CN108049878A - A kind of powder land floor shield cuts the construction method that stake is crossed the river - Google Patents

A kind of powder land floor shield cuts the construction method that stake is crossed the river Download PDF

Info

Publication number
CN108049878A
CN108049878A CN201711115446.9A CN201711115446A CN108049878A CN 108049878 A CN108049878 A CN 108049878A CN 201711115446 A CN201711115446 A CN 201711115446A CN 108049878 A CN108049878 A CN 108049878A
Authority
CN
China
Prior art keywords
shield
river
pressure
construction
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711115446.9A
Other languages
Chinese (zh)
Other versions
CN108049878B (en
Inventor
丁智
洪哲浩
张霄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201711115446.9A priority Critical patent/CN108049878B/en
Publication of CN108049878A publication Critical patent/CN108049878A/en
Application granted granted Critical
Publication of CN108049878B publication Critical patent/CN108049878B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/093Control of the driving shield, e.g. of the hydraulic advancing cylinders
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/12Devices for removing or hauling away excavated material or spoil; Working or loading platforms
    • E21D9/124Helical conveying means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention relates to a kind of powder land floor shields to cut the construction method that stake crosses the river, including:Material prepares;Shield cuts pile foundation concrete measure:Cut pile driving construction control, monitoring and controlling, under wear river Construction control, the working measure of ambiguous barriers, pipeline protection measure;Shield driving parameter setting;Under wear the working measure in river;Control technology after shield crossing pile foundation;Monitoring frequency controls;Control is maked an inspection tour in hole.The beneficial effects of the invention are as follows:Method and step is simple, design is reasonable and construction is simple is convenient, and input cost is relatively low, and Practical Project operation implementation is strong;It can be improved down by the method for the invention and wear drivage efficiency, control attitude of shield machine, so as to reduce the possibility that accident occurs for tunnel, favourable basis is laid for follow-up successfully pass through;Practical value is high and using effect is good, compared to bored tunnel construction method is worn under existing, shortens the construction period, larger to reduce construction cost.

Description

A kind of powder land floor shield cuts the construction method that stake is crossed the river
Technical field
The invention belongs to shield crossings to cut off existing pile foundation technical field, and stake is cut more particularly, to a kind of powder land floor shield The construction method to cross the river.
Background technology
In recent years, as city underground and the Large scale construction of related municipal works, the application of shield tunnel at home are got over Come more.In the shield crossing stage, can run into existing building pile foundation often needs the construction methods such as progress pile pulling to cut off pile foundation, So that shield is normally passed through, but this kind of construction method is long in time limit, and construction cost is high, and more demanding to construction environment, often not Expected construction effect can be reached.
It is more using commonly risk existing for pile construction method is cut.If such as driving speed mistake during the stake of shield machine-cut Soon, it is easy to shield machine is caused to block, while there is pile foundation intrusion in uplink tunnel cross-section one side, opposite side is stratum undisturbed soil. Gesture stability difficulty in tunneling process is larger, if causing the snakelike advance of shield machine, also increases the wind that shield machine blocks Danger;Shield machine may also be seriously damaged, influences subsequent construction.The pile top of driving, broken pile head such as shield machine together Advance causes stratum to backbreak, and influences the control of surface subsidence and follow-up house, the safety of pipeline;In addition, shield spiral Conveyer may be blocked by reinforcing bar, and shield machine can not operate normally.After shield machine cutting pile foundation, the reinforcing bar in pile foundation will enter spiral shell Conveyer is revolved, reinforcing bar causes screw machine stuck, shadow it is possible that be stuck in the gap between helical blade and screw machine sleeve lining Ring later stage driving;If the stake after passing through will be with dotted load action on tunnel duct piece, and load is directly delivered to tunnel lining It builds, tunnel and bridge interaction, can give the safe handling of the two to bring hidden danger during subway circulation;When shield machine passes through river During stream, since earthing is shallower, soil body stability is poor, river bed perforation is be easy to cause, river water pours in down a chimney.
The content of the invention
The purpose of the present invention is overcoming deficiency of the prior art, a kind of powder land floor shield is provided and cuts the construction that stake is crossed the river Method, method and step is simple, and design is rationally and easy construction, construction effect are good, and effectively existing pile foundation can be cut off and successfully worn More stratum, cycle are short and at low cost.
The purpose of the present invention is what is be achieved through the following technical solutions:
This powder land floor shield cuts the construction method that stake is crossed the river, and comprises the following steps:
1) material prepares:Carry out secondary grouting preparation after the wall of section of jurisdiction;Secondary grouting equipment is overhauled in advance;Preparation slip casting Injected hole impact drill is opened in head and the Grouting Pipe being connected with casting head, slip casting machine, preparation section of jurisdiction;Preparation cement, water glass Glass, grouting non-return valve and hand hole plug;
2) shield cuts pile foundation concrete measure:Cut pile driving construction control:Shield controls soil pressure, cutterhead during pile foundation is cut Torque, grouting pressure and the every important parameter of amount of being unearthed;Monitoring and controlling:Arrangement measuring point has surveyed initial value, before shield crossing pile foundation or After shield crossing pile foundation, tunnel axis, surface subsidence deformation and the monitoring of building deformation are carried out, according to monitoring data control Construction overall process processed;Under wear river Construction control:Shield diameter of the height to earth up in river less than one times, then to bridge before promoting It is reinforced, while strengthens the protection to closely bridge pier and prevent river water perfusion;The working measure of ambiguous barriers:According to area Between physical prospecting report, the position of disturbance of analysis object, in progradation pay close attention to cutter head torque variation and thrust variation;Pipeline is protected Shield measure:Investigation is carried out before construction to pipeline along section to implement;It cuts stake entire and crosses the river in work progress, inject bentonite System be in can working condition, occur soil pressure mutation or digging footage amount be unearthed amount non-matching phenomenon when, note in Xiang Tucang Enter bentonite, soil pressure when injection pressure is higher than driving;
3) shield driving parameter setting:Shield controls fltting speed and soil pressure force parameter during cross-over pile base;Shield Structure slows down fltting speed when close to pile foundation, and lubricant is filled to cutterhead;The cutterhead of shield is put again close to fltting speed during pile foundation Slowly;Cutter cuts concrete and reinforcing bar to push away speed mill slowly when the cutterhead of shield is cut;In the case of pushing away speed centainly, cutterhead is with medium turn Speed cuts stake;Soil cabin pressure setting when raising is cut, during dynamic is unearthed, is stably held in a high position by soil pressure, first closes Close casting gate, shield is bored to push away advance, after soil cabin pressure rise to than setting soil cabin pressure it is high after, manually be unearthed, regulating gate Aperture opening ratio is no more than 10%, and soil cabin pressure drops to closed shutter after setting soil cabin pressure, and continuation is bored to be pushed away, and is so cycled;Shield is cut Stake is by rear, and selection intensity is low, solidifies slow slurries type, and grouting amount refers to the feelings tunneled in identical soil layer shield early period Condition is adjusted further according to bridge settlement monitoring data;Pushed position, intrusion and pressure value are remembered in detail during mud jacking Record, is adjusted according to stratum deformation monitor information;Shield equilibrium is at the uniform velocity constructed, control shield attitude variation, per ring inspection pipe The advanced argument of piece;It is promoted during propulsion using steady slope method, gentle slope method;Shield cuts and carries out gesture stability during stake, cutterhead when cutting With pile body comprehensive engagement, between the two without the degree of bias;Improve in the cutterhead front pressure injection bentonite of shield the excavation face soil body and easy The unearthed amount of property, controlled quentity controlled variable and pressure when adding bentonite, bentonitic pressure injection amount and shield is mutually matched;It is equipped with hand-held infrared ray Thermometer judges native storehouse internal temperature situation;Gate before and after being closed when screw machine is gushed and happened;Inspect periodically shield tail oil Fat pipeline and grease pump select the measured shield tail grease of matter;The work of shield tail grease injected system is understood by tunneling record daily Make situation, prejudge failure in advance, and place under repair;
4) working measure in river is worn under:Control shield earth pressure balance;Control the fltting speed of shield;Control shield is entangled Deviator:The posture of a section of jurisdiction is adjusted during propulsion per ring inspection, is promoted using steady slope method, gentle slope method, shield equilibrium is made at the uniform velocity to push away Into, error correct amount to reduce influence of the shield-tunneling construction to ground;Control synchronous grouting amount and grind slurries quality;
5) control technology after shield crossing pile foundation:Behind shield shield tail abjection pile foundation region, which is carried out Two~tetra- slip casting, specific mud jacking amount are adjusted according to the situation of ground settlement monitoring data.
As priority:Before step 1), Suporting structure inspection is carried out, checks synchronous grouting system, foam injection systems, inspection Earth pressure balance system is looked into, checks shield tail grease injected system, hinged sealing system is checked, checks tunnel inner water drainage system, check Communication system.
As priority:In the step 3), when the cutterhead of shield is cut cutter with 1~3mm/min it is slow push away speed mill cut it is mixed Solidifying soil and reinforcing bar, the thrust and torque of shield are controlled as 13000~18000kN and 2500~3500kNm.
As priority:In the step 3), in the case of pushing away speed centainly, cutterhead is cut with the moderate rotation of 1.2~1.5rpm Stake.
As priority:In the step 4), the fltting speed of shield is controlled in 2~3cm/min.
As priority:In the step 4), soil improvement agent is filled into native storehouse if necessary.
The beneficial effects of the invention are as follows:
(1) method and step is simple, design is reasonable and construction is simple is convenient, and input cost is relatively low, and Practical Project operation is implemented Property is strong;
(2) it can be improved down by the method for the invention and wear drivage efficiency, attitude of shield machine be controlled, so as to reduce tunnel The possibility of generation accident lays favourable basis for follow-up successfully pass through;
(3) practical value is high and using effect is good, compared to bored tunnel construction method is worn under existing, shortens construction work It is phase, larger to reduce construction cost;
(4) it is widely applicable, all bored tunnel constructions can be effectively applicable to and shield reinforces the particularly ground such as compound stratum The geology of matter situation complexity has ensured that shield is subsequently passed through that everything goes well with your work and carried out.
Description of the drawings
Fig. 1 is the method flow block diagram of the present invention.
Fig. 2 is shield tunnel and pile foundation position relationship drawing in side sectional elevation
Fig. 3 is that the wear-resisting weldering of cutterhead thickeies schematic diagram.
Fig. 4 is L-type baffle layout diagram at inspection hole.
Fig. 5 is that L-type baffle lays sectional view at inspection hole.
Reference sign:1-shield;2-pile foundation;The wear-resisting weldering thickening layer of 3-cutterhead;4-L-type block;5-screw machine Soil outlet;6-inspection hole;7-access plate sliding area.
Specific embodiment
The present invention is described further with reference to embodiment.The explanation of following embodiments is only intended to help to understand this Invention.It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, also Can to the present invention some improvement and modification can also be carried out, these improvement and modification also fall into the protection domain of the claims in the present invention It is interior.
A kind of powder land floor shield as shown in Figure 1 cuts the construction method technological process that stake is crossed the river.Shield as shown in Figure 2 1 tunnel and 2 position relationship drawing in side sectional elevation of pile foundation.Cutter head of shield machine both sides are that big alloy is circular, and centre is an alloy, is ensured whole A cut surface is all alloy.It cuts concrete dual-pilot cutter both sides to design for Rouno Cormer Pregrinding Wheel, cutterhead can reduce impact when rotating;Cut concrete dual-pilot cutter The blade at top is narrow, and stress is small, easily cuts, when touching reinforcing bar, is more advantageous to cutting.As shown in Figure 3, in cutterhead face Plate increases the thick wear-resisting welderings of 3mm and forms the wear-resisting weldering thickening layer 3 of cutterhead.If during 1 cross-over pile base 2 of shield, knife cutting stake Base 2, breaking concrete block screw machine soil outlet 5, screw machine are caused to be unearthed not smooth, so as to continue to implement to promote.Work as spiral shell When rotation is by card, before inspection hole 6 and cutting inspecting hole is opened, Emergency Preparedness work is carried out.As shown in Figure 4,5, checking at this time Two-way parallel welding L-type block 4 around inspecting hole position is opened in hole 6 in advance, and the L-type block 4 can be used 3~5cm steel plates and cut It forms, L-type block 4 is connected by bolt with inspection hole 6, is in case of emergency pushed away along 7 direction of access plate sliding area Enter cover board, tighten bolt.The specific size of the L-type block 4 to consider cover board insertion when space and do not influence installation bolt Depending on.
For reality in 1 cross-over pile base 2 of shield, if pile breaking phenomenon occurs in pile foundation 2, the working measure taken is as follows:
1) shield 1 injects additive, such as foam, bentonite, carries out soil improvement.And pass through the rotating of cutterhead by broken pile In the native storehouse of incision or squeeze.
2) construct in case of broken pile influences shield 1, shield 1 stops promoting.Using the injected hole of shield machine host to shield machine Front carries out pre-grouting so that the soil body in front of shield machine has certain intensity, ensures the soil strength of 1 excavation face of shield Uniformity, then carry out shield 1 and tunnel.
3) chamber opening operation construction is carried out if necessary.
Detailed process is as follows:
1) shield machine equipment inspection:
1-1) synchronous grouting system, foam injection systems inspection
Grouting pipeline is cleared up, it is ensured that four road pipelines can be used;It checks comprehensively, maintenance grouting pump, it is ensured that available; Grouting pressure sensor is carried out maintenance, it is correct to ensure that each grouting pressure is shown;Foaming pipeline is cleared up, particularly Into the foaming agent pipe before cutterhead, it is ensured that available.
1-2) check earth pressure balance system
Pressure sensor (support pressure sensor and the screw conveyor pressure sensing that shield machine more renews before originating Device), and pressure change is kept a close eye in early period tunneling process, whether analysis pressure sensor damages, if damage, in time into Row is replaced.
1-3) check shield tail grease injected system
For ensure grouting at the tail of the shield machine not spillage or few spillage, prevent shield tail " gushing ", it is necessary to shield grease injected system into Row maintenance ensures that grease pump is working properly, grease lines are unobstructed, adjustment grease injection pressure, it is ensured that grease injection rate.
1-4) check hinged sealing system
To prevent hinged seal failure from hinge point spillage being caused even " to gush ", it is necessary to which hinged sealing system is examined It repaiies, in sand bed tunneling process, it is necessary to which according to machine management regulation, frequency check, maintenance are hinged sealing system on request, it is ensured that complete It is good available.
1-5) check tunnel inner water drainage system
To prevent that tunneling generation " gushing " due to shield 1 influences construction, tunnel internal drainage drainage must be carried out complete The dress watch in face, and prepare enough diaphragm pumps with spare.
1-6) check communication system
Upper and lower communication line and equipment must be overhauled, it is ensured that contacted up and down in work progress and during emergency logical Freely.
2) other materials prepares:
Secondary grouting preparation after the wall of section of jurisdiction is carried out, accomplishes that secondary grouting measure can be started at any time.Two are overhauled in advance Secondary (biliquid) grouting equipment, it is ensured that available.Prepare 6~8 casting heads, prepare 10~15m long Grouting Pipe simultaneously can with casting head, Slip casting machine connection is intact, prepares section of jurisdiction and opens injected hole impact drill two.The daily deposit of cement is no less than 20t, and waterglass is daily Deposit is no less than 2t, and grouting non-return valve and hand hole plug are several.
3) shield 1 cuts 2 concrete measure of pile foundation:
3-1) cut pile driving construction control
It must slow down fltting speed when cutting, shield machine parameter is rationally set.Shield 1 is during pile foundation 2 is cut, it is necessary to Stringent control soil pressure, cutter head torque, grouting pressure, the every important parameter of amount etc. of being unearthed, reduce progradation pile foundation 2 to the greatest extent Situations such as itself global displacement, occurs.
3-2) monitoring and controlling
Arrangement measuring point has surveyed initial value;Before 1 cross-over pile base 2 of shield or after passing through, carry out tunnel axis, surface subsidence deformation, The monitorings such as building deformation effectively control construction overall process according to monitoring data.
River Construction control is worn under 3-3)
Shield 1 diameter of the earthing in river less than one times reinforces bridge before promoting, while reinforcement is to closely The protection of bridge pier and prevent river water perfusion.
3-4) the working measure of ambiguous barriers
It is reported according to section physical prospecting, analyzes the barriers such as waste pile that may be present, substantially distinguish position.It is being advanced over The variation of cutter head torque is paid close attention in journey, the variation of thrust, when torque increases gross thrust increase, tetra- subregions of ABCD have thrust play Increase, sidewinder drastic change explanation and encounter stake.
3-5) pipeline protection measure
According to geologic information and design document that owner provides, investigation should be carried out before construction to pipeline along section and is implemented.
It 3-6) cuts stake entire and crosses the river in work progress, bentonite injected system is in can working condition immediately.Occurring When soil pressure mutation, digging footage amount occur with amount mismatch (backbreaking) phenomenon of being unearthed, bentonite is injected into native storehouse immediately.Injection Soil pressure when pressure is higher than driving, to ensure to backbreak, region is sufficient filling with by bentonite, reduces sedimentation.
4) shield driving parameter setting:
Shield 1 is during cross-over pile base 2, it is necessary to which the stringent control parameters such as fltting speed and soil pressure reduce to the greatest extent The occurrence of itself global displacement of pile foundation 2.For shield 1 at the 6m close to pile foundation 2, when propulsion, must slow down fltting speed, push away Into speed control in 1cm/min, the front soil body forms mud cake in order to prevent, fills lubricant to cutterhead in right amount, and it is suitable to improve the soil body Profit is unearthed;Close to pile foundation 2, fltting speed further slows down cutter head of shield machine.1 digging large diameter pile foundation 2 of shield with " push away slowly speed, The lazy slurry of middle rotating speed, soil conservation pressure, note, control posture " is core control technology.
Speed 4-1) is pushed away slowly
It is basic that 1 cutterhead of shield, which cuts stake with " grinding ", and cutter grinds and cuts concrete and reinforcing bar in which should push away fast, small cutting-in slowly.It examines Consider that this engineering is relatively previous similar to cut engineering difficulty bigger, a risk higher, therefore slower driving speed should be taken, control 1~3mm/min;If it is excessive to cut 1 thrust torques of shield during stake, 1 inherently safe of shield will be not only influenced, it also can be to bridge pier Larger active force is generated, and then influences bridge structure safe, therefore reference case experience, by thrust and moment of torsion control scope point It does not draft as 13000~18000kN and 2500~3500kNm.
Rotating speed in 4-2)
In the case where pushing away speed centainly, cutterhead rotating speed is larger, although single cutting depth of the cutter to pile foundation 2 can be reduced, Thrust torques are advantageously reduced, but then, the cutting linear velocity of cutterhead outer edge cutter is then inevitable big when rotating speed is big, can make Be subject to larger impact load during tool contact pile foundation 2, so as to be easy to cause alloy burst apart very monoblock collapse it is de-.Therefore, to take into account Control reasoning torque and protect cutter dual needs, cutterhead rotating speed do not answer it is excessive also should not be too small, be advisable with moderate rotation, turn Speed control is in 1.2~1.5rpm or so.
4-3) soil conservation pressure
Soil conservation pressure is the key that control bridge settlement.Different from usual driving, disturbance is mainly in knife caused by cutting pile driving construction Disk position, and the bearing capacity of bridge pier and pier derives from the support of its periphery soil body, therefore shield 1 is cut when pile foundation 2 is constructed and is answered The setting of soil cabin pressure should when reducing the disturbance to surrounding soil as far as possible, especially prevent soil body Excessive Settlement and deformation, therefore cutting Suitably improve.Simultaneously dynamic be unearthed during, soil pressure should be stably held in a high position, specifically can by " bored to push away " come It realizes:First completely close casting gate, shield machine is " bored to push away " to advance, after soil pressure be increased to it is higher than setting soil pressure after, be unearthed manually, Regulating gate aperture opening ratio is no more than 10%, and soil pressure drops to closed shutter immediately after setting soil pressure, continues " bored to push away ", so cycles.
4-4) note lazy slurry
Shield 1 cuts stake by rear, and cut-off top stub will act in the slurries of grouting behind shaft or drift lining, to prevent that top is residual Stake continues to generate load to pipe-plate lining after sinking, the slurries type that selection intensity is not high, solidification is slower, on grouting amount Situation about being tunneled in identical soil layer shield early period is can refer to, is adjusted in time further according to bridge settlement monitoring data.Mud jacking amount and Depending on pressure value and stratum deformation monitoring data of the mud jacking point when mud jacking.Mud jacking must assign special messenger to be responsible for, to pushed position, pressure Enter amount, pressure value makes detailed records, and adjusted in time according to stratum deformation monitor information, it is ensured that the construction matter of mud jacking process Amount.
4-5) control posture
During 1 knife cutting of shield or grinding bridge pier, pile foundation 2 reacts on cutterhead, the easy unbalance stress in cutterhead front, 1 gesture stability difficulty of shield is larger.Since shield 1 needs continuous cutting to pass through more bridge piers, if 1 gesture stability of shield is bad, very The stub having been turned off may be caused to act directly on shield casing, in addition also can further increase wind of the end to section of jurisdiction safety Danger, therefore should strengthen the control of 1 posture of shield particularly perpendicular attitude, and when correction should also avoid anxious entangling, entangling suddenly.Ensuring shield In the case of 1 positive settlement Control is good, make shield 1 is balanced at the uniform velocity to construct, 1 attitudes vibration of shield can not be excessive, per ring inspection The advanced argument of section of jurisdiction.It does not entangle suddenly, entangle suddenly during propulsion, it is pay attention to observation section of jurisdiction and the gap of shield shell, the change of opposed area oil pressure more Change amount is gradually changed with unearthed case number and jack stroke, is promoted using steady slope method, gentle slope method, to reduce the shadow of the construction of shield 1 It rings;Posture strictly controls during shield machine-cut stake, and cutterhead and pile body comprehensive engagement, not there is the degree of bias between the two when cutting.
4-6) cutterhead front soil improvement
Bentonitic use.The propulsion of shield 1 need to cut concrete, to ensure that the normal of shield 1 is unearthed, it is necessary to which the moment is in shield The cutterhead front pressure injection bentonite of structure 1 improves the workability of the excavation face soil body, ensures that shield 1 is passed through so as to reduce cutter head torque When have balanced fltting speed, while the soil body in conditioned soil storehouse, pile body fragment is contributed to smoothly to be discharged out of screw machine.Add swollen The amount of must be strictly controlled and pressure during profit soil avoid the soil body from forming orientation under excessive note bentonite amount and higher pressure and pass through Logical medium crack, causes penetrating passage, seriously affects the safe condition in tunnel.According to past construction experience and swelling The relative theory of soil or foaming agent, bentonitic pressure injection amount must be mutually matched with the unearthed amount of shield machine.It is equipped with hand-held infrared Line thermometer, in tunneling process, often tunnels 30 centimeters, and one-shot measurement is carried out to dregs temperature, judges temperature inside native storehouse with this Degree situation.
4-7) screw conveyor gate is controlled and shield tail grease injects
Ensure to close front and rear gate in time when screw machine is gushed and happened, the dregs amount that will gush is preferably minimized.Periodically Check shield tail grease lines, grease pump.Understand the working condition of shield tail grease injected system in time by tunneling record daily, to the greatest extent Failure may be prejudged in advance, repaired in time.The measured shield tail grease of matter is selected simultaneously, and guarantee tail sealing performance be (each ring Pressure injection amount is 35kg, in case of exceptional circumstances, can increase the pressure injection amount of shield tail grease by actual conditions, grease storehouse pressure for 15~ 20bar)。
5) working measure in river is worn under:
5-1) strictly control 1 earth pressure balance of shield
The related construction parameter of stringent control balance pressure, prevents from backbreaking, owes to dig the fluctuation for reducing balance pressure to the greatest extent.
5-2) strictly control the fltting speed of shield 1
Speed should be controlled in 2~3cm/min during propulsion, and equilibrium construction reduces the disturbance to surrounding soil, avoids on the way There is the long period to pause to stop over.
5-3) strictly control 1 correction amount of shield
The posture of a section of jurisdiction is adjusted during propulsion per ring inspection, is promoted using steady slope method, gentle slope method, makes shield 1 balanced even Speed promotes, and stringent error correct amount is to reduce the influence of 1 Construction on Ground of shield.
5-4) strictly control synchronous grouting amount and grind slurries quality
Ensureing will be in place per ring slip casting total amount;During ensureing that shield 1 promotes each case soil, the uniform pressure injection of slurries;Slurry The proportioning of liquid must meet quality standard.
Soil improvement agent 5-5) is filled into native storehouse if necessary, ensures the water-retaining property of the soil body in native storehouse, prevents river water from penetrating through.
6) control technology after 1 cross-over pile base 2 of shield:
Behind 1 shield tail of shield abjection pile foundation, 2 region, secondary ftercompction slurry must be carried out to the area segments tunnel, can carried out if necessary Three times, four slip casting.Design adds injected hole on section of jurisdiction simultaneously.On the premise of original 6 injected holes, and add 10 A injected hole so can ensure that the effect of slip casting with multiple spot, the slip casting of small pressure.By secondary ftercompction starch tunnel and The gap of reinforcing area is replenished in time, and further ensures that the regional land subsidence is controlled, secondary grouting slurries are selected For dual slurry, the ratio of mud 1:1.2 coverage of shield machine cutting pile foundation is the distance of 35 rings, thus take in this 35 ring and When secondary grouting construction.Grouting amount is fixed tentatively as every ring 1.5m3, point 5 pipe sheet assembling holes carry out pressure injection, are per pore pressure fluence 0.3m3, specific mud jacking amount is adjusted in time according to the situation of ground settlement monitoring data.
The present invention has the advantages such as stability is high, speed of application is fast, while can guarantee construction quality, ensures that successive projects are applied Work application prospect is good.

Claims (6)

1. a kind of powder land floor shield cuts the construction method that stake is crossed the river, which is characterized in that comprises the following steps:
1) material prepares:Carry out secondary grouting preparation after the wall of section of jurisdiction;Secondary grouting equipment is overhauled in advance;Preparation casting head with And injected hole impact drill is opened in the Grouting Pipe being connected with casting head, slip casting machine, preparation section of jurisdiction;Preparation cement, waterglass, note Slurry non-return valve and hand hole plug;
2) shield (1) cuts pile foundation (2) concrete measure:Cut pile driving construction control:Shield (1) controls soil during pile foundation (2) is cut Pressure, cutter head torque, grouting pressure and the every important parameter of amount of being unearthed;Monitoring and controlling:Arrangement measuring point has surveyed initial value, shield (1) Before cross-over pile base (2) or after shield (1) cross-over pile base (2), the prison of tunnel axis, surface subsidence deformation and building deformation is carried out Work is surveyed, construction overall process is controlled according to monitoring data;Under wear river Construction control:When the height to earth up in river is less than one times Shield (1) diameter reinforces bridge before then promoting, while strengthens the protection to closely bridge pier and prevent river water perfusion; The working measure of ambiguous barriers:It is reported according to section physical prospecting, the position of disturbance of analysis object, cutterhead is paid close attention in progradation and is turned round The variation of square and the variation of thrust;Pipeline protection measure:Investigation is carried out before construction to pipeline along section to implement;Entirely cutting stake Cross the river in work progress, make bentonite injected system be in can working condition, soil pressure mutation or digging footage amount is occurring with going out During soil amount non-matching phenomenon, injection bentonite in Xiang Tucang, soil pressure when injection pressure is higher than driving;
3) shield (1) propulsive parameter is set:Shield (1) controls fltting speed and soil pressure ginseng during cross-over pile base (2) Number;Shield (1) slows down fltting speed when close to pile foundation (2), and lubricant is filled to cutterhead;The cutterhead of shield (1) is close to pile foundation (2) fltting speed slows down again when;Cutter cuts concrete and reinforcing bar to push away speed mill slowly when the cutterhead of shield (1) is cut;It pushes away fast certain In the case of, cutterhead cuts stake with moderate rotation;Soil cabin pressure setting when raising is cut, it is during dynamic is unearthed, soil pressure is steady Surely a high position is maintained at, first closes casting gate, shield (1) is bored to push away advance, treats soil cabin pressure rise to than setting soil cabin pressure After power height, it is unearthed manually, regulating gate aperture opening ratio is no more than 10%, and soil cabin pressure drops to closed shutter after setting soil cabin pressure, Continue it is bored push away, so cycle;Shield (1) cuts stake by rear, and the slurries type that selection intensity is low, solidification is slow, grouting amount refers to shield The situation that structure early period tunnels in identical soil layer is adjusted further according to bridge settlement monitoring data;During mud jacking to pushed position, Intrusion and pressure value make detailed records, and are adjusted according to stratum deformation monitor information;Shield (1) equilibrium is at the uniform velocity constructed, Shield (1) attitudes vibration is controlled, the advanced argument of section of jurisdiction is checked per ring;It is promoted during propulsion using steady slope method, gentle slope method;Shield (1) It cuts and carries out gesture stability during stake, cutterhead and a pile body comprehensive engagement when cutting, between the two without the degree of bias;Knife in shield (1) Disk front pressure injection bentonite improves the workability of the excavation face soil body, controlled quentity controlled variable and pressure when adding bentonite, bentonitic pressure injection amount It is mutually matched with the unearthed amount of shield (1);It is equipped with hand-held infra-red thermometer and judges native storehouse internal temperature situation;It is sprayed in screw machine Gush gate before and after being closed when happening;Shield tail grease lines and grease pump are inspected periodically, selects the measured shield tail grease of matter;It is logical The working condition that daily driving record understands shield tail grease injected system is crossed, failure is prejudged in advance, and places under repair;
4) working measure in river is worn under:Control shield (1) earth pressure balance;Control the fltting speed of shield (1);Control shield (1) correction amount:The posture of a section of jurisdiction is adjusted during propulsion per ring inspection, is promoted using steady slope method, gentle slope method, makes shield (1) equal Weighing apparatus at the uniform velocity promotes, and error correct amount is to reduce the influence of shield (1) Construction on Ground;Control synchronous grouting amount and grind slurries quality;
5) control technology after shield (1) cross-over pile base (2):Behind shield (1) shield tail abjection pile foundation (2) region, to the area segments Tunnel carries out two~tetra- slip casting, and specific mud jacking amount is adjusted according to the situation of ground settlement monitoring data.
2. powder land floor shield according to claim 1 cuts the construction method that stake is crossed the river, it is characterised in that:In step 1) Before, shield (1) equipment inspection is carried out, checks synchronous grouting system, foam injection systems, checks earth pressure balance system, checks shield Tail grease injected system checks hinged sealing system, checks tunnel inner water drainage system, checks communication system.
3. powder land floor shield according to claim 1 cuts the construction method that stake is crossed the river, it is characterised in that:The step 3) In, cutter cuts concrete and reinforcing bar, the thrust of shield (1) with the slow speed mill that pushes away of 1~3mm/min when the cutterhead of shield (1) is cut 13000~18000kN and 2500~3500kNm are controlled as with torque.
4. powder land floor shield according to claim 1 cuts the construction method that stake is crossed the river, it is characterised in that:The step 3) In, in the case of pushing away speed centainly, cutterhead cuts stake with the moderate rotation of 1.2~1.5rpm.
5. powder land floor shield according to claim 1 cuts the construction method that stake is crossed the river, it is characterised in that:The step 4) In, the fltting speed of shield (1) is controlled in 2~3cm/min.
6. powder land floor shield according to claim 1 cuts the construction method that stake is crossed the river, it is characterised in that:The step 4) In, soil improvement agent is filled into native storehouse if necessary.
CN201711115446.9A 2017-11-13 2017-11-13 A kind of powder land floor shield cuts the construction method that stake is crossed the river Active CN108049878B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711115446.9A CN108049878B (en) 2017-11-13 2017-11-13 A kind of powder land floor shield cuts the construction method that stake is crossed the river

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711115446.9A CN108049878B (en) 2017-11-13 2017-11-13 A kind of powder land floor shield cuts the construction method that stake is crossed the river

Publications (2)

Publication Number Publication Date
CN108049878A true CN108049878A (en) 2018-05-18
CN108049878B CN108049878B (en) 2019-06-25

Family

ID=62120140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711115446.9A Active CN108049878B (en) 2017-11-13 2017-11-13 A kind of powder land floor shield cuts the construction method that stake is crossed the river

Country Status (1)

Country Link
CN (1) CN108049878B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109060395A (en) * 2018-08-27 2018-12-21 郑州大学 The pilot system platform of excision composite foundation pile body is worn under a kind of shield
CN109869158A (en) * 2019-03-20 2019-06-11 南通勘察设计有限公司 Subway shield tunnel construction technique in a kind of sand
CN110374617A (en) * 2019-08-08 2019-10-25 中国建筑第四工程局有限公司 A kind of Shield Method Tunnel for Metro Tunnel Passing construction prestressed cable method
CN110685704A (en) * 2019-10-15 2020-01-14 中铁十二局集团有限公司 Construction method for water bag pebble mixed soil layer earth pressure shield to pass through river channel
CN110985021A (en) * 2019-12-12 2020-04-10 中铁十二局集团第二工程有限公司 Long-distance river-crossing construction method for earth pressure balance shield
CN112031789A (en) * 2020-09-10 2020-12-04 宁波朗达工程科技有限公司 Shield method for preventing water-rich layered soft soil duct piece from squeezing crack and sinking to ground
CN112160758A (en) * 2020-10-19 2021-01-01 中建八局轨道交通建设有限公司 Construction method for slurry shield to penetrate through river dike
CN112365785A (en) * 2020-10-20 2021-02-12 山东大学 Servo type composite earth pressure balance micro shield device and working method
CN112523767A (en) * 2020-11-24 2021-03-19 中铁隧道局集团有限公司 Construction method for shield pile grinding of expansion soil layer
CN112647963A (en) * 2020-12-21 2021-04-13 上海隧道工程有限公司 Construction method for shield to obliquely penetrate existing ground wall
CN112682052A (en) * 2019-10-18 2021-04-20 中铁第六勘察设计院集团有限公司 Construction method for underpinning pile foundation in shield tunnel
CN112922616A (en) * 2019-12-05 2021-06-08 宏润建设集团股份有限公司 Method for controlling shield crossing construction
CN114370285A (en) * 2021-12-27 2022-04-19 上海市基础工程集团有限公司 Method for judging cutting pile foundation of shield machine in soft soil stratum

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0774566A1 (en) * 1995-11-17 1997-05-21 FLOWTEX TECHNOLOGIE-IMPORT VON KABELVERLEGEMASCHINEN GmbH Method for securing in advance the roof when driving tunnels
JP2004060266A (en) * 2002-07-29 2004-02-26 Alpha Civil Engineering:Kk Non-open-cut construction method for underground structure
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN102720508A (en) * 2012-04-28 2012-10-10 中铁二局股份有限公司 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation
CN103527209A (en) * 2013-10-22 2014-01-22 北京交通大学 Micro disturbance tunneling method used for shield machine to tunnel under building on rich water weak formation
CN103603670A (en) * 2013-11-21 2014-02-26 上海市基础工程集团有限公司 Construction method of ultra-deep-earthed shield crossing complex formations
CN104989412A (en) * 2015-06-11 2015-10-21 北京市市政四建设工程有限责任公司 Earth pressure balance type shield long-distance lake-crossing construction technology
CN105804761A (en) * 2016-03-14 2016-07-27 上海隧道工程有限公司 Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0774566A1 (en) * 1995-11-17 1997-05-21 FLOWTEX TECHNOLOGIE-IMPORT VON KABELVERLEGEMASCHINEN GmbH Method for securing in advance the roof when driving tunnels
JP2004060266A (en) * 2002-07-29 2004-02-26 Alpha Civil Engineering:Kk Non-open-cut construction method for underground structure
CN101131090A (en) * 2007-10-09 2008-02-27 中铁二局股份有限公司 Construction method for shallow soil-covered river bed under shield tunnel
CN102720508A (en) * 2012-04-28 2012-10-10 中铁二局股份有限公司 Shield construction method for continuously under-passing dense buildings in silty-soil and silty-sand formation
CN103527209A (en) * 2013-10-22 2014-01-22 北京交通大学 Micro disturbance tunneling method used for shield machine to tunnel under building on rich water weak formation
CN103603670A (en) * 2013-11-21 2014-02-26 上海市基础工程集团有限公司 Construction method of ultra-deep-earthed shield crossing complex formations
CN104989412A (en) * 2015-06-11 2015-10-21 北京市市政四建设工程有限责任公司 Earth pressure balance type shield long-distance lake-crossing construction technology
CN105804761A (en) * 2016-03-14 2016-07-27 上海隧道工程有限公司 Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109060395A (en) * 2018-08-27 2018-12-21 郑州大学 The pilot system platform of excision composite foundation pile body is worn under a kind of shield
CN109060395B (en) * 2018-08-27 2023-12-05 郑州大学 Test system platform for shield underpass cutting composite foundation pile body
CN109869158A (en) * 2019-03-20 2019-06-11 南通勘察设计有限公司 Subway shield tunnel construction technique in a kind of sand
CN109869158B (en) * 2019-03-20 2020-10-30 南通勘察设计有限公司 Construction process for subway shield in sandy soil
CN110374617A (en) * 2019-08-08 2019-10-25 中国建筑第四工程局有限公司 A kind of Shield Method Tunnel for Metro Tunnel Passing construction prestressed cable method
CN110685704A (en) * 2019-10-15 2020-01-14 中铁十二局集团有限公司 Construction method for water bag pebble mixed soil layer earth pressure shield to pass through river channel
CN110685704B (en) * 2019-10-15 2021-08-10 中铁十二局集团有限公司 Construction method for water bag pebble mixed soil layer earth pressure shield to pass through river channel
CN112682052A (en) * 2019-10-18 2021-04-20 中铁第六勘察设计院集团有限公司 Construction method for underpinning pile foundation in shield tunnel
CN112922616A (en) * 2019-12-05 2021-06-08 宏润建设集团股份有限公司 Method for controlling shield crossing construction
CN110985021A (en) * 2019-12-12 2020-04-10 中铁十二局集团第二工程有限公司 Long-distance river-crossing construction method for earth pressure balance shield
CN110985021B (en) * 2019-12-12 2022-02-15 中铁十二局集团第二工程有限公司 Long-distance river-crossing construction method for earth pressure balance shield
CN112031789A (en) * 2020-09-10 2020-12-04 宁波朗达工程科技有限公司 Shield method for preventing water-rich layered soft soil duct piece from squeezing crack and sinking to ground
CN112160758A (en) * 2020-10-19 2021-01-01 中建八局轨道交通建设有限公司 Construction method for slurry shield to penetrate through river dike
CN112365785A (en) * 2020-10-20 2021-02-12 山东大学 Servo type composite earth pressure balance micro shield device and working method
CN112523767A (en) * 2020-11-24 2021-03-19 中铁隧道局集团有限公司 Construction method for shield pile grinding of expansion soil layer
CN112647963A (en) * 2020-12-21 2021-04-13 上海隧道工程有限公司 Construction method for shield to obliquely penetrate existing ground wall
CN114370285A (en) * 2021-12-27 2022-04-19 上海市基础工程集团有限公司 Method for judging cutting pile foundation of shield machine in soft soil stratum

Also Published As

Publication number Publication date
CN108049878B (en) 2019-06-25

Similar Documents

Publication Publication Date Title
CN108049878B (en) A kind of powder land floor shield cuts the construction method that stake is crossed the river
Lin et al. Key techniques and important issues for slurry shield under-passing embankments: A case study of Hangzhou Qiantang River Tunnel
Zhao et al. Tunnelling through a frequently changing and mixed ground: a case history in Singapore
Barla et al. TBM tunnelling in difficult ground conditions
CN105240019A (en) Pipe jacking construction method
CN104343455A (en) Long-distance curved jacking pipe and pipe roof construction technique
Zhang et al. Challenges of earth pressure balance tunnelling in weathered granite with boulders
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
Sze et al. Tunnelling undercrossing existing live MRT tunnels
Luo et al. Evaluating construction risks of modified shield machine applicable to soft soils based on fuzzy comprehensive evaluation method
CN104389613B (en) Slurry balance shield passes through the construction method of jeopardously underground pipelines
CN104653186A (en) Method of earth pressure balance shield crossing reinforced concrete pile foundation building
CN205618170U (en) Protective structure of no template punishment rock mass cavity in tunnel engineering
Wei et al. Deformation characteristics of existing twin tunnels induced by double shield undercrossing with prereinforcement: A case study in Hangzhou
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
Jonker et al. Experiences with the application of innovative shield tunnelling techniques during the construction of the Betuweroute
Chen et al. Cutting, Wear and replacement of cutting tools during shield tunneling
Carlsson et al. Construction experiences from underground works at Forsmark. Compilation report
Zhao et al. Shield Treatment Technology for Large-Size Pebble Stratum
Shirlaw et al. The risk of very large settlements due to EPB tunnelling
Chen et al. Construction Technology of Shield Tunnel Crossing the Middle Channel Section of Yangtze River
Sun et al. Shield Treatment Technology in Extremely Soft Stratum
Wang et al. Shield Tunneling Treatment Technology in Boulder Stratum
Chen et al. Risks of TBM construction and corresponding measures
CN114718585A (en) Shield construction method suitable for passing tidal lake downwards

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20180518

Assignee: HONGRUN CONSTRUCTION GROUP Co.,Ltd.

Assignor: Hong Fu Jin Precision Industry (ShenZhen) Co.,Ltd.

Contract record no.: X2020330000013

Denomination of invention: Construction method of shield pile-cutting river-crossing of silt stratum

Granted publication date: 20190625

License type: Common License

Record date: 20200408

Application publication date: 20180518

Assignee: CHINA RAILWAY TENTH GROUP Co.,Ltd.

Assignor: Hong Fu Jin Precision Industry (ShenZhen) Co.,Ltd.

Contract record no.: X2020330000012

Denomination of invention: Construction method of shield pile-cutting river-crossing of silt stratum

Granted publication date: 20190625

License type: Common License

Record date: 20200408