- Publication number
- CN107913924A CN107913924A CN201711086048.9A CN201711086048A CN107913924A CN 107913924 A CN107913924 A CN 107913924A CN 201711086048 A CN201711086048 A CN 201711086048A CN 107913924 A CN107913924 A CN 107913924A
- Authority
- CN
- China
- Prior art keywords
- tower
- fixed
- straightening
- moulding bed
- hydraulic cylinder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000004891 communication Methods 0.000 title claims abstract description 67
- 238000000465 moulding Methods 0.000 claims abstract description 61
- 238000012545 processing Methods 0.000 claims abstract description 28
- 239000000463 material Substances 0.000 claims abstract description 20
- 238000012546 transfer Methods 0.000 claims abstract description 12
- 230000003068 static effect Effects 0.000 claims description 12
- 238000007493 shaping process Methods 0.000 claims description 6
- 239000007788 liquid Substances 0.000 claims description 4
- 230000000694 effects Effects 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 6
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000006073 displacement reaction Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 7
- 238000003466 welding Methods 0.000 description 6
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000010438 heat treatment Methods 0.000 description 1
- 238000012805 post-processing Methods 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D3/00—Straightening or restoring form of metal rods, metal tubes, metal profiles, or specific articles made therefrom, whether or not in combination with sheet metal parts
- B21D3/10—Straightening or restoring form of metal rods, metal tubes, metal profiles, or specific articles made therefrom, whether or not in combination with sheet metal parts between rams and anvils or abutments
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D—WORKING OR PROCESSING OF SHEET METAL OR METAL TUBES, RODS OR PROFILES WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21D43/00—Feeding, positioning or storing devices combined with, or arranged in, or specially adapted for use in connection with, apparatus for working or processing sheet metal, metal tubes or metal profiles; Associations therewith of cutting devices
- B21D43/02—Advancing work in relation to the stroke of the die or tool
- B21D43/04—Advancing work in relation to the stroke of the die or tool by means in mechanical engagement with the work
Abstract
The present invention relates to one kind communication tower tuning DC waterline, including the feeding moulding bed being arranged in juxtaposition, straightening processing platform and blanking moulding bed, the feeding moulding bed and blanking moulding bed are fixed on the both sides of straightening processing platform, material stock moulding bed is fixed with the inside of blanking moulding bed, the inner side of material stock moulding bed is equipped with truck mobile device, the inner side of the feeding moulding bed is fixed with tower transfer device at right end, the interior Slideslip of straightening processing platform is provided with two tower fixing devices, the side of tower fixing device is equipped with tower mobile device, straightening processing platform front and rear sides are equipped with tower hydraulic centering device, the top of straightening processing platform is equipped with tower machine straightening device.The communication tower tuning DC line structure of the present invention is novel, can be by the batched communication tower straightening on feeding moulding bed, handling apparatus need not be reused in overall process, the advantages of communication tower whole-process automatic can be run in feeding, displacement, blanking, improve production efficiency.
Description
Technical field
The present invention relates to one kind communication tower tuning DC waterline.
Background technology
, it is necessary to various annexes be welded at steel pipe both ends and middle part, in weld job process in communication tower manufacturing enterprise
In, welding deformation can occur for steel pipe.Conventional process steel-pipe welding deformation way be:Using heating straightening after steel-pipe welding deformation
Cool down while straightening or use jack directly apply external force straightening.Technical merit requirement so to welder is excessive,
And speed of welding is low.Therefore a kind of a kind of communication tower tuning DC waterline of rapid welding post processing steel-pipe welding deformation is sought
It is particularly important that.
The content of the invention
In order to solve the above technical problems, the present invention provides a kind of communication tower tuning DC waterline.
The communication tower tuning DC waterline of the present invention, including feeding moulding bed, straightening processing platform and the blanking being arranged in juxtaposition
Moulding bed, the feeding moulding bed and blanking moulding bed are fixed on the both sides of straightening processing platform, material stock are fixed with the inside of blanking moulding bed
Moulding bed, the inner side of material stock moulding bed are equipped with truck mobile device, and the inner side of the feeding moulding bed is fixed with tower at right end and turns
Shipping unit, the interior Slideslip of straightening processing platform are provided with two tower fixing devices, and the side of tower fixing device is equipped with
Tower mobile device, straightening processing platform front and rear sides are equipped with tower hydraulic centering device, are set at the top of straightening processing platform
There is tower machine straightening device.
The communication tower tuning DC waterline of the present invention, the feeding moulding bed include the first chassis, and the first chassis is equipped with two
A the first support beam that can be slid back and forth, the both ends bottom of the first support beam are connected with slip by the first support column and set
The first support bottom girder on the first chassis is put, be equipped with that both ends are fixed by axle chain wheel in the first support beam first pushes away
Plate conveyor chain, the right end side of the first push plate conveyor chain is equipped with to push away with the co-axially fixed travelling gear of axle chain wheel, first
V-shaped groove is equipped with right end at the top of first support beam of plate conveyor chain, the side of one of V-shaped groove is equipped with first and passes
Sensor;The inner side of first chassis is equipped with the first motor, and the output shaft of the first motor is equipped with the first master gear, the first motor
Side above be equipped with the first drive link, the middle part of the first drive link is equipped with idler gear, idler gear and the first main tooth
Connected between wheel by chain, the both ends of the first drive link are respectively and fixedly provided with the drive link tooth being connected by chain with travelling gear
Wheel.
The communication tower tuning DC waterline of the present invention, the straightening processing platform include the second support beam, the second support
Column and bottom plate, the both ends bottom of the second support beam are fixedly connected by two the second support columns with bottom plate respectively;The tower
Machine straightening device includes being fixed on the second motor at the top of the second support beam, and the second motor connects the first driving wire by chain
Thick stick, is connected with two swivel nuts on the outer wall of the first turn-screw, the bottom of swivel nut is respectively and fixedly provided with straightening hydraulic cylinder fixed seat, straightening
The top of hydraulic cylinder fixed seat is fixed on the bottom face of the second support beam by two straightening tracks, and straightening hydraulic cylinder is fixed
Straightening hydraulic cylinder is fixed with inside the bottom face of seat, the hydraulic stem bottom of straightening hydraulic cylinder is connected with straightening shaping wheel;The pipe
Tower fixing device includes static housing, and the bottom of static housing is fixed on the bottom by the slide plate and the first slide of mutual cooperation
On the top end face of plate, the lower section of slide plate is equipped with the second turn-screw connected by feed screw nut, the end of the second turn-screw
Be connected with the 3rd motor, the top of the static housing is equipped with end cap, on end cap activity be plugged with band-type brake, the inside of static housing
Hydraulic cylinder is tensed equipped with the band-type brake being connected with band-type brake, the both sides of band-type brake tension hydraulic cylinder are equipped with the end cap being connected with end cap and hold out against
Hydraulic cylinder;The tower mobile device includes the firm banking being fixed on bottom plate, and rotation liquid is hinged with the top of firm banking
Cylinder pressure, the hydraulic stem top of rotational hydraulic cylinder are hinged with swing arm;The tower hydraulic centering device includes being fixed on the second support
Centering hydraulic cylinder on column side wall, the hydraulic stem inner termination of centering hydraulic cylinder are connected with push plate.
The communication tower tuning DC waterline of the present invention, the blanking moulding bed include front and rear two bottom frameworks being arranged symmetrically,
The top of bottom framework is equipped with the second support bottom girder that can be slid back and forth, and the top of the second support bottom girder is connected by the 3rd support column
The 3rd support beam is connect, the 3rd support beam is equipped with the second push plate conveyor chain, the end side of the second push plate conveyor chain
Second drive link is connected by chain, the side of the second drive link is connected with the 4th motor by chain.
The communication tower tuning DC waterline of the present invention, the material stock moulding bed include the second chassis, and the second chassis is equipped with energy
The central frame enough to horizontally slip, is fixed with top frame at the top of central frame;The truck mobile device is included in being fixed on
Between base of frame rack attached plate, rack attached plate is equipped with driving rack, gear is engaged with driving rack, and the lower section of gear is consolidated
Surely there is truck mobile motor, the output shaft of truck mobile motor is fixedly connected with gear.
The communication tower tuning DC waterline of the present invention, the tower transfer device include fixed frame, are slided on fixed frame
It is dynamic to be provided with sliding frame, the transverse shifting cylinder being connected with sliding frame, slider bar are fixed with the left side of fixed frame
The top slide of frame is provided with two tower lift stands, and the bottom of tower lift stand is respectively and fixedly provided with jacking cylinder.
Beneficial effects of the present invention are compared with prior art:The communication tower tuning DC line structure of the present invention is novel,
Batched communication tower straightening on feeding moulding bed need not can be reused handling apparatus, communication tower is upper in overall process
Whole-process automatic it can be run when material, displacement, blanking, therefore present invention communication tower tuning DC waterline makes with handling apparatus is reduced
With frequency, the advantages of improving production efficiency.
Brief description of the drawings
Fig. 1 is a kind of structure diagram of communication tower tuning DC waterline described in the embodiment of the present invention;
Fig. 2 be feeding moulding bed in a kind of communication tower tuning DC waterline described in the embodiment of the present invention structure diagram it
One;
Fig. 3 be feeding moulding bed in a kind of communication tower tuning DC waterline described in the embodiment of the present invention structure diagram it
Two;
Fig. 4 is the structural representation of straightening processing platform in a kind of communication tower tuning DC waterline described in the embodiment of the present invention
Figure;
Fig. 5 is the structural representation of tower machine straightening device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention
Figure;
Fig. 6 is that tower fixing device is processed with straightening in a kind of communication tower tuning DC waterline described in the embodiment of the present invention
The attachment structure schematic diagram of platform;
Fig. 7 is the sectional view of tower fixing device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention;
Fig. 8 is the structural representation of tower mobile device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention
Figure;
Fig. 9 is the structure of tower hydraulic centering device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention
Schematic diagram;
Figure 10 is the structure diagram of blanking moulding bed in a kind of communication tower tuning DC waterline described in the embodiment of the present invention;
Figure 11 is the structure diagram of material stock moulding bed in a kind of communication tower tuning DC waterline described in the embodiment of the present invention;
Figure 12 is that the structure of truck mobile device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention is shown
It is intended to;
Figure 13 is that the structure of tower transfer device in a kind of communication tower tuning DC waterline described in the embodiment of the present invention is shown
It is intended to.
In figure:
1st, feeding moulding bed;101st, the first chassis;102nd, the first support beam;103rd, the first support column;104th, the first support
Bottom girder;105th, the first push plate conveyor chain;106th, travelling gear;107th, V-shaped groove;108th, first sensor;109th, the first motor;
110th, the first master gear;111st, the first drive link;112nd, idler gear;113rd, drive link gear;2nd, straightening processing platform;201、
Second support beam;202nd, the second support column;203rd, bottom plate;3rd, blanking moulding bed;301st, bottom framework;302nd, the second support bottom girder;
303rd, the 3rd support column;304th, the 3rd support beam;305th, the second push plate conveyor chain;306th, the second drive link;307th, the 4th
Motor;4th, material stock moulding bed;401st, the second chassis;402nd, central frame;403rd, top frame;5th, truck mobile device;501st, rack
Attached plate;502nd, driving rack;503rd, gear;504th, truck mobile motor;6th, tower transfer device;601st, fixed frame;602、
Sliding frame;603rd, transverse shifting cylinder;604th, tower lift stand;605th, jacking cylinder;7th, tower fixing device;701st, it is fixed
Babinet;702nd, slide plate;703rd, the first slide;704th, the second turn-screw;705th, the 3rd motor;706th, end cap;707th, band-type brake;
708th, band-type brake tenses hydraulic cylinder;709th, end cap holds out against hydraulic cylinder;8th, tower mobile device;801st, firm banking;802nd, liquid is rotated
Cylinder pressure;803rd, swing arm;9th, tower hydraulic centering device;901st, centering hydraulic cylinder;902nd, push plate;10th, tower machine straightening device;
1001st, the second motor;1002nd, the first turn-screw;1003rd, swivel nut;1004th, straightening hydraulic cylinder fixed seat;1005th, straightening rail
Road;1006th, straightening hydraulic cylinder;1007th, straightening shaping wheel.
Embodiment
With reference to the accompanying drawings and examples, the embodiment of the present invention is described in further detail.Implement below
Example is used to illustrate the present invention, but is not limited to the scope of the present invention.
As shown in figures 1-13, a kind of communication tower tuning DC waterline, including be arranged in juxtaposition feeding moulding bed 1, straightening processing
Platform 2 and blanking moulding bed 3, the feeding moulding bed 1 and blanking moulding bed 3 are fixed on the both sides of straightening processing platform 2, blanking moulding bed 3
Inner side be fixed with material stock moulding bed 4, the inner side of material stock moulding bed 4 is equipped with truck mobile device 5, and the inner side of the feeding moulding bed 1 is leaned on
Tower transfer device 6 is fixed with nearly right end, the interior Slideslip of straightening processing platform 2 is provided with two tower fixing devices 7, pipe
The side of tower fixing device 7 is equipped with tower mobile device 8, and 2 front and rear sides of straightening processing platform are equipped with tower hydraulic centralizing
Device 9, the top of straightening processing platform 2 are equipped with tower machine straightening device 10.
The communication tower tuning DC waterline of the present invention, the feeding moulding bed 1 include the first chassis 101, on the first chassis 101
Equipped with two the first support beams 102 that can be slid back and forth, the both ends bottom of the first support beam 102 passes through the first support column
103 are connected with the first support bottom girder 104 being slidably arranged on the first chassis 101, and both ends are equipped with the first support beam 102
The the first push plate conveyor chain 105 fixed by axle chain wheel, the right end side of the first push plate conveyor chain 105 is equipped with and shaft
The travelling gear 106 that sprocket coaxiality is fixed, is equipped with V-shaped groove 107, one of V at the right end at the top of the first support beam 102
The side of shape groove 107 is equipped with first sensor 108;The inner side of first chassis 101 is equipped with the first motor 109, the first motor
109 output shaft is equipped with the first master gear 110, and the first drive link 111 is equipped with above the side of the first motor 109, and first passes
The middle part of lever 111 is equipped with idler gear 112, is connected between 112 and first master gear 110 of idler gear by chain,
The both ends of first drive link 111 are respectively and fixedly provided with the drive link gear 113 being connected by chain with travelling gear 106.
The communication tower tuning DC waterline of the present invention, the straightening processing platform 2 include the second support beam 201, second
Support column 202 and bottom plate 203, the both ends bottom of the second support beam 201 pass through two the second support columns 202 and bottom plate respectively
203 are fixedly connected;The tower machine straightening device 10 includes the second motor 1001 for being fixed on the top of the second support beam 202, the
Two motors 1001 connect the first turn-screw 1002 by chain, and two swivel nuts are connected with the outer wall of the first turn-screw 1002
1003, the bottom of swivel nut 1003 is respectively and fixedly provided with straightening hydraulic cylinder fixed seat 1004, and the top of straightening hydraulic cylinder fixed seat 1004 leads to
Cross two straightening tracks 1005 to be fixed on the bottom face of the second support beam 201, the bottom of straightening hydraulic cylinder fixed seat 1004
Straightening hydraulic cylinder 1006 is fixed with inside face, the hydraulic stem bottom of straightening hydraulic cylinder 1006 is connected with straightening shaping wheel 1007;Institute
Stating tower fixing device 7 includes static housing 701, and the bottom of static housing 701 is slided by the slide plate 702 and first of mutual cooperation
Rail 703 is fixed on the top end face of the bottom plate 203, and the lower section of slide plate 702 is equipped with the second transmission connected by feed screw nut
Leading screw 704, the end of the second turn-screw 704 are connected with the 3rd motor 705, and the top of the static housing 701 is equipped with end cap
706, on end cap 706 activity be plugged with band-type brake 707, the band-type brake being connected with band-type brake 707 that is internally provided with of static housing 701 tenses liquid
Cylinder pressure 708, the both sides of band-type brake tension hydraulic cylinder 708 are equipped with the end cap being connected with end cap 706 and hold out against hydraulic cylinder 709;The pipe
Tower mobile device 8 includes the firm banking 801 being fixed on bottom plate 203, and the top of firm banking 801 is hinged with rotational hydraulic cylinder
802, the hydraulic stem top of rotational hydraulic cylinder 802 is hinged with swing arm 803;The tower hydraulic centering device 9 includes being fixed on the
Centering hydraulic cylinder 901 on two support columns, 202 side wall, the hydraulic stem inner termination of centering hydraulic cylinder 901 are connected with push plate 902.
The communication tower tuning DC waterline of the present invention, the blanking moulding bed 3 include front and rear two bottom frameworks being arranged symmetrically
301, the top of bottom framework 301 is equipped with the second support bottom girder 302 that can be slid back and forth, and the top of the second support bottom girder 302 leads to
To cross the 3rd support column 303 and connect the 3rd support beam 304, the 3rd support beam 304 is equipped with the second push plate conveyor chain 305,
The end side of second push plate conveyor chain 305 connects the second drive link 306 by chain, and the side of the second drive link 306 leads to
Cross chain and be connected with the 4th motor 307.
The communication tower tuning DC waterline of the present invention, the material stock moulding bed 4 include the second chassis 401, on the second chassis 401
Equipped with the central frame 402 that can be horizontally slipped, the top of central frame 402 is fixed with top frame 403;The truck movement dress
Putting 5 includes being fixed on the rack attached plate 501 of 402 bottom of central frame, and rack attached plate 501 is equipped with driving rack 502, driving cog
Gear 503 is engaged with bar 502, the lower section of gear 503 is fixed with truck mobile motor 504, the output of truck mobile motor 504
Axis is fixedly connected with gear 503.
The communication tower tuning DC waterline of the present invention, the tower transfer device 6 include fixed frame 601, fixed frame
Slided on 601 and be provided with sliding frame 602, the transverse direction being connected with sliding frame 602 is fixed with the left side of fixed frame 601
Mobile cylinder 603, the top slide of sliding frame 602 are provided with two tower lift stands 604, the bottom of tower lift stand 604
It is respectively and fixedly provided with jacking cylinder 605.
The processing step of the communication tower tuning DC waterline of the present invention is as follows:
Step 1: the communication tube tower crane for needing straightening is transported to feeding moulding bed using handling apparatus, push plate chain is placed on
Between push plate.
Step 2: starting feeding moulding bed motor, push plate chain is rotated is moved to the wait of V-groove feeding by communication tower
Position.
Step 3: communication tower is moved at the V-groove of feeding moulding bed, first sensor senses communication tower in place
Afterwards, signal is passed into PLC control system.
Step 4: control signal is transmitted to tower hydraulic centering device by PLC control system, the centering hydraulic cylinder at both ends is at the same time
Push plate is promoted, push plate promotes communication tower both ends again, shifts communication tower onto center in.
Step 5: after communication tower is located at center, tower transfer device is moved to logical in the promotion of transverse cylinder
Below fuse tube tower position.
Step 6: after tower transfer device is moved to below communication tower position, jacking cylinder rises, and drives tower lift stand
Movement upwards, communication tower is lifted.
Step 7: under the promotion of transverse cylinder, communication tower is moved in straightening processing platform for tower transfer device
Portion.
Step 8: the jacking cylinder of tower transfer device declines, communication tower is placed on above tower fixing device.
Step 9: the both ends band-type brake of tower fixing device is opened communication tower is fixed, then tower fixing device
End cap holds out against hydraulic cylinder and pushes up end cap, and end cap pushes up communication tower.
Step 10: tower machine straightening device is moved to appropriate location, then straightening hydraulic cylinder pushes down on straightening shaping wheel, adjusts
Straight shaping wheel is pressed onto communication tower deformation position again, by the tower deformation position straightening that communicates.
Step 11: after communication tower straightening, the straightening hydraulic cylinder of tower machine straightening device is retracted, the end of tower fixing device
The tight hydraulic cylinder of caping declines, and drives end cap to decline, and band-type brake, which is closed, unclamps communication tower.The rotational hydraulic cylinder of blanking device is beaten
Open, promote swing arm, swing arm promotes communication tower to be moved to from straightening processing platform above blanking moulding bed.
Step 12: blanking moulding bed motor operates, push plate chains advances communication tower expects that downwards moulding bed slope position moves.
Step 13: truck mobile device promotes material stock moulding bed to be moved to the slope position of blanking moulding bed, communication tube is waited
Tower is slided into above material stock moulding bed from slope position.
Step 14: after communication tower is slided on material stock moulding bed, truck mobile device promotes material stock moulding bed to reset, straightening
Good communication tower waits handling apparatus to transport.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, without departing from the technical principles of the invention, some improvement and modification, these improvements and modifications can also be made
Also it should be regarded as protection scope of the present invention.
Claims (6)
1. one kind communication tower tuning DC waterline, including feeding moulding bed (1), straightening processing platform (2) and the blanking being arranged in juxtaposition
Moulding bed (3), it is characterised in that:The feeding moulding bed (1) and blanking moulding bed (3) are fixed on the both sides of straightening processing platform (2), under
Be fixed with material stock moulding bed (4) on the inside of material moulding bed (3), the inner side of material stock moulding bed (4) is equipped with truck mobile device (5), it is described on
The inner side of material moulding bed (1) is fixed with tower transfer device (6) at right end, and the interior Slideslip of straightening processing platform (2) is set
There are two tower fixing devices (7), the side of tower fixing device (7) is equipped with tower mobile device (8), straightening processing platform
(2) front and rear sides are equipped with tower hydraulic centering device (9), and the top of straightening processing platform (2) is equipped with tower machine straightening device
(10)。
2. communication tower tuning DC waterline according to claim 1, it is characterised in that:The feeding moulding bed (1) includes the
One chassis (101), the first chassis (101) are equipped with two the first support beams (102) that can be slid back and forth, and the first support is horizontal
The both ends bottom of beam (102) is connected with the first support being slidably arranged on the first chassis (101) by the first support column (103)
Bottom girder (104), is equipped with the first push plate conveyor chain that both ends are fixed by axle chain wheel in the first support beam (102)
(105), the right end side of the first push plate conveyor chain (105) be equipped with the co-axially fixed travelling gear of axle chain wheel (106), the
V-shaped groove (107) is equipped with right end at the top of one support beam (102), the side of one of V-shaped groove (107) is equipped with first
Sensor (108);The inner side of first chassis (101) is equipped with the first motor (109), on the output shaft of the first motor (109)
Equipped with the first master gear (110), the first drive link (111), the first drive link are equipped with above the side of the first motor (109)
(111) middle part is equipped with idler gear (112), is connected between idler gear (112) and the first master gear (110) by chain
Connect, the both ends of the first drive link (111) are respectively and fixedly provided with the drive link gear (113) being connected by chain with travelling gear (106).
3. communication tower tuning DC waterline according to claim 1, it is characterised in that:Straightening processing platform (2) bag
Include the second support beam (201), the second support column (202) and bottom plate (203), the both ends bottom point of the second support beam (201)
It is not fixedly connected by two the second support columns (202) with bottom plate (203);The tower machine straightening device (10) includes being fixed on the
The second motor (1001) at the top of two support beams (202), the second motor (1001) connect the first turn-screw by chain
(1002), two swivel nuts (1003) are connected with the outer wall of the first turn-screw (1002), the bottom of swivel nut (1003) is fixed
There is straightening hydraulic cylinder fixed seat (1004), the top of straightening hydraulic cylinder fixed seat (1004) is solid by two straightening tracks (1005)
It is scheduled on the bottom face of the second support beam (201), straightening is fixed with inside the bottom face of straightening hydraulic cylinder fixed seat (1004)
Hydraulic cylinder (1006), the hydraulic stem bottom of straightening hydraulic cylinder (1006) are connected with straightening shaping wheel (1007);The tower is fixed
Device (7) includes static housing (701), and the bottom of static housing (701) passes through the slide plate (702) of mutual cooperation and the first slide
(703) it is fixed on the top end face of the bottom plate (203), the lower section of slide plate (702) is equipped with connected by feed screw nut second
Turn-screw (704), the end of the second turn-screw (704) are connected with the 3rd motor (705), the static housing (701)
Top is equipped with end cap (706), on end cap (706) activity be plugged with band-type brake (707), static housing (701) is internally provided with embracing
The band-type brake of lock (707) connection tenses hydraulic cylinder (708), and the both sides that band-type brake tenses hydraulic cylinder (708) are equipped with end cap (706) even
The end cap connect holds out against hydraulic cylinder (709);The tower mobile device (8) includes the firm banking being fixed on bottom plate (203)
(801), rotational hydraulic cylinder (802), the hydraulic stem top hinge of rotational hydraulic cylinder (802) are hinged with the top of firm banking (801)
It is connected to swing arm (803);The tower hydraulic centering device (9) includes the centering liquid being fixed on the second support column (202) side wall
Cylinder pressure (901), the hydraulic stem inner termination of centering hydraulic cylinder (901) are connected with push plate (902).
4. communication tower tuning DC waterline according to claim 1, it is characterised in that:Before the blanking moulding bed (3) includes
Two bottom frameworks (301) being arranged symmetrically afterwards, the top of bottom framework (301) are equipped with the second support bottom girder that can be slid back and forth
(302), second support bottom girder (302) top by the 3rd support column (303) connect the 3rd support beam (304), the 3rd
Support crossbeam (304) is equipped with the second push plate conveyor chain (305), and the end side of the second push plate conveyor chain (305) passes through chain
Bar connects the second drive link (306), and the side of the second drive link (306) is connected with the 4th motor (307) by chain.
5. communication tower tuning DC waterline according to claim 1, it is characterised in that:The material stock moulding bed (4) includes the
Two chassis (401), the second chassis (401) are equipped with the central frame (402) that can be horizontally slipped, the top of central frame (402)
Portion is fixed with top frame (403);The truck mobile device (5) includes being fixed on the rack attached plate of central frame (402) bottom
(501), rack attached plate (501) is equipped with driving rack (502), and gear (503), gear are engaged with driving rack (502)
(503) truck mobile motor (504), output shaft and the fixed company of gear (503) of truck mobile motor (504) are fixed with below
Connect.
6. communication tower tuning DC waterline according to claim 1, it is characterised in that:Tower transfer device (6) bag
Fixed frame (601) is included, is slided on fixed frame (601) and is provided with sliding frame (602), the left side of fixed frame (601)
On be fixed with the transverse shifting cylinder (603) being connected with sliding frame (602), the top slide of sliding frame (602) is provided with
Two tower lift stands (604), the bottom of tower lift stand (604) are respectively and fixedly provided with jacking cylinder (605).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711086048.9A CN107913924B (en) | 2017-11-07 | 2017-11-07 | Communication pipe tower alignment assembly line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711086048.9A CN107913924B (en) | 2017-11-07 | 2017-11-07 | Communication pipe tower alignment assembly line |
Publications (2)
Publication Number | Publication Date |
---|---|
CN107913924A true CN107913924A (en) | 2018-04-17 |
CN107913924B CN107913924B (en) | 2024-02-02 |
Family
ID=61896018
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711086048.9A Active CN107913924B (en) | 2017-11-07 | 2017-11-07 | Communication pipe tower alignment assembly line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107913924B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109809169A (en) * | 2019-03-05 | 2019-05-28 | 威海福瑞机器人有限公司 | A kind of infusion apparatus feeding device |
CN110102598A (en) * | 2019-04-25 | 2019-08-09 | 扬州工业职业技术学院 | A kind of automatic automobile metal plate correction system |
CN110918695A (en) * | 2019-10-11 | 2020-03-27 | 江苏科技大学 | Slender rod piece double-side straightening device and straightening method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002307107A (en) * | 2001-04-13 | 2002-10-22 | Daifuku Co Ltd | Apparatus for straightening bar-shaped member |
CN202910115U (en) * | 2012-10-26 | 2013-05-01 | 天津赛瑞机器设备有限公司 | Full-automatic horizontal-type pressure straightening machine |
CN104128395A (en) * | 2014-07-29 | 2014-11-05 | 中国重型机械研究院股份公司 | Horizontal type pressure straightening machine |
CN204503850U (en) * | 2015-04-01 | 2015-07-29 | 莫伟帅 | A kind of large hydraulic straightener device |
CN204975784U (en) * | 2015-08-18 | 2016-01-20 | 江苏新扬子造船有限公司 | Small -bore straight tube and sleeve pipe manual weld assembly line |
US20160288849A1 (en) * | 2015-04-01 | 2016-10-06 | Guangzhou Mino Automotive Equipment Co., Ltd. | Ground sliding type flexible framing system |
CN207463874U (en) * | 2017-11-07 | 2018-06-08 | 河北北方伟业钢结构制造有限公司 | A kind of communication tower tuning DC waterline |
-
2017
- 2017-11-07 CN CN201711086048.9A patent/CN107913924B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002307107A (en) * | 2001-04-13 | 2002-10-22 | Daifuku Co Ltd | Apparatus for straightening bar-shaped member |
CN202910115U (en) * | 2012-10-26 | 2013-05-01 | 天津赛瑞机器设备有限公司 | Full-automatic horizontal-type pressure straightening machine |
CN104128395A (en) * | 2014-07-29 | 2014-11-05 | 中国重型机械研究院股份公司 | Horizontal type pressure straightening machine |
CN204503850U (en) * | 2015-04-01 | 2015-07-29 | 莫伟帅 | A kind of large hydraulic straightener device |
US20160288849A1 (en) * | 2015-04-01 | 2016-10-06 | Guangzhou Mino Automotive Equipment Co., Ltd. | Ground sliding type flexible framing system |
CN204975784U (en) * | 2015-08-18 | 2016-01-20 | 江苏新扬子造船有限公司 | Small -bore straight tube and sleeve pipe manual weld assembly line |
CN207463874U (en) * | 2017-11-07 | 2018-06-08 | 河北北方伟业钢结构制造有限公司 | A kind of communication tower tuning DC waterline |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109809169A (en) * | 2019-03-05 | 2019-05-28 | 威海福瑞机器人有限公司 | A kind of infusion apparatus feeding device |
CN110102598A (en) * | 2019-04-25 | 2019-08-09 | 扬州工业职业技术学院 | A kind of automatic automobile metal plate correction system |
CN110102598B (en) * | 2019-04-25 | 2021-01-01 | 扬州工业职业技术学院 | Automatic change car panel beating correction system |
CN110918695A (en) * | 2019-10-11 | 2020-03-27 | 江苏科技大学 | Slender rod piece double-side straightening device and straightening method |
CN110918695B (en) * | 2019-10-11 | 2021-04-27 | 江苏科技大学 | Slender rod piece double-side straightening device and straightening method |
Also Published As
Publication number | Publication date |
---|---|
CN107913924B (en) | 2024-02-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107913924A (en) | One kind communication tower tuning DC waterline | |
CN210392756U (en) | Automatic cart based lifting machine of unloading | |
CN107914091A (en) | One kind communication tower automatic welding assembly line | |
CN207463874U (en) | A kind of communication tower tuning DC waterline | |
CN104671112A (en) | Sleeper stacker crane | |
CN207372519U (en) | A kind of communication tower automatic welding assembly line | |
CN106081642A (en) | Tire high speed unstacker and de-stacking method thereof | |
CN204778655U (en) | Pile high car | |
CN204529149U (en) | Sleeper stacker | |
CN104058353B (en) | A kind of hot-rolling Handling device | |
CN115650041A (en) | Detection maintenance workbench for bogie of urban rail transit electric bus | |
CN202283934U (en) | Frame assembly capable of moving loaded goods and transport machine equipped with frame | |
CN201442037U (en) | Heavy-plate cooling-bed double-direction feeding device | |
WO2014201978A1 (en) | Trolley replacing device and trolley replacing method | |
CN205114879U (en) | Special hoist of aluminium alloy with lift dolly | |
CN203640764U (en) | Foldable mounting forklift | |
CN205932490U (en) | High -speed unstacker of tire | |
CN201390774Y (en) | Small-sized wire rod coil loading device | |
CN202175367U (en) | Four-link transport vehicle for rolled cloth | |
CN105752885B (en) | Transfer robot bicycle frame device with collapsible rhaeboscelia | |
CN202186678U (en) | Monocrystal crucible carrying trolley | |
CN217972485U (en) | Lifting mechanism and AGV dolly | |
CN201376794Y (en) | Movable type belt loading conveyor | |
CN105752884B (en) | Vehicle mounted type can climb vehicle transfer robot | |
CN116174637B (en) | Forging equipment for secondary utilization of waste steel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |