CN108107519A - For big section overlength degree shipping reel around multilayer storage cable disk and its application method - Google Patents

For big section overlength degree shipping reel around multilayer storage cable disk and its application method Download PDF

Info

Publication number
CN108107519A
CN108107519A CN201711213515.XA CN201711213515A CN108107519A CN 108107519 A CN108107519 A CN 108107519A CN 201711213515 A CN201711213515 A CN 201711213515A CN 108107519 A CN108107519 A CN 108107519A
Authority
CN
China
Prior art keywords
cable
partition plate
plate
storage
extra large
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711213515.XA
Other languages
Chinese (zh)
Other versions
CN108107519B (en
Inventor
黄晓尧
王晓建
宣耀伟
李捍平
郑新龙
李世强
陈国志
徐健
何旭涛
王亚耀
刘臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG ZHOUSHAN MARINE ELECTRIC POWER TRANSMISSION RESEARCH INSTITUTE Co Ltd
State Grid Zhejiang Electric Power Co Ltd
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
ZHEJIANG ZHOUSHAN MARINE ELECTRIC POWER TRANSMISSION RESEARCH INSTITUTE Co Ltd
State Grid Zhejiang Electric Power Co Ltd
Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG ZHOUSHAN MARINE ELECTRIC POWER TRANSMISSION RESEARCH INSTITUTE Co Ltd, State Grid Zhejiang Electric Power Co Ltd, Zhoushan Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical ZHEJIANG ZHOUSHAN MARINE ELECTRIC POWER TRANSMISSION RESEARCH INSTITUTE Co Ltd
Priority to CN201711213515.XA priority Critical patent/CN108107519B/en
Publication of CN108107519A publication Critical patent/CN108107519A/en
Application granted granted Critical
Publication of CN108107519B publication Critical patent/CN108107519B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G02OPTICS
    • G02BOPTICAL ELEMENTS, SYSTEMS OR APPARATUS
    • G02B6/00Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
    • G02B6/44Mechanical structures for providing tensile strength and external protection for fibres, e.g. optical transmission cables

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Storage Of Web-Like Or Filamentary Materials (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The invention discloses for big section overlength degree shipping reel around multilayer storage cable disk and its application method, be related to a kind of extra large cable storage cable disk.It is to need the technical barrier of key breakthrough at this stage to expand storage cable disk storage cable amount on existing operation platform.The present invention includes interior fence, outer fence, bottom plate, circular partition plate, bottom plate is rounded, interior fence, outer fence, bottom plate match to form the storage cable chamber of upward opening, partition plate is laterally set, storage cable chamber is separated into multilayer storage cable room, partition plate is equipped with to wear the arc groove of cable and the gap adjusting mechanism for adjusting arc well width.Storage cable disk is separated into multilayer by partition plate and stores up cable room by the technical program, every layer of storage independent load in cable room, when cable is stored up to the load limit in lower floor's storage cable room by increasing partition plate, establishing upper strata Chu Lan rooms, increase more storage cable abilities, the storage cable amount of storage cable disk can be effectively promoted, realizes the continuous coiling of extra large cable;If gap adjusting mechanism wears the extra large cable of different-diameter to be applicable in, functional reliability is improved.

Description

For big section overlength degree shipping reel around multilayer storage cable disk and its application method
Technical field
The present invention relates to a kind of extra large cable store up cable disk, more particularly, to big section overlength degree shipping reel around multilayer store up cable disk And its application method.
Background technology
As national marine is made the country prosperous implementation, the demand of extra large cable is significantly increased in market, to voltage class it is also proposed that Higher requirement.Under this background, extra large cable length and sectional area have significant increase, and so just the storage cable amount for storing up cable disk is carried Go out higher requirement.Existing storage cable disk device only has one layer, is made of medial and lateral fence with bottom plate, inside fence radius More than the permission bending radius of extra large cable, fence height and the storage cable number of plies are closely related, and bottom sea need to be met by storing up the cable number of plies Cable allows lateral pressure.In view of the stress of bottom extra large cable, storage cable disk fence height cannot infinitely increase, and be big section in extra large cable During overlength degree extra large cable, to meet the requirement of storage cable amount, the diameter of storage cable disk outer layer fence can only be increased, so not only occupy construction The area of platform is larger, and higher requirement is proposed to operation platform, and traditional method is that storage cable disk is put down with submarine cable operation Platform be transformed and dilatation or limited by submarine cable operation boat deck area and single extra large cable is blocked carry out respectively transport with Construction, which not only adds the expenses made with installation extra large cable connector, also run on maintenance to extra large cable and add risk, because This, how to expand storage cable disk storage cable amount on existing operation platform is to need the technical barrier of key breakthrough at this stage.
The content of the invention
The technical problem to be solved in the present invention and the technical assignment proposed are prior art to be improved with being improved, There is provided for big section overlength degree shipping reel around multilayer store up cable disk, with need not change shipping reel occupy operation platform deck plane For the purpose of the storage cable amount that storage cable disk is significantly promoted on the basis of product.For this purpose, the present invention takes following technical scheme.
For big section overlength degree shipping reel around multilayer store up cable disk, including interior fence, outer fence, bottom plate, the bottom Plate is rounded, and interior fence, outer fence, bottom plate match to form the storage cable chamber of upward opening, further includes circular partition plate, it is described every Plate is laterally set, and storage cable chamber is separated into multilayer storage cable room, the partition plate is equipped with to wear the arc groove of cable and be used for Adjust the gap adjusting mechanism of arc well width.Storage cable disk is separated by partition plate by multilayer and stores up cable room, every layer of storage cable room is independent Load when cable is stored up to the load limit in lower floor's storage cable room by increasing partition plate, establishing upper strata Chu Lan rooms, increases more storage cable energy Power can effectively promote the storage cable amount of storage cable disk, realize the continuous coiling of extra large cable;If gap adjusting mechanism is worn not with being applicable in With the extra large cable of diameter, functional reliability is improved.
As further improving and supplementing to above-mentioned technical proposal, present invention additionally comprises following additional technical features.
The interior fence is formed by multiple interior fence units are stacked up and down, and the outer fence is by multiple outer fence units Stacked up and down to form, madial wall, the lateral wall of outer fence unit of interior fence unit are equipped with supporting rack, the inner ring of partition plate with it is interior Fence unit matches, and outer ring and the outer fence unit of partition plate match;It is identical with the interior fence unit of layer, outer fence cell height. It by the modular construction of interior fence unit, outer fence unit, is not only convenient for carrying, and is convenient for when needing higher fence Stacked to build, by the matching of interior fence unit, outer fence unit and partition plate, multilayer storage cable room is built in realization.
The partition plate opens up multiple identical arc grooves, the arc groove tangent line at the interior fence and interior fence tangent line it Between angle be greater than or equal to 90 degree.Arc groove redirect to upper strata convenient for extra large cable from lower floor, arc groove and arc groove tangent line with Angle between interior fence tangent line is greater than or equal to 90 degree, convenient for when extra large cable goes to upper strata and turns around interior fence by arc groove not It is present with wide-angle bending, extra large cable will not be injured.
It is set on the partition plate there are two the arc groove at difference 180 degree angle, two arc grooves form serpentine clearance groove.Two The arc groove of center symmetric setting can easily make extra large cable be transferred to upper strata Chu Lan rooms, phase from its arc groove nearby Than in multiple arcs slot, simpler in structure, cost is lower.
The partition plate has the top of radial load bearing frame, the interior fence unit and outer fence unit Side is equipped with the locating slot to match with load bearing frame, and the top top surface of interior fence unit and outer fence unit is equipped with tenon, described Interior fence unit, outer fence unit lower end and partition plate corresponding position be equipped with tenon match mortise.By in partition plate Lower section sets load bearing frame, enhances the load ability of partition plate, and the locating slot at the top of interior fence unit and outer fence unit is just In lateralling secure for load bearing frame, realize and the load of load bearing frame in itself is supported;The connecting interface that tenon matches with mortise, no But it is easy to connect secured, and enhance the load ability of partition plate.
The partition plate is spliced by more plates, including base plate and sketch plate;Base plate is in sector, and both sides are straight flange, One side of the sketch plate is straight flange, another side is the arc-shaped edges to form arc groove.By the Modular Structure Design of partition plate, It carries and installation splicing is all very convenient
Each base plate, sketch plate are equipped with load bearing frame.Relatively evenly load can be provided partition plate to act on.
It is connected between adjacent foundation plate, between sketch plate and base plate by connector.Connector is easy to connect securely.
The arc groove and two tangent line angles of outer fence intersection are between 120 degree ~ 160 degree.Rational angle is not But it can effectively reduce extra large cable and be transferred to the buckling problem, and being closed on the premise of load ability is ensured excessively occurred during upper strata The load bearing frame of sketch plate, reduces the use of material, reduces cost on the outside of the removal arc groove of reason.
The connector is hinge and the screw for fixing hinge.Hinge connection mode, it is simply, convenient, securely.
It is a further object to provide it is a kind of for big section overlength degree shipping reel around multilayer storage cable disk make With method, comprise the following steps:
1)The bottom plate for storing up cable disk can be first installed on submarine cable operation platform deck or on rolling bearing by storage cable disk when mounted, Medial and lateral fence unit is arranged on storage cable and tries to get to the heart of a matter on plate, is split into a storage cable room;
2)Start to install partition plate, first installation foundation plate after the completion of bottom storage cable disk winding displacement, during installation foundation plate, base plate is held Power skeleton is placed at the locating slot on inside and outside gusset column, is connected between each base plate by connector, after in base plate, installation is complete Start sketch plate installation, sketch plate is connected with base plate, in installation process will load bearing frame be placed in medial and lateral fence card At slot, for partition plate after installation is complete, the medial and lateral fence unit that the second layer is set above partition plate forms a storage cable room, is further continued for sea Row's cable cloth cable work of cable, carries out building for upper strata Chu Lan rooms, repetitive operation, until arriving after the completion of the storage cable room winding displacement of the floor Up to the required number of plies.It is simple and convenient that cable process is built and arranged in storage cable room.
When extra large cable back twist mode uses height back twist during submarine cable operation, row's cable process is extra large cable out of bottom bottom plate Side is coiling to outside counterclockwise, then is coiling to inside counterclockwise by outside, and being coiling to bottom storage cable disk successively allows the interior of height At side, partition plate is installed at this time, and extra large cable, by continuing to coil on the inside of the nearest arrival upper strata of partition plate, coiling method is still the inverse time Pin from the inside to the outside by it is lower and on;Back twist payout process is inverse winding displacement process, and partition plate is dismantled after the extra large cable cable laying of upper strata, still Cable laying is carried out to bottom extra large cable according to inverse winding displacement process;
When extra large cable back twist mode is using back twist is rotated horizontally during submarine cable operation, row's cable process is inverse from inside bottom for extra large cable Hour hands are coiling to bottom upwards to be allowed at height, then is coiling to against the continuation of inside extra large cable at bottom bottom plate downwards, so in It outwards coils layer by layer, when being coiling at outside permission height, partition plate is installed, should take into full account extra large cable minimum allowable bending half at this time Suitable S types gap is selected to rise on the inside of upper strata storage cable disk behind footpath to continue to be coiled layer by layer by internal layer outer layers counterclockwise;Back twist is put Cable process is still inverse winding displacement process, and partition plate is dismantled after the extra large cable cable laying of upper strata, according to inverse winding displacement process to bottom extra large cable into Row cable laying.It can be easily to realize row's cable in a manner of different back twists.
Advantageous effect:
1st, solve submarine cable operation platform storage cable amount and be limited to storage cable disk and highly have to expand storage cable disk overall diameter or seek bigger The technical barrier of operation platform, extra large cable reserves greatly promote on the premise of same operation platform, without expanding cable circle, change ship The body structure improvement cost excessively high with input;In addition, under the storage cable requirement of identical tonnage, cable disk smaller used, submarine cable operation Platform smaller saves cable disk improvement expenses or large-scale submarine cable operation platform lease expenses, smaller operation platform to a certain degree The passage that means to construct is broader, is more advantageous to that work progress is safe and orderly to carry out.
2nd, the setting of arc groove makes extra large cable meet the requirement of minimum allowable bending radius when passing through gap plate, and extra large cable will not It is damaged when being bent because crossing.
3rd, by adding load bearing frame, improve the load ability of partition plate, prevent extra large cable multilayer arrange around rear appearance every Plate occurs staying problem.
4th, the unit-modularized structure of interior fence, outer fence and partition plate facilitates carrying, installation.
5th, row's cable of different back twist modes can be conveniently realized, row's cable is easy to operation.
Description of the drawings
Fig. 1 is schematic structural view of the invention.
Fig. 2 is overlooking the structure diagram of the present invention.
Fig. 3 is the single layer structure schematic diagram that the present invention does not install partition plate.
In figure:1- outer fences;Fence in 2-;3- partition plates;4- load bearing frames;5- arc grooves;6- bottom plates;7- tenons;301- Base plate;302- sketch plates.
Specific embodiment
Technical scheme is described in further detail below in conjunction with Figure of description.
As shown in Figs. 1-3, for big section overlength degree shipping reel around multilayer store up cable disk, including interior fence 2, outer fence 1, Bottom plate 6, bottom plate 6 is rounded, and interior fence 2, outer fence 1, bottom plate 6, which match, forms the storage cable chamber of upward opening, further includes circular Partition plate 3, partition plate 3 are laterally set, and storage cable chamber is separated into multilayer storage cable room, partition plate 3 be equipped with to wear the arc groove 5 of cable and For adjusting the gap adjusting mechanism of 5 width of arc groove.
Multilayer storage cable room is built in order to easily realize, interior fence 2 is formed by multiple interior fence units are stacked up and down, periphery Column 1 is formed by multiple outer fence units are stacked up and down, and madial wall, the lateral wall of outer fence unit of interior fence unit are equipped with branch Support, the inner ring of partition plate 3 match with interior fence unit, and outer ring and the outer fence unit of partition plate 3 match;With the interior fence list of layer Member, outer fence cell height are identical.By the modular construction of interior fence unit, outer fence unit, it is not only convenient for carrying, and It is built when needing higher fence convenient for stacked, by the matching of interior fence unit, outer fence unit and partition plate 3, easily Multilayer storage cable room is built in realization.
Upper strata row is gone to around being set on partition plate 3 there are two the arc groove 5 at difference 180 degree angle, two from lower floor for the ease of extra large cable Arc groove 5 forms serpentine clearance groove.The angle between 2 tangent line of 5 tangent line of arc groove and interior fence at interior fence 2 is 150 Degree.Arc groove 5 redirect to upper strata convenient for extra large cable from lower floor, the folder between 2 tangent line of arc groove 5 and 5 tangent line of arc groove and interior fence Angle is 150 degree, convenient for that will not make the actual flexion radius of extra large cable when extra large cable goes to upper strata and turns around interior fence 2 by arc groove 5 Allow bending radius less than it, extra large cable will not be injured, the arc groove 5 of two center symmetric settings can easily make extra large cable Upper strata Chu Lan rooms are transferred to from its arc groove 5 nearby, simpler in structure compared to multiple arcs slot 5, cost is more It is low.
In order to enhance the load ability to extra large cable, partition plate 3 has a radial load bearing frame 4, interior fence unit and The top-side of outer fence unit is equipped with the top of the locating slot to match with load bearing frame 4, interior fence unit and outer fence unit Top surface is equipped with tenon 7, and the corresponding position of interior fence unit, the lower end of outer fence unit and partition plate 3 is equipped with the tenon to match with tenon 7 Hole.By setting load bearing frame 4 below partition plate 3, the load ability of partition plate 3, interior fence unit and outer fence unit are enhanced The locating slot at top being laterallyd secure convenient for load bearing frame 4, realize the load support to load bearing frame 4 itself;Tenon 7 and tenon The connecting interface that hole matches, it is not only easy to connect secured, and enhance the load ability of partition plate 3.
For the ease of installing and splicing, partition plate 3 is spliced by more plates, including base plate 301 and sketch plate 302;Basis Plate 301 is straight flange in sector, both sides, and one side of sketch plate 302 is straight flange, another side is the arc-shaped edges to form arc groove 5.Pass through The Modular Structure Design of partition plate 3, is carried and installation splicing is all very convenient.
In order to provide partition plate 3 relatively evenly load effect, each base plate 301, sketch plate 302 are equipped with load bearing frame 4.By the way that load bearing frame 4 is arranged on every piece of 3 lower section of partition plate, relatively evenly load effect can be provided partition plate 3.
In order to it is easy to connect securely, pass through connector between adjacent foundation plate 301, between sketch plate 302 and base plate 301 Connection.Connector is easy to connect securely.
In order to reduce the use of framework material, arc groove 5 and two tangent line angles of 1 intersection of outer fence are 150 degree.Rationally Angle not only can effectively reduce extra large cable and be transferred to the buckling problem of crossing occurred during upper strata, and can ensure load ability Under the premise of reasonably remove the load bearing frame 4 of 5 outside sketch plate 302 of arc groove, reduce the use of material, reduce cost.
In order to easy to connect, secured, connector is hinge and the screw for fixing hinge.Hinge connection mode, simply, It is convenient, securely.
The installation process for storing up cable disk is as follows:
The bottom plate 6 for storing up cable disk is first installed on the rolling bearing of submarine cable operation platform by 1 storage cable disk when mounted, inside and outside gusset Column unit is arranged on the bottom plate 6 of storage cable disk, is split into a storage cable room;
2 start to install after the completion of bottom storage cable disk winding displacement partition plate 3, first installation foundation plate 301, during installation foundation plate 301, hold Power skeleton 4 is placed at the locating slot on inside and outside gusset column, is connected between each base plate 301 by hinge with screw, in base plate 301 Start the installation of sketch plate 302 after installation is complete, sketch plate 302 is connected with base plate 301, it will load bone in installation process Frame 4 is placed at the fence card slot of medial and lateral, and during installation, the mortise of partition plate 3 is connected with the tenon of inside and outside fence, and installation is complete for partition plate 3 Afterwards, the medial and lateral fence unit that the second layer is set above partition plate 3 forms a storage cable room, is further continued for row's cable cloth cable work of extra large cable, Building for upper strata Chu Lan rooms, repetitive operation, until the number of plies needed for reaching are carried out after the completion of the storage cable room winding displacement of the floor.
It is as follows that cable process is arranged according to different back twist modes:
1 when extra large cable back twist mode uses height back twist during submarine cable operation, and row's cable process is extra large cable on the inside of bottom bottom plate 6 Outside is coiling to counterclockwise, then is coiling to inside counterclockwise by outside, and being coiling to bottom storage cable disk successively allows the inside of height Partition plate 3 is installed at place at this time, and extra large cable is reached by partition plate 3 nearest one and continues to coil on the inside of upper strata, and coiling method is still the inverse time Pin from the inside to the outside by it is lower and on;Back twist payout process is inverse winding displacement process, and partition plate 3 is dismantled after the extra large cable cable laying of upper strata, according to It is old that cable laying is carried out to bottom extra large cable according to inverse winding displacement process;
2 when extra large cable back twist mode is using back twist is rotated horizontally during submarine cable operation, and row's cable process is extra large cable from inside bottom The bottom counterclockwise that is coiling to upwards allows at height, then is coiling to against the continuation of inside extra large cable at bottom bottom plate 6 downwards, so certainly It coils layer by layer from inside to outside, when being coiling at outside permission height, partition plate 3 is installed, should take into full account that extra large cable minimum allowable is curved at this time Suitable S types gap is selected to rise on the inside of upper strata storage cable disk after bilge radius to continue to be coiled layer by layer by internal layer outer layers counterclockwise;It moves back It is still inverse winding displacement process to turn round payout process, and partition plate 3 is dismantled after the extra large cable cable laying of upper strata, according to inverse winding displacement process to bottom sea Cable carries out cable laying.
Shown in figure 1 above -3 for big section overlength degree shipping reel around multilayer storage cable disk and its application method be this hair Bright specific embodiment has embodied substantive distinguishing features of the present invention and progress, can be according to actual use needs, in the present invention Enlightenment under, carry out equivalent modifications to it, this programme protection domain row.

Claims (10)

1. for big section overlength degree shipping reel around multilayer store up cable disk, including interior fence(2), outer fence(1), bottom plate(6), institute The bottom plate stated(6)It is rounded, interior fence(2), outer fence(1), bottom plate(6)Match and form the storage cable chamber of upward opening, feature It is:Further include circular partition plate(3), the partition plate(3)It laterally sets, storage cable chamber is separated into multilayer storage cable room, it is described Partition plate(3)It is equipped with to wear the arc groove of cable(5)And for adjusting arc groove(5)The gap adjusting mechanism of width.
2. it is according to claim 1 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is described Interior fence(2)It is formed by multiple interior fence units are stacked up and down, the outer fence(1)It is folded up and down by multiple outer fence units It puts, madial wall, the lateral wall of outer fence unit of interior fence unit are equipped with supporting rack, partition plate(3)Inner ring enclosed with interior Column unit matches, partition plate(3)Outer ring and outer fence unit match;It is identical with the interior fence unit of layer, outer fence cell height.
3. it is according to claim 2 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is described Partition plate(3)Open up multiple identical arc grooves(5), close to interior fence(2)The arc groove at place(5)Tangent line and interior fence(2)It cuts Angle between line is greater than or equal to 90 degree.
4. it is according to claim 3 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is described Partition plate(3)On set that there are two the arc grooves at difference 180 degree angle(5), two arc grooves(5)Form serpentine clearance groove.
5. according to claim 1 or 2 or 3 or 4 for big section overlength degree shipping reel around multilayer store up cable disk, feature It is:The partition plate(3)Have radial load bearing frame(4), the interior fence unit and outer fence unit Top-side is equipped with and load bearing frame(4)The top top surface of the locating slot of matching, interior fence unit and outer fence unit is equipped with tenon Head(7), interior fence unit, the lower end of outer fence unit and the partition plate(3)Corresponding position be equipped with and tenon(7)Match Mortise.
6. it is according to claim 5 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is described Partition plate(3)It is spliced by more plates, including base plate(301)And sketch plate(302);Base plate(301)In sector, both sides are Straight flange, the sketch plate(302)One side be straight flange, another side is to form arc groove(5)Arc-shaped edges.
7. it is according to claim 6 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is each Base plate(301), sketch plate(302)It is equipped with load bearing frame(4).
8. it is according to claim 7 for big section overlength degree shipping reel around multilayer store up cable disk, it is characterised in that:It is adjacent Base plate(301)Between, sketch plate(302)With base plate(301)Between connected by connector.
9. for big section overlength degree shipping reel around multilayer storage cable disk application method, it is characterised in that comprise the following steps:
1)The bottom plate of cable disk will can first be stored up when mounted by storing up cable disk(6)It is installed on submarine cable operation platform deck or rolling bearing On, medial and lateral fence unit is arranged on storage cable and tries to get to the heart of a matter plate(6)On, it is split into a storage cable room;
2)After the completion of bottom storage cable disk winding displacement start that partition plate is installed(3), installation foundation plate first(301), installation foundation plate (301)When, base plate(301)Load bearing frame(4)It is placed at the locating slot on inside and outside gusset column, each base plate(301)Between pass through Connector connects, in base plate(301)Start sketch plate after installation is complete(302)Installation, by sketch plate(302)With base plate (301)It connects, it will load bearing frame in installation process(4)It is placed at the fence card slot of medial and lateral, partition plate(3)After installation is complete, Partition plate(3)The medial and lateral fence unit that top sets the second layer forms a storage cable room, is further continued for row's cable cloth cable work of extra large cable, when Building for upper strata Chu Lan rooms, repetitive operation, until the number of plies needed for reaching are carried out after the completion of the storage cable room winding displacement of the floor.
10. it is according to claim 9 for big section overlength degree shipping reel around multilayer storage cable disk application method, it is special Sign is:When extra large cable back twist mode uses height back twist during submarine cable operation, row's cable process is extra large cable from bottom bottom plate(6) Inside is coiling to outside counterclockwise, then is coiling to inside counterclockwise by outside, and being coiling to bottom storage cable disk successively allows height At inside, partition plate is installed at this time(3), and extra large cable is by partition plate(3)At nearest one reach upper strata on the inside of continue to coil, coiling method according to It is old for counterclockwise from the inside to the outside by it is lower and on;Back twist payout process is inverse winding displacement process, is dismantled after the extra large cable cable laying of upper strata Partition plate(3), cable laying still is carried out to bottom extra large cable according to inverse winding displacement process;
When extra large cable back twist mode is using back twist is rotated horizontally during submarine cable operation, row's cable process is inverse from inside bottom for extra large cable Hour hands are coiling to bottom upwards to be allowed at height, then is coiling to bottom bottom plate downwards against the continuation of inside extra large cable(6)Place, so certainly It coils layer by layer from inside to outside, when being coiling at outside permission height, partition plate is installed(3), extra large cable minimum allowable should be taken into full account at this time Suitable S types gap is selected to rise on the inside of upper strata storage cable disk after bending radius to continue to be coiled layer by layer by internal layer outer layers counterclockwise; Back twist payout process is still inverse winding displacement process, and partition plate is dismantled after the extra large cable cable laying of upper strata(3), according to inverse winding displacement process the bottom of to Layer extra large cable carries out cable laying.
CN201711213515.XA 2017-11-28 2017-11-28 Multi-layer cable storage disc for coiling large-section super-long submarine cable and using method thereof Active CN108107519B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711213515.XA CN108107519B (en) 2017-11-28 2017-11-28 Multi-layer cable storage disc for coiling large-section super-long submarine cable and using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711213515.XA CN108107519B (en) 2017-11-28 2017-11-28 Multi-layer cable storage disc for coiling large-section super-long submarine cable and using method thereof

Publications (2)

Publication Number Publication Date
CN108107519A true CN108107519A (en) 2018-06-01
CN108107519B CN108107519B (en) 2020-04-10

Family

ID=62207812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711213515.XA Active CN108107519B (en) 2017-11-28 2017-11-28 Multi-layer cable storage disc for coiling large-section super-long submarine cable and using method thereof

Country Status (1)

Country Link
CN (1) CN108107519B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110007416A (en) * 2019-04-26 2019-07-12 中海油(天津)管道工程技术有限公司 Cable system and method is worn for the monitoring optical cable installation of submarine pipeline casing annulus
CN117105013A (en) * 2023-10-17 2023-11-24 江苏亨通华海科技股份有限公司 Cable transportation tray frame

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3819847A (en) * 1973-04-16 1974-06-25 J Charles Method and apparatus for storing buried telephone distribution wires
CN2318197Y (en) * 1997-03-08 1999-05-12 李冰 Electric wire, cable dilievery device side panel
CN2338321Y (en) * 1998-08-05 1999-09-15 赖政廷 Electric wire collecting box
CN1332693A (en) * 1998-12-30 2002-01-23 康宁股份有限公司 Optical fiber spool providing access to the inner end of the wound optical fiber
CN1800896A (en) * 2004-12-31 2006-07-12 徐培军 Method for coiling optical fiber in communication equipment
CN201041591Y (en) * 2007-04-28 2008-03-26 上海华诚通信器材有限公司 Fiber shielding board
CN203376509U (en) * 2013-08-09 2014-01-01 昆明华视讯网络科技有限公司 Modularized multilayer winding fiber ring
CN205114689U (en) * 2015-11-24 2016-03-30 陈垚佳 Winding device for cable
CN205204520U (en) * 2015-11-06 2016-05-04 乐视移动智能信息技术(北京)有限公司 Winder
CN205820573U (en) * 2016-07-05 2016-12-21 国网天津市电力公司 A kind of tail optical fiber fiber winding disk

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3819847A (en) * 1973-04-16 1974-06-25 J Charles Method and apparatus for storing buried telephone distribution wires
CN2318197Y (en) * 1997-03-08 1999-05-12 李冰 Electric wire, cable dilievery device side panel
CN2338321Y (en) * 1998-08-05 1999-09-15 赖政廷 Electric wire collecting box
CN1332693A (en) * 1998-12-30 2002-01-23 康宁股份有限公司 Optical fiber spool providing access to the inner end of the wound optical fiber
CN1800896A (en) * 2004-12-31 2006-07-12 徐培军 Method for coiling optical fiber in communication equipment
CN201041591Y (en) * 2007-04-28 2008-03-26 上海华诚通信器材有限公司 Fiber shielding board
CN203376509U (en) * 2013-08-09 2014-01-01 昆明华视讯网络科技有限公司 Modularized multilayer winding fiber ring
CN205204520U (en) * 2015-11-06 2016-05-04 乐视移动智能信息技术(北京)有限公司 Winder
CN205114689U (en) * 2015-11-24 2016-03-30 陈垚佳 Winding device for cable
CN205820573U (en) * 2016-07-05 2016-12-21 国网天津市电力公司 A kind of tail optical fiber fiber winding disk

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110007416A (en) * 2019-04-26 2019-07-12 中海油(天津)管道工程技术有限公司 Cable system and method is worn for the monitoring optical cable installation of submarine pipeline casing annulus
CN117105013A (en) * 2023-10-17 2023-11-24 江苏亨通华海科技股份有限公司 Cable transportation tray frame
CN117105013B (en) * 2023-10-17 2024-01-23 江苏亨通华海科技股份有限公司 Cable transportation tray frame

Also Published As

Publication number Publication date
CN108107519B (en) 2020-04-10

Similar Documents

Publication Publication Date Title
CN108107519A (en) For big section overlength degree shipping reel around multilayer storage cable disk and its application method
US8327908B2 (en) Sectional folding up garage door
CN105564668B (en) A kind of coiling extending arm for being segmented asymptotic expansion successively
CN207924211U (en) A kind of multilayer storage cable disk that big section overlength degree extra large cable can be achieved and continuously coils
CN106536919A (en) Modular system for transporting wind turbine blades
NL2018377B1 (en) METHOD FOR PLACING A WINDMILL
KR20130116876A (en) Ship having a deck comprising a cavity with a built-in rotary plate
US20130186890A1 (en) Tank panels and tanks formed therefrom
US8763309B2 (en) Deployable and inflatable roof, wall, or other structure for stadiums and other venues
CN108275503B (en) Combined sea cable back twist system for multiple section sea cable back twist
CN105178438B (en) Architecture storey rotary system, water supply installation, electric supply installation and drainage arrangement
EP0973980B1 (en) Retractable covering for spaces
WO1998045544A9 (en) Retractable covering for spaces
CN108657885A (en) A kind of cable portable winding transport device
GB2621795A (en) Forming process for ultra-large-diameter annular reinforcing mesh component
CN207177450U (en) Municipal construction fence
CN110374113A (en) Suitable for steel pipe support foundation pit fast support replacing method and active joint
CN208789883U (en) A kind of ship hawser wrap-up
JP2015501760A (en) Openable cover for ships, especially cruise ships
CN209721179U (en) Removable portable actinomycetes box
CN207896580U (en) A kind of new type foldable cable trough
CN106592762A (en) Space assembling type bolt-column joint
CN207467865U (en) A kind of back twist system for being suitable for multiple section extra large cable
CN106593028B (en) Portable stage
CN214532321U (en) Interim rail guard of foundation ditch

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant