CN108104482B - Batter post installation method - Google Patents

Batter post installation method Download PDF

Info

Publication number
CN108104482B
CN108104482B CN201711484606.7A CN201711484606A CN108104482B CN 108104482 B CN108104482 B CN 108104482B CN 201711484606 A CN201711484606 A CN 201711484606A CN 108104482 B CN108104482 B CN 108104482B
Authority
CN
China
Prior art keywords
batter post
steel column
batter
post
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711484606.7A
Other languages
Chinese (zh)
Other versions
CN108104482A (en
Inventor
郭桂钦
周吉林
陈卓英
李先知
陆炳春
闫海涛
吴慧
柯长元
文良波
田丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Cross Central Business District Construction Holding Co Ltd
Original Assignee
Zhuhai Cross Central Business District Construction Holding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Cross Central Business District Construction Holding Co Ltd filed Critical Zhuhai Cross Central Business District Construction Holding Co Ltd
Priority to CN201711484606.7A priority Critical patent/CN108104482B/en
Publication of CN108104482A publication Critical patent/CN108104482A/en
Application granted granted Critical
Publication of CN108104482B publication Critical patent/CN108104482B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This patent discloses the installation methods of batter post, comprising the following steps: step 1: lifting prepares;Step 2: batter post suspension centre setting;Step 3: the lifting of batter post;Step 4: the interim connection of batter post;Step 5: batter post docks regulation measure;Step 6: welding.This programme mainly solves the problems, such as that batter post position adjusts low efficiency when the installation of current batter post.

Description

Batter post installation method
Technical field
The present invention relates to construction steel structure technical fields.
Background technique
With the development of national economy, urban population is increased sharply, and each area, municipal government are to meet local people's culture life need It asks, a large amount of culture and sports buildings etc. are come by construction.Simultaneously for that can embody local humane, pursuit, this mark system building is also got over Come more diversified, this is also that skills in the process of construction proposes higher challenge.
To meet the stress demand such as antitorque, resistance to compression, shearing resistance in building shape and structure, and outline border batter post is gradually appeared (abbreviation batter post).The features such as batter post is big often with standby height in large public building, and sectional dimension is wide.In actual mechanical process, Installation for above-mentioned batter post needs to realize alignment operation, so that the installation site of batter post is accurate, to guarantee the steady of mounting structure It is fixed;But be primarily now to observe to judge by staff, not only judgement is inaccurate, and to the eyesight and environment of staff Visibility requirement is high, and the position of batter post is caused to adjust inaccuracy, needs using multiple observation judgement and adjusts, working efficiency It is low.
Summary of the invention
The invention is intended to provide a kind of batter post installation method, batter post position adjusts low efficiency when solving the installation of current batter post The problem of.
In order to achieve the above object, base case of the invention is as follows: batter post installation method, comprising the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepare wirerope and Snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and on temporary connection plate Reserved hole for hoist;On connecting plate also installation detection lamp, be equipped between any two temporary connection plate protrude into it is auxiliary in batter post Frame is helped, the reflecting mirror of rotation connection reflection detection lamp wiring, reflecting mirror vertical direction are oppositely arranged with detection lamp on auxiliary frame;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, the hole for hoist on snap ring and temporary connection plate connects It connects;Loop wheel machine hooks the lifting that wirerope realizes batter post, and hooks up, rotates when lifting, moving three movements alternately slowly progress, just It slowly falls when position, prevents component from significantly swinging and shaking;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;The light that detection lamp projects is sent out through reflecting mirror It penetrates, staff checks whether batter post has light with the place of docking of steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;When batter post and steel When having light at the docking of column, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column Not exclusively fitting;The adjusting of force block realization batter post vertical direction is pushed by the first jack, the second jack pushes batter post Realize the adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column;When batter post does not have with the place of docking of steel column When light, i.e., the center line of the center line of batter post and steel column is on same straight line, and batter post is bonded completely with steel column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
The advantages of base case: this programme is prompted compared to the installation method of current batter post using reflecting mirror reflection light Staff visually observes instead of staff, enhances the judgment accuracy of staff;When batter post and steel column butt joint, observation Whether light injection is had at its docking, moreover it can be used to which it is straight whether the center line of the center line and steel column that detect batter post is located at same Whether line, batter post are bonded completely with steel column, effectively increase the adjusting efficiency of batter post.
Preferred embodiment one: as the preferred embodiment of basic scheme, installing steel ladder on batter post, can be convenient for staff Operation on steel ladder.
Preferred embodiment two: preferably one preferred embodiment, installation is for drawing the safety for setting safety rope on batter post Ring guarantees the safety for executing the staff of next procedure.
Preferred embodiment three: preferably two preferred embodiment installs sleeper in the bottom of batter post, prevents batter post from lifting by crane When it is dilatory on ground caused by ground or batter post damage.
Preferred embodiment four: preferably three preferred embodiment is equipped with attracting with batter post inner wall on auxiliary frame Magnet;By above-mentioned setting, magnet can the movement of auxiliary frame play the role of guiding, moreover it is possible to further increase temporary connection plate The stability being connect with batter post.
Preferred embodiment five: preferably four preferred embodiment connects elastic elastic on auxiliary frame and reflecting mirror; By above-mentioned setting, after batter post moves to destination, distinguished and admirable disappearance, reflecting mirror can rotate under the action of elastic force elastic generates wind Stream, the distinguished and admirable dregs and sundries that can be used for removing batter post and steel column surface.
Detailed description of the invention
Fig. 1 is the flow diagram of batter post installation method embodiment of the present invention.
Specific embodiment
Below by the further details of explanation of specific embodiment:
Batter post installation method, comprising the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepare wirerope and Snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and on temporary connection plate Reserved hole for hoist.Rigid ladder is also equipped on batter post, it can the operation on steel ladder convenient for staff.Installation is for drawing on batter post If the safety collar of safety rope, guarantee the safety for executing the staff of next procedure.Sleeper is installed in the bottom of batter post, prevents batter post Ground caused by being drawn when lifting on ground or batter post damage.Also installation detects lamp on connecting plate;Any two temporary connection plate Between the auxiliary frame protruded into batter post is installed, the reflecting mirror of rotation connection reflection detection lamp wiring on auxiliary frame, and auxiliary frame With connect elastic elastic on reflecting mirror, reflecting mirror vertical direction is oppositely arranged with detection lamp;Be equipped on auxiliary frame with tiltedly The attracting magnet of column wall;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, the hole for hoist on snap ring and temporary connection plate connects It connects;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;Wherein, vertically Regulation measure: it is mounted on otic placode on four side walls of batter post, force block is installed on otic placode, on the steel column docked with batter post First support plate is installed, first jack of the vertical direction towards force block is installed in the first support plate;Wherein, horizontal to adjust Section measure: being equipped with the second support plate on the steel column docked with batter post, and horizontal direction is equipped in the second support plate towards tiltedly Second jack of column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
When the present embodiment operates, open detection lamp, so that the effect of light that detection lamp projects is on reflecting mirror;Utilize crane It hooks up, rotate when hooking the lifting that wirerope realizes batter post, and lifting, moving three movements alternately slowly progress, delaying when in place It is slow to fall, prevent component from significantly swinging and shaking;During batter post transport, reflecting mirror can occur under the action of distinguished and admirable Rotation, reflecting mirror can circumferentially reflect light, clearer can observe batter post bottom convenient for staff.
Batter post is moved to above the steel column that is docked with batter post, and batter post is close enough with steel column, enables the first jack It enough acts on force block, the second jack can act on batter post, then observe the light of reflecting mirror transmitting;When batter post and steel When having light at the docking of column, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column Not exclusively fitting;It is illuminated using the light that reflecting mirror reflects, the first jack pushes force block to realize batter post vertical direction Adjusting, the second jack pushes batter post to realize the adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column, So that the center line of batter post and the center line of steel column are located on the same line.
Batter post and steel column butt joint observe at its docking whether there are also light to project, can be detected the center line and steel of batter post Whether the center line of column is located at same straight line, and whether batter post is bonded completely with steel column;If there are also light, illustrate batter post The center line of center line and steel column is not at same straight line, and batter post is not bonded completely with steel column, can be very heavy by second Pushing tow moves the adjusting that batter post realizes batter post horizontal direction;If illustrating the center line of batter post center line and steel column without light Positioned at same straight line, batter post is bonded completely with steel column, then is welded to batter post with the place of docking of steel column.

Claims (6)

1. batter post installation method, which comprises the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepares wirerope and snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and is reserved on temporary connection plate Hole for hoist;Also installation detects lamp on connecting plate, and the auxiliary frame protruded into batter post is equipped between any two temporary connection plate, The reflecting mirror of rotation connection reflection detection lamp wiring, reflecting mirror vertical direction are oppositely arranged with detection lamp on auxiliary frame;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, snap ring is connect with the hole for hoist on temporary connection plate;It hangs Machine hooks the lifting that wirerope realizes batter post, and hooks up, rotates when lifting, moving three movements alternately slowly progress, when in place It slowly falls, prevents component from significantly swinging and shaking;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;The light that detection lamp projects emits through reflecting mirror, Staff checks whether batter post has light with the place of docking of steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;Wherein, vertical adjusting Measure: it is mounted on otic placode on four side walls of batter post, force block is installed on otic placode, is installed on the steel column docked with batter post There is the first support plate, first jack of the vertical direction towards force block is installed in the first support plate;When batter post and steel column When having light at docking, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column are endless Full fitting;The adjusting of force block realization batter post vertical direction is pushed by the first jack, the second jack pushes batter post to realize The adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column;The no light in place is docked when batter post and steel column When, i.e., the center line of the center line of batter post and steel column is on same straight line, and batter post is bonded completely with steel column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
2. batter post installation method according to claim 1, it is characterised in that: install steel ladder on batter post, be convenient for work Personnel can the operation on steel ladder.
3. batter post installation method according to claim 2, it is characterised in that: installation sets safety rope for drawing on batter post Safety collar guarantees the safety for executing the staff of next procedure.
4. batter post installation method according to claim 3, it is characterised in that: install sleeper in the bottom of batter post, prevent tiltedly Ground caused by being drawn when column lifts by crane on ground or batter post damage.
5. batter post installation method according to claim 4, it is characterised in that: be equipped on auxiliary frame and batter post inner wall phase The magnet of suction.
6. batter post installation method according to claim 5, it is characterised in that: connected on auxiliary frame and reflecting mirror elastic Elastic.
CN201711484606.7A 2017-12-29 2017-12-29 Batter post installation method Active CN108104482B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711484606.7A CN108104482B (en) 2017-12-29 2017-12-29 Batter post installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711484606.7A CN108104482B (en) 2017-12-29 2017-12-29 Batter post installation method

Publications (2)

Publication Number Publication Date
CN108104482A CN108104482A (en) 2018-06-01
CN108104482B true CN108104482B (en) 2019-11-29

Family

ID=62214973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711484606.7A Active CN108104482B (en) 2017-12-29 2017-12-29 Batter post installation method

Country Status (1)

Country Link
CN (1) CN108104482B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108798032A (en) * 2018-06-11 2018-11-13 上海通用建筑工程有限公司 A kind of hanging method of high-rise steel structure column
CN111519910B (en) * 2020-05-06 2021-11-16 中建八局第一建设有限公司 Multi-angle large-slope steel column hoisting method and protection frame body assembly used in cooperation with same
CN115492397A (en) * 2022-06-01 2022-12-20 中冶(上海)钢结构科技有限公司 Installation method of steel inclined column close to existing inclined structure

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587656B (en) * 2012-03-05 2015-10-07 中建三局建设工程股份有限公司 Super highrise building rectangular steel pipe bending post or tilt column construction
CN104612307B (en) * 2014-12-24 2017-03-08 上海中建八局装饰有限责任公司 Ceiling system and its construction method
CN106284988A (en) * 2016-09-28 2017-01-04 福建荣建集团有限公司 Oblique circular cylinder template and construction method thereof

Also Published As

Publication number Publication date
CN108104482A (en) 2018-06-01

Similar Documents

Publication Publication Date Title
US10435896B2 (en) Apparatus and method for lifting and sliding a structure attached to the wall
CN108104482B (en) Batter post installation method
CN104895335B (en) Method for mounting hanging pillar
CN110241739A (en) Hydraulic climbing formwork digital intelligent control platform
CN105565220A (en) Aerial working platform
CN210217317U (en) Concrete pole inclination correcting unit
CN202416811U (en) Stand for electric drill
CN104404888B (en) A kind of large-scale aerial gradient adjustment Lift-on/Lift-off System and application
AU2014304378B2 (en) Scaffold
JPH10195826A (en) Bridge construction method and device thereof
CN105239804A (en) Assembly and lift-erecting method of indirect air-cooling system stretching platforms
CN201753523U (en) Construction lifting platform with adjustable tilting angle
CN216129981U (en) Integrated integral multifunctional construction platform for pier and towering structure
CN104192738A (en) Crane and arm frame and auxiliary arm supporting device of crane
CN110453836B (en) Oblique glass curtain wall mounting system and mounting method
CN108677749B (en) PLC frequency conversion control system for bridge swivel construction
CN110886214B (en) Mounting and dismounting method of maintenance platform for bridge maintenance vehicle
CN113309256A (en) Construction device and construction method for prefabricated shear wall with post-pouring section
CN112960551B (en) Integral lifting auxiliary device for asymmetric large-scale grid structure
CN111350359A (en) Method and rhombic device for integrally lifting large-span structure
US10533327B2 (en) Rigging lift and method of use
CN209194362U (en) Rod piece connects levelling device between a kind of suspension bridge steel truss beam section
CN112523103A (en) Integrated integral multifunctional construction platform for pier and towering structure
CN205530776U (en) Removable formula damping device that trades of rubber support
CN206203763U (en) Self-driving floor hanging apparatus

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant