CN108104482B - Batter post installation method - Google Patents
Batter post installation method Download PDFInfo
- Publication number
- CN108104482B CN108104482B CN201711484606.7A CN201711484606A CN108104482B CN 108104482 B CN108104482 B CN 108104482B CN 201711484606 A CN201711484606 A CN 201711484606A CN 108104482 B CN108104482 B CN 108104482B
- Authority
- CN
- China
- Prior art keywords
- batter post
- steel column
- batter
- post
- installation method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
This patent discloses the installation methods of batter post, comprising the following steps: step 1: lifting prepares;Step 2: batter post suspension centre setting;Step 3: the lifting of batter post;Step 4: the interim connection of batter post;Step 5: batter post docks regulation measure;Step 6: welding.This programme mainly solves the problems, such as that batter post position adjusts low efficiency when the installation of current batter post.
Description
Technical field
The present invention relates to construction steel structure technical fields.
Background technique
With the development of national economy, urban population is increased sharply, and each area, municipal government are to meet local people's culture life need
It asks, a large amount of culture and sports buildings etc. are come by construction.Simultaneously for that can embody local humane, pursuit, this mark system building is also got over
Come more diversified, this is also that skills in the process of construction proposes higher challenge.
To meet the stress demand such as antitorque, resistance to compression, shearing resistance in building shape and structure, and outline border batter post is gradually appeared
(abbreviation batter post).The features such as batter post is big often with standby height in large public building, and sectional dimension is wide.In actual mechanical process,
Installation for above-mentioned batter post needs to realize alignment operation, so that the installation site of batter post is accurate, to guarantee the steady of mounting structure
It is fixed;But be primarily now to observe to judge by staff, not only judgement is inaccurate, and to the eyesight and environment of staff
Visibility requirement is high, and the position of batter post is caused to adjust inaccuracy, needs using multiple observation judgement and adjusts, working efficiency
It is low.
Summary of the invention
The invention is intended to provide a kind of batter post installation method, batter post position adjusts low efficiency when solving the installation of current batter post
The problem of.
In order to achieve the above object, base case of the invention is as follows: batter post installation method, comprising the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepare wirerope and
Snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and on temporary connection plate
Reserved hole for hoist;On connecting plate also installation detection lamp, be equipped between any two temporary connection plate protrude into it is auxiliary in batter post
Frame is helped, the reflecting mirror of rotation connection reflection detection lamp wiring, reflecting mirror vertical direction are oppositely arranged with detection lamp on auxiliary frame;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, the hole for hoist on snap ring and temporary connection plate connects
It connects;Loop wheel machine hooks the lifting that wirerope realizes batter post, and hooks up, rotates when lifting, moving three movements alternately slowly progress, just
It slowly falls when position, prevents component from significantly swinging and shaking;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;The light that detection lamp projects is sent out through reflecting mirror
It penetrates, staff checks whether batter post has light with the place of docking of steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;When batter post and steel
When having light at the docking of column, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column
Not exclusively fitting;The adjusting of force block realization batter post vertical direction is pushed by the first jack, the second jack pushes batter post
Realize the adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column;When batter post does not have with the place of docking of steel column
When light, i.e., the center line of the center line of batter post and steel column is on same straight line, and batter post is bonded completely with steel column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
The advantages of base case: this programme is prompted compared to the installation method of current batter post using reflecting mirror reflection light
Staff visually observes instead of staff, enhances the judgment accuracy of staff;When batter post and steel column butt joint, observation
Whether light injection is had at its docking, moreover it can be used to which it is straight whether the center line of the center line and steel column that detect batter post is located at same
Whether line, batter post are bonded completely with steel column, effectively increase the adjusting efficiency of batter post.
Preferred embodiment one: as the preferred embodiment of basic scheme, installing steel ladder on batter post, can be convenient for staff
Operation on steel ladder.
Preferred embodiment two: preferably one preferred embodiment, installation is for drawing the safety for setting safety rope on batter post
Ring guarantees the safety for executing the staff of next procedure.
Preferred embodiment three: preferably two preferred embodiment installs sleeper in the bottom of batter post, prevents batter post from lifting by crane
When it is dilatory on ground caused by ground or batter post damage.
Preferred embodiment four: preferably three preferred embodiment is equipped with attracting with batter post inner wall on auxiliary frame
Magnet;By above-mentioned setting, magnet can the movement of auxiliary frame play the role of guiding, moreover it is possible to further increase temporary connection plate
The stability being connect with batter post.
Preferred embodiment five: preferably four preferred embodiment connects elastic elastic on auxiliary frame and reflecting mirror;
By above-mentioned setting, after batter post moves to destination, distinguished and admirable disappearance, reflecting mirror can rotate under the action of elastic force elastic generates wind
Stream, the distinguished and admirable dregs and sundries that can be used for removing batter post and steel column surface.
Detailed description of the invention
Fig. 1 is the flow diagram of batter post installation method embodiment of the present invention.
Specific embodiment
Below by the further details of explanation of specific embodiment:
Batter post installation method, comprising the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepare wirerope and
Snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and on temporary connection plate
Reserved hole for hoist.Rigid ladder is also equipped on batter post, it can the operation on steel ladder convenient for staff.Installation is for drawing on batter post
If the safety collar of safety rope, guarantee the safety for executing the staff of next procedure.Sleeper is installed in the bottom of batter post, prevents batter post
Ground caused by being drawn when lifting on ground or batter post damage.Also installation detects lamp on connecting plate;Any two temporary connection plate
Between the auxiliary frame protruded into batter post is installed, the reflecting mirror of rotation connection reflection detection lamp wiring on auxiliary frame, and auxiliary frame
With connect elastic elastic on reflecting mirror, reflecting mirror vertical direction is oppositely arranged with detection lamp;Be equipped on auxiliary frame with tiltedly
The attracting magnet of column wall;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, the hole for hoist on snap ring and temporary connection plate connects
It connects;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;Wherein, vertically
Regulation measure: it is mounted on otic placode on four side walls of batter post, force block is installed on otic placode, on the steel column docked with batter post
First support plate is installed, first jack of the vertical direction towards force block is installed in the first support plate;Wherein, horizontal to adjust
Section measure: being equipped with the second support plate on the steel column docked with batter post, and horizontal direction is equipped in the second support plate towards tiltedly
Second jack of column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
When the present embodiment operates, open detection lamp, so that the effect of light that detection lamp projects is on reflecting mirror;Utilize crane
It hooks up, rotate when hooking the lifting that wirerope realizes batter post, and lifting, moving three movements alternately slowly progress, delaying when in place
It is slow to fall, prevent component from significantly swinging and shaking;During batter post transport, reflecting mirror can occur under the action of distinguished and admirable
Rotation, reflecting mirror can circumferentially reflect light, clearer can observe batter post bottom convenient for staff.
Batter post is moved to above the steel column that is docked with batter post, and batter post is close enough with steel column, enables the first jack
It enough acts on force block, the second jack can act on batter post, then observe the light of reflecting mirror transmitting;When batter post and steel
When having light at the docking of column, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column
Not exclusively fitting;It is illuminated using the light that reflecting mirror reflects, the first jack pushes force block to realize batter post vertical direction
Adjusting, the second jack pushes batter post to realize the adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column,
So that the center line of batter post and the center line of steel column are located on the same line.
Batter post and steel column butt joint observe at its docking whether there are also light to project, can be detected the center line and steel of batter post
Whether the center line of column is located at same straight line, and whether batter post is bonded completely with steel column;If there are also light, illustrate batter post
The center line of center line and steel column is not at same straight line, and batter post is not bonded completely with steel column, can be very heavy by second
Pushing tow moves the adjusting that batter post realizes batter post horizontal direction;If illustrating the center line of batter post center line and steel column without light
Positioned at same straight line, batter post is bonded completely with steel column, then is welded to batter post with the place of docking of steel column.
Claims (6)
1. batter post installation method, which comprises the following steps:
Step 1: lifting prepares;Prepare hollow batter post, according to the weight and hoisting point position of batter post, prepares wirerope and snap ring;
Step 2: batter post suspension centre setting;It is mounted on temporary connection plate in four side of the top of batter post, and is reserved on temporary connection plate
Hole for hoist;Also installation detects lamp on connecting plate, and the auxiliary frame protruded into batter post is equipped between any two temporary connection plate,
The reflecting mirror of rotation connection reflection detection lamp wiring, reflecting mirror vertical direction are oppositely arranged with detection lamp on auxiliary frame;
Step 3: the lifting of batter post;By wirerope-winding on snap ring, snap ring is connect with the hole for hoist on temporary connection plate;It hangs
Machine hooks the lifting that wirerope realizes batter post, and hooks up, rotates when lifting, moving three movements alternately slowly progress, when in place
It slowly falls, prevents component from significantly swinging and shaking;
Step 4: the interim connection of batter post;Batter post is temporarily docked with steel column;The light that detection lamp projects emits through reflecting mirror,
Staff checks whether batter post has light with the place of docking of steel column;
Step 5: batter post docks regulation measure, mainly includes vertical adjusting measure and Level tune measure;Wherein, vertical adjusting
Measure: it is mounted on otic placode on four side walls of batter post, force block is installed on otic placode, is installed on the steel column docked with batter post
There is the first support plate, first jack of the vertical direction towards force block is installed in the first support plate;When batter post and steel column
When having light at docking, i.e. the center line of batter post and the center line of steel column is not arranged on the same straight line, and batter post and steel column are endless
Full fitting;The adjusting of force block realization batter post vertical direction is pushed by the first jack, the second jack pushes batter post to realize
The adjusting of batter post horizontal direction, i.e., the relative position of adjustable batter post and steel column;The no light in place is docked when batter post and steel column
When, i.e., the center line of the center line of batter post and steel column is on same straight line, and batter post is bonded completely with steel column;
Step 6: welding;After the adjustment for completing batter post, batter post is completed to weld with the place of docking of steel column.
2. batter post installation method according to claim 1, it is characterised in that: install steel ladder on batter post, be convenient for work
Personnel can the operation on steel ladder.
3. batter post installation method according to claim 2, it is characterised in that: installation sets safety rope for drawing on batter post
Safety collar guarantees the safety for executing the staff of next procedure.
4. batter post installation method according to claim 3, it is characterised in that: install sleeper in the bottom of batter post, prevent tiltedly
Ground caused by being drawn when column lifts by crane on ground or batter post damage.
5. batter post installation method according to claim 4, it is characterised in that: be equipped on auxiliary frame and batter post inner wall phase
The magnet of suction.
6. batter post installation method according to claim 5, it is characterised in that: connected on auxiliary frame and reflecting mirror elastic
Elastic.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711484606.7A CN108104482B (en) | 2017-12-29 | 2017-12-29 | Batter post installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711484606.7A CN108104482B (en) | 2017-12-29 | 2017-12-29 | Batter post installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108104482A CN108104482A (en) | 2018-06-01 |
CN108104482B true CN108104482B (en) | 2019-11-29 |
Family
ID=62214973
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711484606.7A Active CN108104482B (en) | 2017-12-29 | 2017-12-29 | Batter post installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108104482B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798032A (en) * | 2018-06-11 | 2018-11-13 | 上海通用建筑工程有限公司 | A kind of hanging method of high-rise steel structure column |
CN111519910B (en) * | 2020-05-06 | 2021-11-16 | 中建八局第一建设有限公司 | Multi-angle large-slope steel column hoisting method and protection frame body assembly used in cooperation with same |
CN115492397A (en) * | 2022-06-01 | 2022-12-20 | 中冶(上海)钢结构科技有限公司 | Installation method of steel inclined column close to existing inclined structure |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102587656B (en) * | 2012-03-05 | 2015-10-07 | 中建三局建设工程股份有限公司 | Super highrise building rectangular steel pipe bending post or tilt column construction |
CN104612307B (en) * | 2014-12-24 | 2017-03-08 | 上海中建八局装饰有限责任公司 | Ceiling system and its construction method |
CN106284988A (en) * | 2016-09-28 | 2017-01-04 | 福建荣建集团有限公司 | Oblique circular cylinder template and construction method thereof |
-
2017
- 2017-12-29 CN CN201711484606.7A patent/CN108104482B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108104482A (en) | 2018-06-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10435896B2 (en) | Apparatus and method for lifting and sliding a structure attached to the wall | |
CN108104482B (en) | Batter post installation method | |
CN104895335B (en) | Method for mounting hanging pillar | |
CN110241739A (en) | Hydraulic climbing formwork digital intelligent control platform | |
CN210217317U (en) | Concrete pole inclination correcting unit | |
CN208415485U (en) | The aerial steel vestibule Lift-on/Lift-off System of multilayer | |
CN202416811U (en) | Stand for electric drill | |
CN104404888B (en) | A kind of large-scale aerial gradient adjustment Lift-on/Lift-off System and application | |
AU2014304378B2 (en) | Scaffold | |
CN112523103A (en) | Integrated integral multifunctional construction platform for pier and towering structure | |
CN111350359A (en) | Method and rhombic device for integrally lifting large-span structure | |
CN217711827U (en) | Steel column adjusting device that takes one's place | |
JPH10195826A (en) | Bridge construction method and device thereof | |
CN206395795U (en) | Hydraulic type cable well lid easy opening device | |
CN105239804A (en) | Assembly and lift-erecting method of indirect air-cooling system stretching platforms | |
CN216129981U (en) | Integrated integral multifunctional construction platform for pier and towering structure | |
CN211232799U (en) | Lifting lamp bracket for navigation aid lamp | |
CN104192738A (en) | Crane and arm frame and auxiliary arm supporting device of crane | |
CN108677749B (en) | PLC frequency conversion control system for bridge swivel construction | |
CN110886214B (en) | Mounting and dismounting method of maintenance platform for bridge maintenance vehicle | |
CN113309256A (en) | Construction device and construction method for prefabricated shear wall with post-pouring section | |
CN112960551B (en) | Integral lifting auxiliary device for asymmetric large-scale grid structure | |
US10533327B2 (en) | Rigging lift and method of use | |
CN209194362U (en) | Rod piece connects levelling device between a kind of suspension bridge steel truss beam section | |
CN205530776U (en) | Removable formula damping device that trades of rubber support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |