CN108127895A CN201711492341.5A CN201711492341A CN108127895A CN 108127895 A CN108127895 A CN 108127895A CN 201711492341 A CN201711492341 A CN 201711492341A CN 108127895 A CN108127895 A CN 108127895A
Authority
CN
China
Prior art keywords
water
water tank
outlet
circulation
cooling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711492341.5A
Other languages
Chinese (zh)
Inventor
侯新源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201711492341.5A priority Critical patent/CN108127895A/en
Publication of CN108127895A publication Critical patent/CN108127895A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C48/00Extrusion moulding, i.e. expressing the moulding material through a die or nozzle which imparts the desired form; Apparatus therefor
    • B29C48/25Component parts, details or accessories; Auxiliary operations
    • B29C48/92Measuring, controlling or regulating
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D29/00Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/01Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor with flat filtering elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D29/00Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor
    • B01D29/50Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor with multiple filtering elements, characterised by their mutual disposition
    • B01D29/56Filters with filtering elements stationary during filtration, e.g. pressure or suction filters, not covered by groups B01D24/00 - B01D27/00; Filtering elements therefor with multiple filtering elements, characterised by their mutual disposition in series connection
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C48/00Extrusion moulding, i.e. expressing the moulding material through a die or nozzle which imparts the desired form; Apparatus therefor
    • B29C48/25Component parts, details or accessories; Auxiliary operations
    • B29C48/88Thermal treatment of the stream of extruded material, e.g. cooling
    • B29C48/911Cooling
    • B29C48/9115Cooling of hollow articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C2948/00Indexing scheme relating to extrusion moulding
    • B29C2948/92Measuring, controlling or regulating
    • B29C2948/92504Controlled parameter
    • B29C2948/92704Temperature
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29CSHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
    • B29C2948/00Indexing scheme relating to extrusion moulding
    • B29C2948/92Measuring, controlling or regulating
    • B29C2948/92819Location or phase of control
    • B29C2948/92923Calibration, after-treatment or cooling zone
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29KINDEXING SCHEME ASSOCIATED WITH SUBCLASSES B29B, B29C OR B29D, RELATING TO MOULDING MATERIALS OR TO MATERIALS FOR MOULDS, REINFORCEMENTS, FILLERS OR PREFORMED PARTS, e.g. INSERTS
    • B29K2027/00Use of polyvinylhalogenides or derivatives thereof as moulding material
    • B29K2027/06PVC, i.e. polyvinylchloride
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B29WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
    • B29LINDEXING SCHEME ASSOCIATED WITH SUBCLASS B29C, RELATING TO PARTICULAR ARTICLES
    • B29L2023/00Tubular articles
    • B29L2023/22Tubes or pipes, i.e. rigid

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)

Abstract

The invention discloses a kind of uniform water cooling plants for pvc pipe production, including cooling water tank, tank bracket and bottom plate are equipped with below the cooling water tank, the cooling water tank is fixed on the tank bracket, the tank bracket is fixed on the bottom plate, the bottom plate is equipped with the first circulation water tank being connect with the cooling water tank, second circulation water tank and third cyclic water tank, cooling water tank left and right ends end is had into nozzle and outlet spout, first partition and second partition are equipped in the cooling water tank, first cyclic annular spray tube, second cyclic annular spray tube, third ring-type spray tube, the first submerged pump is equipped in the first circulation water tank, first quartz heating-pipe, first water temperature sensor and the first liquid level sensor, the cooling water tank is equipped with the first temperature controller, second temperature controller and PLC controller.The invention has the advantages that of simple structure and strong practicability.

Description

A kind of uniform water cooling plant for pvc pipe production
Technical field
The present invention relates to pvc pipe production equipment technology, particularly a kind of uniform water cooling dress for pvc pipe production It puts.
Background technology
PVC pipes are bright in colour, corrosion-resistant, firm and durable, and it is good with processing performance, manufacture at low cost, corrosion resistant Erosion, good insulating, so with wider purposes;In pvc pipe production, shape in water tank of shaping and be very important step Suddenly, it is ensured that the quality of pvc pipe, but now traditional sizing water tank is to carry out sprinkling drop using the water of same temperature Temperature, the pvc pipe temperature squeezed out from extruder is higher, and the quality that may make pvc pipe if there is temperature decrease reduces, therefore have Necessity uses a kind of device that uniform water cooling can be carried out to the pvc pipe of extrusion.
Invention content
The purpose of the present invention is to solve the above problems, devise a kind of uniform water cooling plant for pvc pipe production.
Realize above-mentioned purpose the technical scheme is that, it is a kind of for pvc pipe production uniform water cooling plant, including cold But water tank, the cooling water tank lower section are equipped with tank bracket and bottom plate, and the cooling water tank is fixed on the tank bracket, institute Tank bracket is stated to be fixed on the bottom plate, be equipped on the bottom plate and below the cooling water tank first circulation water tank, Second circulation water tank and third cyclic water tank, the cooling water tank left end are provided with into nozzle, and the cooling water tank right end is provided with out Nozzle, into being equipped with first partition and second partition between nozzle and the outlet spout successively in the cooling water tank and positioned at described, The first partition and the second partition are fixedly connected with the cooling water tank inner wall and the cooling water tank are divided into first It is provided on water cooling chamber, the second water cooling chamber and third water cooling chamber, the first partition and the second partition and leads to for the pvc pipe The opening crossed is equipped with the first cyclic annular spray tube in first water cooling chamber, the first spray is provided on the described first cyclic annular spray tube Water inlet, be provided in first water cooling chamber with the described first spray corresponding first water inlet of water inlet, described first follows Ring water tank is located at below first water cooling chamber, be equipped in the first circulation water tank the first submerged pump, the first quartz heating-pipe, First water temperature sensor and the first liquid level sensor, the first circulation water tank upper end is provided with first circulation water outlet, described cold But the first temperature controller is equipped on water tank and on the outside of first water cooling chamber, the second ring-type is equipped in second water cooling chamber and is sprayed Shower pipe is provided with the second spray water inlet on the second cyclic annular spray tube, is provided in second water cooling chamber and the described second spray Corresponding second water inlet of water inlet is drenched, the second circulation water tank is located at below second water cooling chamber, and described second follows The second submerged pump, the second quartz heating-pipe, the second water temperature sensor and the second liquid level sensor, the cooling are equipped in ring water tank The second temperature controller is equipped on water tank and on the outside of second water cooling chamber, the second circulation water tank upper end is provided with second circulation Water outlet is equipped with third ring-type spray tube in the third water cooling chamber, be provided on the third ring-type spray tube third spray into The mouth of a river, is provided in the third water cooling chamber and the third spray corresponding third water inlet of water inlet, the third cycle Water tank is located at below the third water cooling chamber, be equipped in the third cyclic water tank third submerged pump, third water temperature sensor and Third liquid level sensor, the third cyclic water tank upper end are provided with third circulating outlet, on the cooling water tank and positioned at institute It states and PLC controller is equipped on the outside of third water cooling chamber.
The opening with it is described be the circular open that matches with the outer diameter of PVC pipe into nozzle and the outlet spout, It is described opening with it is described into the center of circle of nozzle and the outlet spout on the same axis.
The first circulation water tank, second circulation water tank and third cyclic water tank upper end are welded with the cooling water tank bottom end It connects, first water cooling chamber bottom end is provided with the first water outlet for penetrating through the first circulation water tank, second water cooling chamber bottom end The second water outlet for penetrating through the second circulation water tank is provided with, third water cooling chamber bottom end is provided with the perforation third recirculated water The third water outlet of case.
Described first cyclic annular spray tube is equipped with several equally distributed first cool water shower heads, the described second cyclic annular spray Shower pipe is equipped with several equally distributed second cool water shower heads, and the third ring-type spray tube is equipped with several be uniformly distributed Third cool water shower head.
The water outlet of first submerged pump be connected be inserted through the first circulation water outlet and first water inlet and With the described first first circulation feed pipe for connecting of spray inlet seal, it is connected at the water outlet of second submerged pump It is inserted through the second circulation water outlet and second water inlet and connect with the described second spray inlet seal second Periodical feeding pipe is connected at the water outlet of the third submerged pump and is inserted through the third circulating outlet and third water inlet Mouth and the third periodical feeding pipe being connect with third spray inlet seal.
The first filtering is equipped in the first circulation water tank and between first water outlet and first submerged pump Net, the first circulation water tank bottom end and is equipped with the first discharge outlet, first discharge outlet below first water outlet Place is equipped with the first drain valve, and the first water supplement port, institute are provided on the first circulation water tank and above first discharge outlet It states and the first water compensating valve is equipped at the first water supplement port.
The second filtering is equipped in the second circulation water tank and between second water outlet and second submerged pump Net, the second circulation water tank bottom end and is equipped with the second discharge outlet, second discharge outlet below second water outlet Place is equipped with the second drain valve, and the second water supplement port, institute are provided on the second circulation water tank and above second discharge outlet It states and the second water compensating valve is equipped at the second water supplement port.
Third is equipped in the third cyclic water tank and between the third water outlet and the third submerged pump to filter Net, the third cyclic water tank bottom end and is equipped with third discharge outlet, the third discharge outlet below the third water outlet Place is equipped with third drain valve, and third water supplement port, institute are provided on the third cyclic water tank and above the third discharge outlet It states and third water compensating valve is equipped at third water supplement port.
First temperature controller is electrically connected with first quartz heating-pipe, the first water temperature sensor, second temperature Device is controlled to be electrically connected with second quartz heating-pipe, the second water temperature sensor.
The PLC controller and first submerged pump, the first liquid level sensor, the second submerged pump, the second level sensing Device, third submerged pump, third water temperature sensor and third liquid level sensor are electrically connected.
A kind of uniform water cooling plant for pvc pipe production made using technical scheme of the present invention, is carried out in three steps Spraying cooling, cooling water temperature decline in gradient, realize the uniform water cooling to pvc pipe after extrusion, improve the production matter of pvc pipe Amount, cooling water filtration can be recycled, and reduce water resource waste.
Description of the drawings
Fig. 1 is a kind of structure diagram of uniform water cooling plant for pvc pipe production of the present invention;
Fig. 2 is a kind of front view of uniform water cooling plant for pvc pipe production of the present invention;
Fig. 3 is a kind of side sectional view for pvc pipe production of the present invention;
Fig. 4 is a kind of side view for pvc pipe production of the present invention;
Fig. 5 is a kind of rearview of uniform water cooling plant for pvc pipe production of the present invention;
In figure, 1, cooling water tank;2nd, tank bracket;3rd, bottom plate;4th, first circulation water tank;5th, second circulation water tank;6th, third is followed Ring water tank;7th, into nozzle;8th, outlet spout;9th, first partition;10th, second partition;11st, the first water cooling chamber;12nd, the second water cooling chamber; 13rd, third water cooling chamber;14th, it is open;15th, the first cyclic annular spray tube;16th, the first submerged pump;17th, the first quartz heating-pipe;18th, One water temperature sensor;19th, the first liquid level sensor;20th, the first temperature controller;21st, the second cyclic annular spray tube;22nd, the second submerged pump; 23rd, the second quartz heating-pipe;24th, the second water temperature sensor;25th, the second liquid level sensor;26th, the second temperature controller;27th, third ring Shape spray tube;28th, third submerged pump;29th, third water temperature sensor;30th, third liquid level sensor;31st, PLC controller;32nd, One water outlet;33rd, the second water outlet;34th, third water outlet;35th, the first cool water shower head;36th, the second cool water shower head; 37th, third cool water shower head;38th, first circulation feed pipe;39th, second circulation feed pipe;40th, third periodical feeding pipe;41、 First filter screen;42nd, the first drain valve;43rd, the first water compensating valve;44th, the second filter screen;45th, the second drain valve;46th, it second mends Water valve;47th, third filter screen;48th, third drain valve;49th, third water compensating valve.
Specific embodiment
The present invention is specifically described below in conjunction with the accompanying drawings, it is as shown in Figs. 1-5, a kind of for the uniform of pvc pipe production Water cooling plant, including cooling water tank 1,1 lower section of cooling water tank is equipped with tank bracket 2 and bottom plate 3, and the cooling water tank 1 is solid It is scheduled on the tank bracket 2, the tank bracket 2 is fixed on the bottom plate 3, on the bottom plate 3 and positioned at the cooling 1 lower section of water tank is equipped with first circulation water tank 4, second circulation water tank 5 and third cyclic water tank 6, and 1 left end of cooling water tank is provided with Into nozzle 7,1 right end of cooling water tank is provided with outlet spout 8, in the cooling water tank 1 and positioned at it is described into nozzle 7 and it is described go out First partition 9 and second partition 10, the first partition 9 and the second partition 10 and the cooling are equipped between nozzle 8 successively 1 inner wall of water tank is fixedly connected and divides the cooling water tank 1 for the first water cooling chamber 11, the second water cooling chamber 12 and third water cooling chamber 13, be provided in the first partition 9 and the second partition 10 for the pvc pipe by opening 14, first water cooling The first cyclic annular spray tube 15 is equipped in room 11, is provided with the first spray water inlet on the described first cyclic annular spray tube 15, described first It is provided in water cooling chamber 11 and is located at institute with the described first spray corresponding first water inlet of water inlet, the first circulation water tank 4 11 lower section of the first water cooling chamber is stated, the first submerged pump 16, the first quartz heating-pipe 17, first are equipped in the first circulation water tank 4 18 and first liquid level sensor 19 of water temperature sensor, 4 upper end of first circulation water tank is provided with first circulation water outlet, described cold But the first temperature controller 20 is equipped on water tank 1 and positioned at first water cooling chamber, 11 outside, the is equipped in second water cooling chamber 12 Two cyclic annular spray tubes 21 are provided with the second spray water inlet on described second cyclic annular spray tube 21, are opened in second water cooling chamber 12 Have and be located at second water cooling chamber with the described second spray corresponding second water inlet of water inlet, the second circulation water tank 5 12 lower sections, the second circulation water tank 5 is interior to be equipped with the second submerged pump 22, the second quartz heating-pipe 23, the second water temperature sensor 24 With the second liquid level sensor 25, the second temperature controller 26 is equipped on the cooling water tank 1 and positioned at 12 outside of the second water cooling chamber, 5 upper end of second circulation water tank is provided with second circulation water outlet, and third ring-type spray tube is equipped in the third water cooling chamber 13 27, third spray water inlet is provided on the third ring-type spray tube 27, is provided with and the third in the third water cooling chamber 13 Spraying the corresponding third water inlet of water inlet, the third cyclic water tank 6 is located at 13 lower section of the third water cooling chamber, and described the Third submerged pump 28, third water temperature sensor 29 and third liquid level sensor 30, the third cycle are equipped in three cyclic water tanks 6 6 upper end of water tank is provided with third circulating outlet, and PLC is equipped on the cooling water tank 1 and positioned at 13 outside of third water cooling chamber Controller 31;The opening 14 with it is described be the circle that matches with the outer diameter of PVC pipe into nozzle 7 and the outlet spout 8 Opening, it is described opening 14 with it is described into the center of circle of nozzle 7 and the outlet spout 8 on the same axis;The first circulation water tank 4th, second circulation water tank 5 and 6 upper end of third cyclic water tank are welded with 1 bottom end of cooling water tank, first water cooling chamber 11 Bottom end is provided with the first water outlet 32 for penetrating through the first circulation water tank 4, and 12 bottom end of the second water cooling chamber is provided with described in perforation Second water outlet 33 of second circulation water tank 5,13 bottom end of third water cooling chamber are provided with the of the perforation third cyclic water tank 6 Three water outlets 34;The first cyclic annular spray tube 15 is equipped with several equally distributed first cool water shower heads 35, and described the Two cyclic annular spray tubes 21 are equipped with several equally distributed second cool water shower heads 36, are set on the third ring-type spray tube 27 There are several equally distributed third cool water shower heads 37;The water outlet of first submerged pump 16, which is connected with, is inserted through described first Circulating outlet and first water inlet and the first circulation feed pipe 38 being connect with the described first spray inlet seal, institute State be connected at the water outlet of second submerged pump 22 be inserted through the second circulation water outlet and second water inlet and with Described second sprays the second circulation feed pipe 39 of inlet seal connection, is connected with and wears at the water outlet of the third submerged pump 28 The third for being inserted through the third circulating outlet and the third water inlet and being connect with third spray inlet seal is followed Ring feed pipe 40;It is equipped in the first circulation water tank 4 and between first water outlet 32 and first submerged pump 16 First filter screen 41,4 bottom end of first circulation water tank and is equipped with the first discharge outlet, institute positioned at first water outlet, 32 lower section It states and the first drain valve 42 is equipped at the first discharge outlet, opened on the first circulation water tank 4 and above first discharge outlet There is the first water supplement port, the first water compensating valve 43 is equipped at first water supplement port;In the second circulation water tank 5 and positioned at described the Equipped with the second filter screen 44,5 bottom end of second circulation water tank and positioned at institute between two water outlets 33 and second submerged pump 22 It states 33 lower section of the second water outlet and is equipped with the second discharge outlet, be equipped with the second drain valve 45 at second discharge outlet, described second follows The second water supplement port is provided on ring water tank 4 and above second discharge outlet, the second moisturizing is equipped at second water supplement port Valve 46;Third mistake is equipped in the third cyclic water tank 6 and between the third water outlet 34 and the third submerged pump 28 Strainer 47,6 bottom end of third cyclic water tank and is equipped with third discharge outlet, the third positioned at 34 lower section of the third water outlet Third drain valve 48 is equipped at discharge outlet, third is provided on the third cyclic water tank 4 and above the third discharge outlet Water supplement port is equipped with third water compensating valve 49 at the third water supplement port;First temperature controller 20 and first quartz heating-pipe 17th, the first water temperature sensor 18 is electrically connected, and second temperature controller 26 is passed with second quartz heating-pipe 23, the second water temperature Sensor 24 is electrically connected;The PLC controller 31 and first submerged pump 16, the first liquid level sensor 19, the second submerged pump 22nd, the second liquid level sensor 25, third submerged pump 28, third water temperature sensor 29 and third liquid level sensor 30 are electrically connected.
The characteristics of the present embodiment is that tank bracket and bottom plate are equipped with below cooling water tank, and cooling water tank is fixed on water tank On stent, tank bracket is fixed on bottom plate, and first circulation water tank, second circulation are equipped on bottom plate and below cooling water tank Water tank and third cyclic water tank, cooling water tank left end are provided with into nozzle, and cooling water tank right end is provided with outlet spout, in cooling water tank and Positioned at into being equipped with first partition and second partition between nozzle and outlet spout successively, first partition and second partition in cooling water tank Wall is fixedly connected and cooling water tank is divided into the first water cooling chamber, the second water cooling chamber and third water cooling chamber, first partition and second every Be provided on plate for pvc pipe by opening, the first cyclic annular spray tube is equipped in the first water cooling chamber, is opened on the first cyclic annular spray tube There is the first spray water inlet, be provided in the first water cooling chamber and the first spray corresponding first water inlet of water inlet, first circulation Water tank is located at below the first water cooling chamber, and the first submerged pump, the first quartz heating-pipe, the first water temperature are equipped in first circulation water tank and is passed Sensor and the first liquid level sensor, first circulation water tank upper end are provided with first circulation water outlet, on cooling water tank and positioned at first The first temperature controller is equipped on the outside of water cooling chamber, the second cyclic annular spray tube is equipped in the second water cooling chamber, is provided on the second cyclic annular spray tube Second sprays water inlet, is provided in the second water cooling chamber and second sprays corresponding second water inlet of water inlet, second circulation water Case is located at below the second water cooling chamber, and the second submerged pump, the second quartz heating-pipe, the second water temperature sensing are equipped in second circulation water tank Device and the second liquid level sensor are equipped with the second temperature controller, second circulation water tank on cooling water tank and on the outside of the second water cooling chamber Upper end is provided with second circulation water outlet, and third ring-type spray tube is equipped in third water cooling chamber, and the is provided on third ring-type spray tube Three spray water inlets, are provided in third water cooling chamber and third sprays the corresponding third water inlet of water inlet, third cyclic water tank Below third water cooling chamber, third submerged pump, third water temperature sensor and third level sensing are equipped in third cyclic water tank Device, third cyclic water tank upper end are provided with third circulating outlet, and being equipped with PLC on cooling water tank and on the outside of third water cooling chamber controls Device processed.A kind of uniform water cooling plant for pvc pipe production made using technical scheme of the present invention, is carried out in three steps spray Cooling, cooling water temperature decline, realize the uniform water cooling to pvc pipe after extrusion, improve the quality of production of pvc pipe in gradient, Cooling water filtration can be recycled, and reduce water resource waste.
In the present embodiment, pvc pipe into nozzle by entering cooling water tank, successively by the first water cooling chamber, the second water cooling It is removed after the spraying cooling of room and third water cooling chamber by outlet spout, the water in first circulation water tank is controlled by the first temperature controller Water in first circulation water tank is heated preset temperature value, when water temperature reaches preset value, the first water temperature by temperature, the first quartz heating-pipe Water temperature signal is transmitted to the first temperature controller by sensor, and the first temperature controller controls the first quartz heating-pipe to keep constant temperature, and first follows Default water temperature in ring water tank should be less than the temperature of pvc pipe, similarly, the water temperature in the second temperature controller control second circulation water tank, Default water temperature in second circulation water tank should be less than the water temperature in first circulation water tank.When recirculated water the temperature inside the box reaches preset value When, chilling spray is controlled to work by PLC controller:First submerged pump will be in first circulation water tank by first circulation feed pipe Water be pumped into the first cyclic annular spray tube, finally reduce PVC by cool water shower to pvc pipe by the first cool water shower head The temperature of pipe, pvc pipe are gradually moved to the second water cooling chamber by the first water cooling chamber;Similarly, the second submerged pump is supplied by second circulation Water in second circulation water tank is pumped into the second cyclic annular spray tube by water pipe, is finally sprayed cooling water by the second cool water shower head It pours on pvc pipe;Water in third cyclic water tank is pumped into third ring-type by third periodical feeding pipe and sprayed by third submerged pump Guan Zhong, finally by third cool water shower head by cool water shower to pvc pipe, after first partition and second partition isolation spray Water, the water after spray is made to flow back into first circulation water tank, respectively by the first water outlet, the second water outlet and third water outlet In two-cycle case and third cyclic water tank, prevent water mix after temperature change, the first filter screen, the second filter screen and the By the contaminant filter in recirculation water, the water after filtering continues to recycle three filter screens.After work, by the first drain valve, Second drain valve and third drain valve are by the impurity and waste water in first circulation water tank, second circulation water tank and third cyclic water tank Discharge;Water amount information is transmitted to PLC controller by the first liquid level sensor, the second liquid level sensor, third liquid level sensor, and Real-time water can be shown in PLC controller, when water shortage, can be mended by the first water compensating valve, the second water compensating valve and third Water valve into first circulation water tank, second circulation water tank and third cyclic water tank plus water, ensure spraying cooling work can normally into Row.
Above-mentioned technical proposal only embodies the optimal technical scheme of technical solution of the present invention, those skilled in the art The principle of the present invention is embodied to some variations that some of which part may be made, belongs to the scope of protection of the present invention it It is interior.

Claims (10)

1. a kind of uniform water cooling plant for pvc pipe production, including cooling water tank(1), which is characterized in that the cooling water tank (1)Lower section is equipped with tank bracket(2)And bottom plate(3), the cooling water tank(1)It is fixed on the tank bracket(2)On, the water Box bracket(2)It is fixed on the bottom plate(3)On, the bottom plate(3)Above and positioned at the cooling water tank(1)Lower section is followed equipped with first Ring water tank(4), second circulation water tank(5)With third cyclic water tank(6), the cooling water tank(1)Left end is provided with into nozzle(7), The cooling water tank(1)Right end is provided with outlet spout(8), the cooling water tank(1)It is interior and positioned at described into nozzle(7)With it is described go out Nozzle(8)Between successively be equipped with first partition(9)And second partition(10), the first partition(9)With the second partition(10) With the cooling water tank(1)Inner wall is fixedly connected and by the cooling water tank(1)It is divided into the first water cooling chamber(11), the second water cooling chamber (12)With third water cooling chamber(13), the first partition(9)With the second partition(10)On be provided with and pass through for the pvc pipe Opening(14), first water cooling chamber(11)Inside it is equipped with the first cyclic annular spray tube(15), the described first cyclic annular spray tube(15) On be provided with the first spray water inlet, first water cooling chamber(11)On be provided with and described first spray water inlet corresponding first Water inlet, the first circulation water tank(4)Positioned at first water cooling chamber(11)Lower section, the first circulation water tank(4)Inside set There is the first submerged pump(16), the first quartz heating-pipe(17), the first water temperature sensor(18)With the first liquid level sensor(19), institute State first circulation water tank(4)Upper end is provided with first circulation water outlet, the cooling water tank(1)Above and positioned at first water cooling chamber (11)Outside is equipped with the first temperature controller(20), second water cooling chamber(12)Inside it is equipped with the second cyclic annular spray tube(21), described Two cyclic annular spray tubes(21)On be provided with the second spray water inlet, second water cooling chamber(12)On be provided with described second spray into Corresponding second water inlet in the mouth of a river, the second circulation water tank(5)Positioned at second water cooling chamber(12)Lower section, described second Cyclic water tank(5)Inside it is equipped with the second submerged pump(22), the second quartz heating-pipe(23), the second water temperature sensor(24)With the second liquid Level sensor(25), the cooling water tank(1)Above and positioned at second water cooling chamber(12)Outside is equipped with the second temperature controller(26), The second circulation water tank(5)Upper end is provided with second circulation water outlet, the third water cooling chamber(13)The interior third ring-type that is equipped with is sprayed Shower pipe(27), the third ring-type spray tube(27)On be provided with third spray water inlet, the third water cooling chamber(13)On be provided with The corresponding third water inlet of water inlet, the third cyclic water tank are sprayed with the third(6)Positioned at the third water cooling chamber (13)Lower section, the third cyclic water tank(6)It is interior to be equipped with third submerged pump(28), third water temperature sensor(29)With third liquid level Sensor(30), the third cyclic water tank(6)Upper end is provided with third circulating outlet, the cooling water tank(1)Above and it is located at The third water cooling chamber(13)Outside is equipped with PLC controller(31).
A kind of 2. uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that the opening (14)With described into nozzle(7)With the outlet spout(8)It is the circular open to match with the outer diameter of PVC pipe, it is described to open Mouthful(14)With described into nozzle(7)With the outlet spout(8)The center of circle on the same axis.
3. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described first Cyclic water tank(4), second circulation water tank(5)With third cyclic water tank(6)Upper end with the cooling water tank(1)Bottom end is welded, First water cooling chamber(11)Bottom end is provided with the perforation first circulation water tank(4)The first water outlet(32), second water Cold house(12)Bottom end is provided with the perforation second circulation water tank(5)The second water outlet(33), the third water cooling chamber(13)Bottom End is provided with the perforation third cyclic water tank(6)Third water outlet(34).
4. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described first Cyclic annular spray tube(15)It is equipped with several equally distributed first cool water shower heads(35), the described second cyclic annular spray tube(21) It is equipped with several equally distributed second cool water shower heads(36), the third ring-type spray tube(27)It is equipped with several uniform The third cool water shower head of distribution(37).
5. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described first Submerged pump(16)Water outlet be connected be inserted through the first circulation water outlet and first water inlet and with described first spray Drench the first circulation feed pipe of inlet seal connection(38), second submerged pump(22)Water outlet at be connected with it is interspersed Cross the second circulation water outlet and second water inlet and the second circulation being connect with the described second spray inlet seal Feed pipe(39), the third submerged pump(28)Water outlet at be connected with and be inserted through the third circulating outlet and the third Water inlet and the third periodical feeding pipe being connect with third spray inlet seal(40).
6. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described first Cyclic water tank(4)It is interior and positioned at first water outlet(32)With first submerged pump(16)Between be equipped with the first filter screen (41), the first circulation water tank(4)Bottom end and positioned at first water outlet(32)Lower section is equipped with the first discharge outlet, and described the The first drain valve is equipped at one discharge outlet(42), the first circulation water tank(4)Above and above first discharge outlet open There is the first water supplement port, the first water compensating valve is equipped at first water supplement port(43).
7. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described second Cyclic water tank(5)It is interior and positioned at second water outlet(33)With second submerged pump(22)Between be equipped with the second filter screen (44), the second circulation water tank(5)Bottom end and positioned at second water outlet(33)Lower section is equipped with the second discharge outlet, and described the The second drain valve is equipped at two discharge outlet(45), the second circulation water tank(4)Above and above second discharge outlet open There is the second water supplement port, the second water compensating valve is equipped at second water supplement port(46).
A kind of 8. uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that the third Cyclic water tank(6)It is interior and positioned at the third water outlet(34)With the third submerged pump(28)Between be equipped with third filter screen (47), the third cyclic water tank(6)Bottom end and positioned at the third water outlet(34)Lower section is equipped with third discharge outlet, and described the Third drain valve is equipped at three discharge outlet(48), the third cyclic water tank(4)Above and above the third discharge outlet open There is third water supplement port, third water compensating valve is equipped at the third water supplement port(49).
9. a kind of uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that described first Temperature controller(20)With first quartz heating-pipe(17), the first water temperature sensor(18)It is electrically connected, second temperature controller (26)With second quartz heating-pipe(23), the second water temperature sensor(24)It is electrically connected.
A kind of 10. uniform water cooling plant for pvc pipe production according to claim 1, which is characterized in that the PLC Controller(31)With first submerged pump(16), the first liquid level sensor(19), the second submerged pump(22), the second level sensing Device(25), third submerged pump(28), third water temperature sensor(29)With third liquid level sensor(30)It is electrically connected.
CN201711492341.5A 2017-12-30 2017-12-30 A kind of uniform water cooling plant for pvc pipe production Pending CN108127895A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711492341.5A CN108127895A (en) 2017-12-30 2017-12-30 A kind of uniform water cooling plant for pvc pipe production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711492341.5A CN108127895A (en) 2017-12-30 2017-12-30 A kind of uniform water cooling plant for pvc pipe production

Publications (1)

Publication Number Publication Date
CN108127895A true CN108127895A (en) 2018-06-08

Family

ID=62394191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711492341.5A Pending CN108127895A (en) 2017-12-30 2017-12-30 A kind of uniform water cooling plant for pvc pipe production

Country Status (1)

Country Link
CN (1) CN108127895A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110948817A (en) * 2019-12-21 2020-04-03 武汉亚联塑业有限公司 Automatic setting equipment for PVC (polyvinyl chloride) pipes
CN112539554A (en) * 2020-12-02 2021-03-23 宜兴市光辉包装材料有限公司 Working water tank and preparation method of PVC heat-shrinkable label film based on same

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205439213U (en) * 2015-12-25 2016-08-10 杜崇铭 Water -chilling plant of plastify production line
CN206030496U (en) * 2016-08-12 2017-03-22 河南开启电力实业有限公司 Cooling system of plastic extruding machine
CN107263845A (en) * 2017-08-02 2017-10-20 江苏赛尔超高压特种管业有限公司 A kind of segmented glass thermoplastic pipes cooling device
CN206589320U (en) * 2016-11-24 2017-10-27 华亭众一兴旺管业有限公司 A kind of plastic pipe molding spray cooling device
CN107471602A (en) * 2017-09-01 2017-12-15 江苏佳润管业有限公司 A kind of polyethylene pipe production cooling device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205439213U (en) * 2015-12-25 2016-08-10 杜崇铭 Water -chilling plant of plastify production line
CN206030496U (en) * 2016-08-12 2017-03-22 河南开启电力实业有限公司 Cooling system of plastic extruding machine
CN206589320U (en) * 2016-11-24 2017-10-27 华亭众一兴旺管业有限公司 A kind of plastic pipe molding spray cooling device
CN107263845A (en) * 2017-08-02 2017-10-20 江苏赛尔超高压特种管业有限公司 A kind of segmented glass thermoplastic pipes cooling device
CN107471602A (en) * 2017-09-01 2017-12-15 江苏佳润管业有限公司 A kind of polyethylene pipe production cooling device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110948817A (en) * 2019-12-21 2020-04-03 武汉亚联塑业有限公司 Automatic setting equipment for PVC (polyvinyl chloride) pipes
CN110948817B (en) * 2019-12-21 2021-05-18 武汉亚联塑业有限公司 Automatic setting equipment for PVC (polyvinyl chloride) pipes
CN112539554A (en) * 2020-12-02 2021-03-23 宜兴市光辉包装材料有限公司 Working water tank and preparation method of PVC heat-shrinkable label film based on same
CN112539554B (en) * 2020-12-02 2022-03-29 宜兴市光辉包装材料有限公司 PVC thermal contraction label film preparation work water tank

Similar Documents

Publication Publication Date Title
CN108127895A (en) A kind of uniform water cooling plant for pvc pipe production
CN107355925A (en) Vertical board pipe adds direct evaporative cooling air conditioner group indirectly
CN104315885A (en) Water cooling heat exchanger
CN205631327U (en) Plastic tubing cooling device that can cyclic utilization water resource
CN209333235U (en) A kind of extraction structure of novel distillation system
CN106168447B (en) More intermediate frequency furnaces and switch board heat exchange water centralized cycle cooling device
CN207546157U (en) The waste heat from tail gas recycling of lithium ferric manganese phosphate and cleaning system
CN201427940Y (en) Water circulation recycling device for cellulose ether production
CN203744441U (en) Aeration cooling system with combination between inertial filter and water spray chamber applicable to power station
CN217383843U (en) Acid-resistant anti-blocking cooling device
CN206986290U (en) Copper sulfate electrolyte cooling device
CN205980811U (en) Cooling back installation is concentrated to many medium frequency induction fur nace and switch board heat exchange water
CN215365876U (en) Quenching and tempering is spray cooling device for steel pipe
CN207562685U (en) Pressure vessel for reverse osmosis
CN220836905U (en) Inner wall and tray flushing device of stripping tower for producing polyvinyl chloride
CN217929966U (en) Switching condensing system that phthalic anhydride preparation in-process was used
CN213285694U (en) Powder spray tower with steam heating automatic control system
CN217315782U (en) Lead brass continuous casting crystallizer with water seal device
CN221182732U (en) Polypeptide solid-phase synthesis reaction kettle convenient to use
CN214131547U (en) Granulator with cleaning function
CN214324137U (en) Harbor treasure cooling water filtration circulation device
CN106962209A (en) A kind of roofing water curtain circulatory system for pig farm
CN213321230U (en) Be used for pvc tubular product cooling setting device
CN207551023U (en) A kind of cycle water pot
CN220936501U (en) Water injection device for wheaten food production line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180608

RJ01 Rejection of invention patent application after publication