CN107942454A - A kind of center type optical cable production technology - Google Patents

A kind of center type optical cable production technology Download PDF

Info

Publication number
CN107942454A
CN107942454A CN201711156372.3A CN201711156372A CN107942454A CN 107942454 A CN107942454 A CN 107942454A CN 201711156372 A CN201711156372 A CN 201711156372A CN 107942454 A CN107942454 A CN 107942454A
Authority
CN
China
Prior art keywords
band
cable
production technology
type optical
ink
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711156372.3A
Other languages
Chinese (zh)
Inventor
许海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Zhongtian Technology Cable Co Ltd
Original Assignee
Guangdong Zhongtian Technology Cable Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Zhongtian Technology Cable Co Ltd filed Critical Guangdong Zhongtian Technology Cable Co Ltd
Priority to CN201711156372.3A priority Critical patent/CN107942454A/en
Publication of CN107942454A publication Critical patent/CN107942454A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G02OPTICS
    • G02BOPTICAL ELEMENTS, SYSTEMS OR APPARATUS
    • G02B6/00Light guides; Structural details of arrangements comprising light guides and other optical elements, e.g. couplings
    • G02B6/44Mechanical structures for providing tensile strength and external protection for fibres, e.g. optical transmission cables
    • G02B6/4479Manufacturing methods of optical cables

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • General Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Manufacturing Of Electric Cables (AREA)

Abstract

The invention discloses a kind of center type optical cable production technology, comprise the following steps:Coloring, secondary coated, stranding and sheath, coloring include bare fibre unwrapping wire, dedusting, injection ink, installation mold, ultra-violet curing;It is secondary coated to be twisted head, factice for filling, extruder head, movable warm water tank, remaining long traction, cold rinse bank, blow-dry device, outside diameter tester, auxiliary traction, takeup tension, double plate take-up including optical fiber unwrapping wire, SZ;The beneficial effects of the invention are as follows:The beneficial effects of the invention are as follows:Product antidetonation, the good buffer effect of production;The cable strength processed is high, service life length;In process, optical fiber is not easily damaged, improves product quality;Processing pollution is small, environmental protection and energy saving;Product yield is high, is that enterprise is cost-effective.

Description

A kind of center type optical cable production technology
Technical field
The present invention relates to one kind in a big way, it is specifically a kind of center type optical cable production technology.
Background technology
The construction of fiber optic network at present is gradually by national backbone network turn-around zone net and Metro access networks, in optical fiber Metropolitan Area Network (MAN) And in access net, it is more by the node connected, generally require to be laid with the optical cable of large core number, and had using optical fiber ribbon cable many excellent Point:Cable configuration can be made smaller by the integrated level of its optical cable of optical fiber ribbon cable, i.e., identical fiber cores, take route resource It is less;Optical cable welding expense is reduced, improves installation effectiveness.Due to the decline of optical fiber cost, the cost reduction of optical fiber ribbon cable, bone The progress of dry fibre ribbon and fiber optic cable manufacture technology so that optical fiber ribbon cable is substantially close with the fibre loss of common loose fibre optical cable; Fibre ribbon has more preferable mechanical performance than optical fiber.
Abroad, optical fiber ribbon cable is also largely used on optical cable long distance line, and it is more in metropolitan Metropolitan Area Network (MAN) at home Using optical fiber ribbon cable.Optical fiber ribbon cable has central beam tube type, layer-twisted type, skeleton construction by its structure.Central beam tube type banding light Cable is since it is with good lateral pressure resistant and bending property, the shape ruler of the maximum i.e. formed objects of its fiber number of unit area The features such as very little its fiber number is maximum is at home and abroad used widely, and central beam tube type optical fiber ribbon cable cable core is in whole optical cable It is basic in design, primarily serve the effect of protection optical fiber, optical fiber ointment filled between casing and fibre ribbon, to fibre ribbon by To playing good cushioning effect during side pressure.
Existing center type optical cable, production technology processed complex, product quality is undesirable, and yields is relatively low, gives enterprise's band The burden in cost is carried out.
The content of the invention
It is proposed in the above background technology to solve it is an object of the invention to provide a kind of center type optical cable production technology Problem.
To achieve the above object, the present invention provides following technical solution:
A kind of center type optical cable production technology, comprises the following steps:
1) colour:
S1 bare fibre unwrapping wire:Check bare fibre packaging should be intact, without collapse line, crimping, loose ring phenomena such as;
S2 dedustings:Quartz ampoule, dancing wheel and belt to curing carry out dedusting;
S3 injections ink, installation mold:Fix ink seat and load onto corresponding mould, into mouth mold:275~350 μm, Outlet mold:250~260 μm, and it is plugged heater and sensor;
S4 ultra-violet curings:Curing oven and ink device are connected, ink heating-up temperature is set, loads onto blank panel and resetted, pressed Reset button in control cabinet;
S5 tractions, tension-adjusting gear:Retractable fibre tension force is adjusted, retractable line tension is 30-50g;
S6 winding and arranging devices;
2) it is secondary coated:
S1SZ is twisted head:It is twisted to " SZ " to check, proofread, to prevent twisting disconnected optical fiber because dead-center position drifts about, check that SZ is twisted The cleaning situation of porcelain eye, " SZ " twisted angle are 360 degree, the potentiometer on adjustment control panel to required value parameter, optical fiber Corresponded with the string holes that " SZ " is twisted;
S2 factice for filling:Ointment constant temperature when 24 is small more than, full filling;
S3 extruder heads;Extrusion temperature scope is 250-270 DEG C;
S4 activity warm water tanks:Optical fiber is by movable warm water tank, the distance between movable warm water tank and die sleeve 5-6cm;Warm water Temperature range:40-60℃;
Long traction more than S5:Remaining long scope is layer stranded cable (0.6~0.8) ‰;
S6 cold rinse banks:Optical fiber passes through cold rinse bank, and cold water temperature is controlled at 18~22 DEG C;
S7 is dried up:Dried up using air-blast device;
S8 outside diameters tester tests light outside diameter, ± 0.02mm of the wall thickness value in standard value;
S9 auxiliary tractions:Auxiliary traction is carried out using straining pulley;
S10 double plate take-ups:Double plate take-up is carried out using admission machine;
3) sheath:
S1 beam tubes unwrapping wire, parallel steel wire unwrapping wire:Beam tube is first shifted onto pay off rack in the following, two addendum cone of pay off rack is dropped to cable Center hole position, to good pin and addendum cone, then presses and button is clamped on operation panel by cable chuck clamping, its is peaceful, is further continued for Same liter of button is pressed, both ends adjustment is horizontal by cable disk lifting to certain altitude;
S2 storage band longitudinal wraps:Strengthening core or cable core are wound by tensioning separated time race, and is pulled to longitudinal wrap platform;
S3 waterstops:Longitudinal wrap work fills waterstop;
S4 preforms mould, longitudinal wrap plug die:Embossing depth is adjusted, two side cock of embossing calender counterclockwise to unclamp, rolls Line shoals;Clockwise to tighten, embossing deepens;Wheel speed with pressure will be stored up and be adjusted to 30 ms/min, storage band knob is pressed and start Band is stored up, by slow-to-fast speed storage band after steadily trend does not touch case side after forward (FWD), 30 ms/min add to 60 ms/min, and band to be composite has stored up Afterwards, the composite band put on tape holder is replaced, after compound belt lacing is by host, recovers former normal speed of production;
S5 extrusion moldings, double-deck bosh cooling:Extruding machine warm area is preheated in advance, controls the first water-saving groove hot water temperature to be 35-50℃;Cooling water is put to sink height 4/5, and adjusts flow, and cable core is pulled out extrusion head together with waterstop;But Sink inflection point can use compared with multiple production line composite band squeezing into material post-tensioning blank pipe to guide wheel is drawn, then again by cable core and resistance Water band is pierced into pipe together;
S6 is dried up:At double-deck bosh two-wheel turning, blowing mouth is set;
The test of S7 outside diameters, power frequency spark, metering lettering:Outside diameter test carries out the test of outside diameter, enters information into power frequency fire Flower machine, and metering distance has been measured at the trial, error is not more than 1%;
S8 tractions, tension adjustment, receive winding displacement:Traction rope is buckled well, starts traction and wind turbine, holds the connection of cable and traction rope Place, sends out traction, after cable end reaches traction pinch roller, assists the first-class cable disk of take-up work to normal condition.
As the further scheme of the present invention:It is described 1) in bare fibre unwrapping wire, when getting optical fiber, fiber reel vertically carries without exception Take, forbid lying or keep flat, the fibre that collapses is caused to prevent going bad or deforming fine adjustment debit.
As further scheme of the invention:1) the middle injection ink, installation mold, use the preceding ink that will be received Fully shake up, when the time is 6-8 small, and stand one hour, discharge bubble, can use;.
As further scheme of the invention:It is described 1) in injection ink, installation mold, ink heating-up temperature for 30~ 45℃。
As further scheme of the invention:It is described 2) in SZ be twisted head, the conducting wire porcelain eye twisted to " SZ " will be done Cleared up once to often producing 50 kilometers.
As further scheme of the invention:It is described 4) in storage band longitudinal wrap, the deep 0.45~0.55mm of steel band line;Aluminium strip With 0.35~0.5mm of steel band embossing of 17mm;0.55~0.65mm of steel band embossing of 60mm~76mm.
As further scheme of the invention:It is described 4) in storage band longitudinal wrap, storage band time control be:Store up within one minute Band, burn band, one minute tape splicing, one minute standby time in one minute.
As further scheme of the invention:It is described 4) in storage with longitudinal wrap tape splicing requirement:Two composite bands are corresponded to and cut Into 45 degree of angles, composite membrane sanding is removed, two are welded with overlapping, and when spot welding first compresses lap, adjusts electric current gear, Open power supply point and be welded into work(, then cut off the power, finally take away soldering tip, part spot welding to be overlapped terminates, by two sides sanding.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the product antidetonation of production, good buffer effect;
2nd, the cable strength processed is high, service life length;
3rd, in process, optical fiber is not easily damaged, improves product quality;
4th, processing pollution is small, environmental protection and energy saving;
5th, product yield is high, is that enterprise is cost-effective.
Embodiment
Technical scheme will be clearly and completely described below, it is clear that described embodiment is this hair Bright part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art exist All other embodiments obtained under the premise of creative work are not made, belong to the scope of protection of the invention.
Embodiment 1:
Comprise the following steps:
1) colour:
S1 bare fibre unwrapping wire:Check bare fibre packaging should be intact, without collapse line, crimping, loose ring phenomena such as;
S2 dedustings:Quartz ampoule, dancing wheel and belt to curing carry out dedusting;
S3 injections ink, installation mold:Fix ink seat and load onto corresponding mould, into mouth mold:275 μm, outlet mold: 250 μm, and it is plugged heater and sensor;
S4 ultra-violet curings:Curing oven and ink device are connected, ink heating-up temperature is set, loads onto blank panel and resetted, pressed Reset button in control cabinet;
S5 tractions, tension-adjusting gear:Retractable fibre tension force is adjusted, retractable line tension is 30g;
S6 winding and arranging devices;
2) it is secondary coated:
S1SZ is twisted head:It is twisted to " SZ " to check, proofread, to prevent twisting disconnected optical fiber because dead-center position drifts about, check that SZ is twisted The cleaning situation of porcelain eye, " SZ " twisted angle are 360 degree, the potentiometer on adjustment control panel to required value parameter, optical fiber Corresponded with the string holes that " SZ " is twisted;
S2 factice for filling:Ointment constant temperature when 24 is small more than, full filling;
S3 extruder heads;Extrusion temperature scope is 250-270 DEG C;
S4 activity warm water tanks:Optical fiber is by movable warm water tank, the distance between movable warm water tank and die sleeve 5cm;Warm water temperature Spend scope:40℃;
Long traction more than S5:Remaining long scope is layer stranded cable (0.6~0.8) ‰;
S6 cold rinse banks:Optical fiber passes through cold rinse bank, and cold water temperature is controlled at 18 DEG C;
S7 is dried up:Dried up using air-blast device;
S8 outside diameters tester tests light outside diameter, ± 0.02mm of the wall thickness value in standard value;
S9 auxiliary tractions:Auxiliary traction is carried out using straining pulley;
S10 double plate take-ups:Double plate take-up is carried out using admission machine;
3) sheath:
S1 beam tubes unwrapping wire, parallel steel wire unwrapping wire:Beam tube is first shifted onto pay off rack in the following, two addendum cone of pay off rack is dropped to cable Center hole position, to good pin and addendum cone, then presses and button is clamped on operation panel by cable chuck clamping, its is peaceful, is further continued for Same liter of button is pressed, both ends adjustment is horizontal by cable disk lifting to certain altitude;
S2 storage band longitudinal wraps:Strengthening core or cable core are wound by tensioning separated time race, and is pulled to longitudinal wrap platform;
S3 waterstops:Longitudinal wrap work fills waterstop;
S4 preforms mould, longitudinal wrap plug die:Embossing depth is adjusted, two side cock of embossing calender counterclockwise to unclamp, rolls Line shoals;Clockwise to tighten, embossing deepens;Wheel speed with pressure will be stored up and be adjusted to 30 ms/min, storage band knob is pressed and start Band is stored up, by slow-to-fast speed storage band after steadily trend does not touch case side after forward (FWD), 30 ms/min add to 60 ms/min, and band to be composite has stored up Afterwards, the composite band put on tape holder is replaced, after compound belt lacing is by host, recovers former normal speed of production;
S5 extrusion moldings, double-deck bosh cooling:Extruding machine warm area is preheated in advance, controls the first water-saving groove hot water temperature to be 35-50℃;Cooling water is put to sink height 4/5, and adjusts flow, and cable core is pulled out extrusion head together with waterstop;But Sink inflection point can use compared with multiple production line composite band squeezing into material post-tensioning blank pipe to guide wheel is drawn, then again by cable core and resistance Water band is pierced into pipe together;
S6 is dried up:At double-deck bosh two-wheel turning, blowing mouth is set;
The test of S7 outside diameters, power frequency spark, metering lettering:Outside diameter test carries out the test of outside diameter, enters information into power frequency fire Flower machine, and metering distance has been measured at the trial, error is not more than 1%;
S8 tractions, tension adjustment, receive winding displacement:Traction rope is buckled well, starts traction and wind turbine, holds the connection of cable and traction rope Place, sends out traction, after cable end reaches traction pinch roller, assists the first-class cable disk of take-up work to normal condition.
It is described 1) in bare fibre unwrapping wire, when getting optical fiber, fiber reel vertically extracts without exception, forbids lying or keeps flat, to prevent Fine adjustment debit is gone bad or deformed and causes the fibre that collapses.
1) the middle injection ink, installation mold, are fully shaken up the ink received using preceding, when the time is 6 small, and One hour is stood, bubble is discharged, can use;.
1) the middle injection ink, installation mold, ink heating-up temperature is 30 DEG C.
It is described 2) in SZ be twisted head, the conducting wire porcelain eye twisted to " SZ " to accomplish it is every production 50 kilometers cleaning once.
It is described 4) in storage band longitudinal wrap, the deep 0.45~0.55mm of steel band line;The steel band embossing 0.35 of aluminium strip and 17mm~ 0.5mm;0.55~0.65mm of steel band embossing of 60mm~76mm.
It is described 4) in storage band longitudinal wrap, storage band time control be:One minute storage band, burn band, one minute tape splicing, one in one minute Standby time minute.
It is described 4) in storage with longitudinal wrap tape splicing requirement:Two composite bands, which correspond to, is cut into 45 degree of angles, removal composite membrane sanding, and two Welded with overlapping, when spot welding first compresses lap, adjusts electric current gear, opens power supply point and is welded into work(, then cuts off electricity Source, finally takes away soldering tip, and part spot welding to be overlapped terminates, by two sides sanding.
Embodiment 2:
Comprise the following steps:
1) colour:
S1 bare fibre unwrapping wire:Check bare fibre packaging should be intact, without collapse line, crimping, loose ring phenomena such as;
S2 dedustings:Quartz ampoule, dancing wheel and belt to curing carry out dedusting;
S3 injections ink, installation mold:Fix ink seat and load onto corresponding mould, into mouth mold:2350 μm, outlet Mould:260 μm, and it is plugged heater and sensor;
S4 ultra-violet curings:Curing oven and ink device are connected, ink heating-up temperature is set, loads onto blank panel and resetted, pressed Reset button in control cabinet;
S5 tractions, tension-adjusting gear:Retractable fibre tension force is adjusted, retractable line tension is 50g;
S6 winding and arranging devices;
2) it is secondary coated:
S1SZ is twisted head:It is twisted to " SZ " to check, proofread, to prevent twisting disconnected optical fiber because dead-center position drifts about, check that SZ is twisted The cleaning situation of porcelain eye, " SZ " twisted angle are 360 degree, the potentiometer on adjustment control panel to required value parameter, optical fiber Corresponded with the string holes that " SZ " is twisted;
S2 factice for filling:Ointment constant temperature when 24 is small more than, full filling;
S3 extruder heads;Extrusion temperature scope is 270 DEG C;
S4 activity warm water tanks:Optical fiber is by movable warm water tank, the distance between movable warm water tank and die sleeve 6cm;Warm water temperature Spend scope:60℃;
Long traction more than S5:Remaining long scope is layer stranded cable (0.6~0.8) ‰;
S6 cold rinse banks:Optical fiber passes through cold rinse bank, and cold water temperature is controlled at 22 DEG C;
S7 is dried up:Dried up using air-blast device;
S8 outside diameters tester tests light outside diameter, ± 0.02mm of the wall thickness value in standard value;
S9 auxiliary tractions:Auxiliary traction is carried out using straining pulley;
S10 double plate take-ups:Double plate take-up is carried out using admission machine;
S1 beam tubes unwrapping wire, parallel steel wire unwrapping wire:Beam tube is first shifted onto pay off rack in the following, two addendum cone of pay off rack is dropped to cable Center hole position, to good pin and addendum cone, then presses and button is clamped on operation panel by cable chuck clamping, its is peaceful, is further continued for Same liter of button is pressed, both ends adjustment is horizontal by cable disk lifting to certain altitude;
S2 storage band longitudinal wraps:Strengthening core or cable core are wound by tensioning separated time race, and is pulled to longitudinal wrap platform;
S3 waterstops:Longitudinal wrap work fills waterstop;
S4 preforms mould, longitudinal wrap plug die:Embossing depth is adjusted, two side cock of embossing calender counterclockwise to unclamp, rolls Line shoals;Clockwise to tighten, embossing deepens;Wheel speed with pressure will be stored up and be adjusted to 30 ms/min, storage band knob is pressed and start Band is stored up, by slow-to-fast speed storage band after steadily trend does not touch case side after forward (FWD), 30 ms/min add to 60 ms/min, and band to be composite has stored up Afterwards, the composite band put on tape holder is replaced, after compound belt lacing is by host, recovers former normal speed of production;
S5 extrusion moldings, double-deck bosh cooling:Extruding machine warm area is preheated in advance, controls the first water-saving groove hot water temperature to be 35-50℃;Cooling water is put to sink height 4/5, and adjusts flow, and cable core is pulled out extrusion head together with waterstop;But Sink inflection point can use compared with multiple production line composite band squeezing into material post-tensioning blank pipe to guide wheel is drawn, then again by cable core and resistance Water band is pierced into pipe together;
S6 is dried up:At double-deck bosh two-wheel turning, blowing mouth is set;
The test of S7 outside diameters, power frequency spark, metering lettering:Outside diameter test carries out the test of outside diameter, enters information into power frequency fire Flower machine, and metering distance has been measured at the trial, error is not more than 1%;
S8 tractions, tension adjustment, receive winding displacement:Traction rope is buckled well, starts traction and wind turbine, holds the connection of cable and traction rope Place, sends out traction, after cable end reaches traction pinch roller, assists the first-class cable disk of take-up work to normal condition.
It is described 1) in bare fibre unwrapping wire, when getting optical fiber, fiber reel vertically extracts without exception, forbids lying or keeps flat, to prevent Fine adjustment debit is gone bad or deformed and causes the fibre that collapses.
1) the middle injection ink, installation mold, are fully shaken up the ink received using preceding, when the time is 6-8 small, and And one hour is stood, bubble is discharged, can be used;.
1) the middle injection ink, installation mold, ink heating-up temperature is 45 DEG C.
It is described 2) in SZ be twisted head, the conducting wire porcelain eye twisted to " SZ " to accomplish it is every production 50 kilometers cleaning once.
It is described 4) in storage band longitudinal wrap, the deep 0.45~0.55mm of steel band line;The steel band embossing 0.35 of aluminium strip and 17mm~ 0.5mm;0.55~0.65mm of steel band embossing of 60mm~76mm.
It is described 4) in storage band longitudinal wrap, storage band time control be:One minute storage band, burn band, one minute tape splicing, one in one minute Standby time minute.
It is described 4) in storage with longitudinal wrap tape splicing requirement:Two composite bands, which correspond to, is cut into 45 degree of angles, removal composite membrane sanding, and two Welded with overlapping, when spot welding first compresses lap, adjusts electric current gear, opens power supply point and is welded into work(, then cuts off electricity Source, finally takes away soldering tip, and part spot welding to be overlapped terminates, by two sides sanding.
The foregoing descriptions are merely the embodiment using this origination techniques content, any those skilled in the art use this wound Make done modifications and changes, all belong to the scope of the claims of this creation opinion, and be not limited to those disclosed embodiments.
If not specified, conventional means of the technological means known to those skilled in the art employed in embodiment, institute The reagent and product of use are also available commercial.The source of agents useful for same, trade name and its composition is listed if necessary Component person, indicates on the first appearance.

Claims (8)

1. a kind of center type optical cable production technology, it is characterized in that, comprise the following steps:
1) colour:
S1 bare fibre unwrapping wire:Check bare fibre packaging should be intact, without collapse line, crimping, loose ring phenomena such as;
S2 dedustings:Quartz ampoule, dancing wheel and belt to curing carry out dedusting;
S3 injections ink, installation mold:Fix ink seat and load onto corresponding mould, into mouth mold:275~350 μm, outlet Mould:250~260 μm, and it is plugged heater and sensor;
S4 ultra-violet curings:Curing oven and ink device are connected, ink heating-up temperature is set, loads onto blank panel and resetted, by master control Reset button on cabinet;
S5 tractions, tension-adjusting gear:Retractable fibre tension force is adjusted, retractable line tension is 30-50g;
S6 winding and arranging devices;
2) it is secondary coated:
S1SZ is twisted head:It is twisted to " SZ " to check, proofread, check that SZ twists the cleaning situation of porcelain eye, " SZ " twisted angle is 360 Degree, the potentiometer adjusted on control panel are corresponded to required value parameter, optical fiber with the string holes that " SZ " is twisted;
S2 factice for filling:Ointment constant temperature when 24 is small more than, full filling;
S3 extruder heads;Extrusion temperature scope is 250-270 DEG C;
S4 activity warm water tanks:Optical fiber is by movable warm water tank, the distance between movable warm water tank and die sleeve 5-6cm;Warm water temperature Scope:40-60℃;
Long traction more than S5:Remaining long scope is layer stranded cable (0.6~0.8) ‰;
S6 cold rinse banks:Optical fiber passes through cold rinse bank, and cold water temperature is controlled at 18~22 DEG C;
S7 is dried up:Dried up using air-blast device;
S8 outside diameters tester tests light outside diameter, ± 0.02mm of the wall thickness value in standard value;
S9 auxiliary tractions:Auxiliary traction is carried out using straining pulley;
S10 double plate take-ups:Double plate take-up is carried out using admission machine;
3) sheath:
S1 beam tubes unwrapping wire, parallel steel wire unwrapping wire:Beam tube is first shifted onto pay off rack in the following, two addendum cone of pay off rack is dropped in cable disk Heart hole site, to good pin and addendum cone, then presses and button is clamped on operation panel by cable chuck clamping, its is peaceful, is further continued for by same Button is risen, both ends adjustment is horizontal by cable disk lifting to certain altitude;
S2 storage band longitudinal wraps:Strengthening core or cable core are wound by tensioning separated time race, and is pulled to longitudinal wrap platform;
S3 waterstops:Longitudinal wrap work fills waterstop;
S4 preforms mould, longitudinal wrap plug die:Embossing depth is adjusted, counterclockwise to unclamp, embossing becomes two side cock of embossing calender It is shallow;Clockwise to tighten, embossing deepens;Wheel speed with pressure will be stored up and be adjusted to 30 ms/min, storage band knob is pressed and start to store up band, By slow-to-fast speed storage band after after forward (FWD), steadily trend does not touch case side, 30 ms/min add to 60 ms/min, after band to be composite has stored up, and replace The composite band on tape holder is put, after compound belt lacing is by host, recovers former normal speed of production;
S5 extrusion moldings, double-deck bosh cooling:Extruding machine warm area is preheated in advance, and it is 35-50 to control the first water-saving groove hot water temperature ℃;Cooling water is put to sink height 4/5, and adjusts flow, and cable core is pulled out extrusion head together with waterstop;But sink is curved Break can use compared with multiple production line composite band squeezing into material post-tensioning blank pipe to guide wheel is drawn, then again by cable core together with waterstop Pierce into pipe;
S6 is dried up:At double-deck bosh two-wheel turning, blowing mouth is set;
The test of S7 outside diameters, power frequency spark, metering lettering:Outside diameter test carries out the test of outside diameter, enters information into power frequency spark machine, And metering distance has been measured at the trial, error is not more than 1%;
S8 tractions, tension adjustment, receive winding displacement:Traction rope is buckled well, starts traction and wind turbine, holds the junction of cable and traction rope, Traction is sent out, after cable end reaches traction pinch roller, assists the first-class cable disk of take-up work to normal condition.
2. center type optical cable production technology according to claim 1, it is characterized in that, it is described 1) in bare fibre unwrapping wire, get During optical fiber, fiber reel vertically extracts without exception, forbids lying or keeps flat, and the fibre that collapses is caused to prevent going bad or deforming fine adjustment debit.
3. center type optical cable production technology according to claim 1, it is characterized in that, 1) the middle injection ink, installation mould Tool, is fully shaken up the ink received using preceding, when the time is 6-8 small, and is stood one hour, is discharged bubble, can make With;.
4. center type optical cable production technology according to claim 1, it is characterized in that, 1) the middle injection ink, installation mould Tool, ink heating-up temperature are 30~45 DEG C.
5. center type optical cable production technology according to claim 1, it is characterized in that, it is described 2) in SZ be twisted head, it is right " SZ " twisted conducting wire porcelain eye will accomplish every 50 kilometers of cleanings of production once.
6. center type optical cable production technology according to claim 1, it is characterized in that, it is described 4) in storage band longitudinal wrap, steel band Deep 0.45~the 0.55mm of line;0.35~0.5mm of steel band embossing of aluminium strip and 17mm;The steel band embossing 0.55 of 60mm~76mm~ 0.65mm。
7. center type optical cable production technology according to claim 1, it is characterized in that, it is described 4) in storage band longitudinal wrap, store up band Time control is:One minute storage band, burn band, one minute tape splicing, one minute standby time in one minute.
8. center type optical cable production technology according to claim 1, it is characterized in that, it is described 4) in tape splicing of the storage with longitudinal wrap It is required that:Two composite bands correspond to and are cut into 45 degree of angles, remove composite membrane sanding, and two are welded with overlapping, and when spot welding first compresses overlapping Part, adjusts electric current gear, opens power supply point and is welded into work(, then cuts off the power, and finally takes away soldering tip, spot welding knot in part to be overlapped Beam, by two sides sanding.
CN201711156372.3A 2017-11-20 2017-11-20 A kind of center type optical cable production technology Pending CN107942454A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711156372.3A CN107942454A (en) 2017-11-20 2017-11-20 A kind of center type optical cable production technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711156372.3A CN107942454A (en) 2017-11-20 2017-11-20 A kind of center type optical cable production technology

Publications (1)

Publication Number Publication Date
CN107942454A true CN107942454A (en) 2018-04-20

Family

ID=61929172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711156372.3A Pending CN107942454A (en) 2017-11-20 2017-11-20 A kind of center type optical cable production technology

Country Status (1)

Country Link
CN (1) CN107942454A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108761677A (en) * 2018-04-26 2018-11-06 上海富瑞电缆股份有限公司 Optical cable production equipment and system
CN113866924A (en) * 2021-10-21 2021-12-31 西安西古光通信有限公司 PET (polyethylene terephthalate) central beam tube type optical cable and manufacturing method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101915972A (en) * 2010-07-03 2010-12-15 蒋菊生 Anti-contraction optical cable and production method thereof
CN102081207A (en) * 2011-01-18 2011-06-01 江苏长飞中利光纤光缆有限公司 Central tube optical cable with compact structure
CN102755851A (en) * 2012-08-07 2012-10-31 浙江富春江光电科技股份有限公司 Gear transmission optical fiber coloring printing ink blender
CN103048750A (en) * 2012-12-27 2013-04-17 青岛中能集团有限公司 Coloring process flow of fire-retardant cable
CN104793305A (en) * 2015-04-23 2015-07-22 龚利芬 Central loose tube optical cable and method for manufacturing same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101915972A (en) * 2010-07-03 2010-12-15 蒋菊生 Anti-contraction optical cable and production method thereof
CN102081207A (en) * 2011-01-18 2011-06-01 江苏长飞中利光纤光缆有限公司 Central tube optical cable with compact structure
CN102755851A (en) * 2012-08-07 2012-10-31 浙江富春江光电科技股份有限公司 Gear transmission optical fiber coloring printing ink blender
CN103048750A (en) * 2012-12-27 2013-04-17 青岛中能集团有限公司 Coloring process flow of fire-retardant cable
CN104793305A (en) * 2015-04-23 2015-07-22 龚利芬 Central loose tube optical cable and method for manufacturing same

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
周叶芳: "光缆施工中的几个注意要点及测试", 《武汉市第二届学术年会、通信学会2006年学术年会论文集》 *
张晓红 等: "光缆工程建设中应注意的几个环节", 《中国有线电视》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108761677A (en) * 2018-04-26 2018-11-06 上海富瑞电缆股份有限公司 Optical cable production equipment and system
CN113866924A (en) * 2021-10-21 2021-12-31 西安西古光通信有限公司 PET (polyethylene terephthalate) central beam tube type optical cable and manufacturing method thereof

Similar Documents

Publication Publication Date Title
AU2018401778B2 (en) A method for producing a flexible optical fiber ribbon and said ribbon.
CN109358399B (en) Layer-stranded miniature optical cable series production device and production process thereof
CN105632645B (en) A kind of compact-sized optoelectrical cable
WO2016058421A1 (en) Equipotential optical fibre unit for high-voltage photoelectric composite cable and preparation method therefor
CN102662220A (en) Loosely sleeved layer-stranded full-dry optical cable and manufacturing method thereof
CN107942454A (en) A kind of center type optical cable production technology
CN105511036A (en) Non-metal layer-stranding cable
CN102096163A (en) Method for producing sheath of nylon cable and extrusion die thereof
CN107728277A (en) A kind of central-beam tube type fiber optic cable integrated production line
CN113406756B (en) Flame-retardant low-release object layer stranded optical cable and preparation method thereof
CN108051894A (en) A kind of double armour optical cable production technologies
CN111474651A (en) 500-core and above-core multi-layer stranded unrepeatered submarine optical cable
CN107037556A (en) A kind of optical cable continuous production method
CN205121025U (en) Pancake self -supporting introduces optical fiber ribbon optical cable
CN110211740A (en) A kind of compound carbon fiber core conducting wire of photoelectricity and production method
CN106932874A (en) The preparation method of filling type optical cable
CN112034571A (en) Anti-shrinkage multi-unit parallel beam tube optical cable and manufacturing method thereof
CN105204133A (en) Preparation method of flat-shaped self-supporting access optical fiber ribbon optical cable and optical cable prepared through preparation method
CN107894634A (en) A kind of single armour optical cable production technology
CN105676382B (en) A method of manufacturing compact-sized optoelectrical cable
CN106950669B (en) Central-beam tube type fiber optic cable and production method
CN104049329A (en) Optical cable of improved structure
CN101504480A (en) Integrated optical communication cable
CN105974539A (en) Lateral pressure and stretching resistance optical fiber ribbon and method for manufacturing same
JP2868068B2 (en) Method for manufacturing self-supporting optical cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180420