CN107907759A - The electricity monitoring system and method for power equipment - Google Patents

The electricity monitoring system and method for power equipment Download PDF

Info

Publication number
CN107907759A
CN107907759A CN201711021110.6A CN201711021110A CN107907759A CN 107907759 A CN107907759 A CN 107907759A CN 201711021110 A CN201711021110 A CN 201711021110A CN 107907759 A CN107907759 A CN 107907759A
Authority
CN
China
Prior art keywords
power
electricity
equipment
characteristic
power consumption
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711021110.6A
Other languages
Chinese (zh)
Inventor
赵威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Information and Telecommunication Branch of State Grid Heilongjiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Information and Telecommunication Branch of State Grid Heilongjiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Information and Telecommunication Branch of State Grid Heilongjiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201711021110.6A priority Critical patent/CN107907759A/en
Publication of CN107907759A publication Critical patent/CN107907759A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Abstract

The present invention relates to a kind of electricity monitoring system and method, is specially a kind of electricity monitoring system and method for anti-electricity-theft power equipment.The present invention is monitored for the electricity for the equipment for repeating identical work daily, including:Data acquisition module, Power system load data and corresponding temporal information for real-time collecting device;Characteristic extracting module, for handling the Power system load data of collection, extracts characteristic;Database, the characteristic set for storage device within each period;Electricity consumption monitoring module, for characteristic of the equipment within the corresponding time in the characteristic of extraction and database to be contrasted, obtains the power consumption parameter of equipment and uses electricity condition;The electricity condition includes working status and electric power whether in the range of given threshold;Power consumption control module, for according to power consumption parameter and with electricity condition, regulation and control instruction to be sent to equipment, determines if that electricity stealing occurs.

Description

The electricity monitoring system and method for power equipment
Technical field
The present invention relates to a kind of electricity monitoring system and method, the electricity monitoring system of more particularly to a kind of power equipment and Method.
Background technology
Managing electric quantity terminal is one of important equipment in electric power management system, positioned at the lowermost layer of whole system, as long as There are information gathering, automatic data logging, remote control, exception monitoring and critical event the function such as to report.Managing electric quantity terminal-pair uses electricity in off-peak hours, Monitoring, the monitoring of power quality in real time, meet the needs of modern electric demand side management and power marketing.
The monitoring of existing electricity it is more by peak clipping, avoid the peak hour and the means such as peak load shifting, but cannot be into for electricity stealing Row monitoring.
The content of the invention
For above-mentioned deficiency, the present invention provides a kind of electricity monitoring system and method for anti-electricity-theft power equipment.
The electricity monitoring system of the power equipment of the present invention, including:
Data acquisition module, Power system load data and corresponding temporal information for real-time collecting device;
Characteristic extracting module, for handling the Power system load data of collection, extracts characteristic;
Database, the characteristic set for storage device within each period;
Electricity consumption monitoring module, for by characteristic of the equipment within the corresponding time in the characteristic of extraction and database Contrasted, obtain the power consumption parameter of equipment and use electricity condition;
The electricity condition includes working status and electric power whether in the range of given threshold;
Power consumption control module, for according to power consumption parameter and with electricity condition, sending regulation and control instruction to equipment, determining if Generation electricity stealing.
Preferably, temporal information is different, its corresponding threshold range is different.
Preferably, the power consumption control module includes:
When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks its true Whether locking equipment has electricity stealing;
When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down equipment Electricity consumption.
Preferably, the power consumption parameter includes active power, reactive power, voltage, electric current and power factor.
The present invention also provides a kind of electricity monitoring method of power equipment, the described method includes:
Data collection steps, Power system load data and corresponding temporal information for real-time collecting device;
Characteristic extraction step, for handling the Power system load data of collection, extracts characteristic;
Data storing steps, the characteristic set for storage device within each period;
Electricity consumption monitoring step, for by characteristic of the equipment within the corresponding time in the characteristic of extraction and database Contrasted, obtain the power consumption parameter of equipment and use electricity condition;
The electricity condition includes working status and electric power whether in the range of given threshold;
Power consumption control step, for according to power consumption parameter and with electricity condition, regulation and control instruction to be sent to equipment.
Preferably, temporal information is different, its corresponding threshold range is different.
Preferably, the power consumption control step includes:
When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks its true Whether locking equipment has electricity stealing;
When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down equipment Electricity consumption.
Preferably, the power consumption parameter includes active power, reactive power, voltage, electric current and power factor.
Above-mentioned technical characteristic can in any suitable manner be combined or substituted by equivalent technical characteristic, as long as can reach To the purpose of the present invention.
The beneficial effects of the present invention are the present invention is monitored for the electricity for the equipment for repeating identical work daily, in number According to the characteristic for the Power system load data that store power equipment of the load within each period in storehouse, in monitoring, obtain The Power system load data of temporal information and power equipment, extracts characteristic;According to the temporal information of acquisition, look in the database To the characteristic in the corresponding period, the characteristic found in the characteristic and database of collection is contrasted, and is determined Whether in the threshold range of setting, control module exports regulation and control instruction, realizes anti-electricity-theft contrast difference according to comparing result.
The minimum value of the threshold range of the present invention is used to determine whether stealing, and the maximum of threshold range is used to determine whether Peak clipping is needed, improves power grid utilization rate.
Brief description of the drawings
Fig. 1 is the principle schematic of the power load monitoring system of the present invention.
Embodiment
Below in conjunction with the attached drawing in the embodiment of the present invention, the technical solution in the embodiment of the present invention is carried out clear, complete Site preparation describes, it is clear that described embodiment is only part of the embodiment of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art obtained on the premise of creative work is not made it is all its His embodiment, belongs to the scope of protection of the invention.
It should be noted that in the case where there is no conflict, the feature in embodiment and embodiment in the present invention can phase Mutually combination.
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings, but not as limiting to the invention.
Illustrating present embodiment with reference to Fig. 1, present embodiment provides a kind of electricity monitoring system of power equipment, including:
Data acquisition module, Power system load data and corresponding temporal information for real-time collecting device;
Characteristic extracting module, for handling the Power system load data of collection, extracts characteristic;
Database, the characteristic set for storage device within each period;
Electricity consumption monitoring module, for by characteristic of the equipment within the corresponding time in the characteristic of extraction and database Contrasted, obtain the power consumption parameter of equipment and use electricity condition;
The electricity condition includes working status and electric power whether in the range of given threshold;
Power consumption control module, for according to power consumption parameter and with electricity condition, regulation and control instruction to be sent to equipment.
Present embodiment is directed to the current monitoring for the equipment for repeating identical work daily, stores load in the database and exists The characteristic of the Power system load data of power equipment in each period, in monitoring, obtains temporal information and power equipment Power system load data, extract characteristic;According to the temporal information of acquisition, the spy in the corresponding period is found in the database Data are levied, the characteristic found in the characteristic and database of collection is contrasted, and determines whether contrast difference is setting Threshold range in, control module exports regulation and control instruction, realizes anti-electricity-theft according to comparing result.
Such as:Monitor cutting machine;
Cutting machine darg content, each action corresponding time and Power system load data are obtained before monitoring, By the storage of its characteristic in the database;
During monitoring, obtain temporal information when monitoring and gather Power system load data in real time, according to temporal information, in data Individual features data are found in storehouse, are contrasted with the characteristic of the Power system load data of collection, difference are obtained, if the difference Value is less than the minimum value of the threshold range of setting, and power consumption control module instruction relevant staff determines whether the cutting machine carries out Stealing.
In preferred embodiment, temporal information is different, its corresponding threshold range is different.
Those skilled in the art can according to the rated power of cutting machine, action and test result given threshold scope, According to peak of power consumption and ebb corresponding time, the scope of given threshold, realizes the control of peak electricity, improves power grid and utilizes Rate.
In preferred embodiment, power consumption control module includes:
When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks its true Whether locking equipment has electricity stealing;
When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down equipment Electricity consumption.
In present embodiment, the minimum value of threshold range is used to determine whether stealing, and the maximum of threshold range is used to sentence It is fixed whether to need peak clipping, improve power grid utilization rate.
In preferred embodiment, the power consumption parameter includes active power, reactive power, voltage, electric current and power factor.
Present embodiment also provides a kind of electricity monitoring method of power equipment, including:
Data collection steps, Power system load data and corresponding temporal information for real-time collecting device;
Characteristic extraction step, for handling the Power system load data of collection, extracts characteristic;
Data storing steps, the characteristic set for storage device within each period;
Electricity consumption monitoring step, for by characteristic of the equipment within the corresponding time in the characteristic of extraction and database Contrasted, obtain the power consumption parameter of equipment and use electricity condition;
The electricity condition includes working status and electric power whether in the range of given threshold;
Power consumption control step, for according to power consumption parameter and with electricity condition, regulation and control instruction to be sent to equipment.
Present embodiment is directed to the current monitoring for the equipment for repeating identical work daily, is store using data storing steps The characteristic of the Power system load data of power equipment of the load within each period, in monitoring, obtains temporal information and electricity The Power system load data of power equipment, extracts characteristic;According to the temporal information of acquisition, the corresponding period is found in the database Interior characteristic, the characteristic found in the characteristic and database of collection are contrasted, and whether determine contrast difference In the threshold range of setting, control module exports regulation and control instruction, realizes anti-electricity-theft according to comparing result.
Such as:Monitor cutting machine;
Cutting machine darg content, each action corresponding time and Power system load data are obtained before monitoring, By the storage of its characteristic in the database;
During monitoring, obtain temporal information when monitoring and gather Power system load data in real time, according to temporal information, in data Individual features data are found in storehouse, are contrasted with the characteristic of the Power system load data of collection, difference are obtained, if the difference Value is less than the minimum value of the threshold range of setting, and power consumption control module instruction relevant staff determines whether the cutting machine carries out Stealing.
In preferred embodiment, temporal information is different, its corresponding threshold range is different.
Those skilled in the art can according to the rated power of cutting machine, action and test result given threshold scope, According to peak of power consumption and ebb corresponding time, the scope of given threshold, realizes the control of peak electricity, improves power grid and utilizes Rate.
In preferred embodiment, the rate-determining steps include:
When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks its true Whether locking equipment has electricity stealing;
When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down equipment Electricity consumption.
In preferred embodiment, the power consumption parameter includes active power, reactive power, voltage, electric current and power factor.
Although the present invention is described herein with reference to specific embodiment, it should be understood that, these realities Apply the example that example is only principles and applications.It should therefore be understood that exemplary embodiment can be carried out Many modifications, and can be designed that other arrangements, the spirit of the invention limited without departing from appended claims And scope.It should be understood that can be by combining different appurtenances different from the described mode of original claim Profit requires and feature specifically described herein.It will also be appreciated that it can be used with reference to the described feature of separate embodiments In other described embodiments.

Claims (8)

  1. A kind of 1. electricity monitoring system of power equipment, it is characterised in that the system comprises:
    Data acquisition module, Power system load data and corresponding temporal information for real-time collecting device;
    Characteristic extracting module, for handling the Power system load data of collection, extracts characteristic;
    Database, the characteristic set for storage device within each period;
    Electricity consumption monitoring module, for characteristic of the equipment in the characteristic of extraction and database within the corresponding time to be carried out Contrast, obtains the power consumption parameter of equipment and uses electricity condition;
    The electricity condition includes working status and electric power whether in the range of given threshold;
    Power consumption control module, for according to power consumption parameter and with electricity condition, sending regulation and control instruction to equipment, determining if to occur Electricity stealing.
  2. 2. the electricity monitoring system of power equipment according to claim 1, it is characterised in that temporal information is different, its is right The threshold range answered is different.
  3. 3. the electricity monitoring system of power equipment according to claim 1 or 2, it is characterised in that the power consumption control mould Block includes:
    When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks it to determine to set It is standby whether to have electricity stealing;
    When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down the electricity consumption of equipment.
  4. 4. the electricity monitoring system of power equipment according to claim 3, it is characterised in that the power consumption parameter includes Work(power, reactive power, voltage, electric current and power factor.
  5. A kind of 5. electricity monitoring method of power equipment, it is characterised in that the described method includes:
    Data collection steps, Power system load data and corresponding temporal information for real-time collecting device;
    Characteristic extraction step, for handling the Power system load data of collection, extracts characteristic;
    Data storing steps, the characteristic set for storage device within each period;
    Electricity consumption monitoring step, for characteristic of the equipment in the characteristic of extraction and database within the corresponding time to be carried out Contrast, obtains the power consumption parameter of equipment and uses electricity condition;
    The electricity condition includes working status and electric power whether in the range of given threshold;
    Power consumption control step, for according to power consumption parameter and with electricity condition, regulation and control instruction to be sent to equipment.
  6. 6. the electricity monitoring method of power equipment according to claim 5, it is characterised in that temporal information is different, its is right The threshold range answered is different.
  7. 7. the electricity monitoring method of the power equipment according to claim 5 or 6, it is characterised in that the power consumption control step Suddenly include:
    When minimum value of the electric power less than given threshold scope, standby signal is sent to relevant staff, asks it to determine to set It is standby whether to have electricity stealing;
    When maximum of the electric power higher than given threshold scope, standby signal is sent to load, asks it to cut down the electricity consumption of equipment.
  8. 8. the electricity monitoring method of power equipment according to claim 7, it is characterised in that the power consumption parameter includes Work(power, reactive power, voltage, electric current and power factor.
CN201711021110.6A 2017-10-26 2017-10-26 The electricity monitoring system and method for power equipment Pending CN107907759A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711021110.6A CN107907759A (en) 2017-10-26 2017-10-26 The electricity monitoring system and method for power equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711021110.6A CN107907759A (en) 2017-10-26 2017-10-26 The electricity monitoring system and method for power equipment

Publications (1)

Publication Number Publication Date
CN107907759A true CN107907759A (en) 2018-04-13

Family

ID=61842486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711021110.6A Pending CN107907759A (en) 2017-10-26 2017-10-26 The electricity monitoring system and method for power equipment

Country Status (1)

Country Link
CN (1) CN107907759A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109727155A (en) * 2018-08-02 2019-05-07 平安科技(深圳)有限公司 Power consumption control method, apparatus, equipment and storage medium based on power quantity predicting
CN110854999A (en) * 2019-11-01 2020-02-28 神华粤电珠海港煤炭码头有限责任公司 Intelligent electric power quantity monitoring system
CN110940852A (en) * 2019-11-05 2020-03-31 江苏三希科技股份有限公司 Anti-cheating electric quantity monitoring method, system and device
CN111443238A (en) * 2020-04-20 2020-07-24 北京智盟信通科技有限公司 Electricity larceny prevention method
CN112185071A (en) * 2020-09-16 2021-01-05 山东莱钢永锋钢铁有限公司 Electrical equipment load early warning method and device and storage equipment
CN113514717A (en) * 2021-04-22 2021-10-19 微企(天津)信息技术有限公司 Non-invasive power load monitoring system
CN116777121A (en) * 2023-08-18 2023-09-19 武汉振铭科技发展有限公司 Illegal electricity consumption checking method based on big data, storage medium and electronic equipment

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103001230A (en) * 2012-11-16 2013-03-27 天津大学 Non-invasive power load monitoring and decomposing current mode matching method
CN103792420A (en) * 2014-01-26 2014-05-14 威胜集团有限公司 Electricity larceny preventing and electricity utilization monitoring method based on load curves
CN104184214A (en) * 2014-09-12 2014-12-03 四川省科本哈根能源科技有限公司 Monitoring method for building electrical loads
CN105067857A (en) * 2015-08-21 2015-11-18 南方电网科学研究院有限责任公司 Electricity consumption information acquisition system and analysis method
CN105807111A (en) * 2014-12-31 2016-07-27 中国电信股份有限公司 Electricity stealing load control method of electricity facility, intelligent electricity management device and system
CN106685086A (en) * 2017-01-19 2017-05-17 国网山东省电力公司邹城市供电公司 Remote power utilization management system
CN106780112A (en) * 2016-11-28 2017-05-31 国网山东省电力公司济宁供电公司 Electric service interactive system and method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103001230A (en) * 2012-11-16 2013-03-27 天津大学 Non-invasive power load monitoring and decomposing current mode matching method
CN103792420A (en) * 2014-01-26 2014-05-14 威胜集团有限公司 Electricity larceny preventing and electricity utilization monitoring method based on load curves
CN104184214A (en) * 2014-09-12 2014-12-03 四川省科本哈根能源科技有限公司 Monitoring method for building electrical loads
CN105807111A (en) * 2014-12-31 2016-07-27 中国电信股份有限公司 Electricity stealing load control method of electricity facility, intelligent electricity management device and system
CN105067857A (en) * 2015-08-21 2015-11-18 南方电网科学研究院有限责任公司 Electricity consumption information acquisition system and analysis method
CN106780112A (en) * 2016-11-28 2017-05-31 国网山东省电力公司济宁供电公司 Electric service interactive system and method
CN106685086A (en) * 2017-01-19 2017-05-17 国网山东省电力公司邹城市供电公司 Remote power utilization management system

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109727155A (en) * 2018-08-02 2019-05-07 平安科技(深圳)有限公司 Power consumption control method, apparatus, equipment and storage medium based on power quantity predicting
WO2020024534A1 (en) * 2018-08-02 2020-02-06 平安科技(深圳)有限公司 Power consumption control method, apparatus, and device based on electric quantity prediction, and storage medium
CN110854999A (en) * 2019-11-01 2020-02-28 神华粤电珠海港煤炭码头有限责任公司 Intelligent electric power quantity monitoring system
CN110940852A (en) * 2019-11-05 2020-03-31 江苏三希科技股份有限公司 Anti-cheating electric quantity monitoring method, system and device
CN111443238A (en) * 2020-04-20 2020-07-24 北京智盟信通科技有限公司 Electricity larceny prevention method
CN112185071A (en) * 2020-09-16 2021-01-05 山东莱钢永锋钢铁有限公司 Electrical equipment load early warning method and device and storage equipment
CN112185071B (en) * 2020-09-16 2023-02-17 山东莱钢永锋钢铁有限公司 Electrical equipment load early warning method and device and storage equipment
CN113514717A (en) * 2021-04-22 2021-10-19 微企(天津)信息技术有限公司 Non-invasive power load monitoring system
CN116777121A (en) * 2023-08-18 2023-09-19 武汉振铭科技发展有限公司 Illegal electricity consumption checking method based on big data, storage medium and electronic equipment
CN116777121B (en) * 2023-08-18 2023-11-03 武汉振铭科技发展有限公司 Illegal electricity consumption checking method based on big data, storage medium and electronic equipment

Similar Documents

Publication Publication Date Title
CN107907759A (en) The electricity monitoring system and method for power equipment
CN108665186B (en) Distribution transformer overload power failure monitoring method and device based on metering automation system
CN115498640B (en) Micro-grid energy control method and system based on virtual power plant
CN103701212A (en) Method and system for monitoring and analyzing power grid safety and stability control device
CN107703854A (en) power load monitoring system and method
CN112564179B (en) Method, system, device and medium for improving and optimizing power distribution network
CN202550669U (en) Data acquisition system for power equipment
CN103545921A (en) Urban distribution transformer area autonomous control optimization power system and monitoring system thereof
CN112467879A (en) Intelligent monitoring system, method and equipment for park energy
CN113806420A (en) Power grid data monitoring method and device
CN115619291B (en) Super capacitor hybrid energy storage management system based on data analysis
CN106558881B (en) A kind of cloud electric power energy-saving control method based on expert tactics diagnosis
CN112600309B (en) Low-voltage power distribution intelligent diagnosis system with wave recording function
CN110277835B (en) Low-voltage user overvoltage risk monitoring method based on electricity utilization information acquisition system
CN111654112B (en) Reactive compensation capacitor early warning method, device and system
CN207442461U (en) A kind of power consuming administrative system
CN114614564A (en) Multi-channel low-voltage shunt monitoring device based on HPLC communication and topology identification method
KR102222847B1 (en) Hierarchical type power control system
CN105449856A (en) Method for monitoring electric power device in long distance
CN115665590B (en) Internet of things data acquisition system and method based on eSIM card and 5G communication
CN116566057B (en) User terminal fault detection system for virtual power plant
CN116505630B (en) Method and system for prolonging service life of power supply battery of fire-fighting Internet of things equipment
CN108562830B (en) Power distribution network damage degree judging method and system based on time synchronism
CN115965212A (en) Power grid power failure data management method and device and computer equipment
CN107508300B (en) Energy storage device state processing method and device and unit energy system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180413