CN107905188B - Anchoring method for outlet anchor point of hydropower station - Google Patents

Anchoring method for outlet anchor point of hydropower station Download PDF

Info

Publication number
CN107905188B
CN107905188B CN201711384258.6A CN201711384258A CN107905188B CN 107905188 B CN107905188 B CN 107905188B CN 201711384258 A CN201711384258 A CN 201711384258A CN 107905188 B CN107905188 B CN 107905188B
Authority
CN
China
Prior art keywords
anchor
rod
backing plate
hanging point
wire hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711384258.6A
Other languages
Chinese (zh)
Other versions
CN107905188A (en
Inventor
杨曼
贺双喜
向贤镜
严成斌
杨盛
陈琰
石文杰
王明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Guiyang Engineering Corp Ltd
Original Assignee
PowerChina Guiyang Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Guiyang Engineering Corp Ltd filed Critical PowerChina Guiyang Engineering Corp Ltd
Priority to CN201711384258.6A priority Critical patent/CN107905188B/en
Publication of CN107905188A publication Critical patent/CN107905188A/en
Application granted granted Critical
Publication of CN107905188B publication Critical patent/CN107905188B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a hydropower station outlet anchor point anchoring method, which is characterized in that an anchor rod is arranged in a side slope to serve as an anchoring body, and the end part of the anchor rod in the side slope is connected with an anchor backing plate through a nut. In addition, the anchor backing plate is connected with a wire hanging point rod serving as a wire hanging point by utilizing a nut, so that the outgoing tension is transmitted to the anchor rod through the wire hanging point, and the anchor rod is anchored. The specifications of the anchor rod can be calculated and selected according to the wire outlet tension, and the deflection angle of the anchor rod in the side slope can be adjusted according to the wire outlet requirement.

Description

Anchoring method for outlet anchor point of hydropower station
Technical Field
The invention belongs to the technical field of water conservancy, hydropower and electric power engineering application, and particularly relates to a method and a structure for anchoring a switch station wire and a ground wire outlet anchor point.
Background
At present, the outlet of a hydropower station generally adopts a direct leading-out scheme, namely, a lead is directly led to a terminal tower from an outlet gantry, and when the outlet tension and the deflection angle exceed the limits, a mode of increasing a middle rotating tower is generally adopted, so that the span between outlet towers is reduced, the outlet tension is reduced, and the deflection angle is adjusted. The existing outgoing line mode outgoing line towers are high in manufacturing cost, the transfer tower has certain requirements on terrain conditions, and for example, the transfer tower cannot be added between river-crossing towers.
Disclosure of Invention
The invention aims to solve the technical problem of providing an anchor point anchoring method for outlet wires of a hydropower station, which can fully utilize favorable terrain, natural slopes or building walls and the like on site, greatly simplify the outlet wire mode without adding a middle rotating tower by matching with the anchor point anchoring method, save the engineering investment, accelerate the construction progress and facilitate and flexible construction; on the other hand, the limiting factors of the outgoing line tension and the deflection angle are small, the application range is wide, and the method can be widely popularized.
The technical scheme of the invention is as follows:
a hydropower station outlet anchor point anchoring method comprises the following steps:
firstly, constructing anchor rods on natural slopes, artificial slopes or building walls, and meeting the strength requirement after grouting the anchor rods;
secondly, after the anchor backing plate and the on-site anchor rod are provided with the holes, the anchor backing plate and the anchor rod are connected;
thirdly, connecting the anchor backing plate with a wire hanging point rod;
fourthly, connecting a wire hanging point rod with a wire clamp to lead out wires;
and fifthly, after adjusting the wire outlet fasteners and the connecting pieces (the wire outlet fasteners and the connecting pieces can be selected according to the parameters of the wires) to meet the requirements, pouring concrete outer anchor piers to protect the connecting ends of the anchor backing plate, the anchor rods and the wire hanging point rods.
The anchor backing plate is provided with an anchor bolt hole, and the anchor rod is connected with the anchor backing plate through the anchor bolt hole and a nut.
And a wire hanging point bolt hole is formed in the anchor backing plate, and a wire hanging point rod is connected with the anchor backing plate through the wire hanging point bolt hole and a nut.
A hydropower station outlet anchoring structure comprises an anchor rod, wherein the rear end of the anchor rod is connected with an anchor backing plate, and the anchor backing plate is connected with a wire hanging point rod; the connecting point of the anchor rod and the anchor backing plate and the connecting point of the anchor backing plate and the wire hanging point rod are arranged in the cast-in-place concrete outer anchor pier.
The anchor rod is anchored on a natural side slope, an artificial side slope or a building wall body.
The invention sets anchor rod in the slope as anchor body, the end of anchor rod is connected with anchor backing plate by nut. The anchor backing plate is connected with an exposed wire hanging point rod serving as a wire hanging point by a nut, so that outlet tension is transmitted to the anchor rod in the side slope through the wire hanging point rod and the anchor backing plate, and the anchor rod is anchored. The specifications of the anchor rod can be calculated and selected according to the wire outlet tension, and the deflection angle of the anchor rod can be adjusted according to the wire outlet requirement.
Compared with the prior art, the invention has the following advantages:
(1) Compared with the steel structure outlet, the anchor rod outlet is convenient to construct, few in restricted factors and beneficial to implementation.
(2) The anchor rod, the anchor backing plate and the outgoing line hanging point rod are connected through nuts in the whole process, welding and other high-altitude operation work is avoided, and the construction method is simple.
(3) The anchor rod is connected with the method through the nut conveniently and quickly, and later-period maintenance is facilitated.
(4) The anchor rod construction is suitable for various terrains such as steep terrain, canyon terrain and the like, and is beneficial to popularization.
The outgoing line anchor point anchoring method has the advantages of strong applicability, simple construction, low later operation and maintenance cost and popularization value.
Drawings
Fig. 1 is a schematic view of the anchoring of an outlet anchor rod;
FIG. 2 is a schematic diagram of an outlet anchor connection;
in the figure: 1-anchor rod, 2-anchor backing plate, 3-wire hanging point rod, 4-anchor rod bolt hole, 5-wire hanging point bolt hole, 6-concrete outer anchor pier, 7-natural side slope, artificial side slope or building wall.
Detailed Description
The following describes the implementation of the present invention with reference to the attached drawings.
The arrangement of the present invention is further described below with reference to the accompanying drawings. As shown in figure 1, the structure meanings are as follows, 1-anchor rod, 2-anchor backing plate, 3-wire hanging point rod, 4-anchor rod bolt hole, 5-wire hanging point bolt hole, 6-concrete outer anchor pier, 7-natural side slope, artificial side slope or building wall.
Firstly, constructing an anchor rod 1 on a side slope or a building wall 7, and grouting the anchor rod 1 to meet the strength requirement;
secondly, after the anchor backing plates 2 are matched with the field anchor rods 1, as shown in fig. 2, one anchor backing plate 2 is connected with 4 anchor rods 1, the connection points of the anchor rods 1 and the anchor backing plates 2 are positioned at 4 corners of the anchor backing plates 2, and the anchor backing plates 2 are connected with the anchor rods 1 through nuts;
thirdly, connecting the anchor backing plate 2 with the wire hanging point rod 3 by using a nut, wherein a wire hanging point bolt hole 5 is positioned in the middle of the anchor backing plate 2 as shown in fig. 2;
fourthly, the wire hanging point rod 3 is connected with a wire clamp to be led out;
and fifthly, after the wire outlet fasteners and the connecting pieces are adjusted to meet the requirements, pouring connecting ends of the concrete outer anchor pier 6, the anchor backing plate 2, the anchor rod 1 and the wire hanging point rod 3. The outlet fastener and the connecting piece can be selected according to the wire parameters.
Through the steps, the direct line outgoing of the side slope can be realized, the construction is convenient and fast, the engineering investment is saved, and when available natural side slopes, artificial side slopes or building walls exist in the field, the line outgoing anchoring method can replace a turret in a metal structure, so that the use of the metal structure is reduced, and the later operation and maintenance cost of the metal structure is reduced. The outgoing line anchor point anchoring method is high in applicability, easy to implement and easy to popularize.

Claims (3)

1. The method for anchoring the outlet anchor point of the hydropower station is characterized by comprising the following steps of:
firstly, constructing an anchor rod (1) on a natural side slope, an artificial side slope or a building wall body (7), wherein the anchor rod (1) meets the strength requirement after grouting;
secondly, after the anchor backing plate (2) and the on-site anchor rod (1) are provided with holes, the anchor backing plate (2) and the anchor rod (1) are connected;
thirdly, connecting the anchor backing plate (2) with the wire hanging point rod (3);
fourthly, the wire hanging point rod (3) is connected with a wire clamp to be led out;
and fifthly, adjusting the outgoing line fasteners and the connecting pieces, and pouring concrete outer anchor piers (6) to protect the connecting ends of the anchor backing plate (2), the anchor rods (1) and the wire hanging point rods (3).
2. The hydropower station outlet anchor point anchoring method according to claim 1, wherein: an anchor bolt hole (4) is formed in the anchor backing plate (2), and the anchor rod (1) is connected with the anchor backing plate (2) through the anchor bolt hole (4) and a nut.
3. The hydropower station outlet anchor point anchoring method according to claim 1, wherein: the anchor backing plate (2) is provided with a wire hanging point bolt hole (5), and the wire hanging point rod (3) is connected with the anchor backing plate (2) through the wire hanging point bolt hole (5) and a nut.
CN201711384258.6A 2017-12-20 2017-12-20 Anchoring method for outlet anchor point of hydropower station Active CN107905188B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711384258.6A CN107905188B (en) 2017-12-20 2017-12-20 Anchoring method for outlet anchor point of hydropower station

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711384258.6A CN107905188B (en) 2017-12-20 2017-12-20 Anchoring method for outlet anchor point of hydropower station

Publications (2)

Publication Number Publication Date
CN107905188A CN107905188A (en) 2018-04-13
CN107905188B true CN107905188B (en) 2023-03-14

Family

ID=61870504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711384258.6A Active CN107905188B (en) 2017-12-20 2017-12-20 Anchoring method for outlet anchor point of hydropower station

Country Status (1)

Country Link
CN (1) CN107905188B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002105967A (en) * 2000-10-02 2002-04-10 Yuuki Oguri Setting method of anchor bolt corresponding to inclined ground and fixing device of anchor bolt
CN202144591U (en) * 2011-07-04 2012-02-15 北京鑫实路桥建设有限公司 Anchor device pedestal positioned at orifice of anchor hole of highway rock side slope prestressed steel strands
CN102905967A (en) * 2010-04-16 2013-01-30 布鲁帕特有限公司 Offshore marine anchor
JP2017014799A (en) * 2015-07-01 2017-01-19 グリーン産業株式会社 Movement prevention method and system for slope frame
CN206599782U (en) * 2017-03-20 2017-10-31 中勘冶金勘察设计研究院有限责任公司 A kind of adjustable Auxiliary support device of anchor pole tensioning
CN207828932U (en) * 2017-12-20 2018-09-07 中国电建集团贵阳勘测设计研究院有限公司 A kind of power station outlet anchor point anchor structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9169822B2 (en) * 2011-06-15 2015-10-27 National Taiwan University Deep ocean current power plant and constructing procedure thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002105967A (en) * 2000-10-02 2002-04-10 Yuuki Oguri Setting method of anchor bolt corresponding to inclined ground and fixing device of anchor bolt
CN102905967A (en) * 2010-04-16 2013-01-30 布鲁帕特有限公司 Offshore marine anchor
CN202144591U (en) * 2011-07-04 2012-02-15 北京鑫实路桥建设有限公司 Anchor device pedestal positioned at orifice of anchor hole of highway rock side slope prestressed steel strands
JP2017014799A (en) * 2015-07-01 2017-01-19 グリーン産業株式会社 Movement prevention method and system for slope frame
CN206599782U (en) * 2017-03-20 2017-10-31 中勘冶金勘察设计研究院有限责任公司 A kind of adjustable Auxiliary support device of anchor pole tensioning
CN207828932U (en) * 2017-12-20 2018-09-07 中国电建集团贵阳勘测设计研究院有限公司 A kind of power station outlet anchor point anchor structure

Also Published As

Publication number Publication date
CN107905188A (en) 2018-04-13

Similar Documents

Publication Publication Date Title
CN107905188B (en) Anchoring method for outlet anchor point of hydropower station
CN202416260U (en) Transverse prestressed reinforced structure of concrete aqueduct
CN110439353A (en) A kind of erection construction method of concrete wire pole overturning-preventing
CN201730109U (en) Novel fan foundation for intertidal zone wind farm
CN204858400U (en) Slope shaft tower unscrambler
CN207828932U (en) A kind of power station outlet anchor point anchor structure
CN202039377U (en) Prestressed steel stranded wire-combined anchor bolt
CN200999346Y (en) Fully steel-made universal reinforced type pole tower pile
CN201473966U (en) Novel paving base structure of L type suspension rigid foundation for rocky crane beams in underground plants
CN201221448Y (en) Tridimensional adjustable combined type prestress anchor bolt
CN209584374U (en) A kind of in-service concrete bearing platform cathode protection device of offshore wind farm
CN206707932U (en) The antifatigue combining structure wind tower of prestressing force
CN201738454U (en) Unit type connecting piece for connecting beam slab and wall
CN210917329U (en) Movable connection anchor disc of prefabricated single tubular pile of overhead transmission line shaft tower
CN206204985U (en) A kind of environment-friendly type assembled grouting behind shaft or drift lining steel cylinder pile foundation
CN211007872U (en) Electric iron tower reinforcing apparatus convenient to installation
CN104453336B (en) Base structure of high-pressure steel pipe pole
CN208857835U (en) A kind of auxiliary reinforcing device of power transmission tower foundation bolt
CN201963021U (en) Post-tensioning prestressing-force multi-section concrete wind-power generation tower frame
CN204570688U (en) A kind of enlarged footing anti-float anchor rod device
CN105714844A (en) Compound foundation for power transmission tower
CN201167221Y (en) Strain clamp for high-strength steel core aluminum alloy stranded wire
CN111764732A (en) Prestress assembly type concrete power generation tower
CN202023132U (en) Channel net
CN200982075Y (en) Anti-corrosion reinforcing structure for frame and bracket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant