CN108103953B - Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method - Google Patents

Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method Download PDF

Info

Publication number
CN108103953B
CN108103953B CN201711391072.3A CN201711391072A CN108103953B CN 108103953 B CN108103953 B CN 108103953B CN 201711391072 A CN201711391072 A CN 201711391072A CN 108103953 B CN108103953 B CN 108103953B
Authority
CN
China
Prior art keywords
slider
steel truss
truss girder
vertical jack
pushing tow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711391072.3A
Other languages
Chinese (zh)
Other versions
CN108103953A (en
Inventor
宋伟俊
龚国锋
陈宁贤
张静
曲江峰
王钰
郭万良
连延金
吴广
闫雪松
朱林达
章耀林
汤和达
张斌
冯文园
朱永盛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201711391072.3A priority Critical patent/CN108103953B/en
Publication of CN108103953A publication Critical patent/CN108103953A/en
Application granted granted Critical
Publication of CN108103953B publication Critical patent/CN108103953B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A kind of high-block bridge degree steel truss girder bridge double-slider push construction method, utilize Integral Panel Points of Steel Truss Girder eccentric force performance, before being arranged under adjacent node between same node, rear slider, before, middle part, vertical jack afterwards, by an internode apart from substep pushing tow, different vertical supporting modes is used according to pushing tow step, reduce slipway beam and pier shaft moment of flexure, pier shaft stress is set to meet design requirement, to prepare pushing tow state, front-slider is supported on steel truss girder connection bias allowable offset position, rear slider is supported on immediately below steel truss girder connection, adjacent node has support at this time, single reaction of supports is smaller, slipway beam moment of flexure and pier shaft eccentric bending moment are smaller, along pushing tow direction pushing tow forward, by preceding, afterwards, the top lifting of middle vertical portion jack is fallen after rise, to preceding, rear slider is switched, when double-slider supports, reduce single reaction of supports;When single sliding block supports, reduce maximum point counter-force position at a distance from pier center, to reduce slipway beam moment of flexure and pier shaft eccentric bending moment.

Description

Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method
Technical field:
The present invention relates to bridge construction field, in particular to a kind of high-block bridge degree steel truss girder bridge double-slider pushing tow is applied Work method.
Background technique:
Longspan steel truss girder bridge incremental launching construction generallys use horizontal continuity jack with single sliding block hauling construction, incremental launching construction The reaction of supports is big in the process, and support force is big by pier.For high-block bridge degree steel truss girder bridge, support height height by pier is landed, just Degree control difficulty is big, and installation difficulty is big, at high cost, security risk is high;Pier-side bracket is not landed as used, then pier-side bracket stress Greatly, pier shaft eccentric bending moment is big, and security risk is high.
Summary of the invention:
In view of this, it is necessary to provide a kind of high-block bridge degree steel truss girder bridge double-slider push construction method.Of the invention Construction method eliminates landing pier collateral branch frame and effectively reduces slipway beam moment of flexure using double-slider scheme and pier shaft bias is curved Square improves structure safety stock.
One kind being suitable for high-block bridge degree steel truss girder bridge double-slider push construction method, and equipment used in this method includes sliding Road beam, front-slider, rear slider, preceding vertical jack, the vertical jack in middle part, rear vertical jack, level jack and anchoring part, This method utilize Integral Panel Points of Steel Truss Girder eccentric force performance, under same steel truss girder adjacent node arrange front-slider, rear slider, Preceding vertical jack, the vertical jack in middle part and rear vertical jack, by an internode range segment separating substep pushing tow, according to pushing tow Step uses different vertical supporting modes, reduces slipway beam and pier shaft moment of flexure, pier shaft stress is made to meet design requirement, to prepare Pushing tow state, front-slider are supported on steel truss girder connection bias allowable offset position, and rear slider is supported on immediately below steel truss girder connection, Adjacent node has support at this time, and single reaction of supports is smaller, and slipway beam moment of flexure and pier shaft eccentric bending moment are smaller, along pushing tow direction to Preceding pushing tow is fallen after rise by the top lifting of preceding vertical jack, rear vertical jack and middle vertical portion jack, to front-slider, rear sliding Two sliding block of block is switched, and when double-slider supports, reduces single reaction of supports;When single sliding block supports, reduce maximum point counter-force position At a distance from pier center, to reduce slipway beam moment of flexure and pier shaft eccentric bending moment.
Preferably, high-block bridge degree steel truss girder bridge double-slider push construction method, including with preferable construction procedure:
Step 1, pushing tow prepare, and two nodes are node N and node N-1, node N and node N-1 away from pier top before and after steel truss girder Center line is apart from identical, and front-slider is located at steel truss girder front nodal point N eccentric part, under rear slider is located at steel truss girder posterior nodal point N-1 just Side;Preceding vertical jack is located at level jack anchoring part rear, and rear vertical jack is located at rear slider rear;It is leaned in slideway front end Nearly medium position is packed into the vertical jack in middle part;Vertical top is come to nothing at this time, and steel strand wires are anchored on front and back ends sliding block simultaneously, preceding, Rear slider supports steel truss girder jointly;
Step 2, along the pushing tow direction distance that pushing process requires forward, rear vertical jack moves forward to steel truss girder deutomerite At the allowable offset position of the rear point N-1;In preceding vertical jack, rear vertical jack top pad, steel truss girder top lifting preparation is carried out;
Step 3, preceding vertical jack, rear vertical jack synchronize top lifting steel truss girder, and front-slider removes one layer of pad block, It is offloaded to rear slider stress, removes the vertical jack in middle part, carries out pushing tow preparation;
Step 4, along pushing tow direction, pushing tow, the permission that pushing tow distance subtracts 2 times for steel truss girder panel length are inclined forward for continuation Heart distance, the vertical jack in middle part is re-installed on rear side of node N-1 at allowable offset position by pushing tow afterwards in place, rear vertical It is very heavy to be located at immediately below node N-2;At middle part, vertical jack and rear vertical jack top surface pad, it is quasi- to carry out vertical top lifting It is standby;
Step 5 is synchronized top lifting steel truss girder to rear slider and is come to nothing by the vertical jack in middle part, rear vertical jack;
Step 6 makes after its pad that vertically very heavy heights of roofs is identical with middle part in front-slider top surface pad;Individually in unloading The vertical jack in portion makes front-slider and the common stress of rear vertical jack;
Step 7 removes the vertical jack in middle part, and rear slider is moved back to allowable offset position on front side of steel truss girder connection N-2 Set place;
Step 8 reinstalls the vertical jack in middle part on rear side of the steel truss girder posterior nodal point N-1 at allowable offset position, and rear Vertical jack synchronizes top lifting steel truss girder, removes front-slider top surface pad, and front-slider is moved back to steel truss girder posterior nodal point N-1 just Lower section;
Step 9, the vertical jack in middle part and rear vertical jack synchronize be offloaded to the common stress of front-slider, rear slider;
Step 10, along pushing tow direction, pushing tow certain distance, this distance are steel truss girder nodal support allowable offset forward for continuation Value;
Step 11, preceding vertical jack, rear vertical jack synchronize top lifting steel truss girder, after front-slider, rear slider synchronize Certain distance is moved, this distance is steel truss girder nodal support allowable offset value;Preceding vertical jack, rear vertical jack are synchronized and are unloaded It carries, steel truss girder support force is converted to front-slider, rear slider;Pushing tow operating condition reverts to step 1, an internode pushing tow step at this time It is rapid to complete, it is ready for next internode incremental launching construction.
Steel truss girder is in the case where adjacent node has support, the eccentric stress of integral node, in steel truss girder two adjacent sections Point setting sliding block and vertical jack.When adjacent two nodes is identical away from pier top centre distance, two sliding block of front and back is supported respectively Corresponding node, pier shaft two sides moment of flexure balance, moment of flexure or eccentric bending moment are minimum without acceptance of persons for pier shaft.When sliding block is away from pier top center line distance When less than half internode girder steel length, by vertical jack top lifting, falls after rise, release front-slider stress, prop up rear slider individually Steel truss girder is supportted, rear slider is closer away from pier center at this time, and eccentric distance is small, reduces pier shaft eccentric bending moment.It is double by setting front and back Sliding block effectively reduces eccentric bending moment suffered by bridge pier during pushing tow.
Eccentric distance farther out when, supported by two sliding blocks, reduce the vertical counter-force of single fulcrum, it is curved to reduce slipway beam Square;When being converted to single sliding block support, eccentric distance reduces, and reduces slipway beam moment of flexure.
By the way that double-slider is arranged in adjacent node, the vertical counter-force of single fulcrum is reduced, steel truss girder connection is reduced and locally answers Power, enhancing structure safety stock.
By the intermediate vertical jack of setting, being dismounted for multiple times sliding block during pushing tow is avoided, is improved work efficiency.
It is provided by the invention to be suitable for high-block bridge degree steel truss girder bridge double-slider push construction method, eliminate traditional landing Sliding block and vertical thousand is arranged in steel truss girder adjacent two nodes using the eccentric force performance of Integral Panel Points of Steel Truss Girder in pier collateral branch frame Jin top.When adjacent two nodes is identical away from pier top centre distance, two sliding block of front and back supports respective corresponding node, two lateral bending of pier shaft Square balance, moment of flexure or eccentric bending moment are minimum without acceptance of persons for pier shaft.When less than half away from pier top center line distance internode girder steel of sliding block is long When spending, by vertical jack top lifting, falls after rise, release front-slider stress, so that rear slider is individually supported steel truss girder, at this time rear slider Closer away from pier center, eccentric distance is small, reduces pier shaft eccentric bending moment.By setting front and back double-slider, top is effectively reduced Push through eccentric bending moment suffered by bridge pier in journey.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.
The content being not described in detail in this specification belongs to the prior art well known to professional and technical personnel in the field.
Detailed description of the invention:
Fig. 1 is the one status architecture schematic diagram of construction of high-block bridge degree steel truss girder bridge double-slider push construction method.
The status architecture of the step of Fig. 2 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method one Schematic diagram.
The status architecture of the step of Fig. 3 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method two Schematic diagram.
The status architecture of the step of Fig. 4 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method three Schematic diagram.
The status architecture of the step of Fig. 5 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method four Schematic diagram.
The status architecture of the step of Fig. 6 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method five Schematic diagram.
The status architecture of the step of Fig. 7 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method six Schematic diagram.
The status architecture of the step of Fig. 8 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method seven Schematic diagram.
The status architecture of the step of Fig. 9 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method eight Schematic diagram.
The state knot of the step of Figure 10 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method nine Structure schematic diagram.
The state knot of the step of Figure 11 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method ten Structure schematic diagram.
The state of the step of Figure 12 is the Specific construction of high-block bridge degree steel truss girder bridge double-slider push construction method 11 Structural schematic diagram.
In figure: front nodal point N, posterior nodal point N-1, node N-2, front-slider 1, rear slider 2, steel truss girder 3, level jack 4, preceding Vertical jack 5, the vertical jack 6 in middle part, rear vertical jack 7, slipway beam 8, pier shaft 9, pushing tow direction 10, eccentric position 11, anchoring part 12.
Specific embodiment:
Referring to Fig. 1, the present invention is using Integral Panel Points of Steel Truss Girder eccentric force performance, in same steel truss girder adjacent node Lower arrangement sliding block and vertical jack, by an internode range segment separating substep pushing tow, according to pushing tow step using different vertical Supporting way reduces slipway beam and pier shaft moment of flexure, pier shaft stress is made to meet design requirement.For prepare pushing tow state, front-slider 1 Support is in 3 node bias allowable offset position 11 of steel truss girder, and rear slider 2 is supported on immediately below 3 node of steel truss girder, at this time adjacent node There is support, single reaction of supports is smaller, and 8 moment of flexure of slipway beam and 9 eccentric bending moment of pier shaft are smaller.Along the pushing tow forward of pushing tow direction 10, It is fallen after rise by the top lifting of preceding vertical jack 5, rear vertical jack 7 and middle part jack 6, to 2 liang of front-slider 1, rear slider cunnings Block is switched, and when double-slider supports, reduces single reaction of supports;When single sliding block supports, reduce in maximum point counter-force position and pier The distance of the heart, to reduce 9 eccentric bending moment of 8 moment of flexure of slipway beam and pier shaft.
Please refer to Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9, Figure 10, Figure 11 and Figure 12, high-block bridge degree Steel truss girder bridge double-slider push construction method, including following construction procedure:
Step 1, pushing tow prepare, and two nodes are front nodal point N and posterior nodal point N-1, front nodal point N and posterior nodal point before and after steel truss girder N-1 is away from pier top center line apart from identical, and front-slider 1 is located at 3 front nodal point N eccentric part of steel truss girder, after rear slider 2 is located at steel truss girder 3 Immediately below node N-1;Preceding vertical jack 5 is located at 12 rear of level jack 4 and anchoring part, and rear vertical jack 7 is sliding after being located at 2 rear of block.The vertical jack 6 in the middle part of slideway front end is packed into close to medium position.Vertical top is come to nothing at this time, steel strand wires while anchor It is fixed in front-slider 1, on rear slider 2, forward and backward sliding block supports steel truss girder 3 jointly, and eccentric bending moment suffered by pier shaft is smaller.
Step 2, along pushing tow direction 10, pushing tow certain distance, this distance are 3 nodal support allowable offset of steel truss girder forward Value, rear vertical jack 7 move forward at 3 posterior nodal point rear allowable offset position 11 of steel truss girder.In preceding vertical jack 5, rear perpendicular Pad is pushed up to jack 7, carries out 3 top lifting of steel truss girder preparation.
Step 3, preceding vertical jack 5, rear vertical jack 7 synchronize top lifting steel truss girder 3, and front-slider 1 removes one layer of pad Block is offloaded to 2 stress of rear slider, removes the vertical jack 6 in middle part, carries out pushing tow preparation.
Step 4 continues along the pushing tow forward of pushing tow direction 10, and pushing tow distance is that 3 panel length of steel truss girder subtracts 2 times and permits The vertical jack 6 in middle part is re-installed on rear side of node N-1 at allowable offset position 11 by eccentric distance perhaps, pushing tow afterwards in place, Vertical jack 7 is located at immediately below node N-2 afterwards.At middle part, 7 top surface pad of vertical jack 6 and rear vertical jack, is carried out Vertical top lifting prepares.
Step 5 is synchronized top lifting steel truss girder 3 to rear slider 2 and is come to nothing by the vertical jack 6 in middle part, rear vertical jack 7.
Step 6 makes identical as vertical 6 height of jack in middle part after its pad in 1 top surface pad of front-slider.Individually unload The vertical jack 6 in middle part is carried, front-slider 1 and the common stress of rear vertical jack 7 are made.
Step 7 removes the vertical jack 6 in middle part, and rear slider 2 is moved back to allowable offset on front side of 3 node N-2 of steel truss girder At position 11.
Step 8 reinstalls the vertical jack in middle part on rear side of the posterior nodal point N-1 of steel truss girder 3 at allowable offset position 11 6, top lifting steel truss girder 3 synchronous with rear vertical jack 7 removes 1 top surface pad of front-slider, and front-slider 1 is moved back to steel truss girder 3 Immediately below posterior nodal point N-1.
Step 9, the vertical jack 6 in middle part and rear vertical jack 7 synchronize be offloaded to front-slider 1, rear slider 2 jointly by Power.
Step 10, along pushing tow direction 10, pushing tow certain distance, this distance are that 3 nodal support of steel truss girder allows partially forward for continuation Center value.
Step 11, preceding vertical jack 5, rear vertical jack 7 synchronize top lifting steel truss girder 3, and front-slider 1, rear slider 2 are same Step moves back certain distance, this distance is 3 nodal support allowable offset value of steel truss girder;Preceding vertical jack 5, rear vertical jack 7 Synchronous unloading, 3 support force of steel truss girder are converted to front-slider 1, rear slider 2.Pushing tow operating condition reverts to step 1 at this time, and one Internode pushing tow step is completed, and next internode incremental launching construction is ready for.
It is provided by the invention to be suitable for high-block bridge degree steel truss girder bridge double-slider push construction method, eliminate traditional landing Sliding block and vertical thousand is arranged in steel truss girder adjacent two nodes using the eccentric force performance of Integral Panel Points of Steel Truss Girder in pier collateral branch frame Jin top.When adjacent two nodes is identical away from pier top centre distance, two sliding block of front and back supports respective corresponding node, two lateral bending of pier shaft Square balance, moment of flexure or eccentric bending moment are minimum without acceptance of persons for pier shaft.When less than half away from pier top center line distance internode girder steel of sliding block is long When spending, by vertical jack top lifting, falls after rise, release front-slider stress, so that rear slider is individually supported steel truss girder, at this time rear slider Closer away from pier center, eccentric distance is small, reduces pier shaft eccentric bending moment.By setting front and back double-slider, top is effectively reduced Push through eccentric bending moment suffered by bridge pier in journey.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art Mind and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.The content being not described in detail in this specification belongs to this The prior art well known to skilled artisan.

Claims (2)

1. a kind of high-block bridge degree steel truss girder bridge double-slider push construction method, it is characterised in that: high-block bridge degree steel truss girder bridge Equipment used in double-slider push construction method includes slipway beam, front-slider, rear slider, preceding vertical jack, middle part vertical thousand Jin top, rear vertical jack, level jack and anchoring part, this method utilizes Integral Panel Points of Steel Truss Girder eccentric force performance, same Front-slider, rear slider, preceding vertical jack, the vertical jack in middle part and rear vertical very heavy are arranged under one steel truss girder adjacent node One internode range segment separating substep pushing tow is used different vertical supporting modes according to pushing tow step by top, reduce slipway beam and Pier shaft moment of flexure makes pier shaft stress meet design requirement, and to prepare pushing tow state, front-slider is supported on the permission of steel truss girder connection bias Eccentric position, rear slider are supported on immediately below steel truss girder connection, and adjacent node has support at this time, and single reaction of supports is smaller, sliding Road beam moment of flexure and pier shaft eccentric bending moment are smaller, along pushing tow direction pushing tow forward, by preceding vertical jack, rear vertical jack and The top lifting of middle vertical portion jack is fallen after rise, is switched to front-slider, two sliding block of rear slider, when double-slider supports, reduces single branch Point counter-force;When single sliding block supports, reduce maximum point counter-force position at a distance from pier center, to reduce slipway beam moment of flexure and pier shaft Eccentric bending moment.
2. high-block bridge degree steel truss girder bridge double-slider push construction method as described in claim 1, it is characterised in that: high pier is big Span steel truss girder bridge double-slider push construction method, including following construction procedure:
Step 1, pushing tow prepare, and two nodes are node N and node N-1, node N and node N-1 away from pier top center before and after steel truss girder Linear distance is identical, and front-slider is located at steel truss girder front nodal point N eccentric part, and rear slider is located at immediately below steel truss girder posterior nodal point N-1;It is preceding perpendicular It is located at level jack anchoring part rear to jack, rear vertical jack is located at rear slider rear;In slideway front end close to middle part Position is packed into the vertical jack in middle part;Vertical top is come to nothing at this time, and steel strand wires are anchored on front and back ends sliding block simultaneously, forward and backward sliding block Common support steel truss girder;
Step 2, along the pushing tow direction distance that pushing process requires forward, rear vertical jack moves forward to steel truss girder posterior nodal point N-1 At the allowable offset position of rear;In preceding vertical jack, rear vertical jack top pad, steel truss girder top lifting preparation is carried out;
Step 3, preceding vertical jack, rear vertical jack synchronize top lifting steel truss girder, and front-slider removes one layer of pad block, unloading To rear slider stress, the vertical jack in middle part is removed, carries out pushing tow preparation;
Step 4 continues along pushing tow direction pushing tow forward, pushing tow distance be steel truss girder panel length subtract 2 times of allowable offset away from From the vertical jack in middle part is re-installed on rear side of node N-1 at allowable offset position by pushing tow afterwards in place, rear vertical very heavy Immediately below node N-2;At middle part, vertical jack and rear vertical jack top surface pad, carry out vertical top lifting and prepare;
Step 5 is synchronized top lifting steel truss girder to rear slider and is come to nothing by the vertical jack in middle part, rear vertical jack;
Step 6 makes after its pad that vertically very heavy heights of roofs is identical with middle part in front-slider top surface pad;Individually unloading middle part is perpendicular To jack, make front-slider and the common stress of rear vertical jack;
Step 7 removes the vertical jack in middle part, and rear slider is moved back to allowable offset position on front side of steel truss girder connection N-2;
Step 8 reinstalls the vertical jack in middle part on rear side of the steel truss girder posterior nodal point N-1 at allowable offset position, and rear vertical Jack synchronize top lifting steel truss girder, remove front-slider top surface pad, and by front-slider move back to steel truss girder posterior nodal point N-1 just under Side;
Step 9, the vertical jack in middle part and rear vertical jack synchronize be offloaded to the common stress of front-slider, rear slider;
Step 10, along pushing tow direction, pushing tow certain distance, this distance are steel truss girder nodal support allowable offset value forward for continuation;
Step 11, preceding vertical jack, rear vertical jack synchronize top lifting steel truss girder, and front-slider, rear slider, which synchronize, moves back one Set a distance, this distance are steel truss girder nodal support allowable offset value;
Preceding vertical jack, rear vertical jack synchronize unloading, and steel truss girder support force is converted to front-slider, rear slider;At this time Pushing tow operating condition reverts to step 1, and an internode pushing tow step is completed, and is ready for next internode incremental launching construction.
CN201711391072.3A 2018-03-09 2018-03-09 Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method Active CN108103953B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711391072.3A CN108103953B (en) 2018-03-09 2018-03-09 Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711391072.3A CN108103953B (en) 2018-03-09 2018-03-09 Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method

Publications (2)

Publication Number Publication Date
CN108103953A CN108103953A (en) 2018-06-01
CN108103953B true CN108103953B (en) 2019-10-15

Family

ID=62211634

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711391072.3A Active CN108103953B (en) 2018-03-09 2018-03-09 Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method

Country Status (1)

Country Link
CN (1) CN108103953B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108708294B (en) * 2018-07-11 2023-12-12 中铁大桥局集团第六工程有限公司 Short slideway beam for pushing construction of unequal-section truss beam and pushing method
CN112832134B (en) * 2021-01-06 2022-05-06 中铁大桥局集团有限公司 Construction method for dragging pier through steel truss girder
CN113846563B (en) * 2021-09-18 2023-04-07 中铁大桥局集团有限公司 Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004238796A (en) * 2003-02-03 2004-08-26 Kawada Construction Co Ltd Floor-slab separator
CN101906755A (en) * 2010-09-06 2010-12-08 中铁大桥局集团有限公司 Three-truss continuous steel truss girder pushing device and arrangement method thereof
CN102383378A (en) * 2011-11-28 2012-03-21 中铁大桥局股份有限公司 Successive launching method for high temporary piers
CN205046480U (en) * 2015-08-21 2016-02-24 中交武汉港湾工程设计研究院有限公司 Steel purlin girder segment point self -adaptation pushes away system in top in succession
CN105544412A (en) * 2016-02-01 2016-05-04 中铁四局集团钢结构有限公司 Incremental launching construction method for three-main-truss rigid suspension cable stiffening continuous steel truss girder with stiffening chord
CN205276140U (en) * 2015-11-23 2016-06-01 柳州欧维姆工程有限公司 Continuous steel longeron multi -point synchronization automatic cycle of large -span piston shoes top in turn pushes away system
CN105696470A (en) * 2016-01-18 2016-06-22 中国铁建大桥工程局集团有限公司 Synchronous quick steel box girder in-situ incremental launching and tower column construction method
CN105986549A (en) * 2016-01-07 2016-10-05 中铁四局集团钢结构有限公司 Method for controlling changes in three-truss height difference of combined highway and railway bridge for structural system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004238796A (en) * 2003-02-03 2004-08-26 Kawada Construction Co Ltd Floor-slab separator
CN101906755A (en) * 2010-09-06 2010-12-08 中铁大桥局集团有限公司 Three-truss continuous steel truss girder pushing device and arrangement method thereof
CN102383378A (en) * 2011-11-28 2012-03-21 中铁大桥局股份有限公司 Successive launching method for high temporary piers
CN205046480U (en) * 2015-08-21 2016-02-24 中交武汉港湾工程设计研究院有限公司 Steel purlin girder segment point self -adaptation pushes away system in top in succession
CN205276140U (en) * 2015-11-23 2016-06-01 柳州欧维姆工程有限公司 Continuous steel longeron multi -point synchronization automatic cycle of large -span piston shoes top in turn pushes away system
CN105986549A (en) * 2016-01-07 2016-10-05 中铁四局集团钢结构有限公司 Method for controlling changes in three-truss height difference of combined highway and railway bridge for structural system
CN105696470A (en) * 2016-01-18 2016-06-22 中国铁建大桥工程局集团有限公司 Synchronous quick steel box girder in-situ incremental launching and tower column construction method
CN105544412A (en) * 2016-02-01 2016-05-04 中铁四局集团钢结构有限公司 Incremental launching construction method for three-main-truss rigid suspension cable stiffening continuous steel truss girder with stiffening chord

Also Published As

Publication number Publication date
CN108103953A (en) 2018-06-01

Similar Documents

Publication Publication Date Title
CN108103953B (en) Suitable for high-block bridge degree steel truss girder bridge double-slider push construction method
CN101831874B (en) Multipoint synchronous push construction method for porous large-span continuous steel truss girder
CN112726427B (en) Incremental launching construction method and incremental launching construction device for steel truss girder
CN107489103A (en) Large-span Steel Box Beam tower with suspended cable aids in push construction method
CN103510475A (en) Long-distance pushing construction method of thee-main-truss steel truss beam in single-connection and double-span modes without guide beam
CN109610330A (en) A kind of Bridge Erector passing method
CN104631324A (en) Front supporting point hanging basket construction process used for inclined pull bridge super-wide flange girder
CN108360387A (en) A kind of continuous just trusses sliding roadway arch steel bridge rapid constructing method
CN105951603A (en) Pushing and lifting device of walking type pushing system
CN113846563A (en) Construction method for side span and auxiliary span steel truss girder erection of large-span cable-stayed bridge
CN107034790B (en) Method for reducing support internal force during steel beam symmetrical double-cantilever assembly
CN108824210A (en) The preloading method of bridge bracket
CN113431346B (en) Slippage jig frame for large-span steel truss construction and construction method
CN109868722A (en) A kind of pier method on box beam end construction and box beam convenient for upper pier
CN203546599U (en) Pier-side bracket
EP0182753B1 (en) Launching system, especially for continuous-beam bridges made up of prefabricated segments
CN103866699A (en) Rail-free type walking hanging basket
CN106760565B (en) A kind of automatic method for discharging construction of structure
CN113718662B (en) Pushing and sliding method suitable for steel truss girder with complex vertical curve
CN101892634A (en) Top pushing mechanism of steel box girder of single longitudinal clapboard on wide bridge deck and top pushing method
US2914783A (en) Bridge construction
CN205576759U (en) Symmetrical propulsion system of synchronization of bridge cantilever crane dress in -process
CN212426804U (en) Hang basket moving system
CN103061262A (en) Cable-crossing crane and application method thereof
CN102134834A (en) Small pier construction diamond cradle

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant