CN108166927B - It is a kind of for determining the appraisal procedure of horizontal well construction mode - Google Patents

It is a kind of for determining the appraisal procedure of horizontal well construction mode Download PDF

Info

Publication number
CN108166927B
CN108166927B CN201711391721.XA CN201711391721A CN108166927B CN 108166927 B CN108166927 B CN 108166927B CN 201711391721 A CN201711391721 A CN 201711391721A CN 108166927 B CN108166927 B CN 108166927B
Authority
CN
China
Prior art keywords
construction
horizontal well
section
horizontal
phi
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711391721.XA
Other languages
Chinese (zh)
Other versions
CN108166927A (en
Inventor
谌建祁
宁金生
陈琪
蒙启腾
王万庆
李小鹏
罗军营
刘李宏
王俊海
石崇东
王孝强
袁君
王浩
乔维
梁蛟龙
朱轩禄
单建雷
李富斌
李长远
王杰
赵福德
李刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Chuanqing Drilling Engineering Co Ltd
Original Assignee
Changqing Drilling Co of CNPC Chuanqing Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changqing Drilling Co of CNPC Chuanqing Drilling Engineering Co Ltd filed Critical Changqing Drilling Co of CNPC Chuanqing Drilling Engineering Co Ltd
Priority to CN201711391721.XA priority Critical patent/CN108166927B/en
Publication of CN108166927A publication Critical patent/CN108166927A/en
Application granted granted Critical
Publication of CN108166927B publication Critical patent/CN108166927B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/046Directional drilling horizontal drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/02Determining slope or direction
    • E21B47/022Determining slope or direction of the borehole, e.g. using geomagnetism
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/06Deflecting the direction of boreholes
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/10Correction of deflected boreholes

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Geophysics (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention relates to a kind of for determining the appraisal procedure of horizontal well construction mode, comprising the following steps: Step 1: obtaining horizontal well relevant parameter, relevant parameter includes k1、O、D、k2、L1、L2、L3、L4、μ、mg、α1、α2、α3、α4、G1、G2、G3、G4;Step 2: obtaining horizontal well construction degree-of-difficulty factor according to relevant parameter, wherein

Description

Evaluation method for judging construction mode of horizontal well
Technical Field
The invention relates to the field of drilling engineering in drilling of oil and natural gas horizontal wells, in particular to an evaluation method for judging a horizontal well construction mode.
Background
The horizontal well is communicated with a well section with relatively good permeability in a well hole with the length of hundreds of meters in a reservoir, the probability of crude oil and natural gas flowing into the well hole is increased, staged fracturing and blockage removal can be planned, and the horizontal well becomes an effective way for developing low-permeability oil and gas reservoirs and old oil and gas reservoirs. According to the development requirement of petroleum and natural gas, horizontal wells are developed from two-dimensional horizontal wells to three-dimensional horizontal wells, multi-branch horizontal wells and other special process wells. Along with the development of the three-dimensional horizontal well and the multi-branch horizontal well, the construction difficulty of the horizontal well is increased. In the prior art, the evaluation of the construction difficulty of the horizontal well is only difficult or simple in qualitative mode, and a method for comprehensively evaluating the construction difficulty of the horizontal well and a corresponding construction method do not exist. Therefore, certain waste of material resources, financial resources and manpower is caused to construction units; for wells with too high construction difficulty, an oil field company does not evaluate the comprehensive difficulty in the early construction period, and equipment and the prior art cannot meet the construction requirements or the prior art cannot achieve the development purpose, so that the development plan cannot be completed as required.
Disclosure of Invention
In order to solve the problems, the invention provides an evaluation method for judging the construction mode of a horizontal well, which can comprehensively evaluate the construction difficulty of special process wells such as the horizontal well, a branch horizontal well and the like and adopt an adaptive construction method according to the evaluation result, so that an oil field company can complete a development plan on time.
The technical scheme of the invention is as follows: an evaluation method for judging a construction mode of a horizontal well comprises the following steps:
step one, obtaining relevant parameters of the horizontal well, wherein the relevant parameters comprise k1、O、D、k2、L1、L2、L3、L4、μ、mg、α1、α2、α3、α4、G1、G2、G3、G4
Wherein k is1For actual dog leg degree of the inclination-increasing section, O is the offset distance, D is the vertical depth increment of the inclination-stabilizing deviation-correcting section, k2Is the actual dog leg degree of the torsional azimuth section, L1Length of straight well, L2For length of the correction segment, L3To increase the length of the ramp section, L4For horizontal section length, μ is the tool-to-borehole wall friction coefficient, mg is tool gravity, α1For vertical well section angle of inclination, α2To correct for section skew angle, α3For increasing slant angle of deviated section, α4Is horizontal section angle of inclination, G1Is the suspended weight of a vertical shaft section G2Suspended weight of the correction section, G3To increase the suspended weight of the ramp section, G4Is the hanging weight of the horizontal section;
step two, obtaining a horizontal well construction difficulty coefficient according to the relevant parameters,
wherein,
wherein K is the construction difficulty coefficient of the horizontal well, K'1For the maximum dog-leg degree of the oblique-increasing section,in order to make the friction resistance be good,is suspended weight, k'2Maximum dogleg degree of torsional azimuth segment, a1Is a first weight, a2Is a second weight;
step three, determining a horizontal well construction method according to the horizontal well construction difficulty coefficient,
when K is more than or equal to 0 and less than or equal to 0.3, the construction difficulty is simple, a simple construction method is adopted,
when K is more than 0.3 and less than or equal to 0.6, the construction difficulty is moderate, a common construction method is adopted,
when K is more than 0.6 and less than or equal to 1, the construction difficulty is complex, and a complex construction method is adopted.
A is a1=0.3,a2=0.2。
K is1’=20。
K is2’=20。
The above-mentioned
The above-mentioned
The invention has the beneficial effects that: by using the evaluation method, each parameter in the horizontal well is used as a calculation item, comparison is carried out according to the characteristic and the limiting value of each parameter, then weight distribution is carried out on each ratio in combination with site construction, before engineering deployment and construction, the construction difficulty of each horizontal well is comprehensively evaluated, and the construction method is selected, so that equipment and materials are reasonably allocated, the development risk of an oil field company is reduced, the economic loss of a construction unit is reduced, and the economic benefits of the oil field company and the construction unit are maximized.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The first embodiment is as follows:
an evaluation method for judging a construction mode of a horizontal well comprises the following steps:
step one, obtaining relevant parameters of the horizontal well, wherein the relevant parameters comprise k1、O、D、k2、L1、L2、L3、L4、μ、mg、α1、α2、α3、α4、G1、G2、G3、G4
Wherein k is1For actual dog leg degree of the inclination-increasing section, O is the offset distance, D is the vertical depth increment of the inclination-stabilizing deviation-correcting section, k2Is the actual dog leg degree of the torsional azimuth section, L1Length of straight well, L2For length of the correction segment, L3To increase the length of the ramp section, L4For horizontal section length, μ is the tool-to-borehole wall friction coefficient, mg is tool gravity, α1For vertical well section angle of inclination, α2To correct for section skew angle, α3For increasing slant angle of deviated section, α4Is horizontal section angle of inclination, G1Is the suspended weight of a vertical shaft section G2Suspended weight of the correction section, G3To increase the suspended weight of the ramp section, G4Is the hanging weight of the horizontal section;
step two, obtaining a horizontal well construction difficulty coefficient according to the relevant parameters,
wherein,
wherein K is the construction difficulty coefficient of the horizontal well, K'1For the maximum dog-leg degree of the oblique-increasing section,in order to make the friction resistance be good,is suspended weight, k'2Maximum dogleg degree of torsional azimuth segment, a1Is a first weight, a2Is a second weight;
step three, determining a horizontal well construction method according to the horizontal well construction difficulty coefficient,
when K is more than or equal to 0 and less than or equal to 0.3, the construction difficulty is simple, a simple construction method is adopted,
when K is more than 0.3 and less than or equal to 0.6, the construction difficulty is moderate, a common construction method is adopted,
when K is more than 0.6 and less than or equal to 1, the construction difficulty is complex, and a complex construction method is adopted.
The influence on the construction of the three-dimensional horizontal well of the Changqing compact gas reservoir mainly comprises four factors:
1. the target fore distance (the influence of the dog leg degree and the build rate on the construction difficulty is reflected);
2. offset distance (the influence of the offset distance on the construction difficulty is reflected by the deflection ratio);
3. total horizontal displacement (the total horizontal displacement is the sum of the absolute values of the offset distance and the apparent translation, and the influence of the total horizontal displacement on the construction difficulty is reflected by friction resistance and hanging weight);
4. the orientation difficulty (the influence of the dogleg degree and the build rate on the construction difficulty) is reflected.
In the construction of the inclined shaft section of the horizontal well for the dense gas reservoir in Changqing, the build-up rate of a single-bending screw rod of 1.5 degrees matched with a PDC drill bit is 30 degrees/100 m (the build-up rate is the full bending angle of a drill hole formed in a unit build-up drilling advancing rule, the dogleg degree is the angle from one point in the well hole to another point, the advancing direction of the well hole changes, the build-up rate is equal to the value of the corresponding dogleg degree, the following encountered conditions are the same, and theoretically, the construction can be carried out as long as the average build-up rate of the inclined shaft section is less than 30 degrees/100 m.
In the construction of the three-dimensional horizontal well, the longer the total horizontal displacement (the sum of the offset distance and the apparent translation), the greater the construction difficulty, when the total displacement reaches a certain value, the frictional resistance of the drilling tool is equal to the hanging weight value of the drilling tool during sliding, the subsequent construction cannot be carried out, and the frictional resistance is in direct proportion to the well offset distance and the apparent translation, so that the frictional resistance value of the well and the hanging weight ratio of the drilling tool are used as one judgment value of the method for comprehensively evaluating the construction difficulty of the horizontal well.
In the three-dimensional horizontal well deviation rectifying construction, after the deviation of a stable deviation well reaches 30 degrees, the deviation rectifying construction difficulty is high, and the construction efficiency is poor, so that the actual deviation ratio and the tg30 degree ratio are used as one judgment value of the method for comprehensively evaluating the horizontal well construction difficulty. The sag in the sag ratio here is the effective sag, i.e.: the vertical depth of the middle target is increased, the first inclination increasing short section is increased, and the second inclination increasing section is increased vertically.
When the three-dimensional horizontal well is constructed in the deviation rectifying and twisting direction, the ratio of the dog leg degree generated in the twisting direction to the average maximum dog leg degree in construction is used as one judgment value of the method for comprehensively evaluating the construction difficulty of the horizontal well, like the deflection increasing section.
By obtaining each parameter value in the construction of the horizontal well, namely the actual dog leg degree (k) of the deflection increasing section1) Offset (O), vertical increment of steady slope (D), friction resistanceSuspended weightAnd calculating a horizontal well construction difficulty coefficient (K), and determining a corresponding construction method according to the difficulty coefficient (K). Wherein K is less than or equal to 1, and the construction degree of difficulty is less when the K value is littleer, and when the K value is bigger, the construction degree of difficulty is bigger, and when K equals 1, the construction degree of difficulty reaches the biggest. According to the long-term practical construction situation, the construction difficulty is divided into three grades, namely simple (when K is more than or equal to 0 and less than or equal to 0.3), medium (when K is more than 0.3 and less than or equal to 0.6) and complex (when K is more than 0.6 and less than or equal to 1), a simple construction method, a general construction method and a complex construction method are correspondingly adopted, and different construction methods correspond to different drilling tool combinations and drilling fluid systems.
By adopting the construction method, each parameter in the horizontal well is used as a calculation item, comparison is carried out according to the characteristics and the limiting value of each parameter, and then weight distribution is carried out on each ratio in combination with site construction. Before engineering deployment and construction, the construction difficulty of each horizontal well is comprehensively evaluated, so that equipment and materials are reasonably allocated, the development risk of an oil field company is reduced, the economic loss of a construction unit is reduced, and the economic benefits of the oil field company and the construction unit are maximized.
Example two:
a is a1=0.3,a2=0.2。
K is1’=20。
K is2’=20。
The above-mentioned
The above-mentioned
In the construction of the inclined shaft section of the horizontal well of the dense gas reservoir in Changqing, the build-up rate of a PDC drill bit matched with a 1.5-degree single-bending screw is 30 degrees/100 m (the build-up rate is the full bending angle of a drill hole formed in a unit build-up drilling footage, the dogleg degree is the angle from one point in the well hole to another point, the change angle of the advancing direction of the well hole is equal to the numerical value of the corresponding dogleg degree, the following encountered conditions are the same, theoretically, the construction can be carried out as long as the average build-up rate of the inclined shaft section is less than 30 degrees/100 m, but in the actual construction, the construction is influenced by factors such as strata, screws, drill bits, drilling fluid and the like, the actual build-up rate can not reach the theoretical build-up rate, and the continuous sliding drilling of the whole shaft section is unrealistic, so when the average build-up rate of the inclined shaft section reaches 20 degrees/100 m in the actual, the average maximum dog leg degree in construction is 20 degrees/100 m, and the actual increasing rate k of each well is used1And the ratio of 20 is used as one judgment value of the method for comprehensively evaluating the construction difficulty of the horizontal well.
When the three-dimensional horizontal well is constructed in the deviation rectifying and twisting direction, the ratio of the dog-leg degree generated in the twisting direction to the average maximum dog-leg degree (20 degrees/100 m) in construction is used as one judgment value of the method for comprehensively evaluating the construction difficulty of the horizontal well, as in the deflection increasing section.
According to the influence of each parameter on the construction difficulty in the actual construction, carrying out grade quantization weight distribution and determining a first weight (a)1) Is 0.3, second weight (a)2) And the number is 0.2, so that each parameter can more scientifically reflect the construction difficulty.
I.e. according to the formulaAnd calculating the construction difficulty coefficient (K) of the horizontal well.
The simple construction method is that a drill tool combination of a phi 215.9mm diamond compact drill bit, a phi 165mm screw drill tool (1.35 degrees), a phi 165mm back pressure valve, a phi 165mm wireless instrument connector, a phi 165mm non-magnetic drill collar, a phi 165 matched connector, a phi 127mm weighted drill rod and a phi 127mm drill rod is adopted in the inclined shaft section.
In the horizontal section, a drill tool combination of a phi 152.4mm diamond compact drill bit, a phi 127mm screw drill tool (1.0 degrees), a phi 148mm centralizer, a phi 120mm back pressure valve, a phi 127mm wireless instrument connector, a phi 120mm non-magnetic drill collar, a phi 120mm conversion connector, a phi 101.6mm weighted drill rod, a phi 101.6mm weighted drill rod and a phi 101.6mm drill rod is adopted.
The mud system adopts a composite salt drilling fluid system.
The general construction method is that a drill tool combination of a phi 215.9mm diamond compact drill bit, a phi 165mm screw drill tool (1.5 degrees), a phi 165mm back pressure valve, a phi 165mm wireless instrument connector, a phi 165mm non-magnetic drill collar, a phi 165 matched connector, a phi 127mm weighted drill rod and a phi 127mm drill rod is adopted in an inclined shaft section.
In the horizontal section, a drill tool combination of a phi 152.4mm diamond compact drill bit, a phi 127 screw drill (1.25 degrees), a phi 148mm centralizer, a phi 120mm back pressure valve, a phi 127mm wireless instrument connector, a phi 120mm non-magnetic drill collar, a phi 120mm conversion connector, a phi 101.6mm weighted drill rod, a phi 101.6mm weighted drill rod and a phi 101.6mm drill rod is adopted.
The mud system adopts a composite salt drilling fluid system.
The difference between the general construction method and the simple construction method is that a phi 165mm screw drilling tool (1.35 degrees) is changed into a phi 165mm screw drilling tool (1.5 degrees) in an inclined shaft section, and a phi 127mm screw drilling tool (1.0 degrees) is changed into a phi 127 screw drilling tool (1.25 degrees) in a horizontal section.
The complex construction method is that a drilling tool combination of a phi 215.9mm diamond compact bit (or a phi 215.9mm tricone bit) plus a phi 165mm screw drilling tool (1.5 degrees), a phi 165mm back pressure valve, a phi 165mm wireless instrument connector, a phi 165mm non-magnetic drill collar, a phi 165 matched connector, a phi 127mm weighted drilling rod and a phi 127mm drilling rod is adopted in the inclined shaft section.
In the horizontal section, a drill tool combination of a phi 152.4mm diamond compact drill bit (or a phi 215.9mm tricone drill bit), a phi 127 screw drill tool (1.25 degrees), a phi 148mm centralizer, a phi 120mm return pressure valve, a phi 127mm wireless instrument connector, a phi 120mm non-magnetic drill collar, a phi 120mm conversion connector, a phi 101.6mm weighted drill rod, a phi 120mm hydraulic oscillator, a phi 101.6mm drill rod, a phi 101.6mm weighted drill rod and a phi 101.6mm drill rod is adopted.
The mud system adopts a composite salt drilling fluid system or an oil-based drilling fluid system which are matched with each other.
The complicated construction method is different from the common construction method in that a hydraulic oscillator with phi 120mm is added in the horizontal section of the complicated construction method, and a mud system is changed from a composite salt drilling fluid system to a composite salt drilling fluid system or an oil-based drilling fluid system and is used in a matched manner.
It should be noted that the technical solutions in the embodiments may be combined with each other, but must be realized by those skilled in the art, and when the technical solutions are contradictory or cannot be realized, such a combination of the technical solutions should not be considered to exist, and is not within the protection scope of the present invention.

Claims (6)

1. An evaluation method for judging a construction mode of a horizontal well comprises the following steps:
step one, obtaining relevant parameters of the horizontal well, wherein the relevant parameters comprise k1、O、D、k2、L1、L2、L3、L4、μ、mg、α1、α2、α3、α4、G1、G2、G3、G4
Wherein k is1For increasing actual dogleg degree of slope section, O is offset distance, D is slope stabilizing and correcting sectionVertical depth increment, k2Is the actual dog leg degree of the torsional azimuth section, L1Length of straight well, L2For length of the correction segment, L3To increase the length of the ramp section, L4For horizontal section length, μ is the tool-to-borehole wall friction coefficient, mg is tool gravity, α1For vertical well section angle of inclination, α2To correct for section skew angle, α3For increasing slant angle of deviated section, α4Is horizontal section angle of inclination, G1Is the suspended weight of a vertical shaft section G2Suspended weight of the correction section, G3To increase the suspended weight of the ramp section, G4Is the hanging weight of the horizontal section;
step two, obtaining a horizontal well construction difficulty coefficient according to the relevant parameters,
wherein,
wherein K is the construction difficulty coefficient of the horizontal well, K'1For the maximum dog-leg degree of the oblique-increasing section,in order to make the friction resistance be good,is suspended weight, k'2Maximum dogleg degree of torsional azimuth segment, a1Is a first weight, a2Is a second weight;
step three, determining a horizontal well construction method according to the horizontal well construction difficulty coefficient,
when K is more than or equal to 0 and less than or equal to 0.3, the construction difficulty is simple, a simple construction method is adopted,
when K is more than 0.3 and less than or equal to 0.6, the construction difficulty is moderate, a common construction method is adopted,
when K is more than 0.6 and less than or equal to 1, the construction difficulty is complex, and a complex construction method is adopted.
2. The evaluation method for judging the construction mode of the horizontal well according to claim 1, which is characterized by comprising the following steps of: a is a1=0.3,a2=0.2。
3. The evaluation method for judging the construction mode of the horizontal well according to claim 1, which is characterized by comprising the following steps of: k 'to'1=20。
4. The evaluation method for judging the construction mode of the horizontal well according to claim 1, which is characterized by comprising the following steps of: k 'to'2=20。
5. The evaluation method for judging the construction mode of the horizontal well according to claim 1, which is characterized by comprising the following steps of: the above-mentioned
6. The evaluation method for judging the construction mode of the horizontal well according to claim 1, which is characterized by comprising the following steps of: the above-mentioned
CN201711391721.XA 2017-12-21 2017-12-21 It is a kind of for determining the appraisal procedure of horizontal well construction mode Active CN108166927B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711391721.XA CN108166927B (en) 2017-12-21 2017-12-21 It is a kind of for determining the appraisal procedure of horizontal well construction mode

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711391721.XA CN108166927B (en) 2017-12-21 2017-12-21 It is a kind of for determining the appraisal procedure of horizontal well construction mode

Publications (2)

Publication Number Publication Date
CN108166927A CN108166927A (en) 2018-06-15
CN108166927B true CN108166927B (en) 2019-06-04

Family

ID=62522907

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711391721.XA Active CN108166927B (en) 2017-12-21 2017-12-21 It is a kind of for determining the appraisal procedure of horizontal well construction mode

Country Status (1)

Country Link
CN (1) CN108166927B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112681978B (en) * 2019-10-18 2022-11-11 中国石油天然气集团有限公司 Tilt stabilizing control method for rotary guide system
CN114382427A (en) * 2021-12-31 2022-04-22 中国石油天然气集团有限公司 Horizontal well debris bed treatment method and device
CN116029528B (en) * 2023-02-17 2024-01-23 惠州华厦工程咨询有限公司 Intelligent management platform for building engineering data information

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1936264A (en) * 2005-09-20 2007-03-28 中国石油化工股份有限公司 Method for designing well-drilling borehole track
CN101173598A (en) * 2006-10-31 2008-05-07 中国石油化工股份有限公司 Funicular curve well drilling rail design method using stratum natural deflecting rule
CN103993830A (en) * 2014-05-13 2014-08-20 中国石油化工股份有限公司 Method for determining medium-and-large-radius track of two-dimensional small-pre-target-displacement horizontal well
CN104481400A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well borehole track controlling method
CN104481398A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well drilling construction method
CN104615803A (en) * 2014-12-10 2015-05-13 中国石油化工股份有限公司 Three-dimensional horizontal well borehole trajectory design method and system
CN104747165A (en) * 2015-01-27 2015-07-01 中国石油天然气股份有限公司 Three-dimensional horizontal well body profile design method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1936264A (en) * 2005-09-20 2007-03-28 中国石油化工股份有限公司 Method for designing well-drilling borehole track
CN101173598A (en) * 2006-10-31 2008-05-07 中国石油化工股份有限公司 Funicular curve well drilling rail design method using stratum natural deflecting rule
CN103993830A (en) * 2014-05-13 2014-08-20 中国石油化工股份有限公司 Method for determining medium-and-large-radius track of two-dimensional small-pre-target-displacement horizontal well
CN104481400A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well borehole track controlling method
CN104481398A (en) * 2014-12-10 2015-04-01 中国石油化工股份有限公司 Three-dimensional (3D) horizontal well drilling construction method
CN104615803A (en) * 2014-12-10 2015-05-13 中国石油化工股份有限公司 Three-dimensional horizontal well borehole trajectory design method and system
CN104747165A (en) * 2015-01-27 2015-07-01 中国石油天然气股份有限公司 Three-dimensional horizontal well body profile design method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
C2256长靶前位移侧钻水平井水平段轨迹控制;闫友勇等;《新疆石油科技》;20110331;第21卷(第1期);第12-15页
延长油田特殊地貌条件下水平井钻井技术难点与对策;李伟峰等;《非常规油气》;20170831;第4卷(第4期);第102-106页

Also Published As

Publication number Publication date
CN108166927A (en) 2018-06-15

Similar Documents

Publication Publication Date Title
CN104481400B (en) A kind of three-dimensional horizontal well track control method
Augustine et al. A comparison of geothermal with oil and gas well drilling costs
Payne et al. Critical technologies for success in extended reach drilling
Polsky et al. Enhanced geothermal systems (EGS) well construction technology evaluation report
CN108166927B (en) It is a kind of for determining the appraisal procedure of horizontal well construction mode
CN109915018B (en) Method for determining tool face angle in three-dimensional borehole trajectory control
Dumas et al. Report on geothermal drilling
Xia et al. Key technologies for well drilling and completion in ultra-deep sour gas reservoirs, Yuanba Gasfield, Sichuan Basin
Sonowal et al. How continuous improvement lead to the longest horizontal well in the world
Janwadkar et al. BHA and Drillstring Modeling Maximizes Drilling Performance in Lateral Wells of Barnett Shale Gas Field of N. Texas
Gelfgat et al. Drillstring with aluminum alloy pipes design and practices
Glebov et al. Yurkharovskoye extended reach drilling campaign resulted in the successful completion of record multilateral well
Rezmer-Cooper et al. Field data supports the use of stiffness and tortuosity in solving complex well design problems
CN114635654A (en) Method, system, device and computer readable storage medium for determining well cleanliness
Alkhaldy et al. Innovative Approach in Sidetracking Wells in Kuwait Brown Field Development Reduces Drilling Hazards and Improves Well Productivity
Bhatkar et al. Casing While Drilling
Eddison et al. Downhole adjustable gauge stabilizer improves drilling efficiency in directional wells
Kuznetcov ROP optimization and modelling in directional drilling process
Newton et al. A Case Study Comparison of Wells Drilled With and Without MWD Directional Surveys on the Claymore Platform in the North Sea
Thomas et al. Overcoming Weight Transfer Challenges in Complex, Shallow, Extended Reach Wells on Alaska's North Slope.
Fu et al. Research of Drilling and Completion Technologies for Heavy Oil in Venezuela and Offshore Presalt Hydrocarbons in Brazil
O’Bryan et al. A study of the effects of bit gauge length and stabilizer placement on the build and drop tendencies of PDC bits
Leaf et al. A Review of Horizontal Methods and Drilling Technology
Bertarelli et al. Margarita 10: Drilling Strategy of the Fastest Well in the Bolivian Sub-Andean Region
Bryant et al. Applications and Limitations of Horizontal Drilling in Oklahoma

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20211018

Address after: 100007 Oil Mansion, 9 North Avenue, Dongcheng District, Beijing, Dongzhimen

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC CHUANQING DRILLING ENGINEERING Co.,Ltd.

Address before: Room 1902, Changqing building, 151 Weiyang Road, Xi'an, Shaanxi 710018

Patentee before: CNPC CHUANQING DRILLING ENGINEERING CO., LTD. CHANGQING WELL DRILLING GENERAL Co.

TR01 Transfer of patent right