CN108150175A - Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam - Google Patents
Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam Download PDFInfo
- Publication number
- CN108150175A CN108150175A CN201810006170.9A CN201810006170A CN108150175A CN 108150175 A CN108150175 A CN 108150175A CN 201810006170 A CN201810006170 A CN 201810006170A CN 108150175 A CN108150175 A CN 108150175A
- Authority
- CN
- China
- Prior art keywords
- shaft
- dead zone
- wall
- coal seam
- supporting construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/04—Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
Abstract
The invention discloses the supporting construction that shaft of vertical well passes through the old dead zone in coal seam, belong to vertical supporting field;The technical problem to be solved is that being filled after providing a kind of Shaft Linings to shaft of vertical well, top plate and bottom plate are reinforced, prevent back and two from helping the supporting construction destroyed, be caving;Solve technical solution that the technical problem uses for:Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam, and wall seat is increased newly in the excessively mined out section base slab stability rock stratum of vertical;It crosses empty well wall and wall seat and supporting is poured into a mould using armored concrete, work stone pier is set in goaf, the dead zone between work stone pier and the borehole wall carries out grouting filling to roof absciss layer area using slabstone slurry placement using high molecular bonding material;It the composite can be widely applied to vertical supporting field.
Description
Technical field
Shaft of vertical well of the present invention passes through the supporting construction of the old dead zone in coal seam, belongs to vertical support technology field.
Background technology
Existing shaft of vertical well passes through the old dead zone in coal seam, generally using drain hole draining and excludes pernicious gas, wedge of driving piles
Advance support is carried out, anchor net is studied and walling crib backboard carries out gib, pouring reinforcement concrete arch carries out permanent support, simultaneously
Carry out grouting behind shaft or drift lining, prevent the borehole wall from water drenching occur, but the top plate in old dead zone tunnel is not reinforced, after Shaft Linings dead zone not into
Row filling causes back and two to help the phenomenon that appearance is destroyed, is caving in construction more, has made shaft of vertical well and constructed
Can not be according to normal supporting in engineering, supporting is not in place, be easy to cause safety accident.
Invention content
The invention overcomes the deficiencies of the prior art, and provides being filled after a kind of Shaft Linings to shaft of vertical well,
Top plate and bottom plate are reinforced, prevent back and two from helping the supporting construction destroyed, be caving.
In order to solve the above-mentioned technical problem, the technical solution adopted by the present invention is:Shaft of vertical well passes through the old dead zone in coal seam
Supporting construction, including wall seat, work stone pier, grouted anchor bar and concrete, wall seat is arranged on the stabilization rock stratum below seat earth
On, work stone pier is arranged in coal seam goaf, and grouted anchor bar is disposed on roof absciss layer area, carries out bolt grouting,
Shaft wall and wall seat are poured using concrete;
Work stone pier is 3m ~ 5m apart from shaft wall outer distance, and the goaf between work stone pier and shaft wall carries out
Filling.
Reinforcing bar is provided in the shaft wall, the concrete Quan labels are not less than C30, the Concrete Thick
It spends for 50mm.
Goaf filling between the work stone pier and shaft wall uses slabstone mortar.
Roof absciss layer area's slip casting uses high molecular bonding material.
Pre-buried drainpipe is provided between the shaft of vertical well wall seat and work stone pier.
The present invention has the advantages that compared with prior art.
The 1st, work stone pier is set in goaf, work stone pier and the borehole wall outer distance are 3 ~ 5m, while work stone pier with
Borehole wall outer goaf is filled, and increases stability and safety of the tunnel in old dead zone.
2nd, grouted anchor bar is set in roof absciss layer area, to roof delamination area slip casting high molecular bonding material, increases
The stability of top plate, prevents roof caving, convenient for construction, increases safety.
Description of the drawings
The present invention is described further below in conjunction with the accompanying drawings.
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is the structure diagram of wall seat.
1 it is wall seat in figure, 2 be work stone pier, 3 be grouted anchor bar, 4 be concrete, 5 be roof delamination area, 6 is mined out
Area, 7 be bottom plate, 8 be stablize rock stratum, 9 be pre-buried drainpipe, 10 be slabstone mortar, 11 be shaft wall.
Specific embodiment
As shown in Figure 1 and Figure 2, shaft of vertical well of the present invention passes through the supporting construction of the old dead zone in coal seam, including wall seat 1, work stone wall
Pile 2, grouted anchor bar 3 and concrete 4, wall seat 1 are arranged on the stabilization rock stratum 8 of 7 lower section of seat earth, and work stone pier 2 is arranged on
In coal seam goaf 6, grouted anchor bar 3 is disposed on 5th area of roof absciss layer, carries out bolt grouting, shaft wall 11 and wall
Seat 1 is poured using concrete 4, and work stone pier 2 is 3m ~ 5m apart from shaft wall outer distance, to work stone pier 2 and vertical
Goaf 6 between the borehole wall 11 is filled, and reinforcing bar is provided in shaft wall 11, and the 4 Quan labels of concrete are not low
In C30,4 thickness of concrete is 50mm, and the filling of goaf 6 between work stone pier 2 and shaft wall 11 uses piece
Stone sand slurry 10,5 slip casting of roof absciss layer area uses high molecular bonding material, shaft of vertical well wall seat 1 and work stone pier 2 it
Between be provided with pre-buried drainpipe 9.
In the use of the present invention, being symmetrical arranged wall seat 1 in stabilization rock stratum 8 below seat earth 7, wall seat 1 uses steel
Reinforced concrete pours, and disclosed broken, soft coal body rock mass is taken down, and carries out gib using anchor net, carries out
It constructs in next step, the setting work stone pier 2 in the goaf 6, work stone pier 2 is 3m ~ 5m apart from 11 outer of shaft wall distance, wall
The height and thickness of pile are adjusted according to field condition, and the dead zone between work stone pier 2 and shaft wall 11 uses slabstone
Mortar 10 is filled, and the borehole wall is poured using armored concrete, and borehole wall surface uses gunite concrete strengthening supporting, together
When reduce ventilation resistance, strength grade of concrete is not lower than C30, thickness 50mm, and anchor is carried out in roof absciss layer area 5
Bar slip casting injects high molecular bonding material, the rock in roof delamination area 5 is bonded, and prevents destruction and slump, influences construction peace
Entirely, the safety of shaft of vertical well is increased.
The embodiment of the present invention is explained in detail above in conjunction with attached drawing, but the present invention is not limited to above-mentioned implementations
Example, within the knowledge of a person skilled in the art, can also make under the premise of present inventive concept is not departed from
Go out various change.
Claims (5)
1. shaft of vertical well passes through the supporting construction of the old dead zone in coal seam, it is characterised in that:Including wall seat(1), work stone pier(2), note
Starch anchor pole(3)And concrete(4), wall seat(1)It is arranged on seat earth(7)The stabilization rock stratum of lower section(8)On, work stone pier(2)
It is arranged on coal seam goaf(6)It is interior, grouted anchor bar(3)It is disposed on roof absciss layer(5)Area carries out bolt grouting, stands
The well borehole wall(11)With wall seat(1)Use concrete(4)It is poured;
Work stone pier(2)Apart from shaft wall outer, distance is 3m ~ 5m, to work stone pier(2)With shaft wall(11)Between
Goaf(6)It is filled.
2. shaft of vertical well according to claim 1 passes through the supporting construction of the old dead zone in coal seam, it is characterised in that:Described is vertical
The well borehole wall(11)Inside it is provided with reinforcing bar, the concrete(4)Quan labels are not less than C30, the concrete(4)Thickness is
50mm。
3. shaft of vertical well according to claim 1 passes through the supporting construction of the old dead zone in coal seam, it is characterised in that:The material
Stone walling pile(2)With shaft wall(11)Between goaf(6)Filling uses slabstone mortar(10).
4. shaft of vertical well according to claim 1 passes through the supporting construction of the old dead zone in coal seam, it is characterised in that:The coal
Floor roof delamination area(5)Slip casting uses high molecular bonding material.
5. shaft of vertical well according to claim 1 passes through the supporting construction of the old dead zone in coal seam, it is characterised in that:Described is vertical
Well shaft wall seat(1)With work stone pier(2)Between be provided with pre-buried drainpipe(9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810006170.9A CN108150175A (en) | 2018-01-04 | 2018-01-04 | Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810006170.9A CN108150175A (en) | 2018-01-04 | 2018-01-04 | Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108150175A true CN108150175A (en) | 2018-06-12 |
Family
ID=62460648
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810006170.9A Pending CN108150175A (en) | 2018-01-04 | 2018-01-04 | Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108150175A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109184752A (en) * | 2018-09-29 | 2019-01-11 | 陕西陕煤黄陵矿业有限公司 | A kind of coal mine supporting construction and its method for protecting support for passing through old kiln goaf |
CN110331994A (en) * | 2019-04-30 | 2019-10-15 | 宁夏久威矿山安全工程有限责任公司 | A kind of digging laneway absciss layer breaking roof water drenching control method |
CN110424968A (en) * | 2019-07-04 | 2019-11-08 | 北京科技大学 | A kind of pit shaft reinforcement means based on anchor note anti-corrosion measure |
CN113847036A (en) * | 2021-10-25 | 2021-12-28 | 安徽理工大学 | Double-wall seat structure for deep drilling shaft after well wall bottom breaking and construction method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071940A (en) * | 2010-12-31 | 2011-05-25 | 大同煤矿集团有限责任公司 | Construction method for mine shaft through multilayer goaf |
CN103835723A (en) * | 2013-11-11 | 2014-06-04 | 北京中煤矿山工程有限公司 | Comprehensive pretreatment method for shaft penetration in mined-out area stratum |
CN104389634A (en) * | 2014-09-16 | 2015-03-04 | 中国矿业大学 | Mine vertical shaft/sieve shaft well wall structure and controllable dewatering method thereof |
CN104612695A (en) * | 2015-01-29 | 2015-05-13 | 湖南科技大学 | Repairing and reinforcing method for vertical shaft wall collapsed fiercely |
CN106246188A (en) * | 2016-10-18 | 2016-12-21 | 中国矿业大学 | The system and method that the preventing and treating coal mine shaft lining shaft deformation of stratum settlement compatibility of deformation is destroyed |
-
2018
- 2018-01-04 CN CN201810006170.9A patent/CN108150175A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102071940A (en) * | 2010-12-31 | 2011-05-25 | 大同煤矿集团有限责任公司 | Construction method for mine shaft through multilayer goaf |
CN103835723A (en) * | 2013-11-11 | 2014-06-04 | 北京中煤矿山工程有限公司 | Comprehensive pretreatment method for shaft penetration in mined-out area stratum |
CN104389634A (en) * | 2014-09-16 | 2015-03-04 | 中国矿业大学 | Mine vertical shaft/sieve shaft well wall structure and controllable dewatering method thereof |
CN104612695A (en) * | 2015-01-29 | 2015-05-13 | 湖南科技大学 | Repairing and reinforcing method for vertical shaft wall collapsed fiercely |
CN106246188A (en) * | 2016-10-18 | 2016-12-21 | 中国矿业大学 | The system and method that the preventing and treating coal mine shaft lining shaft deformation of stratum settlement compatibility of deformation is destroyed |
Non-Patent Citations (2)
Title |
---|
崔永红: "立井井筒过含水老空巷综合支护及堵水技术", 《煤炭工程》 * |
白玉龙: ""回风立井过空巷支护技术研究", 《山西焦煤科技》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109184752A (en) * | 2018-09-29 | 2019-01-11 | 陕西陕煤黄陵矿业有限公司 | A kind of coal mine supporting construction and its method for protecting support for passing through old kiln goaf |
CN110331994A (en) * | 2019-04-30 | 2019-10-15 | 宁夏久威矿山安全工程有限责任公司 | A kind of digging laneway absciss layer breaking roof water drenching control method |
CN110331994B (en) * | 2019-04-30 | 2023-08-15 | 宁夏久威矿山安全工程有限责任公司 | Method for preventing and controlling water spraying of separation broken roof of tunneling roadway |
CN110424968A (en) * | 2019-07-04 | 2019-11-08 | 北京科技大学 | A kind of pit shaft reinforcement means based on anchor note anti-corrosion measure |
CN110424968B (en) * | 2019-07-04 | 2020-07-17 | 北京科技大学 | Shaft reinforcing method based on anchoring and grouting anti-corrosion measures |
CN113847036A (en) * | 2021-10-25 | 2021-12-28 | 安徽理工大学 | Double-wall seat structure for deep drilling shaft after well wall bottom breaking and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105239586B (en) | Method for supporting foundation pit by adopting support structure | |
CN101886545B (en) | Method for treating bottom heave of soft rock roadway by using micro broken stone pipe cast pile | |
CN202969392U (en) | Complex geology deep excavation pit combined support | |
CN106522270B (en) | A kind of the pile foundation barricade antidetonation retaining structure and construction method of the buffer layer containing EPS | |
CN108150175A (en) | Shaft of vertical well passes through the supporting construction of the old dead zone in coal seam | |
CN205742213U (en) | Foundation pit supporting construction | |
CN102226403A (en) | Construction method of large-span subway station main body by using arched cover method and station main body structure | |
CN106759376B (en) | For closing on the construction method of the Anchored Sheet Pile Wall for Excavation system of existing underground structure | |
CN104763435B (en) | Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area | |
CN201991017U (en) | Subway large-span station body structure based on arch cover method construction forming | |
CN206859232U (en) | A kind of inclined steel-pipe pile anchor structure | |
CN105569726A (en) | Gob-side entry retaining method for GFRP (Glass Fiber Reinforced Polymer) tube concrete pier stud and gangue concrete wall | |
CN109595029B (en) | Goaf partial stowage supporting structure and its construction method under the conditions of tight roof | |
CN102828518A (en) | Manual hole digging support pile prestress anchor cable anchoring structure and construction method of anchoring structure | |
CN108798702A (en) | A kind of method for protecting support of big cross section large-deformation tunnel in soft rock | |
CN108915700A (en) | A kind of association type Floor Heave in Roadway administering method | |
CN107503362A (en) | A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability | |
CN105484763B (en) | A kind of semiclosed reinforced concrete segment method for protecting support of deep coalmine | |
CN105926667A (en) | Retaining wall | |
CN107964980A (en) | Lattice counterfort wall and construction method with earth anchor | |
CN102330436A (en) | Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank | |
CN105649106B (en) | The retaining wall structure and its construction method of steel pipe bone rib | |
CN106567391B (en) | A kind of flat building enclosure of rocky stratum subway entrance sectional type molten steel and construction method | |
CN107165173A (en) | A kind of foundation pit supporting system and its construction method | |
CN109882205A (en) | It is a kind of to pass through large-scale suspention backfill structure and construction method without filling solution cavity tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180612 |
|
RJ01 | Rejection of invention patent application after publication |