It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng Download PDF

Info

Publication number
CN108104096A
CN108104096A CN201810017418.1A CN201810017418A CN108104096A CN 108104096 A CN108104096 A CN 108104096A CN 201810017418 A CN201810017418 A CN 201810017418A CN 108104096 A CN108104096 A CN 108104096A
Authority
CN
China
Prior art keywords
runoff
plots
runoff plots
ridge
sand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810017418.1A
Other languages
Chinese (zh)
Inventor
李俊
刘志强
张翼
邹小玲
高智
王静
殷朝华
林靓靓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201810017418.1A priority Critical patent/CN108104096A/en
Publication of CN108104096A publication Critical patent/CN108104096A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N33/00Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00
    • G01N33/24Earth materials

Abstract

The present invention provides a kind of runoff plots side ridge construction methods for preventing runoff lateral leakage, and after the earth's surface on the runoff plots side to be performed ridge removes ground flora, parallel erection template, bankets among template at the ridge of runoff plots side to be laid.The layered that bankets fills, compaction in layers, reaches design height until ground compacting part is higher by earth's surface, rammed earth external table in ground is fixed using sand carving with glue glue spraying for form removal, forms sand carving compound protective layer;After sand carving with after compound protective layer colloid solidification, the sand finish outside colloid.The present invention also provides a kind of runoff plots Bian Geng for preventing leakage.The present invention can be under a kind of execution conditions of lower cost, it prevents runoff plots lateral leakage, improve water and soil conservation runoff observation on plots data precision and reasonability, solves the problems, such as that the construction of traditional runoff plots side ridge causes that runoff lateral leakage is multiple at the connectivity gap of Bian Geng bottoms and then causes happening for the runoff plots surface soil erosion distribution observation rule actual rule of deviation.

Description

The construction method and runoff on a kind of runoff plots side ridge for preventing runoff lateral leakage are small Area Bian Geng
Technical field
The present invention relates to water and soil conservation value technical field, more particularly to a kind of setting for water and soil conservation field monitoring The construction method and runoff plots Bian Geng applied.
Background technology
Soil erosion is distributed in China, and bringing soil erosion under control work generally requires water and soil conservation value and carries For data supporting.Runoff plots are that soil erosion quantifies positioning view as common ground observation facility in water and soil conservation value The basis of survey is mainly used for gathering soil erosion data, reflects the soil erosion situation in certain area, and evaluation water and soil conservation is arranged The implementation result applied, the designing and implementing for water-and-soil conservation measures after being provide reference frame.And obtain local runoff mud Sand measures one of the most frequently used, most accurate, most classical method.The build of runoff plots is to obtain the important ring of accurate observation data Section, the safeguard procedures of cell have abutment wall and protection band, and cell abutment wall is mostly by cement, brick, precast concrete or metallic plate etc. Material build is rectangular, and for stopping that external rainwash enters, embedment 30~40cm of underground is used for 20~30cm above ground level Obstruct the interflow subsurface drainage outflow in cell.General single side abutment wall accomplishes knife-edge oblique angle more, and inclined-plane is outside;Disjunctor abutment wall is made more V-arrangement is used for draining, prevents extra water from entering.Traditional runoff plots side is disadvantageous in that existing for the ridge:
First, existing runoff plots while the ridge construction using lay while the ridge at excavate rectangle groove after, use brick, stone It builds by laying bricks or stones or the mode of concreting forms the side ridge.In masonry structure and Soil Surrounding contact site, narrow and small perforation can be formed Property gap, the runoff that runoff plots slope surface generates when causing rainfall is inside runoff plots by way of this connectivity gap side seepage Go out beyond runoff plots, cause the run-off that runoff plots exit observes that can be led when serious much smaller than actual runoff yield Runoff plots is caused just to announce to scrap when completing construction.
Second, after the completion of constructing on the existing runoff plots side ridge, because of the reason for expanding with heat and contract with cold and side ridge material and the soil body The reason for material is inconsistent causes Bian Geng bottoms connectivity crack that can gradually expand increasing with rising-heat contracting-cold and runoff sapping Greatly.This construction technology can cause runoff plots part footpath to flow down to ooze, the soil that the runoff plots slope surface observed is generated by rainfall Earth erosion distribution rule cannot represent local actual value, and observation will usually be less than local actual value.Meanwhile runoff constantly from Side ridge pedestal connectivity gap leakage can form the boundary effect of runoff plots production stream, lean in runoff plots and generated through Bian Geng positions Erosion groove, guiding runoff transfer the integrated distribution at the ridge of side from runoff plots slope surface NATURAL DISTRIBUTION, the soil observed are caused to be invaded Erosion rule is happened with what nature soil erosion regular deviateed..
3rd, the usual haul distance of the equilateral ridge material of block stone, brick, concrete and purchase, construction cost are higher, cause runoff small Area's civil engineering cost is higher.
The content of the invention
First of the present invention is designed to provide a kind of runoff plots side ridge construction method for preventing runoff lateral leakage, Under a kind of execution conditions of lower cost, prevent runoff plots lateral leakage, improve water and soil conservation runoff observation on plots data Precision and rational construction method cause runoff at the connectivity gap of Bian Geng bottoms to solve the construction of traditional runoff plots side ridge Lateral leakage is multiple and then runoff plots surface soil erosion distributions observation rule is caused to deviate happening for actual rule Problem.
Technical solution is used by the invention solves above-mentioned technical problem:
A kind of runoff plots side ridge construction method for preventing runoff lateral leakage, it is characterised in that in runoff plots Bian Geng to be performed Earth's surface remove ground flora after, do not implement to excavate, parallel erection template, template and runoff at the ridge of runoff plots side to be laid Cell side ridge design width is consistent, and is banketed among template.The layered that bankets fills, compaction in layers, until on the ground Compacting part is higher by earth's surface and reaches design height, and form removal consolidates rammed earth external table in ground using sand carving with glue glue spraying It is fixed, form sand carving compound protective layer;After sand carving with after compound protective layer colloid solidification, the sand finish outside colloid.
The present invention second is designed to provide a kind of runoff plots Bian Geng for preventing leakage, can be constructed using the above method Building.The present invention uses following technical scheme therefore:
A kind of runoff plots Bian Geng for preventing leakage, it is characterised in that:Including by the molding side ridge main body of rammed earth, in side ridge master It is external that sand carving compound protective layer is set;Sand finish is set with outside compound protective layer in sand carving.
Further, the substrate on the side ridge is made of compacting soil.
Further, the side ridge is directly tamped using backfill.
It applies the inventive method to water and soil conservation value runoff plots to build, the runoff plots side ridge is made to melt with bottom solum Be integrated, when will not form brick, stone-laying, concreting caused by Bian Geng bottoms connectivity gap, footpath when preventing precipitation The footpath that stream cell slope surface generates flows through the side ridge and leaks into outside runoff plots, it is ensured that runoff plots slope runoff can be protected during rainfall Nature flowing is held, the soil erosion regular observed is enable to be consistent with actual rule;It is collected into runoff plots afflux pond Silt can represent the actual conditions of the erosion caused by sloping surfaces, improve runoff observation on plots experimental precision, while substantially reduce civil engineering and apply Work cost.
The present invention can not effectively prevent Bian Geng bottoms and soil contact site when solving the construction of traditional runoff plots side ridge Formed connectivity gap and cause runoff plots runoff from the problem of lateral leakage, prevented at the ridge of side runoff leak and caused by soil Earth corrodes observation and the situation of actual value observation substantial deviation, improves experiment accuracy.Main advantages of the present invention and improvement For:
First, the side ridge is set on runoff plots periphery, the build material such as cement, brick, precast concrete or metallic plate is changed For compacting soil and fixation is played with glue in surface spray sand carving, Bian Geng bottoms rammed earth and runoff plots soil during rammed earth Earth, which is combined together, will not form connectivity gap, and the runoff that runoff plots slope surface generates when avoiding rainfall is out of runoff plots Portion by way of this connectivity gap side seepage go out beyond runoff plots the problem of.
Second, the runoff that runoff plots slope surface generates during rainfall will not be inside runoff plots by way of this connectivity gap side Go out to seepage flow beyond runoff plots, avoid the edge effect of the generation because of leakage, so as to ensure that runoff plots slope runoff energy Enough runoff movements under natural conditions are consistent, and the soil erosion regular observed is made to be use up with nature soil erosion regular It may be consistent, promote the reasonability of runoff plots experimental result.
3rd, it is only necessary to soil is backfilling and compacted, glue spraying, sand finish, save in the structure of traditional side ridge because It buys the civil construction that cement, brick, concrete etc. are built needed for material to pay wages, greatly reduce in the process of construction of runoff plots Required financial cost.
Description of the drawings
Fig. 1 is the floor plan of detection runoff plots.
Fig. 2 is the diagrammatic cross-section of detection runoff plots.
Fig. 3 is the partial cross section enlarged diagram on the runoff plots side of the present invention ridge.
Fig. 4 is the vertical section schematic diagram on the runoff plots side of the present invention ridge.
Fig. 5 is the construction process figure on the runoff plots side of the present invention ridge.
Specific embodiment
Referring to the drawings.Drawing reference numeral 100 is monitoring runoff plots slope surface, and drawing reference numeral 200 is afflux pond.Drawing reference numeral 300 be runoff plots Bian Geng.
After the earth's surface on the runoff plots side to be performed ridge removes ground flora, do not implement to excavate, in runoff plots to be laid Parallel erection template 400 at the ridge of side, template 400 are consistent with runoff plots side ridge design width, are filled out among template Soil, the soil can directly use backfill 500.The layered that bankets fills, compaction in layers, until side ridge main body 1 is higher by earth's surface 2 Height for 20cm or so, rammed earth external table in ground is fixed using sand carving with glue glue spraying for form removal 400, is formed husky For carving with compound protective layer 3, protection and fixed is played the role of on opposite side ridge surface,;After sand carving with after compound protective layer colloid solidification, in glue Protection and fixed is played the role of on sand finish 4 outside body, opposite side ridge surface.Treat that sand finish layer reaches the intensity back ridge It uses.
Structure feature the foregoing is merely specific embodiments of the present invention, but the present invention is not limited thereto, Ren Heben The technical staff in field in the field of the invention, all cover among protection scope of the present invention by the variation or modification made.

Claims (4)

1. a kind of runoff plots side ridge construction method for preventing runoff lateral leakage, it is characterised in that on runoff plots side to be performed After the earth's surface on the ridge removes ground flora, do not implement to excavate, parallel erection template, template and footpath at the ridge of runoff plots side to be laid Design width in the stream cell side ridge is consistent, and is banketed among template;The layered that bankets fills, compaction in layers, until ground Upper compacting part is higher by earth's surface and reaches design height, and form removal carries out rammed earth external table in ground using sand carving with glue glue spraying It is fixed, form sand carving compound protective layer;After sand carving with after compound protective layer colloid solidification, the sand finish outside colloid.
2. a kind of runoff plots Bian Geng for preventing leakage, it is characterised in that:Including by the molding side ridge main body of rammed earth, in Bian Geng Sand carving compound protective layer is set outside main body;Sand finish is set with outside compound protective layer in sand carving.
3. a kind of runoff plots Bian Geng for preventing leakage as claimed in claim 2, it is characterised in that:The substrate on the side ridge is by tamping Soil is formed.
4. a kind of runoff plots Bian Geng for preventing leakage as claimed in claim 2, it is characterised in that:Side ridge main body is direct It is tamped using backfill.
CN201810017418.1A 2018-01-09 2018-01-09 It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng Pending CN108104096A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810017418.1A CN108104096A (en) 2018-01-09 2018-01-09 It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810017418.1A CN108104096A (en) 2018-01-09 2018-01-09 It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng

Publications (1)

Publication Number Publication Date
CN108104096A true CN108104096A (en) 2018-06-01

Family

ID=62218902

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810017418.1A Pending CN108104096A (en) 2018-01-09 2018-01-09 It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng

Country Status (1)

Country Link
CN (1) CN108104096A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109030771A (en) * 2018-06-25 2018-12-18 南京林业大学 Soil loss monitoring runoff plots

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1038484A (en) * 1988-06-11 1990-01-03 湖南省电力勘测设计院 Build the method for the gravity flow ash embankment on the ridge, limit with flyash
CN102926390A (en) * 2012-11-09 2013-02-13 北京北林绿源生态技术研究院有限责任公司 Method of shallow reinforcement and surface reinforcement of loess slope
CN104563266A (en) * 2014-06-17 2015-04-29 贵州大学 Rural domestic sewage high-ridge rice field irrigation regulation control system and construction method thereof
CN204435353U (en) * 2015-02-09 2015-07-01 重庆师范大学 A kind of corrosion-proof type soil stone compound ridge bank
CN105409376A (en) * 2015-11-09 2016-03-23 北京林业大学 Method for preparing lands for afforestation in loess gully regions
CN106284691A (en) * 2016-08-26 2017-01-04 上海二十冶建设有限公司 The external door of a kind of ground external heat insulating wall, the anti-seepage construction method on window limit
CN208996016U (en) * 2018-01-09 2019-06-18 中国电建集团华东勘测设计研究院有限公司 A kind of runoff plots Bian Geng preventing leakage

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1038484A (en) * 1988-06-11 1990-01-03 湖南省电力勘测设计院 Build the method for the gravity flow ash embankment on the ridge, limit with flyash
CN102926390A (en) * 2012-11-09 2013-02-13 北京北林绿源生态技术研究院有限责任公司 Method of shallow reinforcement and surface reinforcement of loess slope
CN104563266A (en) * 2014-06-17 2015-04-29 贵州大学 Rural domestic sewage high-ridge rice field irrigation regulation control system and construction method thereof
CN204435353U (en) * 2015-02-09 2015-07-01 重庆师范大学 A kind of corrosion-proof type soil stone compound ridge bank
CN105409376A (en) * 2015-11-09 2016-03-23 北京林业大学 Method for preparing lands for afforestation in loess gully regions
CN106284691A (en) * 2016-08-26 2017-01-04 上海二十冶建设有限公司 The external door of a kind of ground external heat insulating wall, the anti-seepage construction method on window limit
CN208996016U (en) * 2018-01-09 2019-06-18 中国电建集团华东勘测设计研究院有限公司 A kind of runoff plots Bian Geng preventing leakage

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109030771A (en) * 2018-06-25 2018-12-18 南京林业大学 Soil loss monitoring runoff plots

Similar Documents

Publication Publication Date Title
CN101864960B (en) Carst region double-arch road tunnel construction method
CN109630137B (en) An a kind of tunnel high position passes through the backfill processing construction method of huge molten chamber
CN104452809B (en) A kind of super shallow tunnel cover and cut construction method
CN104564128B (en) A kind of shallow-depth-excavation tunnel construction deformation monitoring method
CN104500077B (en) A kind of shallow-depth-excavation tunnel passes through cottage area construction method
CN107938692B (en) Drainage and recharging construction method and structure
CN105569058A (en) Expansive soil cutting structure and construction method thereof
CN109113129A (en) A kind of construction method of irrigation and drainage system and canal for water conveyance
CN103147442A (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN103774616A (en) Construction method for ecological retaining wall built by self-embedded blocks
CN106320120A (en) Construction process for pile slab type non-soil roadbed highway
CN208309312U (en) Reinforced earth retaining wall embankment drainage system
CN109403332B (en) Method for combined excavation of layered bench sections of deep foundation pit of sandy cobble thick covering layer wide shallow valley
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN109706952A (en) Large-scale well-sinking construction method
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN108252176A (en) A kind of pavement engineering construction method equipped with inspection shaft
CN114575355A (en) Soil protection and descent construction method
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN212272234U (en) High-strength combined template for open groove section of large-section inclined shaft
CN106567365B (en) Earth and rockfill dam longitudinal reinforcement construction method
CN208996016U (en) A kind of runoff plots Bian Geng preventing leakage
CN108104096A (en) It is a kind of to prevent the construction method on the runoff plots side ridge of runoff lateral leakage and runoff plots Bian Geng
CN207828994U (en) It is a kind of draining and recharge constructing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180601

WD01 Invention patent application deemed withdrawn after publication