;
Top sliding rail pre-installs tooling for carrying, is fixedly connected with rack;
Lower slide track pre-installs tooling for back transfer, is arranged on the underface of top sliding rail, is fixed with rack
Connection;
Tooling is lifted platform, for the pre-installation tooling carried on lower slide track to be raised to top sliding rail, is arranged on
The front of lower slide track, is fixedly connected with rack;
Tooling recycles platform, for recycling the pre-installation tooling that tail end is slid on the sliding rail of top to lower slide track, if
It puts in the dead astern of lower slide track, is fixedly connected with rack;
Shipment track for the Pre-Cutter-Type Anti-Vibration Hammer that riveting is completed to be removed from pre-installation tooling, is arranged on top and slides rail
Road dead astern, is fixedly connected with rack;
At least two caulking guns rivet Pre-Cutter-Type Anti-Vibration Hammer simultaneously from the left and right sides, are arranged on left and right above the sliding rail of top
It in the rack of both sides, connects with hydraulic pump, is electrically connected with control circuit;
The control circuit is electrically connected with hydraulic pump.
2. a kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform according to claim 1, which is characterized in that the rack is also set
Upper limit device is equipped with, the upper limit device includes:
At least two pieces of movable plates are arranged on the pre-installation tooling on the sliding rail of top below frame top bottom alignment, run through
Frame top is sequentially connected with vertical translation hydraulic unit driver;
Vertical translation hydraulic unit driver is arranged on frame top center, is sequentially connected with movable plate, is connected with hydraulic pump;
Several base pressure sensors, may be contained within movable plate bottom, are electrically connected with control circuit.
3. a kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform according to claim 1, which is characterized in that the rack, also
Including:
At least two top tooling shifters are arranged on front on the sliding rail horizontal plane of top, top tooling shifter
Horizontal distance is more than tooling and is lifted platform width, is connected with hydraulic pump;
At least two lower part tooling shifters are arranged on dead astern on lower slide track horizontal plane, lower part tooling shifter
Horizontal distance should be greater than the width of tooling recycling platform, be connected with hydraulic pump;
At least two caulking gun horizontal position adjustment devices, are fixedly connected respectively with the caulking gun being arranged at left and right sides of rack, with
Rack is fixedly connected, and is connected with hydraulic pump.
A kind of 4. Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform according to claim 1, which is characterized in that the pre-installation work
Dress, including:
Base frame, front are undercut type, and groove is equipped among base frame for disposing steel strand wires positioning table, hook shelves and tup
Positioning table with top sliding rail cooperating, is spirally connected with placement steel strand wires positioning table and tup positioning table, is disposed with hook
Frame is fixedly connected;
Steel strand wires positioning table is faced in concave, and top is provided with arc groove for disposing steel strand wires, and middle part recessed portion is equipped with
Screw hole, steel strand wires positioning table are spirally connected with base frame;
At least two tup positioning tables are arranged on left side tup positioning table and are arranged on left side steel strand wires positioning table with a left side, and right side is right
Claim installation, be spirally connected by being arranged on the screw hole among tup positioning table with base frame;
Shelves are linked up with, place to the rear on base frame central axes is arranged on, is fixedly connected with base frame.
A kind of 5. Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform according to claim 1, which is characterized in that the shipment rail
Road,
Top is provided with arc adapting table, and arc adapting table front end is equipped with protrusion, and arc adapting table bottom is equipped with supporting rod;
Arc adapting table rear is fixedly connected with oblique track, and oblique track is used for shipment, is fixedly connected with rack.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711228544.3A CN108233252B (en) | 2017-11-29 | 2017-11-29 | Automatic riveting platform of preformed helical damper |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711228544.3A CN108233252B (en) | 2017-11-29 | 2017-11-29 | Automatic riveting platform of preformed helical damper |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108233252A true CN108233252A (en) | 2018-06-29 |
CN108233252B CN108233252B (en) | 2020-04-10 |
Family
ID=62652937
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711228544.3A Active CN108233252B (en) | 2017-11-29 | 2017-11-29 | Automatic riveting platform of preformed helical damper |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108233252B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07336853A (en) * | 1994-06-08 | 1995-12-22 | Furukawa Electric Co Ltd:The | Twist preventing damper |
CN101269629A (en) * | 2007-03-23 | 2008-09-24 | 庄大清 | Process technique for shockproof hammer |
CN102082407A (en) * | 2009-12-01 | 2011-06-01 | 江苏天南电力器材有限公司 | Hammerhead of anti-vibration hammer as well as production process and device thereof |
CN205304187U (en) * | 2016-01-19 | 2016-06-08 | 河北黑牛电力金具有限公司 | Damper tup riveting tools |
CN106734826A (en) * | 2016-11-23 | 2017-05-31 | 合肥智博生物科技有限公司 | A kind of riveting screw mechanism and it is provided with the rotating disc type screw locking machine of the mechanism |
CN206595678U (en) * | 2017-04-13 | 2017-10-27 | 安徽固齐线路器材有限公司 | A kind of Pre-Cutter-Type Anti-Vibration Hammer with deep bead |
-
2017
- 2017-11-29 CN CN201711228544.3A patent/CN108233252B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH07336853A (en) * | 1994-06-08 | 1995-12-22 | Furukawa Electric Co Ltd:The | Twist preventing damper |
CN101269629A (en) * | 2007-03-23 | 2008-09-24 | 庄大清 | Process technique for shockproof hammer |
CN102082407A (en) * | 2009-12-01 | 2011-06-01 | 江苏天南电力器材有限公司 | Hammerhead of anti-vibration hammer as well as production process and device thereof |
CN205304187U (en) * | 2016-01-19 | 2016-06-08 | 河北黑牛电力金具有限公司 | Damper tup riveting tools |
CN106734826A (en) * | 2016-11-23 | 2017-05-31 | 合肥智博生物科技有限公司 | A kind of riveting screw mechanism and it is provided with the rotating disc type screw locking machine of the mechanism |
CN206595678U (en) * | 2017-04-13 | 2017-10-27 | 安徽固齐线路器材有限公司 | A kind of Pre-Cutter-Type Anti-Vibration Hammer with deep bead |
Also Published As
Publication number | Publication date |
---|---|
CN108233252B (en) | 2020-04-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205147758U (en) | A anchor clamps for work piece lock | |
CN209867248U (en) | High-efficient two horizontal hydraulic pressure of die spin riveter | |
CN110227739A (en) | Fast roll changing levelling machine | |
CN108233252A (en) | A kind of Pre-Cutter-Type Anti-Vibration Hammer automatic riveting platform | |
CN205519100U (en) | Novel C type panel beating is bent device | |
CN102896178A (en) | Cold processing method of metal sheet corner piece and special metal sheet corner forming machine therefor | |
CN114433718B (en) | Door shell and door handle forming equipment | |
CN207358730U (en) | A kind of pan automatic trimming assembly line | |
CN213707635U (en) | Sheet material transfer device for steel plate stamping production equipment | |
CN205043070U (en) | Draw bail of isothermal forging heating electric stove | |
CN211727191U (en) | Stamping die | |
CN211161323U (en) | Bending machine for machining U-shaped steel plate | |
CN206253495U (en) | A kind of reverse single processing assembly of steel tower corner iron | |
CN207823855U (en) | A kind of metallic chair automatic riveter | |
CN2845954Y (en) | Portal metal plate press rivet machine | |
CN206185033U (en) | Iron -clad reviting machine | |
CN206028400U (en) | Full -automatic squeezer | |
CN206925187U (en) | A kind of hemmer of flanger bearing liner | |
CN105584932A (en) | Lifting tool of finished product operating mechanism | |
CN218475814U (en) | Sheet metal part traceless bending device | |
CN211161334U (en) | Device for bending joint panel | |
CN110918713A (en) | High-stability bending device for aluminum profile | |
CN215315199U (en) | Automatic pressure riveting device for sheet metal workpiece | |
CN108941317A (en) | A kind of tooling for processing disagreement head | |
CN109967574A (en) | A kind of multistage veneer reeling machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: An automatic riveting platform for pre-twisted anti-vibration hammer Effective date of registration: 20230224 Granted publication date: 20200410 Pledgee: Wuhu wanshe sub branch of China Construction Bank Co.,Ltd. Pledgor: ZHONGANDA ELECTRIC TECHNOLOGY CO.,LTD. Registration number: Y2023980033394 |