CN108092263A - 一种dg并网选址的方法 - Google Patents
一种dg并网选址的方法 Download PDFInfo
- Publication number
- CN108092263A CN108092263A CN201711377841.4A CN201711377841A CN108092263A CN 108092263 A CN108092263 A CN 108092263A CN 201711377841 A CN201711377841 A CN 201711377841A CN 108092263 A CN108092263 A CN 108092263A
- Authority
- CN
- China
- Prior art keywords
- power
- node
- grid
- load
- average equivalent
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 9
- 238000010248 power generation Methods 0.000 claims description 10
- 238000004364 calculation method Methods 0.000 claims description 9
- 238000010187 selection method Methods 0.000 claims description 6
- 230000005540 biological transmission Effects 0.000 claims description 4
- 238000012935 Averaging Methods 0.000 claims description 3
- 230000005611 electricity Effects 0.000 abstract 1
- 238000011161 development Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 238000003012 network analysis Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明公开了一种DG并网选址的方法,其特征是,包括如下步骤:1)构建电力网络拓扑模型;2)计算各个负载节点到电源节点的平均等效距离L1;3)计算整个电网的负载节点到电源节点平均等效距离L2;4)计算L1的方差D;5)确定DG的合理并网位置:对步骤4)获取的D数据序列进行排队,D值最小时DG接入的位置即为DG的合理并网位置。这种方法通过实际环境数据,能获得最优分布式发电并网位置,使得配电网能够快速达到稳定工作状态。
Description
技术领域
本发明涉及复杂电力网络分析技术领域,具体是一种分布式发电(DistributedGeneration,简称DG)并网选址的方法。
背景技术
电力网络是电力系统的重要组成部分,其可靠性和安全性对电力系统安全、高效运行具有重要意义。随着社会的进步,新能源的发展,各种各样发电方式得到应用,如太阳能发电,潮汐发电,风能发电等,相对于传统的发电方式,分布式电源更为清洁,有益于环境保护,经济效益更明显,越来越被更多国家所推广。
然而大量DG的接入改变了传统配电网供电方式,给电网的安全稳定运行带来威胁,对配电网的规划设计、安全管理、运行检修等方面的发展提出更多的要求。主要影响在以下几个方面,配电源的网络结构变得更加复杂,改变了潮流方向;DG的随机、间歇式发电给配电网的负荷预测带来困难;分布式电源的合理布置可以减少线路损耗,降低输配电成本;DG的接入位置不同将影响着电网的负载能力。
目前,关于分布式发电接入配电网的位置对配电网的规划与运行的影响有了很多的研究,分布式发电选址问题是一个复杂的问题,寻找最优并网位置较为困难,目前在用的方法主要是从节点度,节点的邻居度,节点的平均距离等方面进行考虑。
发明内容
本发明的目的是针对现有技术的不足,而提供一种DG并网选址的方法。这种方法通过实际环境数据,能获得最优分布式发电并网位置,使得配电网能够快速达到稳定工作状态。
实现本发明目的的技术方案是:
一种DG并网选址的方法,包括如下步骤:
1)构建电力网络拓扑模型:依据实际电力网络架构,构建电力网络拓扑模型,所述电力网络拓扑模型包括节点和链路,将实际电力系统中的发电厂和用户分别抽象为复杂电力网络中的电源节点和负载节点,将连接发电厂和用户的输电线路抽象为复杂电力网络中的边,获取电网中各节点的功率和各条连边的距离值,电源节点发出功率,负载节点消耗功率;
2)计算各个负载节点到电源节点的平均等效距离L1:结合步骤1)构建的电力网络拓扑模型中节点功率与连边距离,获得与DG并网位置相关的各个负载节点到电源节点的平均等效距离,称为L1;
3)计算整个电网的负载节点到电源节点平均等效距离L2:对步骤2)获取的L1取平均值,得到整个电网的负载节点到电源节点平均等效距离,称为L2;
4)计算L1的方差:根据L2,计算L1的方差,称为D;
5)确定DG的合理并网位置:对步骤4)获取的D数据序列进行排队,D值最小时DG接入的位置即为DG的合理并网位置。
步骤2)中所述L1计算公式为:
其中,L1(i)表示在当前DG接入位置下,节点i到电源节点的平均等效距离;
Lij表示节点i到节点j之间的最短距离,pi表示负载节点消耗的功率,pj表示发电节点消耗的功率,Ng表示原电网电源节点个数,NDG表示分布式电源个数。
步骤3)中所述L2计算公式为:
其中,Ni为电网中负载节点个数。
步骤4)中所述方差D的计算公式为:
其中,D表示在当前DG接入位置下L1的方差值。
这种方法通过实际环境数据,能获得最优分布式发电并网位置,使得配电网能够快速达到稳定工作状态。
附图说明
图1为实施例方法的流程示意图;
图2为实施例中电力网络拓扑模型示意图。
具体实施方式
下面结合附图和实施例对本发明内容作进一步阐述,但不是对本发明的限定。
实施例:
参照图1,一种DG并网选址的方法,包括如下步骤:
1)构建电力网络拓扑模型:依据实际电力网络架构,构建电力网络拓扑模型,所述电力网络拓扑模型包括节点和链路,将实际电力系统中的发电厂和用户分别抽象为复杂电力网络中的电源节点和负载节点,将连接发电厂和用户的输电线路抽象为复杂电力网络中的边,获取电网中各节点的功率和各条连边的距离值,电源节点发出功率,负载节点消耗功率,本例,电力网络拓扑模型如图2所示为IEEE30标准测试系统为例,IEEE30系统属于英国电网系统中的一部分,拥有6个发电机节点和24个负载节点,为了研究方便,我们初始设定,每条连边距离均为1,所有负载节点消耗相同的功率,发电机发出的功率等于负载消耗的功率,原始发电机和DG节点均向电网提供相同的功率,原电网中有Ng个发电机节点,发电机功率为pg,Ni个负荷节点,负荷功率为pi,NDG个DG节点,DG功率为pDG,由于要满足系统功率平衡,则设pi=-1,pg>0,pDG>0,则
2)计算各个负载节点到电源节点的平均等效距离L1:令一个或多个DG接入原电网中的节点,结合步骤1)构建的电力网络拓扑模型中节点功率与连边距离,获得与DG并网位置相关的各个负载节点到电源节点的平均等效距离,称为L1,已有的研究成果和结论表明,DG与负载节点相连接,电力网络同步性能更好,我们在此只考虑DG与负载节点相连的方式。令DG个数为1,接入如2所示电网中负载节点,表1表示DG接入3号节点后,电网中各负载节点到电源节点的平均等效距离:
表1:
表2表示DG接入4号节点后,电网中各负载节点到电源节点的平均等效距离:
表2:
3)计算整个电网的负载节点到电源节点平均等效距离L2:对步骤2)获取的L1取平均值,得到整个电网的负载节点到电源节点平均等效距离,称为L2,对于如2所示电网,将DG分别与电网中的负载节点相连接,每次接入后,计算整个电网的平均等效距离,表3表示DG接入节点i后,整个电网的平均等效距离情况:
表3:
4)计算L1的方差:根据L2,计算L1的方差,称为D,对于如2所示电网,计算每次接入DG后的网络D值,得到表4DG接入节点i后的网络D值:
表4:
5)确定DG的合理并网位置:对步骤4)获取的D数据序列进行排队,D值最小时DG接入的位置即为DG的合理并网位置,对比表4中的数据,如图2所示电网的DG合理并网位置应是26号节点。
步骤2)中所述L1计算公式为:
其中,L1(i)表示在当前DG接入位置下,节点i到电源节点的平均等效距离,Lij表示节点i到节点j之间的最短距离,pi表示负载节点消耗的功率,pj表示发电节点消耗的功率,Ng表示原电网电源节点个数,NDG表示分布式电源个数。
步骤3)中所述L2计算公式为:
其中,Ni为电网中负载节点个数。
步骤4)中所述方差D的计算公式为:
其中,D表示在当前DG接入位置下L1的方差值。
Claims (4)
1.一种DG并网选址的方法,其特征是,包括如下步骤:
1)构建电力网络拓扑模型:依据实际电力网络架构,构建电力网络拓扑模型,所述电力网络拓扑模型包括节点和链路,将实际电力系统中的发电厂和用户分别抽象为复杂电力网络中的电源节点和负载节点,将连接发电厂和用户的输电线路抽象为复杂电力网络中的边,获取电网中各节点的功率和各条连边的距离值,电源节点发出功率,负载节点消耗功率;
2)计算各个负载节点到电源节点的平均等效距离L1:结合步骤1)构建的电力网络拓扑模型中节点功率与连边距离,获得与DG并网位置相关的各个负载节点到电源节点的平均等效距离,称为L1;
3)计算整个电网的负载节点到电源节点平均等效距离L2:对步骤2)获取的L1取平均值,得到整个电网的负载节点到电源节点平均等效距离,称为L2;
4)计算L1的方差:根据L2,计算L1的方差,称为D;
5)确定DG的合理并网位置:对步骤4)获取的D数据序列进行排队,D值最小时DG接入的位置即为DG的合理并网位置。
2.根据权利要求1所述的DG并网选址的方法,其特征是,步骤2)中所述L1计算公式为:
<mrow>
<mi>L</mi>
<mn>1</mn>
<mrow>
<mo>(</mo>
<mi>i</mi>
<mo>)</mo>
</mrow>
<mo>=</mo>
<mrow>
<mo>(</mo>
<munderover>
<mo>&Sigma;</mo>
<mrow>
<mi>j</mi>
<mo>=</mo>
<mn>1</mn>
</mrow>
<mrow>
<msub>
<mi>N</mi>
<mi>g</mi>
</msub>
<mo>+</mo>
<msub>
<mi>N</mi>
<mrow>
<mi>D</mi>
<mi>G</mi>
</mrow>
</msub>
</mrow>
</munderover>
<mfrac>
<mrow>
<mo>|</mo>
<msub>
<mi>p</mi>
<mi>i</mi>
</msub>
<mo>|</mo>
<mo>&CenterDot;</mo>
<msub>
<mi>L</mi>
<mrow>
<mi>i</mi>
<mi>j</mi>
</mrow>
</msub>
</mrow>
<mrow>
<mo>|</mo>
<msub>
<mi>p</mi>
<mi>j</mi>
</msub>
<mo>|</mo>
</mrow>
</mfrac>
<mo>)</mo>
</mrow>
<mo>&CenterDot;</mo>
<mfrac>
<mn>1</mn>
<mrow>
<mo>(</mo>
<msub>
<mi>N</mi>
<mi>g</mi>
</msub>
<mo>+</mo>
<msub>
<mi>N</mi>
<mrow>
<mi>D</mi>
<mi>G</mi>
</mrow>
</msub>
<mo>)</mo>
</mrow>
</mfrac>
</mrow>
其中,L1(i)表示在当前DG接入位置下,节点i到电源节点的平均等效距离,Lij表示节点i到节点j之间的最短距离,pi表示负载节点消耗的功率,pj表示发电节点消耗的功率,Ng表示原电网电源节点个数,NDG表示分布式电源个数。
3.根据权利要求1所述的DG并网选址的方法,其特征是,步骤3)中所述L2计算公式为:
<mrow>
<mi>L</mi>
<mn>2</mn>
<mo>=</mo>
<munderover>
<mi>&Sigma;</mi>
<mrow>
<mi>i</mi>
<mo>=</mo>
<mn>1</mn>
</mrow>
<msub>
<mi>N</mi>
<mi>i</mi>
</msub>
</munderover>
<mi>L</mi>
<mn>1</mn>
<mrow>
<mo>(</mo>
<mi>i</mi>
<mo>)</mo>
</mrow>
<mo>/</mo>
<msub>
<mi>N</mi>
<mi>i</mi>
</msub>
</mrow>
其中,Ni为电网中负载节点个数。
4.根据权利要求1所述的DG并网选址的方法,其特征是,步骤4)中所述方差D的计算公式为:
<mrow>
<mi>D</mi>
<mo>=</mo>
<mfrac>
<mn>1</mn>
<msub>
<mi>N</mi>
<mi>i</mi>
</msub>
</mfrac>
<munderover>
<mo>&Sigma;</mo>
<mrow>
<mi>i</mi>
<mo>=</mo>
<mn>1</mn>
</mrow>
<msub>
<mi>N</mi>
<mi>i</mi>
</msub>
</munderover>
<msup>
<mrow>
<mo>(</mo>
<mi>L</mi>
<mn>1</mn>
<mo>(</mo>
<mi>i</mi>
<mo>)</mo>
<mo>-</mo>
<mi>L</mi>
<mn>2</mn>
<mo>)</mo>
</mrow>
<mn>2</mn>
</msup>
</mrow>
其中,D表示在当前DG接入位置下L1的方差值。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711377841.4A CN108092263B (zh) | 2017-12-19 | 2017-12-19 | 一种dg并网选址的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711377841.4A CN108092263B (zh) | 2017-12-19 | 2017-12-19 | 一种dg并网选址的方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108092263A true CN108092263A (zh) | 2018-05-29 |
CN108092263B CN108092263B (zh) | 2021-01-01 |
Family
ID=62177315
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711377841.4A Expired - Fee Related CN108092263B (zh) | 2017-12-19 | 2017-12-19 | 一种dg并网选址的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108092263B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114979153A (zh) * | 2022-04-07 | 2022-08-30 | 浙江大华技术股份有限公司 | 负载均衡方法、计算机设备及存储装置 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080122293A1 (en) * | 2006-10-13 | 2008-05-29 | Pv Powered, Inc. | System and Method for Anti-Islanding, Such as Anti-Islanding for a Grid-Connected Photovoltaic Inverter |
CN103887823A (zh) * | 2014-04-10 | 2014-06-25 | 武汉大学 | 基于模糊层次分析的微电网并网位置选取方法 |
CN106447061A (zh) * | 2015-08-06 | 2017-02-22 | 北京电研华源电力技术有限公司 | 分布式电源定容选址的方法 |
-
2017
- 2017-12-19 CN CN201711377841.4A patent/CN108092263B/zh not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080122293A1 (en) * | 2006-10-13 | 2008-05-29 | Pv Powered, Inc. | System and Method for Anti-Islanding, Such as Anti-Islanding for a Grid-Connected Photovoltaic Inverter |
CN103887823A (zh) * | 2014-04-10 | 2014-06-25 | 武汉大学 | 基于模糊层次分析的微电网并网位置选取方法 |
CN106447061A (zh) * | 2015-08-06 | 2017-02-22 | 北京电研华源电力技术有限公司 | 分布式电源定容选址的方法 |
Non-Patent Citations (2)
Title |
---|
王意 等: "分布式电站入网方式对电网同步的影响", 《广西师范大学学报(自然科学版)》 * |
谭玉东 等: "基于电气距离的复杂电网关键节点识别", 《中国电机工程学报》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114979153A (zh) * | 2022-04-07 | 2022-08-30 | 浙江大华技术股份有限公司 | 负载均衡方法、计算机设备及存储装置 |
CN114979153B (zh) * | 2022-04-07 | 2023-10-27 | 浙江大华技术股份有限公司 | 负载均衡方法、计算机设备及存储装置 |
Also Published As
Publication number | Publication date |
---|---|
CN108092263B (zh) | 2021-01-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108039726B (zh) | 一种基于多智能体系统的能源局域网分布式协同控制方法 | |
Ustun et al. | Modeling of a centralized microgrid protection system and distributed energy resources according to IEC 61850-7-420 | |
CN107506854B (zh) | 一种考虑差异化场景的220kV电网网架结构规划方法 | |
AlSkaif et al. | Decentralized optimal power flow in distribution networks using blockchain | |
CN104680424A (zh) | 大型光伏电站的电压电能情况预估方法 | |
CN106532710B (zh) | 计及电压稳定约束的微电网潮流优化方法 | |
CN105870949B (zh) | 一种基于分布式梯度算法的微电网储能单元优化控制方法 | |
CN109818369B (zh) | 一种计及出力模糊随机性的分布式电源规划方法 | |
CN107609675B (zh) | 一种基于多智能体系统趋同控制的经济调度运行方法 | |
CN108388688A (zh) | 一种主动配电网可靠性评估方法 | |
CN108199381A (zh) | 一种用于风电接入系统电压稳定性的切负荷地点选择方法 | |
US20200091725A1 (en) | Micro inverter and controller | |
CN112234611A (zh) | 一种基于计算机建模的配电网整定计算方法与系统 | |
Saleh | The analysis and development of a power flow-based controller for microgrid systems | |
CN106991229B (zh) | 一种针对复杂拓扑的风电场等值建模方法 | |
CN108092263A (zh) | 一种dg并网选址的方法 | |
Wang et al. | Optimal distribution network expansion planning incorporating distributed generation | |
Pico et al. | Reachability analysis of power system frequency dynamics with new high-capacity HVAC and HVDC transmission lines | |
Ustun et al. | Modeling and simulation of a microgrid protection system with central protection unit | |
Bonetto et al. | On the interplay of distributed power loss reduction and communication in low voltage microgrids | |
Gabriels et al. | Proposed framework for integration of optimal current injection and multi-agent control of the LV distribution network | |
Bodapatla et al. | Loss reduction by optimal placement of distributed generation on a radial feeder | |
CN104218607A (zh) | 基于人工鱼群和禁忌搜索算法在新能源接入系统中的应用 | |
CN105337300B (zh) | 微电网接入配电网时的交换功率控制方法及装置 | |
Molazei et al. | Vector swarm optimization algorithm for distributed generator allocation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20210101 |