CN108019228A - A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method - Google Patents

A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method Download PDF

Info

Publication number
CN108019228A
CN108019228A CN201810042515.6A CN201810042515A CN108019228A CN 108019228 A CN108019228 A CN 108019228A CN 201810042515 A CN201810042515 A CN 201810042515A CN 108019228 A CN108019228 A CN 108019228A
Authority
CN
China
Prior art keywords
antiarch
flexibility
cushion cap
allows
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810042515.6A
Other languages
Chinese (zh)
Inventor
黄金坤
王圣萍
庞建勇
刘光程
何壮志
莫奕新
严旺
庞虹宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Science and Technology
Original Assignee
Anhui University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Science and Technology filed Critical Anhui University of Science and Technology
Priority to CN201810042515.6A priority Critical patent/CN108019228A/en
Publication of CN108019228A publication Critical patent/CN108019228A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • E21D11/22Clamps or other yieldable means for interconnecting adjacent arch members either rigidly, or allowing arch member parts to slide when subjected to excessive pressure
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Abstract

The present invention provides the combined retaining structure and its construction method for the improvement floor lift in gallery that a kind of flexibility allows pressure, it is characterised in that it includes flexibility allows fill concrete between pressure device, bar frame antiarch device, frame, floor grouting anchor pole, FLOOR ANCHOR and bottom plate to excavate six, position part;Bottom plate has been excavated according to construction method and has excavated position, excavates out the cushion cap and antiarch groove on bottom plate respectively;Pressure device is allowed to be placed on cushion cap flexibility, bar frame antiarch device is placed in the antiarch groove that has excavated and both ends and is welded in the flexible lateral wall for allowing pressure device, is subsequently filled fill concrete between frame so that it is concordant with back-plane design face absolute altitude and be integrally incorporated in bar frame antiarch device interior;Allowed in flexibility on pressure device and equidistantly set up floor grouting anchor pole and grouting and reinforcing along its radial direction, allowed the outside plate of pressure device to arrange FLOOR ANCHOR also cross the flexibility at both ends, complete the installation of overall combined retaining structure.

Description

A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method
Technical field
The present invention relates to Roadway Support Technology field, the joint of the improvement floor lift in gallery of pressure is allowed more particularly to a kind of flexibility Supporting construction and its construction method.
Background technology
With the increase of coal mining depth, the geological conditions residing for coal mine roadway also becomes increasingly complex, especially soft Under the conditions of rock, its supporting difficulty bigger.And soft rock has classification, swelling soft-rock is exactly one of representative, and dilatancy Soft-rock tunnel is than other kinds of Deformation in Soft Rock Tunnel more it is apparent that bottom distension is larger.Local Weak support theoretical research shows bottom Distension phenomenon is to induce the principal element of roadway damage, therefore it is particularly important that improvement bottom distension phenomenon.
But in existing bottom distension resolution, bottom plate anchor pole, FLOOR ANCHOR are usually set, open up gas pressure relief slot, slip casting Reinforce, the methods of underplate concrete antiarch, arrangement metal truss and shape steel bracket is set.But in soft-rock tunnel smashed to pieces In, since crustal stress is larger, the above-mentioned method for protecting support of single use is ineffective, even if wherein certain several scheme effect are applied in combination Fruit appoint it is so not good enough, therefore propose a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method, realize Multiple scheme is applied in combination, and supporting construction is simple, easy for construction, significant effect.
The content of the invention
For the deficiency of existing method, the combined supporting knot of the improvement floor lift in gallery of pressure is allowed the present invention provides a kind of flexibility Structure and its construction method, the scheme provided is simple and feasible, can effectively administer the bottom distension phenomenon in swelling soft-rock tunnel, protects Hinder the safe handling in tunnel.
To achieve the above object, the present invention is achieved by the following technical programs:
A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method, it is characterised in that including Bar frame antiarch device, flexibility allow fill concrete between pressure device, frame, bottom plate to excavate position, FLOOR ANCHOR and bottom plate note Starch six parts of anchor pole;Excavate the three row cushion cap and two row on the bottom plate excavation position in advance along tunnel direction of advance The antiarch groove, the three row cushion caps are equally spaced along span length direction, and end two arranges the cushion cap and abuts tunnel two Side of side bottom, the two row antiarch grooves are arranged between the three row cushion cap;Pressure device is allowed to be placed on the cushion cap flexibility, The bar frame antiarch device is placed in the antiarch groove that has excavated and both ends are connected to the flexibility and allow pressure device Lateral wall, be subsequently filled fill concrete between the frame and cause it concordant with back-plane design face absolute altitude and by the bar frame In antiarch device is integrally incorporated in;Allowed in the flexibility and equidistantly set up the good floor grouting anchor on pressure device along its radial direction Bar and grouting and reinforcing, arrange the FLOOR ANCHOR also cross the flexible outside plate for allowing pressure device described in both ends, complete overall The installation of combined retaining structure.
Further, the bar frame antiarch device, including minor arc muscle, secondary arc muscle, dowel, crane span structure muscle and longitudinal direction Muscle;The rack main element of the bar frame antiarch device is made of the dowel, the crane span structure muscle and the longitudinal rib; The longitudinal rib is equidistantly divided at 4 points, and the dowel has four and its distal point is respectively welded at the longitudinal rib left end Point, a quarter point, at 3/4ths points and right endpoint, the head-end of two dowels of left end is connected, two institutes of right end The head-end for stating dowel is connected so that the dowel and the longitudinal rib are in approximately the same plane;The crane span structure muscle is arc, The left end point of the crane span structure muscle is welded in the end attachment of two dowels of left end, right endpoint is welded in right end two The end attachment of the dowel, arc midpoint are connected to the half point of the longitudinal rib, it is formed the reinforcing bar The main element of rack antiarch device;The minor arc muscle and the secondary arc muscle middle part for arc and with the antiarch groove radian It coincide, end is straight to take the side for being placed on the cushion cap;The minor arc muscle has three, respectively from the longitudinal rib left end point, two / a little and at right endpoint pass through, the secondary arc muscle has two, is brought out into the open respectively from the dowel connecting pin at left and right end Cross;By the rack main element direction that the dowel, the crane span structure muscle and the longitudinal rib are formed and the minor arc muscle and institute It is vertical and anti-along the radian of the minor arc muscle and secondary arc muscle arrangement, the whole bar frame of composition to state time arc muscle direction Encircle device.
Further, the flexibility allows pressure device, including channel steel, small sleeve, big sleeve, reinforcement spring and rubber block;Institute Stating channel steel has two pieces and groove are opposite to be placed in parallel, along tunnel direction of advance arrangement in column;Described small sleeve one end is welded in The channel steel groove inner wall of side, the other end are inserted in one end of the big sleeve and under pressure can be along described big The inner wall of sleeve slides, and the other end of the big sleeve is welded in the channel steel groove inner wall of opposite side, while described small The outer ring of sleeve and the big sleeve has surround a circle reinforcement spring and the reinforcement spring both ends are also welded in both sides The channel steel groove inner wall is to prevent the small sleeve and the big sleeve laterally twists off or out of plumb when the small sleeve is pressurized Slided along the inner wall of the big sleeve;The above-mentioned big sleeve assembled, the small sleeve and the reinforcement spring device Constituting the flexibility allows the main body of pressure device to allow splenium part, and main body makes splenium part equidistant along the direction of advance of the channel steel Arrangement;The rubber block is finally filled into vacancy between the channel steel, the whole flexibility is formed and allows pressure device.
Further, the bottom plate excavates position, including cushion cap and antiarch groove;Side bottom of the cushion cap along roadway's sides Position starts to excavate, and three row are equally spaced along span length, and end two is arranged during the cushion cap abuts and be slightly less than with side bottom Between position the cushion cap;The antiarch groove is arranged between the three row cushion cap, and the radian of antiarch is according to tunnel geological conditions Determine.
Further, the present invention also provides a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction Method, including following construction method:
A. according to the design drawing of drift section, drift section is excavated out, excavates out the bottom successively at bottom plate position Plate excavates the cushion cap at position and the antiarch groove;The cushion cap at the roadway's sides and contacts baseplate excavate, along Span length equidistantly distributed and excavate three groups altogether, cushion cap width described in two groups of end is slightly less than one group middle described hold Platform, the cushion cap allow pressure device to place the flexibility;Then antiarch groove described in two groups is excavated between the cushion cap, it is described Antiarch groove radian is depending on the concrete condition of tunnel, to place the antiarch part of the bar frame antiarch device;
B. after the completion of the bottom plate excavates the cushion cap at position and the antiarch groove excavates, the flexibility is allowed into press fitting Storing is placed on the cushion cap;The flexibility on the cushion cap of both sides allows pressure device to be close to roadway's sides side wall and places, institute One section of the opposite side indwelling of cushion cap is stated to place the straight position in end of the bar frame antiarch device;Held described in middle The flexibility on platform allows pressure device to be positioned over the middle part of the cushion cap, and one section of both sides indwelling is placing the bar-mat reinforcement The straight position in end of frame antiarch device;
C. the flexibility allows pressure device to be divided into two parts processing, is positioned over the flexibility described in both sides on cushion cap and allows press fitting The web of the channel steel in the outside put reserves the FLOOR ANCHOR and passes through hole and helping bottom corresponding position by the base angle The hole of anchor pole is drilled with place, and the flexibility being positioned on the middle cushion cap allows pressure device to be not required to reserving hole;Along lane The flexibility of road direction of advance arrangement allows what the big sleeve, the small sleeve and the reinforcement spring of pressure device formed to allow Between pressure system, reserve the hole of the floor grouting anchor pole according to design and be drilled with place on the cushion cap in advance;Remaining The filling upper rubber block in position ensures that the flexibility allows the flexibility of pressure device;
D. the FLOOR ANCHOR and the floor grouting rockbolt installation into respective reserving hole position and are anchored, at the same time Grouting and reinforcing is carried out to the floor grouting anchor pole;The FLOOR ANCHOR and the floor grouting rockbolt installation are in same section On, and the flexibility allows the big sleeve of pressure device, the small sleeve and the reinforcement spring form allows pressure system and institute The FLOOR ANCHOR and the floor grouting anchor pole are stated along tunnel direction of advance arranged crosswise, forms plum blossom-shaped arrangement shape;
E. after the completion of above-mentioned steps A~D, the bar frame antiarch device is installed;By the bar frame antiarch device Antiarch position be positioned in the antiarch groove, the radian at antiarch position coincide with the antiarch groove radian, the bar frame The sidepiece that the end flat part bit parallel overlap joint of antiarch device is positioned over the cushion cap reserves section and with being placed on the cushion cap The flexibility allows the sidewall weld of pressure device;Taken in the end flat part bit parallel of the bar frame antiarch device welding position Connect the sidepiece for being positioned over the cushion cap and the flexibility with being placed on the cushion cap allows the big sleeve, described small of pressure device The lateral wall for pressure system that what sleeve and the reinforcement spring were formed allow, realizes and effectively allows pressure;
F. after all components are installed in place, fill concrete between the frame is filled in the antiarch groove so that the frame Between fill concrete the gap on the bar frame antiarch device periphery is filled full, while cause concreting to reach tunnel The designed elevation of bottom plate section, allows pressure device to handle, can brush Huang if necessary without to the flexibility on the cushion cap Oil is to prevent from corroding;
Compared with prior art, the technique effect that possesses of the present invention is:
A kind of above-mentioned flexibility allows the combined retaining structure for administering floor lift in gallery of pressure and its construction method administering expansion Property Soft Rock Roadway Floor Heave when, the problem of breaking surrounding rock of roadway floor is jacked up by the extruding force at both ends can be efficiently solved, led to Cross it is flexible allow pressure allow press manage and frame between armored concrete antiarch effect so that roadway floor be in stable state, change Shape is small, greatly improves work efficiency, and reduces repair of laneway rate.
Brief description of the drawings
Fig. 1 be a kind of flexibility allow pressure improvement floor lift in gallery the total schematic diagram of combined retaining structure;
Fig. 2 be a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure schematic front view;
Fig. 3 be a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure schematic top plan view;
Fig. 4 be a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure bar frame antiarch schematic diagram;
Fig. 5 is that a kind of flexibility allows the combined retaining structure flexibility of the improvement floor lift in gallery of pressure to allow pressure device schematic diagram;
Fig. 6 is that a kind of flexibility allows the combined retaining structure bottom plate of the improvement floor lift in gallery of pressure to excavate position front view;
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, the technical solution in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is Part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art All other embodiments obtained without creative efforts, belong to the scope of protection of the invention.
With reference to Fig. 1 to Fig. 6, the present invention provides a kind of flexibility allow the improvement floor lift in gallery of pressure combined retaining structure and its Construction method, it is characterised in that allow fill concrete 3, bottom plate between pressure device 2, frame including bar frame antiarch device 1, flexibility Excavate 6 six position 4, FLOOR ANCHOR 5 and floor grouting anchor pole parts;The bottom plate is excavated in advance along tunnel direction of advance The three row cushion caps 41 and two excavated on position 4 arrange the antiarch groove 42, and three arrange the cushion caps 41 along span length direction It is equally spaced, end two arranges the cushion cap 41 and is arranged in against roadway's sides side bottom, the two row antiarch grooves 42 described in three row Between cushion cap 41;Pressure device 2 is allowed to be placed on the cushion cap 41 flexibility, the bar frame antiarch device 1 is placed in out In the antiarch groove 42 that has dug and both ends are connected to the flexibility and allow the lateral wall of pressure device 2, are subsequently filled between the frame Fill concrete 3 causes it concordant with back-plane design face absolute altitude and is integrally incorporated in the bar frame antiarch device 1 interior; The flexibility allows equidistantly sets up the good floor grouting anchor pole 6 and grouting and reinforcing on pressure device 1 along its radial direction, also cross The flexible outside plate for allowing pressure device 2 arranges the FLOOR ANCHOR 5 described in both ends, completes the installation of overall combined retaining structure.
Further, the bar frame antiarch device 1, including minor arc muscle 11, secondary arc muscle 12, dowel 13, crane span structure muscle 14 and longitudinal rib 15;The rack main element of the bar frame antiarch device 1 is by the dowel 13,14 and of crane span structure muscle The longitudinal rib 15 forms;The longitudinal rib 15 is equidistantly divided at 4 points, and the dowel 13 has four and its distal point is distinguished It is welded on 15 left end point of longitudinal rib, a quarter point, at 3/4ths points and right endpoint, the dowel 13 of left end two Head-end be connected, the head-end of the dowel 13 of right end two is connected so that the dowel 13 and the longitudinal rib 15 In approximately the same plane;The crane span structure muscle 14 is arc, and the left end point of the crane span structure muscle 14 is welded in two connections of left end The end attachment of muscle 13, right endpoint are welded in the end attachment of the dowel 13 of right end two, and arc midpoint is connected to The half point of the longitudinal rib 15, makes it form the main element of the bar frame antiarch device 1;The minor arc muscle 11 With secondary 12 middle part of arc muscle arc and to coincide with 42 radian of antiarch groove, end is straight to take and is placed on the cushion cap 41 Side;The minor arc muscle 11 has three, is passed through respectively at 15 left end point of longitudinal rib, half point and right endpoint, The secondary arc muscle 12 has two, is passed through respectively from 13 connection end point of the dowel at left and right end;By the dowel 13, institute State rack main element direction and the minor arc muscle 11 and secondary 12 side of arc muscle that crane span structure muscle 14 and the longitudinal rib 15 are formed To vertically and along the radian of the minor arc muscle 11 and the secondary arc muscle 12 arranging, the whole bar frame antiarch device is formed 1。
Further, the flexibility allows pressure device 2, including channel steel 21, small sleeve 22, big sleeve 23,24 and of reinforcement spring Rubber block 25;The channel steel 21 has two pieces and groove is placed in parallel relatively, along tunnel direction of advance arrangement in column;The small set 22 one end of cylinder are welded in 21 groove inner wall of the channel steel of side, and the other end is inserted in one end of the big sleeve 23 and makees in pressure It can be slided with lower along the inner wall of the big sleeve 23, the other end of the big sleeve 23 is welded in the channel steel of opposite side 21 groove inner walls, while the circle reinforcement spring 24 and institute have been surround in the outer ring of the small sleeve 22 and the big sleeve 23 State 24 both ends of reinforcement spring and be also welded in 21 groove inner walls of the channel steel of both sides to prevent the small sleeve 22 and the big set Out of plumb is slided along the inner wall of the big sleeve 23 when cylinder 23 laterally twists off or the small sleeve 22 is pressurized;It is above-mentioned to assemble The big sleeve 23, the small sleeve 22 and 24 device of the reinforcement spring, which constitute the flexibility, allows the main body of pressure device 2 to allow Splenium part, main body allow splenium part to be equally spaced along the direction of advance of the channel steel 21;Finally the rubber block 25 is filled Vacancy between the channel steel 21, forms the whole flexibility and allows pressure device 2.
Further, the bottom plate excavates position 4, including cushion cap 41 and antiarch groove 42;The cushion cap 41 is along tunnel two The side bottom position of side starts to excavate, and is equally spaced three row along span length, end two arranges the cushion cap 41 with helping bottom to abut And it is slightly less than the cushion cap 41 of middle part;The antiarch groove 42 is arranged between the three row cushion cap 41, the radian of antiarch Determined according to tunnel geological conditions.
Further, the present invention also provides a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction Method, including following construction method:
A. according to the design drawing of drift section, drift section is excavated out, excavates out the bottom successively at bottom plate position Plate excavates the cushion cap 41 at position 4 and the antiarch groove 42;The cushion cap 41 at the roadway's sides and contacts baseplate open Dig, excavate along span length equidistantly distributed and altogether three groups, 41 width of cushion cap described in two groups of end is slightly less than one group middle The cushion cap 41, the cushion cap 41 allows pressure device 2 to place the flexibility;Then two groups are excavated between the cushion cap 41 The antiarch groove 42,41 radian of antiarch groove is depending on the concrete condition of tunnel, to place the bar frame antiarch device 1 Antiarch part;
B. after the completion of the bottom plate excavates the cushion cap 41 at position 4 and the antiarch groove 42 excavates, by the flexibility Pressure device 2 is allowed to be positioned on the cushion cap 41;The flexibility on the cushion cap 41 of both sides allows pressure device 2 to be close to roadway's sides Wall is helped to place, one section of the opposite side indwelling of the cushion cap 41 is placing the end flat part of the bar frame antiarch device 1 Position;The flexibility on the middle cushion cap 41 allows pressure device 2 to be positioned over the middle part of the cushion cap 41, both sides indwelling one Section is placing the straight position in end of the bar frame antiarch device 1;
C. the flexibility allows pressure device 2 to be divided into two parts processing, is positioned over the flexibility described in both sides on cushion cap 41 and allows The web of the channel steel 21 in the outside of pressure device 2 reserves the FLOOR ANCHOR 5 and passes through hole and incited somebody to action in side bottom corresponding position The hole of the FLOOR ANCHOR 6 is drilled with place, and the flexibility being positioned on the middle cushion cap 41 allows pressure device 2 to be not required to reserve Hole;The flexibility arranged along tunnel direction of advance allows the big sleeve 23 of pressure device 2, the small sleeve 22 and described What reinforcement spring 24 was formed allows between pressure system, and the hole of the floor grouting anchor pole 5 is reserved and in advance described according to design It is drilled with cushion cap 41 in place;Remaining position upper rubber block 25 of filling ensures that the flexibility allows the flexibility of pressure device 2;
D. the FLOOR ANCHOR 6 and the floor grouting anchor pole 5 are installed into respective reserving hole position and anchored, together When to the floor grouting anchor pole 5 carry out grouting and reinforcing;The FLOOR ANCHOR 6 and the floor grouting anchor pole 5 are installed on same On a section, and the flexibility allows what the big sleeve 23, the small sleeve 22 and the reinforcement spring 24 of pressure device 2 were formed Pressure system is allowed, along tunnel direction of advance arranged crosswise, to form plum with the FLOOR ANCHOR 6 and the floor grouting anchor pole 5 Flower-shaped arrangement shape;
E. after the completion of above-mentioned steps A~D, the bar frame antiarch device 1 is installed;By the bar frame antiarch device 1 antiarch position is positioned in the antiarch groove 42, and the radian at antiarch position coincide with 42 radian of antiarch groove, the reinforcing bar The sidepiece that the end flat part bit parallel overlap joint of rack antiarch device 1 is positioned over the cushion cap 41 reserves section and with being placed in described hold The flexibility on platform 41 allows the sidewall weld of pressure device 2;Welding position is straight in the end of the bar frame antiarch device 1 Position is parallel to overlap the sidepiece for being positioned over the cushion cap 41 and the flexibility with being placed on the cushion cap 41 allows the institute of pressure device 2 State big sleeve 23, the small sleeve 22 and the reinforcement spring 24 are formed allows the lateral wall of pressure system, realize and effectively allow pressure;
F. after all components are installed in place, the fill concrete 3 between the filling frame in the antiarch groove 42 so that described Fill concrete 3 fills the gap on 1 periphery of bar frame antiarch device full between frame, while concreting is reached The designed elevation of roadway floor section, allows pressure device 2 to handle, if necessary may be used without to the flexibility on the cushion cap 41 Butter is brushed to prevent from corroding.
It should be noted that herein, term " comprising ", "comprising" or its any other variant are intended to non-row His property includes, so that process, method, article or equipment including a series of elements not only include those key elements, and And other elements that are not explicitly listed are further included, or further include as this process, method, article or equipment institute inherently Key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that including institute State in process, method, article or the equipment of key element that also there are other identical element.
The above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although with reference to the foregoing embodiments The present invention is described in detail, it will be understood by those of ordinary skill in the art that:It still can be to foregoing each implementation Technical solution described in example is modified, or carries out equivalent substitution to which part technical characteristic;And these modification or Replace, the essence of appropriate technical solution is departed from the spirit and scope of various embodiments of the present invention technical solution.

Claims (5)

1. a kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method, it is characterised in that including steel Muscle rack antiarch device 1, flexibility allow fill concrete 3 between pressure device 2, frame, bottom plate to excavate position 4, FLOOR ANCHOR 5 and bottom plate 6 six parts of grouted anchor bar;Excavate the three row cushion caps 41 on the bottom plate excavation position 4 in advance along tunnel direction of advance With the two row antiarch grooves 42, the three row cushion caps 41 are equally spaced along span length direction, and end two arranges the cushion cap 41 are arranged between the three row cushion cap 41 against roadway's sides side bottom, the two row antiarch grooves 42;The flexibility is allowed into press fitting Put 2 to be placed on the cushion cap 41, the bar frame antiarch device 1 is placed in the antiarch groove 42 excavated and both ends It is connected to the flexibility and allows the lateral wall of pressure device 2, fill concrete 3 is so that itself and back-plane design face between being subsequently filled the frame Absolute altitude is concordant and is integrally incorporated in the bar frame antiarch device 1 interior;Allowed in the flexibility on pressure device 1 along its radial direction The good floor grouting anchor pole 6 and grouting and reinforcing are equidistantly set up, also cross the flexible outside steel for allowing pressure device 2 described in both ends Plate arranges the FLOOR ANCHOR 5, completes the installation of overall combined retaining structure.
2. a kind of flexibility as claimed in claim 1 allows the combined retaining structure and its construction method of the improvement floor lift in gallery of pressure, It is characterized in that, the bar frame antiarch device 1, including minor arc muscle 11, secondary arc muscle 12, dowel 13, crane span structure muscle 14 and vertical To muscle 15;The rack main element of the bar frame antiarch device 1 is by the dowel 13, the crane span structure muscle 14 and described vertical Formed to muscle 15;The longitudinal rib 15 is equidistantly divided at 4 points, and the dowel 13 has four and its distal point is respectively welded at 15 left end point of longitudinal rib, a quarter point, at 3/4ths points and right endpoint, the head end of the dowel 13 of left end two Point is connected, and the head-end of the dowel 13 of right end two is connected so that the dowel 13 and the longitudinal rib 15 are same A plane;The crane span structure muscle 14 is arc, and the left end point of the crane span structure muscle 14 is welded in the dowel 13 of left end two End attachment, right endpoint are welded in the end attachment of the dowel 13 of right end two, and arc midpoint is connected to described vertical To the half point of muscle 15, it is set to form the main element of the bar frame antiarch device 1;The minor arc muscle 11 and described Secondary 12 middle part of arc muscle coincide for arc and with 42 radian of antiarch groove, and end is straight to take the side for being placed on the cushion cap 41 Side;The minor arc muscle 11 has three, is passed through respectively at 15 left end point of longitudinal rib, half point and right endpoint, described Secondary arc muscle 12 has two, is passed through respectively from 13 connection end point of the dowel at left and right end;By the dowel 13, the bridge Hang down with the minor arc muscle 11 and secondary 12 direction of arc muscle in the rack main element direction that frame muscle 14 and the longitudinal rib 15 are formed Directly and along the radian of the minor arc muscle 11 and the secondary arc muscle 12 arrange, form the whole bar frame antiarch device 1.
3. a kind of flexibility as claimed in claim 1 allows the combined retaining structure and its construction method of the improvement floor lift in gallery of pressure, It is characterized in that, the flexibility allows pressure device 2, including channel steel 21, small sleeve 22, big sleeve 23, reinforcement spring 24 and rubber block 25;The channel steel 21 has two pieces and groove is placed in parallel relatively, along tunnel direction of advance arrangement in column;The small sleeve 22 1 End is welded in 21 groove inner wall of the channel steel of side, and the other end is inserted in one end of the big sleeve 23 and under pressure may be used To be slided along the inner wall of the big sleeve 23, the other end of the big sleeve 23 is welded in 21 groove of the channel steel of opposite side Inner wall, while a circle reinforcement spring 24 and the reinforcement have been surround in the outer ring of the small sleeve 22 and the big sleeve 23 24 both ends of spring are also welded in 21 groove inner walls of the channel steel of both sides to prevent the small sleeve 22 and 23 side of big sleeve Slided to out of plumb when twisting off or the small sleeve 22 is pressurized along the inner wall of the big sleeve 23;It is above-mentioned assemble it is described big Sleeve 23, the small sleeve 22 and 24 device of the reinforcement spring, which constitute the flexibility, allows the main body of pressure device 2 to allow splenium part, Main body allows splenium part to be equally spaced along the direction of advance of the channel steel 21;The rubber block 25 is finally filled into the groove Vacancy between steel 21, forms the whole flexibility and allows pressure device 2.
4. a kind of flexibility as claimed in claim 1 allows the combined retaining structure and its construction method of the improvement floor lift in gallery of pressure, It is characterized in that, the bottom plate excavates position 4, including cushion cap 41 and antiarch groove 42;Side of the cushion cap 41 along roadway's sides Bottom position starts to excavate, and three row are equally spaced along span length, and end two arranges the cushion cap 41 and abutted with side bottom and smaller The cushion cap 41 in middle part;The antiarch groove 42 is arranged between the three row cushion cap 41, and the radian of antiarch is according to lane Road geology conditional decision.
5. a kind of flexibility as described in Claims 1 to 4 allow pressure improvement floor lift in gallery combined retaining structure and its construction party Method, it is characterised in that including following construction method:
A. according to the design drawing of drift section, drift section is excavated out, the bottom plate is excavated out successively at bottom plate position and opens Dig the cushion cap 41 at position 4 and the antiarch groove 42;The cushion cap 41 at the roadway's sides and contacts baseplate excavate, edge Span length equidistantly distributed and excavate three groups altogether, 41 width of cushion cap described in two groups of end is slightly less than the described of one group of centre Cushion cap 41, the cushion cap 41 allow pressure device 2 to place the flexibility;Then excavated between the cushion cap 41 anti-described in two groups Encircle groove 42,41 radian of antiarch groove is depending on the concrete condition of tunnel, to place the antiarch of the bar frame antiarch device 1 Part;
B. after the completion of the bottom plate excavates the cushion cap 41 at position 4 and the antiarch groove 42 excavates, the flexibility is allowed into pressure Device 2 is positioned on the cushion cap 41;The flexibility on the cushion cap 41 of both sides allows pressure device 2 to be close to roadway's sides side wall Place, one section of the opposite side indwelling of the cushion cap 41 is placing the straight position in end of the bar frame antiarch device 1;In Between the cushion cap 41 on the flexibility allow pressure device 2 to be positioned over the middle part of the cushion cap 41, one section of both sides indwelling with To place the straight position in end of the bar frame antiarch device 1;
C. the flexibility allows pressure device 2 to be divided into two parts processing, is positioned over the flexibility described in both sides on cushion cap 41 and allows press fitting Put the channel steel 21 in 2 outside web reserve the FLOOR ANCHOR 5 pass through hole and side bottom corresponding position will described in The hole of FLOOR ANCHOR 6 is drilled with place, and the flexibility being positioned on the middle cushion cap 41 allows pressure device 2 to be not required to preformed hole Hole;The flexibility arranged along tunnel direction of advance allow the big sleeve 23 of pressure device 2, the small sleeve 22 and it is described plus What strong spring 24 was formed allows between pressure system, reserves the hole of the floor grouting anchor pole 5 according to design and is held in advance described It is drilled with platform 41 in place;Remaining position upper rubber block 25 of filling ensures that the flexibility allows the flexibility of pressure device 2;
D. the FLOOR ANCHOR 6 and the floor grouting anchor pole 5 are installed into respective reserving hole position and anchored, at the same it is right The floor grouting anchor pole 5 carries out grouting and reinforcing;The FLOOR ANCHOR 6 and the floor grouting anchor pole 5 are installed on same disconnected On face, and the flexibility allows the pressure that allows that the big sleeve 23 of pressure device 2, the small sleeve 22 and the reinforcement spring 24 form System, along tunnel direction of advance arranged crosswise, forms plum blossom-shaped with the FLOOR ANCHOR 6 and the floor grouting anchor pole 5 Arrange shape;
E. after the completion of above-mentioned steps A~D, the bar frame antiarch device 1 is installed;By the bar frame antiarch device 1 Antiarch position is positioned in the antiarch groove 42, and the radian at antiarch position coincide with 42 radian of antiarch groove, the bar-mat reinforcement The sidepiece that the end flat part bit parallel overlap joint of frame antiarch device 1 is positioned over the cushion cap 41 reserves section and with being placed in the cushion cap The flexibility on 41 allows the sidewall weld of pressure device 2;End flat part of the welding position in the bar frame antiarch device 1 Bit parallel overlap joint is positioned over the sidepiece of the cushion cap 41 and the flexibility with being placed on the cushion cap 41 allows described in pressure device 2 The lateral wall for pressure system that what big sleeve 23, the small sleeve 22 and the reinforcement spring 24 were formed allow, realizes and effectively allows pressure;
F. after all components are installed in place, the fill concrete 3 between the filling frame in the antiarch groove 42 so that between the frame Fill concrete 3 fills in the gap on 1 periphery of bar frame antiarch device completely, while causes concreting to reach tunnel The designed elevation of bottom plate section, allows pressure device 2 to handle, can brush if necessary without to the flexibility on the cushion cap 41 Butter is to prevent from corroding.
CN201810042515.6A 2018-01-17 2018-01-17 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method Withdrawn CN108019228A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810042515.6A CN108019228A (en) 2018-01-17 2018-01-17 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810042515.6A CN108019228A (en) 2018-01-17 2018-01-17 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method

Publications (1)

Publication Number Publication Date
CN108019228A true CN108019228A (en) 2018-05-11

Family

ID=62072663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810042515.6A Withdrawn CN108019228A (en) 2018-01-17 2018-01-17 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method

Country Status (1)

Country Link
CN (1) CN108019228A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109681237A (en) * 2018-12-20 2019-04-26 上海应用技术大学 A kind of supporting construction and construction method of Soft Rock Roadway Floor Heave
CN114151108A (en) * 2021-11-18 2022-03-08 山东济矿鲁能煤电股份有限公司阳城煤矿 Support method for soft rock chamber bottom heave treatment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0046818A1 (en) * 1980-09-02 1982-03-10 GTG Gesteins- und Tiefbau GmbH Sliding clamping assembly for mine roof support arches
CN103615273A (en) * 2013-12-04 2014-03-05 山东大学 Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN106223985A (en) * 2016-10-10 2016-12-14 安徽理工大学 The construction method of composite anchored net and this composite anchored net for administering distension at the bottom of deep-well high stress and soft rock mine roadway
CN106285724A (en) * 2016-10-14 2017-01-04 成都理工大学 A kind of tunnel is by pressure type support system
CN106437780A (en) * 2016-10-13 2017-02-22 安徽理工大学 Combined structure of reinforced concrete reverse arch and anchor rods and for managing roadway bottom swelling and construction method of combined structure
CN106968687A (en) * 2017-04-01 2017-07-21 湖南科技大学 The closed annulus yield supporting device of half-edge coal seam stope drift active workings and method for protecting support
CN207905829U (en) * 2018-01-17 2018-09-25 安徽理工大学 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0046818A1 (en) * 1980-09-02 1982-03-10 GTG Gesteins- und Tiefbau GmbH Sliding clamping assembly for mine roof support arches
CN103615273A (en) * 2013-12-04 2014-03-05 山东大学 Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN106223985A (en) * 2016-10-10 2016-12-14 安徽理工大学 The construction method of composite anchored net and this composite anchored net for administering distension at the bottom of deep-well high stress and soft rock mine roadway
CN106437780A (en) * 2016-10-13 2017-02-22 安徽理工大学 Combined structure of reinforced concrete reverse arch and anchor rods and for managing roadway bottom swelling and construction method of combined structure
CN106285724A (en) * 2016-10-14 2017-01-04 成都理工大学 A kind of tunnel is by pressure type support system
CN106968687A (en) * 2017-04-01 2017-07-21 湖南科技大学 The closed annulus yield supporting device of half-edge coal seam stope drift active workings and method for protecting support
CN207905829U (en) * 2018-01-17 2018-09-25 安徽理工大学 A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109681237A (en) * 2018-12-20 2019-04-26 上海应用技术大学 A kind of supporting construction and construction method of Soft Rock Roadway Floor Heave
CN114151108A (en) * 2021-11-18 2022-03-08 山东济矿鲁能煤电股份有限公司阳城煤矿 Support method for soft rock chamber bottom heave treatment
CN114151108B (en) * 2021-11-18 2024-03-22 山东济矿鲁能煤电股份有限公司阳城煤矿 Soft rock chamber bottom drum treatment supporting method

Similar Documents

Publication Publication Date Title
CN108894787B (en) Leave the pressure break release method of ore pillar stress concentration in Overburden gob area
CN203756182U (en) Support structure applied to shallow road tunnel in weak rock area
CN103174434B (en) Construction method of dissymmetric double-linking-arch tunnel structure
CN104265322B (en) Control method of asymmetric deformation of deep mine roadway surrounding rock
CN107605489A (en) Three line Large span tunnel inclined shafts enter positive cavity construction method
CN202543906U (en) Precast pile with reserved grouting pipes
CN204783044U (en) Coombe topography loose slope body bevel tunnel in mountain area advances supporting construction in hole
CN107120124A (en) A kind of method for protecting support for tunnel
CN111535817A (en) Working face double-lane tunneling small coal pillar reinforcement construction method
CN109184733B (en) Soft rock chamber bottom heave treatment supporting structure and method based on prefabricated bottom arc plate
CN104047613A (en) Method for anchoring coal mine tunnel bottom plate
CN105134269A (en) Control technology for roadway surrounding rock achieving cooperative load bearing by enabling anchor cables to penetrate through sheds
CN112282806B (en) Thick coal seam forced mining roadway blasting pressure relief and long anchor rod cooperative roof control method
CN104763442A (en) High-intensity large-shrinkage sealed cambered-plate support structural element
CN102605767A (en) Precast pile reserved with grouting pipe and piling process of precast pile
US3968655A (en) Method of reinforcing tunnels before excavation
CN108570983A (en) The pile base construction method and its casing of non-filler large size solution cavity
CN108019228A (en) A kind of flexibility allow pressure improvement floor lift in gallery combined retaining structure and its construction method
CN102518451B (en) Construction method of shotcrete support for water contained loess geological tunnel
CN105156114A (en) Enlarging repair and reinforcement method of roadways at crossing
CN104948207B (en) For improving the device of swell-shrink characteristic soil property large cross-section tunnel steel arch-shelf load-carrying properties
CN106968687A (en) The closed annulus yield supporting device of half-edge coal seam stope drift active workings and method for protecting support
CN109882225A (en) It is extending to repeat Grouting Pipe and the repeatable grouted anchor bar of double circles
CN212535724U (en) Anchor rod locking device convenient to install and fix
CN110985002B (en) Tunnel construction method for horizontal semi-soft semi-hard section stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180511