CN108197767A - In the Intelligent Decision-making Method of fortune supervisory control of substation information table - Google Patents
In the Intelligent Decision-making Method of fortune supervisory control of substation information table Download PDFInfo
- Publication number
- CN108197767A CN108197767A CN201810275238.3A CN201810275238A CN108197767A CN 108197767 A CN108197767 A CN 108197767A CN 201810275238 A CN201810275238 A CN 201810275238A CN 108197767 A CN108197767 A CN 108197767A
- Authority
- CN
- China
- Prior art keywords
- information table
- substation
- interval
- fortune
- station information
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000012544 monitoring process Methods 0.000 claims abstract description 28
- 238000005457 optimization Methods 0.000 claims abstract description 5
- 238000013506 data mapping Methods 0.000 claims abstract description 4
- 230000008676 import Effects 0.000 claims abstract description 4
- 238000012913 prioritisation Methods 0.000 claims abstract description 4
- 239000000284 extract Substances 0.000 claims description 3
- 230000009466 transformation Effects 0.000 claims description 3
- 238000012545 processing Methods 0.000 abstract description 3
- 238000012550 audit Methods 0.000 description 3
- 230000001276 controlling effect Effects 0.000 description 1
- 238000013480 data collection Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Human Resources & Organizations (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Development Economics (AREA)
- Game Theory and Decision Science (AREA)
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The present invention relates to a kind of Intelligent Decision-making Method in fortune supervisory control of substation information table, technical characteristics are:The parameter of substation is modeled, establishes complete basis signal library;Establish the typical incidence relation of transformer substation voltage grade connection type spacing devices;Import operation station information table;Interval data is automatically extracted according to operation station information table, establishes the incidence relation of interval, equipment and monitoring data;The prioritization scheme of result and monitoring data mapping relations generating run station information table is disposed according to signal;The dynamic of operation station information table optimization situation is tracked and automatically updated.The present invention is on the basis of to parameter models such as the voltage class of substation, connection type, interval types, using self-learning algorithm, form the structuring processing of substation information, good suggestion is provided for auditor, significantly reduce the workload and operating pressure of auditor, the time is saved, is improved work efficiency.
Description
Technical field
The invention belongs to intelligent substation technical field, especially a kind of intelligent decision in fortune supervisory control of substation information table
Method.
Background technology
In electric system " big operation " is implemented, the monitoring information access amount of 500 kv substations is with newly-built intelligence change
The monitoring signal in power station accesses regulation and control center and is significantly increased, and the workload for regulating and controlling center is also doubled and redoubled.How is monitoring signal
Could it is complete, accurate, be collected into regulation and control center in time, how so that data collection standardization, standardization, completeization, accurately
The work such as change become a problem.Monitoring information establishment, audit, approval workload are huge, and substantially pure craft objectively exists
Combing and optimization to monitoring information is not thorough enough, and management and control is not rigorous enough, the quality of data of monitoring information is influenced, to power system monitor
Operation brings hidden danger and risk.
Invention content
It is an object of the invention to overcome the deficiencies in the prior art, propose a kind of intelligence in fortune supervisory control of substation information table
Decision-making technique can provide more good suggestion, it is ensured that substation for information table auditor to the audit approval of monitoring information
Monitoring information table is consistent with state net monitoring information standard.
The present invention solves its technical problem and following technical scheme is taken to realize:
A kind of Intelligent Decision-making Method in fortune supervisory control of substation information table includes the following steps:
Step 1, foundation electric power typical information table, operation platform account and primary connection figure, build the parameter of substation
Mould establishes complete basis signal library;
Step 2, the typical incidence relation for establishing substation-voltage class-connection type-interval-equipment;
Step 3 imports operation station information table;
Step 4 automatically extracts interval data according to operation station information table, monitoring information incorporated into specific interval automatically and
Equipment establishes the incidence relation of interval, equipment and monitoring data;
Step 5, the prioritization scheme that result and monitoring data mapping relations generating run station information table are disposed according to signal;
Step 6 is tracked and is automatically updated to the dynamic of operation station information table optimization situation.
The underlying parameter of the basis signal library configuration monitoring information table includes power transformation station name, voltage class, wiring shape
Formula, compartment name, equipment principle and equipment manufacturer's model.
Operation station information table includes substation information, interval information, facility information and monitoring of tools data.
The advantages and positive effects of the present invention are:
The present invention by establishing standard signal library, initialization substation essential information, by supervisory control of substation signal structure
Processing (incorporating interval and signal disposition into including signal) simultaneously provides matched as a result, being examined for information table with the progress of standard signal library
Core personnel provide more good suggestion to the audit approval of monitoring information, it is ensured that supervisory control of substation information table and state's net monitoring information
Standard is consistent.The present invention uses on the basis of to parameter models such as the voltage class of substation, connection type, interval types
Self-learning algorithm forms the structuring processing of substation information, provides good suggestion for auditor, significantly reduce careful
The workload and operating pressure of core personnel, saves the time, improves work efficiency.
Description of the drawings
Fig. 1 is the principle of the present invention schematic diagram.
Specific embodiment
The present invention will be further described with reference to embodiments.
A kind of Intelligent Decision-making Method in fortune supervisory control of substation information table, as shown in Figure 1, including the following steps:
Step 1, foundation state net typical information table, operation platform account and primary connection figure, build the parameter of substation
Mould establishes complete basis signal library.The underlying parameter of configuration monitoring information table includes power transformation station name, electricity in basis signal library
Press grade, connection type, compartment name, equipment principle/producer's model etc..
Step 2, the typical incidence relation for establishing substation-voltage class-connection type-interval-equipment.
Step 3 imports operation station information table.Operation station information table includes substation using Excel file, information table data
Information, interval information, facility information, monitoring of tools data etc..
Step 4 automatically extracts interval data according to operation station information table, monitoring information incorporated into specific interval automatically and
Equipment establishes the incidence relation of interval, equipment and monitoring data.
Step 5, the prioritization scheme that result and monitoring data mapping relations generating run station information table are disposed according to signal.
Step 6 is tracked and is automatically updated to the dynamic of operation station information table optimization situation.
It is emphasized that embodiment of the present invention is illustrative rather than limited, therefore present invention packet
Include the embodiment being not limited to described in specific embodiment, it is every by those skilled in the art according to the technique and scheme of the present invention
The other embodiment obtained, also belongs to the scope of protection of the invention.
Claims (3)
1. a kind of Intelligent Decision-making Method in fortune supervisory control of substation information table, it is characterised in that include the following steps:
Step 1, foundation electric power typical information table, operation platform account and primary connection figure, model the parameter of substation, build
Vertical complete basis signal library;
Step 2, the typical incidence relation for establishing substation-voltage class-connection type-interval-equipment;
Step 3 imports operation station information table;
Step 4 automatically extracts interval data according to operation station information table, automatically incorporates monitoring information to being specifically spaced and set into
It is standby, establish the incidence relation of interval, equipment and monitoring data;
Step 5, the prioritization scheme that result and monitoring data mapping relations generating run station information table are disposed according to signal;
Step 6 is tracked and is automatically updated to the dynamic of operation station information table optimization situation.
2. the Intelligent Decision-making Method according to claim 1 in fortune supervisory control of substation information table, it is characterised in that:The base
The underlying parameter of plinth signal library configuration monitoring information table includes power transformation station name, voltage class, connection type, compartment name, sets
Standby principle and equipment manufacturer's model.
3. the Intelligent Decision-making Method according to claim 1 in fortune supervisory control of substation information table, it is characterised in that:The fortune
Row station information table includes substation information, interval information, facility information and monitoring of tools data.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810275238.3A CN108197767A (en) | 2018-03-30 | 2018-03-30 | In the Intelligent Decision-making Method of fortune supervisory control of substation information table |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810275238.3A CN108197767A (en) | 2018-03-30 | 2018-03-30 | In the Intelligent Decision-making Method of fortune supervisory control of substation information table |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108197767A true CN108197767A (en) | 2018-06-22 |
Family
ID=62596499
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810275238.3A Pending CN108197767A (en) | 2018-03-30 | 2018-03-30 | In the Intelligent Decision-making Method of fortune supervisory control of substation information table |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108197767A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110378809A (en) * | 2019-07-29 | 2019-10-25 | 国网河北省电力公司 | A kind of intelligent check method of supervisory control of substation information table information data |
CN110502604A (en) * | 2019-08-26 | 2019-11-26 | 云南电网有限责任公司 | A kind of automatic method of disposal in the monitoring information table combing of fortune station |
CN110765986A (en) * | 2019-11-13 | 2020-02-07 | 云南电网有限责任公司普洱供电局 | Method for automatically auditing monitoring signals of main station of power system |
CN110888973A (en) * | 2019-11-18 | 2020-03-17 | 云南电网有限责任公司普洱供电局 | Method for automatically structuring and carding monitoring information table |
CN113535676A (en) * | 2021-06-07 | 2021-10-22 | 国网甘肃省电力公司白银供电公司 | Intelligent decision-making expert database system based on monitoring information and intelligent management and control method |
-
2018
- 2018-03-30 CN CN201810275238.3A patent/CN108197767A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110378809A (en) * | 2019-07-29 | 2019-10-25 | 国网河北省电力公司 | A kind of intelligent check method of supervisory control of substation information table information data |
CN110502604A (en) * | 2019-08-26 | 2019-11-26 | 云南电网有限责任公司 | A kind of automatic method of disposal in the monitoring information table combing of fortune station |
CN110502604B (en) * | 2019-08-26 | 2022-09-30 | 云南电网有限责任公司 | Automatic disposal method for combing monitoring information table in transport station |
CN110765986A (en) * | 2019-11-13 | 2020-02-07 | 云南电网有限责任公司普洱供电局 | Method for automatically auditing monitoring signals of main station of power system |
CN110888973A (en) * | 2019-11-18 | 2020-03-17 | 云南电网有限责任公司普洱供电局 | Method for automatically structuring and carding monitoring information table |
CN113535676A (en) * | 2021-06-07 | 2021-10-22 | 国网甘肃省电力公司白银供电公司 | Intelligent decision-making expert database system based on monitoring information and intelligent management and control method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108197767A (en) | In the Intelligent Decision-making Method of fortune supervisory control of substation information table | |
CN110378809A (en) | A kind of intelligent check method of supervisory control of substation information table information data | |
CN107330056B (en) | Wind power plant SCADA system based on big data cloud computing platform and operation method thereof | |
CN105095600B (en) | A kind of intelligent substation and regulation and control center cooperative modeling method | |
CN104808615A (en) | Method of automatically generating power device monitoring information table | |
CN101447698B (en) | Centralized type wave recording system of digital transformer substation | |
CN106532935B (en) | For carrying out the method and its system of secondary system of intelligent substation fault diagnosis | |
CN102255389B (en) | Method for implementing intensive intelligent substation based on intelligent power grid system | |
CN103310306B (en) | Wind electricity storage field integrated information management system for monitoring and monitoring management method | |
CN108282026A (en) | A kind of high-tension switch gear novel maintenance system | |
CN105117532A (en) | Modeling method for intelligent substation secondary equipment interval information model | |
CN101964542A (en) | Method for accessing IEC61970 dispatching EMS system to IEC61850 digital transformer substation | |
CN104123427A (en) | Regional distributed photovoltaic power generation system modeling method based on IEC61850 standard | |
CN103823920A (en) | Modeling and interaction method of dispatching automation system running supervision information | |
CN104538957A (en) | Power grid model self-adaptive processing method for counting low-frequency low-voltage load shedding capacity | |
CN108448721A (en) | The method of electric system main station monitoring signal and standard signal Auto-matching | |
CN210422883U (en) | Multi-wind-field fan electric centralized control system based on c/s framework | |
CN103501056A (en) | Regional and county integrated automatic voltage control system | |
WO2020052098A1 (en) | Hierarchical management system and method for centralized operation and maintenance of transformer substations, and computer storage medium | |
CN103049661B (en) | GIS remaining life appraisal procedure and system | |
CN108572983A (en) | The intelligent prompt method of data inputting in a kind of supervisory control of substation information table generating process | |
CN104299172A (en) | Power grid weak link comprehensive recognition method | |
CN213392511U (en) | State monitoring and intelligent decision making system for electrical equipment of wind power plant | |
CN206820478U (en) | Based on the uncertain wind-powered electricity generation regulator control system contributed of wind-powered electricity generation | |
CN115983548A (en) | Power distribution network intelligent planning method based on artificial intelligence technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180622 |
|
WD01 | Invention patent application deemed withdrawn after publication |