CN107991955A - Timing monitoring steel-making continuous casting wraps greatly the system and method for station information - Google Patents
Timing monitoring steel-making continuous casting wraps greatly the system and method for station information Download PDFInfo
- Publication number
- CN107991955A CN107991955A CN201711131780.3A CN201711131780A CN107991955A CN 107991955 A CN107991955 A CN 107991955A CN 201711131780 A CN201711131780 A CN 201711131780A CN 107991955 A CN107991955 A CN 107991955A
- Authority
- CN
- China
- Prior art keywords
- data
- module
- stage
- continuous casting
- appearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/048—Monitoring; Safety
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Automation & Control Theory (AREA)
- Continuous Casting (AREA)
Abstract
The present invention provides the system and method that a kind of timing monitoring steel-making continuous casting wraps greatly station information, system includes data acquisition module, data memory module, Back Administration Module, data analysis module, data generation module, appeared on the stage signal by Con casting ladle of the data collecting module collected from live industrial personal computer, be sent into data memory module storage;Using Back Administration Module periodically by data analysis module, call after station information carries out analysis judgement on the Con casting ladle in data analysis module, by data generation module formed with information, and record and display corresponding information.Operator's operation without client just can be promptly and accurately generation Con casting ladle appear on the stage useful data, improve data analysis capabilities and managerial ability that iron and steel enterprise's Con casting ladle is appeared on the stage, effectively solve the region limitation of station information on Con casting ladle, professional limitation, excavate the problems such as limitation, management limitation, it is stable and reliable in work, simple to operate.
Description
Technical field
The present invention relates to a kind of system and method, more particularly to timing monitoring steel-making continuous casting wrap greatly station information system and
Method, belongs to steel-making continuous casting equipment information management technical field.
Background technology
Continuous casting is a very noticeable technology of contemporary development of iron & steel industry, and continuous casting can not only simplify production work
Sequence, improves the recovery rate of metal, saves energy expenditure, improves working conditions, slab quality is good, and life easy to automate
Production and control, thus as the mainstream of present age steel-making, and most common steelmaking equipment is used at present.It is continuous casting refining that ladle, which is appeared on the stage,
The important component of steel technique, station information mainly has scene viewing, middle control data, the Intranet of continuous casting Central Control Room on ladle at present
Monitor video etc., there are following problem for these information:(1)Region limitation:In Central Control Room or there can only be continuous casting to regard
There is information on the ground of frequency monitoring just now.(2)Professional limitation:It should be understood that the relevant knowledge that continuous-casting steel-making ladle is appeared on the stage, without phase
Pass professional knowledge, which differs, surely to be understood.(3)Excavate limitation:Continuous-casting steel-making ladle relevant information of appearing on the stage is stored in Central Control Room equipment
On, data mining can not be carried out substantially.(4)Manage limitation:Continuous casting is the important procedure of steel-making, and manager is because some trival matters
After leaving Central Control Room, field condition can be just understood, it is impossible to produced problem in each class's continuous-casting steel-making is handled in time, is managed
Control.For this reason, it is necessary to research and develop the system and method that a kind of energy timing monitoring steel-making continuous casting wraps greatly the platform condition of production.
The content of the invention
The first object of the present invention is that region existing for station information on steel-making continuous casting ladle can effectively be solved by providing one kind
Limitation, professional limitation, excavate the problems such as limitation, management limitation, and stable and reliable in work, simple to operate,
The system that timing monitoring steel-making continuous casting wraps greatly station information;Second purpose is to provide a kind of big based on timing monitoring steel-making continuous casting
The system for wrapping station information realizes the method that monitoring steel-making continuous casting wraps greatly station information.
What the first object of the present invention was realized in:The system that a kind of timing monitoring steel-making continuous casting wraps greatly station information,
Including data acquisition module, data memory module, Back Administration Module, data analysis module, data generation module, wherein:Institute
State the upstream of data acquisition module and be connected with the continuous casting industrial computer data installed at the scene, the upstream of downstream and data memory module
Data connection, the downstream of data memory module are connected with data analysis module upstream data, and data analysis module upstream also with
Back Administration Module data connection, downstream and data generation module data connection.
What the second object of the present invention was realized in:It is a kind of to be based on what timing monitoring steel-making continuous casting wrapped greatly station information
System, the method that monitoring steel-making continuous casting wraps greatly station information, the system comprises data acquisition module, data memory module, backstage
Management module, data analysis module, data generation module, wherein:The upstream of the data acquisition module is with installing at the scene
The upstream data of the connection of continuous casting industrial computer data, downstream and data memory module connects, the downstream of data memory module and data
Analysis module upstream data connects, and data analysis module upstream is also given birth to Back Administration Module data connection, downstream and data
Connected into module data, the described method includes the following steps:
A, information gathering:Appeared on the stage after signal, will be adopted by Con casting ladle of the data collecting module collected from live industrial personal computer
The signal of collection changes into the data that computer can identify;
B, information stores:The data of step A are stored into data memory module;
C, information analysis:Back Administration Module passes through thread scans periodically by data analysis module using Java
Data in data memory module, carry out analysis judgement, and confirmation is after continuous casting wraps station information greatly, forms useful data;
D, information generates:Useful data in data analysis module is generated corresponding data sheet by data generation module, at the same time
Useful data recorded in data memory module and preserve, while authority users to share is shown to by internal network.
The continuous casting, which wraps greatly station information, includes appear on the stage time, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, molten steel of appearing on the stage
The information such as chemical composition.
The data analysis module analysis judgement of the step C comprises the following steps:
A. judge to appear on the stage time, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, whether continuous casting is big for ladle chemistry data of appearing on the stage
Wrap station information;
B. judge that continuous casting wraps greatly whether the big bag weight in station information is more than 100 tons;
C. continuously judged big bag weight change whether within 50 kilograms in 20 seconds;
D. it is eligible, the time of appearing on the stage, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, steel of appearing on the stage within 50 kilograms
Hydrochemical Composition data are that continuous casting wraps greatly station information.
The present invention utilizes industrial personal computer and data acquisition module, data memory module, Back Administration Module, data analysis mould
This system of block, data generation module, monitoring steel-making continuous casting wrap greatly station information, are specifically:Pass through data collecting module collected
Con casting ladle from live industrial personal computer is appeared on the stage signal, is sent into data memory module storage;Periodically led to using Back Administration Module
Cross data analysis module, call after station information carries out analysis judgement on the Con casting ladle in data analysis module, generated by data
Module formed with information, and record and display corresponding information.Operator without client operates, just can be promptly and accurately
The corresponding data information that generation Con casting ladle is appeared on the stage, improves data analysis capabilities and management energy that iron and steel enterprise's Con casting ladle is appeared on the stage
Power.The present invention can effectively solve the region limitation of station information on Con casting ladle, specialty limitation, excavate limitation, management board
It is the problems such as sex-limited, stable and reliable in work, simple to operate.
Brief description of the drawings
Fig. 1 is general flow chart of the present invention;
In Fig. 1:1- data acquisition modules, 2- data memory modules, 3- Back Administration Modules, 4- data analysis modules, 5- data
Generation module.
Embodiment
The invention will be further described below in conjunction with the accompanying drawings, but the present invention is not any limitation as in any way, is based on
Present invention teach that any conversion or improvement made, each fall within protection scope of the present invention.
As shown in Figure 1, the system that timing monitoring steel-making continuous casting provided by the invention wraps greatly station information, including data acquisition
Module 1, data memory module 2, Back Administration Module 3, data analysis module 4, data generation module 5, wherein:The data are adopted
The upstream for collecting module 1 is connected with installation continuous casting industrial computer data at the scene, the upstream data company of downstream and data memory module 2
Connect, the downstream of data memory module 2 is connected with 4 upstream data of data analysis module, and 4 upstream of data analysis module also with backstage
5 data connection of 3 data connection of management module, downstream and data generation module.
The data acquisition module 1 includes data acquisition software and 1613 cards.
The data memory module 2 includes database and common network interface card.
The report data that the data generation module 5 generates is shared for internal network.
The common net is arranged with rights management.
The system of the present invention for wrapping station information greatly based on timing monitoring steel-making continuous casting, monitoring steel-making continuous casting wrap greatly platform
The method of information, the system comprises data acquisition module 1, data memory module 2, Back Administration Module 3, data analysis module
4th, data generation module 5, wherein:The upstream of the data acquisition module 1 is connected with installing continuous casting industrial computer data at the scene,
Downstream is connected with the upstream data of data memory module 2, downstream and 4 upstream data of data analysis module of data memory module 2
Connection, and 4 upstream of data analysis module also connects with 3 data connection of Back Administration Module, downstream and 5 data of data generation module
Connect, the described method includes the following steps:
A, information gathering:The Con casting ladle from live industrial personal computer is gathered by data acquisition module 1 to appear on the stage after signal, will be adopted
The signal of collection changes into the data that computer can identify;
B, information stores:The data of step A are stored into data memory module 2;
C, information analysis:Back Administration Module 3 is swept periodically by data analysis module 4 using Java by thread
The data in data memory module 2 are retouched, carry out analysis judgement, confirmation is after continuous casting wraps station information greatly, forms useful data;
D, information generates:Useful data in data analysis module 4 is generated corresponding data sheet by data generation module 5, together
When useful data recorded in data memory module 2 preserve, while authority users to share is shown to by internal network.
The continuous casting, which wraps greatly station information, includes appear on the stage time, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, molten steel of appearing on the stage
The information such as chemical composition.
The data analysis module 4 of the step C is analyzed judgement and is comprised the following steps:
A. judge to appear on the stage time, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, whether continuous casting is big for ladle chemistry data of appearing on the stage
Wrap station information;
B. judge that continuous casting wraps greatly whether the big bag weight in station information is more than 100 tons;
C. continuously judged big bag weight change whether within 50 kilograms in 20 seconds;
D. it is eligible, the time of appearing on the stage, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, steel of appearing on the stage within 50 kilograms
Hydrochemical Composition data are that continuous casting wraps greatly station information.
Claims (4)
1. the system that a kind of timing monitoring steel-making continuous casting wraps greatly station information, including data acquisition module, data memory module, after
Platform management module, data analysis module, data generation module, it is characterised in that:The upstream of the data acquisition module and installation
Continuous casting industrial computer data connection at the scene, the upstream data of downstream and data memory module connect, under data memory module
Trip be connected with data analysis module upstream data, and data analysis module upstream also with Back Administration Module data connection, downstream
With data generation module data connection.
2. a kind of system for wrapping station information greatly based on timing monitoring steel-making continuous casting described in claim 1, monitoring steel-making continuous casting is big
The method for wrapping station information, it is characterised in that the system comprises data acquisition module, data memory module, back-stage management mould
Block, data analysis module, data generation module, wherein:Continuous casting work of the upstream of the data acquisition module with installation at the scene
The upstream data connection of control machine data connection, downstream and data memory module, downstream and the data analysis mould of data memory module
Block upstream data connect, and data analysis module upstream also with Back Administration Module data connection, downstream and data generation module
Data connection;The described method includes the following steps:
A, information gathering:Appeared on the stage after signal, will be adopted by Con casting ladle of the data collecting module collected from live industrial personal computer
The signal of collection changes into the data that computer can identify;
B, information stores:The data of step A are stored into data memory module;
C, information analysis:Back Administration Module passes through thread scans periodically by data analysis module using Java
Data in data memory module, carry out analysis judgement, and confirmation is after continuous casting wraps station information greatly, forms useful data;
D, information generates:Useful data in data analysis module is generated corresponding data sheet by data generation module, at the same time
Useful data recorded in data memory module and preserve, while authority users to share is shown to by internal network.
3. according to the method described in claim 2, when it is characterized in that the Con casting ladle of the step A is appeared on the stage, information includes appearing on the stage
Between, the information such as ladle weight of appearing on the stage, Metal Weight of appearing on the stage, ladle chemistry of appearing on the stage.
4. according to the method described in claim 2, it is characterized in that the step C data analysis module analysis judgement include under
Row step:
A. judge to appear on the stage time, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, whether continuous casting is big for ladle chemistry data of appearing on the stage
Wrap station information;
B. judge that continuous casting wraps greatly whether the big bag weight in station information is more than 100 tons;
C. continuously judged big bag weight change whether within 50 kilograms in 20 seconds;
D. it is eligible, the time of appearing on the stage, ladle weight of appearing on the stage, Metal Weight of appearing on the stage, steel of appearing on the stage within 50 kilograms
Hydrochemical Composition data are that continuous casting wraps greatly station information.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711131780.3A CN107991955A (en) | 2017-11-15 | 2017-11-15 | Timing monitoring steel-making continuous casting wraps greatly the system and method for station information |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711131780.3A CN107991955A (en) | 2017-11-15 | 2017-11-15 | Timing monitoring steel-making continuous casting wraps greatly the system and method for station information |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107991955A true CN107991955A (en) | 2018-05-04 |
Family
ID=62030884
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711131780.3A Pending CN107991955A (en) | 2017-11-15 | 2017-11-15 | Timing monitoring steel-making continuous casting wraps greatly the system and method for station information |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107991955A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109465416A (en) * | 2018-11-01 | 2019-03-15 | 云南昆钢电子信息科技有限公司 | It is a kind of to open the system and method poured applied to monitoring continuous casting production |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103472811A (en) * | 2013-09-27 | 2013-12-25 | 济钢集团有限公司 | Steelmaking second-stage process control system and steelmaking second-stage process control method |
CN104133451A (en) * | 2014-07-31 | 2014-11-05 | 武钢集团昆明钢铁股份有限公司 | Management system and method for steel-making argon blowing ladle |
CN205229785U (en) * | 2015-09-30 | 2016-05-11 | 芜湖新兴铸管有限责任公司 | Continuous casting divides base system |
CN106707930A (en) * | 2016-12-09 | 2017-05-24 | 武钢集团昆明钢铁股份有限公司 | Continuous casting ladle conveying-to-platform management system and method |
-
2017
- 2017-11-15 CN CN201711131780.3A patent/CN107991955A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103472811A (en) * | 2013-09-27 | 2013-12-25 | 济钢集团有限公司 | Steelmaking second-stage process control system and steelmaking second-stage process control method |
CN104133451A (en) * | 2014-07-31 | 2014-11-05 | 武钢集团昆明钢铁股份有限公司 | Management system and method for steel-making argon blowing ladle |
CN205229785U (en) * | 2015-09-30 | 2016-05-11 | 芜湖新兴铸管有限责任公司 | Continuous casting divides base system |
CN106707930A (en) * | 2016-12-09 | 2017-05-24 | 武钢集团昆明钢铁股份有限公司 | Continuous casting ladle conveying-to-platform management system and method |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109465416A (en) * | 2018-11-01 | 2019-03-15 | 云南昆钢电子信息科技有限公司 | It is a kind of to open the system and method poured applied to monitoring continuous casting production |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110378606B (en) | Mobile visual safety management and control system | |
CN106026405B (en) | Relay protection in-service monitoring based on EMS system and analysis system | |
CN103324175B (en) | A kind of managing and control system of aluminium section bar production line | |
CN104035404A (en) | Development method for operation order real-time state monitoring | |
CN104133415B (en) | A kind of steelmaking converter molten steel management system and method | |
CN111591778A (en) | Remote monitoring management system and method for stacker-reclaimer based on Internet technology | |
CN103684940A (en) | TD-LTE (time division long term evolution) based power distribution and utilization network business management system | |
CN107798489A (en) | A kind of electric network operation site safety management method based on wechat platform | |
CN105023117A (en) | Electrified detection standardized operation management system based on mobile and cloud computing technologies | |
CN110264164A (en) | Promotion of item method and system based on visualization inspection | |
CN104133451A (en) | Management system and method for steel-making argon blowing ladle | |
CN113566883A (en) | Power cable monitoring method and system based on Internet of things and storage medium | |
CN101917061A (en) | Automatic inspection method and device for substation | |
CN209728814U (en) | A kind of molten iron information tracking system | |
CN107991955A (en) | Timing monitoring steel-making continuous casting wraps greatly the system and method for station information | |
CN109465416A (en) | It is a kind of to open the system and method poured applied to monitoring continuous casting production | |
CN106707930A (en) | Continuous casting ladle conveying-to-platform management system and method | |
CN208571705U (en) | A kind of 500kV substation fault recording teletransmission data monitoring system | |
CN107979174B (en) | Workflow operation method based on power grid operation management system | |
CN113810797B (en) | Intelligent ODN management system and method based on optical port state monitoring | |
CN206322013U (en) | A kind of novel casting factory network control system | |
TWI742999B (en) | Apparatus, system, method and computer-readable medium for networking device data missing analysis and supplement | |
CN107196796A (en) | A kind of apparatus and method for collecting server management system log information | |
CN111371874B (en) | Industrial data transmission method and device, storage medium and electronic equipment | |
KR100194181B1 (en) | City exchange network management system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180504 |