CN108118703A - With the compacting method of rock drill backfill foundation pit - Google Patents

With the compacting method of rock drill backfill foundation pit Download PDF

Info

Publication number
CN108118703A
CN108118703A CN201611076487.7A CN201611076487A CN108118703A CN 108118703 A CN108118703 A CN 108118703A CN 201611076487 A CN201611076487 A CN 201611076487A CN 108118703 A CN108118703 A CN 108118703A
Authority
CN
China
Prior art keywords
rock drill
rammed
backfill
foundation pit
compacting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611076487.7A
Other languages
Chinese (zh)
Inventor
王天野
王瑜
张志敏
冯桢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201611076487.7A priority Critical patent/CN108118703A/en
Publication of CN108118703A publication Critical patent/CN108118703A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil

Abstract

The present invention relates to a kind of compacting methods with rock drill backfill foundation pit, and foundation pit backfilling material is inserted in foundation pit narrow space, backfilling material is spread out;Tamping plate is installed on the bore bit of rock drill;Backfilling material is rammed with rock drill, it rams and is stacked when ramming, overlapping area is no less than 1/3, and each tamping point is rammed no less than 68 and hit, while ramming using the mechanical large arm of rock drill be downwardly applied to pressure for aid in compacting, each tamping operation face is rammed no less than twice;Symmetrical backfill construction is carried out, in structure both sides or the symmetrical back-filling in layers compacting of surrounding, after backfill rams one layer, carries out compactness detection in time, after meeting design requirement, record, which is rammed, hits number and pass;Above each layer backfill is rammed, and is operated by the pass of record, until being backfilled to design altitude, forbids to ram plate touching underground structure during ramming.The present invention solves the problems, such as that narrow and hazard space can not be tamped or to tamp effect poor, it is ensured that narrow space compacting quality.

Description

With the compacting method of rock drill backfill foundation pit
Technical field
The present invention relates to a kind of compacting method for backfilling foundation pit, specifically with the compacting side of rock drill backfill foundation pit Method.
Background technology
In the engineering constructions such as previous architectural engineering, municipal works, foundation pit backfill construction quality is often difficult to control, especially It is not easy to the space of operation in narrow, dangerous and personnel, and backfill quality is even more to be difficult to ensure that construction of structures throwing often occur After entering use, there is soil body sedimentation, the affiliated facilities such as its step, ramp is caused to open due to backfilling leakiness in the foundation pit on periphery Phenomena such as splitting, sinking;What is more in Municipal Road Engineering construction, the pipeline, inspection shaft and the structure that are arranged under road Object since its groove space is narrow, dangerous, is not easy to construction personnel's operation, and backfill construction especially compaction in layers is frequently present of Carelessness carries out, and road is caused to be open to the traffic using soon, road surface differential settlement occur in well lid periphery and pipeline position, to vehicle It is current to cause some potential safety problems.
The content of the invention
It is contemplated that the defects of overcoming the prior art, provides a kind of compacting method with rock drill backfill foundation pit, solves The problem of effect is poor can not be tamped or be tamped to narrow and hazard space, it is ensured that narrow space tamps quality.
In order to solve the above-mentioned technical problem, the present invention is realized in:
A kind of compacting method with rock drill backfill foundation pit, it is characterised in that it includes the following steps:
Step 1:Foundation pit backfilling material is inserted in foundation pit narrow space, when filling thickness is inconsistent, backfilling material is spread out;
Step 2:Tamping plate is installed on the bore bit of rock drill;
Step 3:Rock drill is started shooting, and backfilling material is rammed with rock drill, is rammed and is stacked when ramming, and overlapping area is no less than 1/3, Each tamping point is rammed no less than 6-8 and is hit, while ramming using the mechanical large arm of rock drill be downwardly applied to pressure for aid in rammer Real, each tamping operation face is rammed no less than twice;
Step 4:Symmetrical backfill construction is carried out, one layer is rammed in structure both sides or the symmetrical back-filling in layers compacting of surrounding, backfill and finishes Afterwards, compactness detection is carried out in time, and after meeting design requirement, record, which is rammed, hits number and pass;
Step 5:Above each layer backfill is rammed, and is operated by the pass of record, until design altitude is backfilled to, it is tight during ramming Taboo rams plate touching underground structure.
The compacting method with rock drill backfill foundation pit, it is characterised in that:The tamping plate includes one block of steel plate, the steel Four angle kerve of plate, hot-working make its four side bend downward 10 °, and corner incision is closed up and welded, piece steel of steel plate lower weld Stick, the steel plate lower end diameter is identical with rock drill bit diameter, and reinforcement steel plate is welded between steel plate and rod iron.
The compacting method with rock drill backfill foundation pit, it is characterised in that:Back-filling in layers thickness is 500-600mm.
The beneficial effects of the invention are as follows:By installing tamping plate additional in rock drill fibre head, and generated using it in operation process Impact energy and large arm can flexibly and comfortably into narrow, hazard space the characteristics of, with successfully solving in engineering construction Under narrow, hazard space back-filling in layers compacting quality it is bad the problem of.
This method practicality simply is easy to grasp, and good application effect, operating efficiency is high, improves underground narrow space backfilling working Efficiency and earthwork compacting construction quality, can effectively eliminate the danger that underground is narrow, hazard space is brought to operating personnel's operation, It is simple in structure, it is operated convenient for grasping, is easy to materials processing, processing cost is low, and popularizing application prospect is wide.
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structure diagram of four angle kerve of steel plate of tamping plate of the present invention.
Fig. 2 is the structure diagram after four angle kerve of the steel plate welding of tamping plate of the present invention.
Fig. 3 is the structure diagram of tamping plate of the present invention.
Specific embodiment
As shown in Figure 1:A kind of compacting method with rock drill backfill foundation pit, it includes the following steps:
Step 1:By foundation pit backfilling material(Usually element soil)It inserts in foundation pit narrow space, when filling thickness is inconsistent, will return Filling chock material, which is spread out, makes its basically identical;
Step 2:Tamping plate is installed on the bore bit of rock drill;The tamping plate includes one block of steel plate 1, four angle kerve 2 of steel plate, heat Processing makes its four side bend downward 10 °, and corner incision is closed up and welded, piece rod iron 3 of steel plate lower weld, the steel plate lower end Diameter is identical with rock drill bit diameter, and reinforcement steel plate 4 is welded between steel plate and rod iron;
Step 3:Rock drill is started shooting, and backfilling material is rammed with rock drill, is rammed and is stacked when ramming, and overlapping area is no less than 1/3, Each tamping point is rammed no less than 6-8 and is hit, while ramming using the mechanical large arm of rock drill be downwardly applied to pressure for aid in rammer Real, each tamping operation face is rammed no less than twice;
Step 4:Symmetrical backfill construction is carried out, one layer is rammed in structure both sides or the symmetrical back-filling in layers compacting of surrounding, backfill and finishes Afterwards, compactness detection is carried out in time, and after meeting design requirement, record, which is rammed, hits number and pass;
Step 5:Above each layer backfill is rammed, and is operated by the pass of record, until design altitude is backfilled to, it is tight during ramming Taboo rams plate touching underground structure.
Since the method for the present invention tamping energy derives from the pressure of mechanical large arm application, while rushing for rock drill has been superimposed again It hits, heavy tamping energy is larger, and therefore, back-filling in layers thickness can increase to 500-600mm.

Claims (3)

1. a kind of compacting method with rock drill backfill foundation pit, it is characterised in that it includes the following steps:
Step 1:Foundation pit backfilling material is inserted in foundation pit narrow space, when filling thickness is inconsistent, backfilling material is spread out;
Step 2:Tamping plate is installed on the bore bit of rock drill;
Step 3:Rock drill is started shooting, and backfilling material is rammed with rock drill, is rammed and is stacked when ramming, and overlapping area is no less than 1/3, Each tamping point is rammed no less than 6-8 and is hit, while ramming using the mechanical large arm of rock drill be downwardly applied to pressure for aid in rammer Real, each tamping operation face is rammed no less than twice;
Step 4:Symmetrical backfill construction is carried out, one layer is rammed in structure both sides or the symmetrical back-filling in layers compacting of surrounding, backfill and finishes Afterwards, compactness detection is carried out in time, and after meeting design requirement, record, which is rammed, hits number and pass;
Step 5:Above each layer backfill is rammed, and is operated by the pass of record, until design altitude is backfilled to, it is tight during ramming Taboo rams plate touching underground structure.
2. the compacting method according to claim 1 with rock drill backfill foundation pit, it is characterised in that:The tamping plate includes one Block steel plate, four angle kerve of steel plate, hot-working make its four side bend downward 10 °, and corner incision is closed up and welded, steel plate lower part A rod iron is welded, the steel plate lower end diameter is identical with rock drill bit diameter, and reinforcement steel plate is welded between steel plate and rod iron.
3. the compacting method according to claim 1 with rock drill backfill foundation pit, it is characterised in that:Back-filling in layers thickness is 500-600mm。
CN201611076487.7A 2016-11-30 2016-11-30 With the compacting method of rock drill backfill foundation pit Pending CN108118703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611076487.7A CN108118703A (en) 2016-11-30 2016-11-30 With the compacting method of rock drill backfill foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611076487.7A CN108118703A (en) 2016-11-30 2016-11-30 With the compacting method of rock drill backfill foundation pit

Publications (1)

Publication Number Publication Date
CN108118703A true CN108118703A (en) 2018-06-05

Family

ID=62227053

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611076487.7A Pending CN108118703A (en) 2016-11-30 2016-11-30 With the compacting method of rock drill backfill foundation pit

Country Status (1)

Country Link
CN (1) CN108118703A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115324078A (en) * 2022-08-24 2022-11-11 中国二十冶集团有限公司 Rapid remediation treatment method for local uneven settlement of roadbed

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030644A (en) * 2000-06-16 2002-01-31 Bomag Gmbh & Co Ohg Method and apparatus for measuring of compaction degree
CN2661904Y (en) * 2003-12-30 2004-12-08 洛阳风动工具厂 Multifunctional internal combustion rock drill
CN202881926U (en) * 2012-10-25 2013-04-17 中铁十二局集团有限公司 Quartering hammer type tamping device
CN104032789A (en) * 2014-06-27 2014-09-10 国家电网公司 Earthwork punning structure used with excavator
CN205676876U (en) * 2016-05-19 2016-11-09 卢怀友 A kind of ramming header structure changing ramming area

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002030644A (en) * 2000-06-16 2002-01-31 Bomag Gmbh & Co Ohg Method and apparatus for measuring of compaction degree
CN2661904Y (en) * 2003-12-30 2004-12-08 洛阳风动工具厂 Multifunctional internal combustion rock drill
CN202881926U (en) * 2012-10-25 2013-04-17 中铁十二局集团有限公司 Quartering hammer type tamping device
CN104032789A (en) * 2014-06-27 2014-09-10 国家电网公司 Earthwork punning structure used with excavator
CN205676876U (en) * 2016-05-19 2016-11-09 卢怀友 A kind of ramming header structure changing ramming area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115324078A (en) * 2022-08-24 2022-11-11 中国二十冶集团有限公司 Rapid remediation treatment method for local uneven settlement of roadbed

Similar Documents

Publication Publication Date Title
Mohamad et al. Challenges in construction over soft soil-case studies in Malaysia
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
Alexiew et al. Geotextile-Encased Columns
CN108252291A (en) The construction method of the coastal backfill super thick foundation of gravelly soil of 25000KN.m heavy tamping treatments
Slocombe Dynamic compaction
CN105040692B (en) A kind of construction method of precast concrete pile body carrier pile
CN111550283A (en) Method for reducing damage by alternately laying gangue filling and bag grouting combined support
Cao et al. Performance of slurry TBM tunnelling in sandy cobble ground—a case study in Lanzhou
Serridge et al. Application of the Rapid Impact Compaction (RIC) technique for risk mitigation in problematic soils
CN108118703A (en) With the compacting method of rock drill backfill foundation pit
Svinkin Sensible determination of pile capacity by dynamic methods
CN104315251B (en) Artificial pipe jacking construction method under soil stone combination geological conditions
CN109024129A (en) The compacted construction method of high-fill roadbed
Dobie et al. Working platforms for tracked plant–BR 470 guideline and a revised approach to stabilisation design with multiaxial hexagonal geogrids
CN211113598U (en) Karst cave handling system for deep foundation pit pile foundation construction in karst area
Zheng et al. Performance evaluation of abandoned fly ash deposit improved by dynamic compaction for construction of highway embankment
CN103015438A (en) Collapsible loess subgrade landslide treatment method
CN101302922B (en) Construction method of horizontal orienting drill crossing sand cobble and gravel formation
CN207919533U (en) The hydraulic shock ramming machine reequiped using quartering hammer
CN111827252A (en) Dynamic compaction foundation reinforcing method capable of protecting adjacent building structures
Sze et al. Application of shaft grouting technique in deep foundations-Hong Kong experience
Liu et al. Settlement monitoring and analysis for soft foundation of an expressway widening project
Li et al. Mechanical analysis of roof subsidence based on rheological properties of solid backfill materials
CN104153356A (en) Concrete pile construction equipment and method
Terente et al. Pile driving and pile installation risk in weak rock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180605