CN108108916A - A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium - Google Patents
A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium Download PDFInfo
- Publication number
- CN108108916A CN108108916A CN201810044307.XA CN201810044307A CN108108916A CN 108108916 A CN108108916 A CN 108108916A CN 201810044307 A CN201810044307 A CN 201810044307A CN 108108916 A CN108108916 A CN 108108916A
- Authority
- CN
- China
- Prior art keywords
- construction
- design
- attribute
- time
- procurement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063114—Status monitoring or status determination for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/109—Time management, e.g. calendars, reminders, meetings or time accounting
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
The invention discloses a kind of EPC PROJECT TIMEs control system, method and apparatus and storage medium, the systems to include:Module is designed, for receiving designing scheme input by user;The designing scheme is N number of division of labor journey specially by the EPC Project decompositions, and is each designing scheme for dividing engineering installation Design and procurement attribute and design and construction attribute;Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute and practice of construction attribute;Procurement module is more than that the buying sends alarm when setting aside some time when the actual purchase end time for showing each division of labor Design and procurement attribute of journey and actual purchase attribute;Construction module for showing each division of labor design and construction attribute of journey and practice of construction attribute, is more than that the construction sends alarm when setting aside some time when the practice of construction end time, rationally utilizes the time in the project cycle, improve the progress efficiency of project.
Description
Technical field
The present invention relates to power engineering to contract field, more specifically to a kind of EPC PROJECT TIMEs control method, is
System and equipment and a kind of computer readable storage medium.
Background technology
In conventional electric power project implementing process, three design, buying, construction engineering processes are contracted respectively to different electric power
Unit so that entire workflow, which generates, isolates, and then influences the progress and systems organization of entire engineering, also can indirect belt
The problems such as certain cooperation and cost raise.EPC (English full name:Engineer Procure Construct, Chinese full name:
General contract of civil engineering) thought be to integrate three engineerings, general contractor is responsible for entire project implementation process, no longer with list
Only subcontractor's identity construction project is conducive to overall planning and the Collaboration of entire project, can effectively solve design with
The connection problem of construction, the intermediate link for reducing buying and construction, the smooth practicability solved in arrangement and method for construction, technical, peace
Contradiction between full property is a kind of Project Realization pattern of Novel scientific.
Therefore, how rationally using in the project cycle time, the progress efficiency that improves project be those skilled in the art
Problem to be solved.
The content of the invention
It can it is an object of the invention to provide a kind of EPC PROJECT TIMEs control method, system and equipment and a kind of computer
Storage medium is read, rationally utilizes the time in the project cycle, improves the progress efficiency of project.
To achieve the above object, the present invention provides a kind of EPC PROJECT TIMEs control system, including design module, buying
Module and construction module;
The design module, for receiving designing scheme input by user;The designing scheme is specially will be EPC described
Mesh is decomposed into N number of division of labor journey, and is each designing scheme for dividing engineering installation Design and procurement attribute and attribute of designing and constructing,
Wherein, N is positive integer;
Wherein, it is reserved to include Design and procurement initial time, Design and procurement end time and buying for the Design and procurement attribute
Time, the design and construction attribute include design and construction initial time, design and construction end time and construction and set aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute
With practice of construction attribute, the actual purchase attribute includes actual purchase initial time, actual purchase end time and has purchased
Cheng Du, the practice of construction attribute include practice of construction initial time, practice of construction end time and level of construction completion;
The procurement module for showing each division of labor Design and procurement attribute of journey and actual purchase attribute, works as institute
It is more than that the buying sends alarm when setting aside some time to state the actual purchase end time;
The construction module for showing each division of labor design and construction attribute of journey and practice of construction attribute, works as institute
It is more than that the construction sends alarm when setting aside some time to state the practice of construction end time.
Wherein, the design module includes:
Startup project unit, for receiving and showing the essential attribute of project input by user, wherein, the essential attribute
Including project name, expense budget, start time and it is expected that construction time started;
Result of design unit is submitted, for receiving the designing scheme;
Design evaluation unit, for showing the assessment result of the designing scheme;
Design clearing Payment Unit, payment information is designed for showing.
Wherein, the procurement module includes:
Receiving unit, for receiving the buying bill of materials of each division of labor journey;
Buying division of labor thread management unit, for showing each division of labor Design and procurement attribute of journey and actual purchase category
Property;
Purchase bidding unit, for showing purchase bidding information;
Unit is checked and accepted in buying, for showing the check and acceptance result that material is purchased in each buying bill of materials;
Buying clearing Payment Unit, payment information is purchased for showing;
Alarm Unit is purchased, for being more than that the buying sends announcement when setting aside some time when the actual purchase end time
It is alert.
Wherein, the procurement module further includes:
Feedback unit is purchased, for sending alarm when the buying completeness reaches the first preset value.
Wherein, the construction module includes:
Construction bid unit, for showing construction bid information;
Construction division of labor thread management unit, for showing each division of labor design and construction attribute of journey and practice of construction category
Property;
Delivery receiving acceptance unit, for showing the delivery receiving acceptance result of each division of labor journey;
Construction clearing Payment Unit, for showing payment information of constructing;
Construction Alarm Unit, for being more than that the construction sends announcement when setting aside some time when the practice of construction end time
It is alert.
Wherein, the construction module further includes:
Construction feedback unit, for sending alarm when the level of construction completion reaches the second preset value.
To achieve the above object, the present invention provides a kind of EPC PROJECT TIMEs control method, including:
It designs module and receives designing scheme input by user;
Wherein, the designing scheme is N number of division of labor journey specially by the EPC Project decompositions, and is each division of labor
Journey sets the designing scheme of Design and procurement attribute and attribute of designing and constructing, wherein, N is positive integer;
Wherein, it is reserved to include Design and procurement initial time, Design and procurement end time and buying for the Design and procurement attribute
Time, the design and construction attribute include design and construction initial time, design and construction end time and construction and set aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute
With practice of construction attribute, the actual purchase attribute includes actual purchase initial time, actual purchase end time and has purchased
Cheng Du, the practice of construction attribute include practice of construction initial time, practice of construction end time and level of construction completion;
Procurement module shows each division of labor Design and procurement attribute of journey and actual purchase attribute, when the actual purchase
End time is more than that the buying sends alarm when setting aside some time;
Construction module shows each division of labor design and construction attribute of journey and practice of construction attribute, when the practice of construction
End time is more than that the construction sends alarm when setting aside some time.
Wherein, the design module receives designing scheme input by user, including:
The design mould startup project unit in the block receives and shows the essential attribute of project input by user, wherein,
The essential attribute includes project name, expense budget, starts time and it is expected that construction time started;
The design mould is in the block to submit result of design unit to receive the designing scheme;
The design mould design evaluation unit in the block shows the assessment result of the designing scheme;
The design mould design clearing Payment Unit display design payment information in the block.
To achieve the above object, the present invention provides a kind of EPC PROJECT TIMEs control device, including:
Memory, for storing computer program;
Processor is realized such as the step of above-mentioned EPC PROJECT TIMEs control method during for performing the computer program.
To achieve the above object, the present invention provides a kind of computer readable storage medium, the computer-readable storages
Computer program is stored on medium, realizes that above-mentioned EPC PROJECT TIMEs such as control when the computer program is executed by processor
Method.
By above scheme, a kind of EPC PROJECT TIMEs control system provided by the invention includes design module, buying
Module and construction module;The design module, for receiving designing scheme input by user;The designing scheme is specially by institute
EPC Project decompositions are stated as N number of division of labor journey, and each divide setting for engineering installation Design and procurement attribute and attribute of designing and constructing to be described
Meter scheme, wherein, N is positive integer;Wherein, the Design and procurement attribute includes Design and procurement initial time, Design and procurement terminates
Time and buying are set aside some time, and the design and construction attribute includes design and construction initial time, design and construction end time and applies
Work is set aside some time;Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase
Attribute and practice of construction attribute, the actual purchase attribute include actual purchase initial time, actual purchase end time and adopt
Completeness is purchased, the practice of construction attribute includes practice of construction initial time, practice of construction end time and level of construction completion;Institute
Procurement module is stated, for showing each division of labor Design and procurement attribute of journey and actual purchase attribute, when the actual purchase
End time is more than that the buying sends alarm when setting aside some time;The construction module, for showing each division of labor journey
Design and construction attribute and practice of construction attribute are more than that the construction sends announcement when setting aside some time when the practice of construction end time
It is alert.
EPC PROJECT TIMEs control system provided by the invention is realized using procurement module and construction module to engineering item
The early warning of mesh duration can enable all departments superintendent more system intuitively see the planning of engineering, progress, occur when the duration
When abnormal, i.e. the physical end time is more than when setting aside some time, and system sends early warning, and superintendent is helped to find the original of problem appearance
Cause, and solution is taken in advance.It can be seen that the system not only dramatically reduces what the manually estimation duration of a project brought
Deviation, and from the angle of system superintendent is helped to monitor project progress in real time prevents overdue, the phenomenon that stopping work, reduction
The time cost of administrative staff enables design, buying, the linking and realization of three processes of construction more science, so as to most
The profit of enterprise is improved to limits, promotes the competitiveness in market, improves the progress efficiency of project.The invention also discloses one
Kind EPC PROJECT TIMEs control method and equipment and a kind of computer readable storage medium, equally can realize above-mentioned technique effect.
Description of the drawings
It in order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention, for those of ordinary skill in the art, without creative efforts, can be with
Other attached drawings are obtained according to these attached drawings.
Fig. 1 is a kind of structure chart of EPC PROJECT TIMEs control system disclosed by the embodiments of the present invention;
Fig. 2 is a kind of flow chart of EPC PROJECT TIMEs control method disclosed by the embodiments of the present invention;
Fig. 3 is a kind of structure chart of EPC PROJECT TIMEs control device disclosed by the embodiments of the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete
Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, those of ordinary skill in the art are obtained every other without creative efforts
Embodiment belongs to the scope of protection of the invention.
The embodiment of the invention discloses a kind of EPC PROJECT TIMEs control systems, rationally using the time in the project cycle, carry
The high progress efficiency of project.
Referring to Fig. 1, a kind of structure chart of EPC PROJECT TIMEs control system disclosed by the embodiments of the present invention, as shown in Figure 1,
Including design module 101, procurement module 102 and construction module 103;
The design module 101, for receiving designing scheme input by user;The designing scheme is specially by described in
EPC Project decompositions are N number of division of labor journey, and are each design for dividing engineering installation Design and procurement attribute and attribute of designing and constructing
Scheme, wherein, N is positive integer;
Wherein, it is reserved to include Design and procurement initial time, Design and procurement end time and buying for the Design and procurement attribute
Time, the design and construction attribute include design and construction initial time, design and construction end time and construction and set aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute
With practice of construction attribute, the actual purchase attribute includes actual purchase initial time, actual purchase end time and has purchased
Cheng Du, the practice of construction attribute include practice of construction initial time, practice of construction end time and level of construction completion;
EPC PROJECT TIMEs control system provided by the invention, may be employed Visual Studio 2012 carry out interface and
The exploitation of background function realizes the docking of design subsystem, purchase subsystem and several big modules of subsystem of constructing.Database can
To use SQL Server databases, in development technique language C# language can be selected to be based on asp.net technologies and carry out system generation
Code is write.
In specific implementation, designer designs the record stage by stage for being designed the time after project by designing module
Enter, upload design drawing and detailed annotation is illustrated to design, is i.e. EPC Project decompositions are N number of division of labor journey by designer, and are every
It is a that engineering installation Design and procurement attribute and design and construction attribute is divided to be uploaded to design module.After submitting specification and file, adopt
Purchase and construction personnel will see the specification in the stage in design module and the duration and propose deficiency and suggest.Realize design
The design in stage and buying, the crossing parallel of construction in time.
It should be noted that each division of labor journey has Design and procurement attribute, design and construction attribute, actual purchase attribute and reality
The border construction attributes such as attribute, wherein, Design and procurement attribute can include Design and procurement initial time, the Design and procurement end time and
Buying is set aside some time, and it is pre- that design and construction attribute can include design and construction initial time, design and construction end time and construction
Time etc. is stayed, actual purchase attribute can include actual purchase initial time, actual purchase end time and buying completeness etc.,
Practice of construction attribute can include practice of construction initial time, practice of construction end time and level of construction completion etc..
It is understood that designer can also be believed by the assessment result and payment for designing module typing designing scheme
Breath will all be shown after the completion of typing in design module.
Specifically, design module 101 can include:
Startup project unit, for receiving and showing the essential attribute of project input by user, wherein, the essential attribute
Including project name, expense budget, start time and it is expected that construction time started;
Result of design unit is submitted, for receiving the designing scheme;
Design evaluation unit, for showing the assessment result of the designing scheme;
Design clearing Payment Unit, payment information is designed for showing.
The procurement module 102, for showing each division of labor Design and procurement attribute of journey and actual purchase attribute, when
The actual purchase end time is more than that the buying sends alarm when setting aside some time;
In specific implementation, procurement staff is by procurement module combination market conditions and equipment ordering situation etc., pair sets
The designing scheme of meter module is advised, and the corresponding procurement data of typing.It is adopted in the implementation process of buying by technology realization
The time management of flow is purchased, including buying hour typing, change etc..And be connected with construction module, using the think of of " parallel "
Think, rational allocation and control are carried out to the time purchased and constructed, when finding that buying hour is not inconsistent with initial time, that is, work as institute
It is more than buying when setting aside some time to state the actual purchase end time, is alerted in time to supervisor and points out trouble node institute
.The present embodiment is not defined the concrete mode of alarm, for example, can by the cell phone apparatus of the system and supervisor into
Row binding is alerted by the way of mobile phone vibrations, and those skilled in the art can flexibly select other according to actual conditions
Alarm mode.
It is understood that procurement staff can also by procurement module typing purchase the bill of materials, purchase bidding information,
It purchases payment information and purchases in the bill of materials check and acceptance result for purchasing material, can be shown after the completion of typing by procurement module
Show.
Specifically, procurement module 102 can include:
Receiving unit, for receiving the buying bill of materials of each division of labor journey;
Buying division of labor thread management unit, for showing each division of labor Design and procurement attribute of journey and actual purchase category
Property;
Purchase bidding unit, for showing purchase bidding information;
Unit is checked and accepted in buying, for showing the check and acceptance result that material is purchased in each buying bill of materials;
Buying clearing Payment Unit, payment information is purchased for showing;
Alarm Unit is purchased, for being more than that the buying sends announcement when setting aside some time when the actual purchase end time
It is alert.
It should be noted that procurement module can also include the function of design of feedback, i.e., when the buying of a certain division of labor journey is
Prompting will be sent to supervisor when completing, specifically, procurement module 102 can also include:Feedback unit is purchased, in institute
It states when buying completeness reaches the first preset value and sends alarm.Do not limit the concrete mode of alarm equally herein, and not to first
Preset value is set, and those skilled in the art can flexibly set according to actual conditions.
It is understood that the buying that the mode that buying completeness may be employed characterizes a certain division of labor journey is near completion, when
Can also so buying hour be utilized to characterize.For example, a certain division of labor journey is 10 days in design phase estimated buying hour, when purchase into
Prompting is sent when row is to 8 angel.
The construction module 103, for showing each division of labor design and construction attribute of journey and practice of construction attribute, when
The practice of construction end time is more than that the construction sends alarm when setting aside some time.
In specific implementation, constructing, module is similar with procurement module, and construction personnel passes through module combination practice of construction of constructing
Situation etc. advises to the designing scheme for designing module, and the corresponding construction data of typing.Pass through in the implementation process of construction
Technology realizes the time management of construction process, including construction time typing, change etc..
When finding that the construction time is not inconsistent with initial time, i.e., it is more than that the construction is pre- when the practice of construction end time
When staying the time, alerted in time to supervisor and point out trouble node place.The present embodiment not to the concrete mode of alarm into
Row limits, such as can bind the cell phone apparatus of the system and supervisor, is accused by the way of mobile phone vibrations
Alert, those skilled in the art can flexibly select other alarm modes according to actual conditions.
It is understood that construction personnel can also pass through procurement module typing construction bid information, construction payment information
Delivery receiving acceptance with each division of labor journey after the completion of typing by module of constructing as a result, can be shown.
Specifically, the construction module 103 can include:
Construction bid unit, for showing construction bid information;
Construction division of labor thread management unit, for showing each division of labor design and construction attribute of journey and practice of construction category
Property;
Delivery receiving acceptance unit, for showing the delivery receiving acceptance result of each division of labor journey;
Construction clearing Payment Unit, for showing payment information of constructing;
Construction Alarm Unit, for being more than that the construction sends announcement when setting aside some time when the practice of construction end time
It is alert.
It should be noted that construction module can also include the function of design of feedback, i.e., when the construction of a certain division of labor journey is
Prompting will be sent to supervisor when completing, specifically, construction module 103 can also include:Construction feedback unit, in institute
It states when level of construction completion reaches the second preset value and sends alarm.Do not limit the concrete mode of alarm equally herein, and not to second
Preset value is set, and those skilled in the art can flexibly set according to actual conditions.
It is understood that the construction that the mode that level of construction completion may be employed characterizes a certain division of labor journey will be completed, certainly
The construction time can also be utilized to characterize.For example, a certain division of labor journey is 10 days in the design phase estimated construction time, when construction carries out
Prompting is sent during to 8 angel.
EPC PROJECT TIMEs control system provided in an embodiment of the present invention is realized pair using procurement module and construction module
The early warning of project construction period can enable all departments superintendent more system intuitively see the planning of engineering, progress, work as work
When phase occurs abnormal, i.e. the physical end time is more than when setting aside some time, and system sends early warning, and superintendent is helped to find problem appearance
The reason for, and solution is taken in advance.It can be seen that the system not only dramatically reduces manually estimation duration of a project band
The deviation come, and from the angle of system superintendent is helped to monitor project progress in real time prevents overdue, the phenomenon that stopping work,
The time cost of administrative staff is reduced, enables design, buying, the linking and realization of three processes of construction more science, from
And the profit of enterprise is improved to greatest extent, the competitiveness in market is promoted, improves the progress efficiency of project.
A kind of EPC PROJECT TIMEs control method provided in an embodiment of the present invention is introduced below, described below one
Kind EPC PROJECT TIMEs control method can be cross-referenced with a kind of above-described EPC PROJECT TIMEs control system.
Referring to Fig. 2, a kind of flow chart of EPC PROJECT TIMEs control method provided in an embodiment of the present invention, as shown in Fig. 2,
Including:
S201:It designs module and receives designing scheme input by user;
Wherein, the designing scheme is N number of division of labor journey specially by the EPC Project decompositions, and is each division of labor
Journey sets the designing scheme of Design and procurement attribute and attribute of designing and constructing, wherein, N is positive integer;
Wherein, it is reserved to include Design and procurement initial time, Design and procurement end time and buying for the Design and procurement attribute
Time, the design and construction attribute include design and construction initial time, design and construction end time and construction and set aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute
With practice of construction attribute, the actual purchase attribute includes actual purchase initial time, actual purchase end time and has purchased
Cheng Du, the practice of construction attribute include practice of construction initial time, practice of construction end time and level of construction completion;
S202:Procurement module shows each division of labor Design and procurement attribute of journey and actual purchase attribute, when the reality
The border buying end time is more than that the buying sends alarm when setting aside some time;Construction module shows the design of each division of labor journey
Construction attribute and practice of construction attribute are more than that the construction sends alarm when setting aside some time when the practice of construction end time.
EPC PROJECT TIMEs control method provided in an embodiment of the present invention is realized pair using procurement module and construction module
The early warning of project construction period can enable all departments superintendent more system intuitively see the planning of engineering, progress, work as work
When phase occurs abnormal, i.e. the physical end time is more than when setting aside some time, and system sends early warning, and superintendent is helped to find problem appearance
The reason for, and solution is taken in advance.It can be seen that the system not only dramatically reduces manually estimation duration of a project band
The deviation come, and from the angle of system superintendent is helped to monitor project progress in real time prevents overdue, the phenomenon that stopping work,
The time cost of administrative staff is reduced, enables design, buying, the linking and realization of three processes of construction more science, from
And the profit of enterprise is improved to greatest extent, the competitiveness in market is promoted, improves the progress efficiency of project.
On the basis of above-described embodiment, preferably, the design module receives design input by user
Scheme, including:
The design mould startup project unit in the block receives and shows the essential attribute of project input by user, wherein,
The essential attribute includes project name, expense budget, starts time and it is expected that construction time started;
The design mould is in the block to submit result of design unit to receive the designing scheme;
The design mould design evaluation unit in the block shows the assessment result of the designing scheme;
The design mould design clearing Payment Unit display design payment information in the block.
On the basis of above-described embodiment, preferably, the procurement module shows each division of labor journey
Design and procurement attribute and actual purchase attribute, when the actual purchase end time be more than it is described buying set aside some time when send
Alarm, including:
Receiving unit in the procurement module receives the buying bill of materials of each division of labor journey;
Buying division of labor thread management unit in the procurement module show Design and procurement attribute of each division of labor journey with
Actual purchase attribute;
Purchase bidding unit in the procurement module shows purchase bidding information;
Buying in the procurement module checks and accepts unit and shows the examination that material is purchased in each buying bill of materials
As a result;
Buying clearing Payment Unit display buying payment information in the procurement module;
Buying Alarm Unit in the procurement module is when the actual purchase end time is more than that the buying is reserved
Between when send alarm.
On the basis of above-described embodiment, preferably, further include:
Buying feedback unit in the procurement module sends alarm when the buying completeness reaches the first preset value.
On the basis of above-described embodiment, preferably, the construction module shows each division of labor journey
Design and construction attribute and practice of construction attribute, when the practice of construction end time be more than it is described construction set aside some time when send
Alarm, including:
Construction mould construction bid unit in the block shows construction bid information;
The construction mould construction division of labor thread management unit in the block show the design and construction attribute of each division of labor journey with
Practice of construction attribute;
The construction mould delivery receiving acceptance unit in the block shows the delivery receiving acceptance result of each division of labor journey;
The construction mould construction clearing Payment Unit display construction payment information in the block;
The construction mould construction Alarm Unit in the block is when the practice of construction end time is more than that the construction is reserved
Between when send alarm.
On the basis of above-described embodiment, preferably, further include:
The construction mould construction feedback unit in the block sends alarm when the level of construction completion reaches the second preset value.
Present invention also provides a kind of EPC PROJECT TIMEs control devices, referring to Fig. 3, one kind provided in an embodiment of the present invention
The structure chart of EPC PROJECT TIME control devices, as shown in figure 3, including:
Memory 301, for storing computer program;
Processor 302, for performing computer program when, can realize the step of above-described embodiment provides.Certainly
The EPC PROJECT TIMEs control device can also include the components such as various network interfaces, power supply.
EPC PROJECT TIMEs control device provided in an embodiment of the present invention is realized pair using procurement module and construction module
The early warning of project construction period can enable all departments superintendent more system intuitively see the planning of engineering, progress, work as work
When phase occurs abnormal, i.e. the physical end time is more than when setting aside some time, and system sends early warning, and superintendent is helped to find problem appearance
The reason for, and solution is taken in advance.It can be seen that the system not only dramatically reduces manually estimation duration of a project band
The deviation come, and from the angle of system superintendent is helped to monitor project progress in real time prevents overdue, the phenomenon that stopping work,
The time cost of administrative staff is reduced, enables design, buying, the linking and realization of three processes of construction more science, from
And the profit of enterprise is improved to greatest extent, the competitiveness in market is promoted, improves the progress efficiency of project.
Present invention also provides a kind of computer readable storage mediums, are stored thereon with computer program, the computer
Program can realize the step of above-described embodiment provides when being executed by processor.The storage medium can include:USB flash disk, movement
Hard disk, read-only memory (Read-Only Memory, ROM), random access memory (Random Access Memory,
RAM), the various media that can store program code such as magnetic disc or CD.
Each embodiment is described by the way of progressive in this specification, the highlights of each of the examples are with other
The difference of embodiment, just to refer each other for identical similar portion between each embodiment.
The foregoing description of the disclosed embodiments enables professional and technical personnel in the field to realize or use the present invention.
A variety of modifications of these embodiments will be apparent for those skilled in the art, it is as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention
The embodiments shown herein is not intended to be limited to, and is to fit to and the principles and novel features disclosed herein phase one
The most wide scope caused.
Each embodiment is described by the way of progressive in specification, the highlights of each of the examples are with other realities
Apply the difference of example, just to refer each other for identical similar portion between each embodiment.For system disclosed in embodiment
Speech, since it is corresponded to the methods disclosed in the examples, so description is fairly simple, related part is referring to method part illustration
.It should be pointed out that for those skilled in the art, on the premise of the application principle is not departed from, also
Can to the application, some improvement and modification can also be carried out, these improvement and modification also fall into the application scope of the claims
It is interior.
It should also be noted that, in the present specification, relational terms such as first and second and the like be used merely to by
One entity or operation are distinguished with another entity or operation, without necessarily requiring or implying these entities or operation
Between there are any actual relationship or orders.Moreover, term " comprising ", "comprising" or its any other variant meaning
Covering non-exclusive inclusion, so that process, method, article or equipment including a series of elements not only include that
A little elements, but also including other elements that are not explicitly listed or further include for this process, method, article or
The intrinsic element of equipment.In the absence of more restrictions, the element limited by sentence "including a ...", is not arranged
Except also there are other identical elements in the process, method, article or apparatus that includes the element.
Claims (10)
1. a kind of EPC PROJECT TIMEs control system, which is characterized in that including design module, procurement module and construction module;
The design module, for receiving designing scheme input by user;The designing scheme is specially by the EPC projects point
It solves as N number of division of labor journey, and is each designing scheme for dividing engineering installation Design and procurement attribute and attribute of designing and constructing,
In, N is positive integer;
Wherein, the Design and procurement attribute is set aside some time including Design and procurement initial time, Design and procurement end time and buying,
The design and construction attribute includes design and construction initial time, design and construction end time and construction and sets aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute and reality
Border construction attribute, the actual purchase attribute include actual purchase initial time, actual purchase end time and buying completeness,
The practice of construction attribute includes practice of construction initial time, practice of construction end time and level of construction completion;
The procurement module, for showing each division of labor Design and procurement attribute of journey and actual purchase attribute, when the reality
The border buying end time is more than that the buying sends alarm when setting aside some time;
The construction module, for showing each division of labor design and construction attribute of journey and practice of construction attribute, when the reality
The border construction end time is more than that the construction sends alarm when setting aside some time.
2. EPC PROJECT TIMEs control system according to claim 1, which is characterized in that the design module includes:
Startup project unit, for receiving and showing the essential attribute of project input by user, wherein, the essential attribute includes
Project name, expense budget start time and it is expected that construction time started;
Result of design unit is submitted, for receiving the designing scheme;
Design evaluation unit, for showing the assessment result of the designing scheme;
Design clearing Payment Unit, payment information is designed for showing.
3. EPC PROJECT TIMEs control system according to claim 1, which is characterized in that the procurement module includes:
Receiving unit, for receiving the buying bill of materials of each division of labor journey;
Buying division of labor thread management unit, for showing each division of labor Design and procurement attribute of journey and actual purchase attribute;
Purchase bidding unit, for showing purchase bidding information;
Unit is checked and accepted in buying, for showing the check and acceptance result that material is purchased in each buying bill of materials;
Buying clearing Payment Unit, payment information is purchased for showing;
Alarm Unit is purchased, for being more than that the buying sends alarm when setting aside some time when the actual purchase end time.
4. EPC PROJECT TIMEs control system according to claim 3, which is characterized in that the procurement module further includes:
Feedback unit is purchased, for sending alarm when the buying completeness reaches the first preset value.
5. EPC PROJECT TIMEs control system according to claim 1, which is characterized in that the construction module includes:
Construction bid unit, for showing construction bid information;
Construction division of labor thread management unit, for showing each division of labor design and construction attribute of journey and practice of construction attribute;
Delivery receiving acceptance unit, for showing the delivery receiving acceptance result of each division of labor journey;
Construction clearing Payment Unit, for showing payment information of constructing;
Construction Alarm Unit, for being more than that the construction sends alarm when setting aside some time when the practice of construction end time.
6. EPC PROJECT TIMEs control system according to claim 1, which is characterized in that the construction module further includes:
Construction feedback unit, for sending alarm when the level of construction completion reaches the second preset value.
7. a kind of EPC PROJECT TIMEs control method, which is characterized in that including:
It designs module and receives designing scheme input by user;
Wherein, the designing scheme is N number of division of labor journey specially by the EPC Project decompositions, and is set for each division of labor journey
The designing scheme of Design and procurement attribute and attribute of designing and constructing is put, wherein, N is positive integer;
Wherein, the Design and procurement attribute is set aside some time including Design and procurement initial time, Design and procurement end time and buying,
The design and construction attribute includes design and construction initial time, design and construction end time and construction and sets aside some time;
Wherein, each division of labor journey has the Design and procurement attribute, the design and construction attribute, actual purchase attribute and reality
Border construction attribute, the actual purchase attribute include actual purchase initial time, actual purchase end time and buying completeness,
The practice of construction attribute includes practice of construction initial time, practice of construction end time and level of construction completion;
Procurement module shows each division of labor Design and procurement attribute of journey and actual purchase attribute, when the actual purchase terminates
Time is more than that the buying sends alarm when setting aside some time;
Construction module shows each division of labor design and construction attribute of journey and practice of construction attribute, when the practice of construction terminates
Time is more than that the construction sends alarm when setting aside some time.
8. EPC PROJECT TIMEs control method according to claim 7, which is characterized in that it is defeated that the design module receives user
The designing scheme entered, including:
The design mould startup project unit in the block receives and shows the essential attribute of project input by user, wherein, it is described
Essential attribute includes project name, expense budget, starts time and it is expected that construction time started;
The design mould is in the block to submit result of design unit to receive the designing scheme;
The design mould design evaluation unit in the block shows the assessment result of the designing scheme;
The design mould design clearing Payment Unit display design payment information in the block.
9. a kind of EPC PROJECT TIMEs control device, which is characterized in that including:
Memory, for storing computer program;
Processor realizes the EPC PROJECT TIMEs control method as described in claim 7 or 8 during for performing the computer program
The step of.
10. a kind of computer readable storage medium, which is characterized in that be stored with computer on the computer readable storage medium
Program realizes the EPC PROJECT TIMEs control method as described in claim 7 or 8 when the computer program is executed by processor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810044307.XA CN108108916A (en) | 2018-01-17 | 2018-01-17 | A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810044307.XA CN108108916A (en) | 2018-01-17 | 2018-01-17 | A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108108916A true CN108108916A (en) | 2018-06-01 |
Family
ID=62219699
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810044307.XA Pending CN108108916A (en) | 2018-01-17 | 2018-01-17 | A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108108916A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109740835A (en) * | 2018-11-14 | 2019-05-10 | 遵义华正电缆桥架有限公司 | A kind of power construction command system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN106855969A (en) * | 2015-12-08 | 2017-06-16 | 阿里巴巴集团控股有限公司 | A kind of method and system for determining time-out time |
CN107358340A (en) * | 2017-06-23 | 2017-11-17 | 深圳云联万企科技有限公司 | A kind of project management system based on list of engineering |
CN107491936A (en) * | 2017-08-04 | 2017-12-19 | 鸿鑫互联科技(北京)股份有限公司 | A kind of intelligent engineering project control platform and method |
CN108288148A (en) * | 2018-01-17 | 2018-07-17 | 杭州清源电力设计有限公司 | A kind of EPC Project Procurement Managements method, system and equipment and storage medium |
-
2018
- 2018-01-17 CN CN201810044307.XA patent/CN108108916A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103136636A (en) * | 2013-03-15 | 2013-06-05 | 中广核工程有限公司 | Nuclear power project progress measuring method and system |
CN106855969A (en) * | 2015-12-08 | 2017-06-16 | 阿里巴巴集团控股有限公司 | A kind of method and system for determining time-out time |
CN107358340A (en) * | 2017-06-23 | 2017-11-17 | 深圳云联万企科技有限公司 | A kind of project management system based on list of engineering |
CN107491936A (en) * | 2017-08-04 | 2017-12-19 | 鸿鑫互联科技(北京)股份有限公司 | A kind of intelligent engineering project control platform and method |
CN108288148A (en) * | 2018-01-17 | 2018-07-17 | 杭州清源电力设计有限公司 | A kind of EPC Project Procurement Managements method, system and equipment and storage medium |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109740835A (en) * | 2018-11-14 | 2019-05-10 | 遵义华正电缆桥架有限公司 | A kind of power construction command system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Xu et al. | A framework for BIM-enabled life-cycle information management of construction project | |
US8606548B2 (en) | Energy facility control system | |
CN203165006U (en) | Engineering project management system | |
CN113822605A (en) | Block chain-based carbon asset management system and method and electronic equipment | |
CN106408351A (en) | WeChat based CRM system for small and medium enterprises | |
US20140310715A1 (en) | Modeling and Consuming Business Policy Rules | |
CN115049365A (en) | Application commissioning information processing method and device and computer equipment | |
CN108108916A (en) | A kind of EPC PROJECT TIMEs control method, system and equipment and storage medium | |
Sadiah et al. | Design of the Inventory Application of CV Diva Karya Mandiri Using Rad (Rapid Application Development) | |
KR102365292B1 (en) | A method for managing the lifecycle of a complex engineering object and a system for its implementation | |
Waspodo et al. | Development of car rental management information system | |
CN112651583A (en) | Fixed asset checking method and device, mobile terminal and storage medium | |
CA2836922A1 (en) | Interactive, real-time system and method for monitoring professional fees | |
Thi et al. | A review of quality frameworks in information systems | |
CN107622381A (en) | Record workpoints account checking method and device | |
TW202238471A (en) | Document configuration and circulation method | |
CN113554408A (en) | Capital efficiency supervision big data platform | |
CN112241858A (en) | Equipment material management system | |
Mokhlis et al. | Connecting Data, Model and Process to Streamline and Enhance Single-Point Production Well Test Validation | |
US11677621B2 (en) | System for generating data center asset configuration recommendations | |
Putra et al. | Project Monitoring System for Material Circulation | |
Qurratul | Development Of Car Rental Management Information System (Case Study: Avis Indonesia) | |
CN113722402B (en) | Method and device for constructing data warehouse based on business model and storage medium | |
May et al. | A Development of a Management Information System for Home Appliance Repairing | |
Zúñiga et al. | Management Support Systems Model for Incident Resolution in FinTech based on Business Intelligence. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180601 |