CN107882591A - A kind of assembled hangers suspension member, prompt assembling device and installation method - Google Patents

A kind of assembled hangers suspension member, prompt assembling device and installation method Download PDF

Info

Publication number
CN107882591A
CN107882591A CN201711298924.4A CN201711298924A CN107882591A CN 107882591 A CN107882591 A CN 107882591A CN 201711298924 A CN201711298924 A CN 201711298924A CN 107882591 A CN107882591 A CN 107882591A
Authority
CN
China
Prior art keywords
hangers
bolt
suspension member
pressing plate
assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711298924.4A
Other languages
Chinese (zh)
Inventor
李章东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kang Yuan Rail Transport Technology (fujian) Co Ltd
Original Assignee
Kang Yuan Rail Transport Technology (fujian) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kang Yuan Rail Transport Technology (fujian) Co Ltd filed Critical Kang Yuan Rail Transport Technology (fujian) Co Ltd
Priority to CN201711298924.4A priority Critical patent/CN107882591A/en
Publication of CN107882591A publication Critical patent/CN107882591A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/02Suspension devices for tubes or the like, e.g. for ventilating ducts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Abstract

The invention discloses a kind of assembled hangers suspension member, prompt assembling device and installation method, wherein, the prompt assembling device is used for subway tunnel electromechanical equipment and pipeline is installed, including:Shield duct piece left member, shield duct piece right member, arc section of jurisdiction connecting bolt, segment bolt clamp nut left member, segment bolt clamp nut right member, assembled hangers suspension member, external chute and T-bolt component;Shield duct piece left member is spliced with shield duct piece right member by arc section of jurisdiction connecting bolt;Assembled hangers suspension member is arranged in the left mounting groove of shield duct piece left member bottom, is connected with shield duct piece left member;Or, assembled hangers suspension member is arranged in the right mounting groove of shield duct piece right member bottom, is connected with shield duct piece right member;External chute is arranged in the pendant groove of the assembled hangers suspension member by T-bolt component, nesting.The Fast Installation of subway tunnel electromechanical equipment and pipeline is realized by the present invention.

Description

A kind of assembled hangers suspension member, prompt assembling device and installation method
Technical field
The invention belongs to shield tunnel construction technology field, more particularly to a kind of assembled hangers suspension member, prompt assembling device and Installation method.
Background technology
As various regions large- and-medium size cities metro project starts successively, shield method determines definitely in city tunnel construction Dominant position, someone is referred to as city tunnel engineering method.The installation of existing Shield-bored tunnels electromechanical equipment and pipeline, typically Using traditional punching tendon-planted craft, its must the intensive punching on shield tunnel construction, damage is so had to tunnel structure, The integrality of protection path structure is unable to, while the shortcomings of construction and installation are complicated and pipeline installation period is long also be present;And build Make higher with maintenance cost.
The content of the invention
The technology of the present invention solves problem:Overcome the deficiencies in the prior art, there is provided a kind of assembled hangers suspension member, prompt dress dress Put and installation method, to realize the Fast Installation of subway tunnel electromechanical equipment and pipeline.
In order to solve the above-mentioned technical problem, the invention discloses a kind of assembled hangers suspension member, including:Hangers (5-1), ear Hole (5-2), suspension member body (5-3), pendant groove (5-4) and multiple fastening bolt holes (5-6);
Earhole (5-2) is provided with hangers (5-1) end face;
Hangers (5-1) and suspension member body (5-3) are integral type structure;Or, hangers (5-1) is connected with suspension member body (5-3);
Side of the suspension member body (5-3) away from hangers (5-1) is provided with the pendant groove (5-4) that Open Side Down;
Two side channel frame (5-5) bottoms of pendant groove (5-4) are provided with multiple fastening bolt holes (5-6).
Accordingly, the invention also discloses a kind of prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, bag Include:Shield duct piece left member (1-1), shield duct piece right member (1-2), arc section of jurisdiction connecting bolt (2), segment bolt clamp nut are left Part (3-1), segment bolt clamp nut right member (3-2), assembled hangers suspension member (5), external chute (6) and T-bolt component (8);
Shield duct piece left member (1-1) is spliced with shield duct piece right member (1-1) by arc section of jurisdiction connecting bolt (2);Wherein, One end of arc section of jurisdiction connecting bolt (2) is connected by segment bolt clamp nut left member (3-1) with shield duct piece left member (1-1) Fixed, the other end of arc section of jurisdiction connecting bolt (2) passes through segment bolt clamp nut right member (3-2) and shield duct piece right member (1-2) is connected;
Shield duct piece left member (1-1) bottom is provided with a left mounting groove (1-11), and shield duct piece right member (1-2) bottom is set There is a right mounting groove (1-21);
Assembled hangers suspension member (5) is arranged in left mounting groove (1-11), passes through arc section of jurisdiction connecting bolt (2) and section of jurisdiction Bolt clamp nut left member (3-1), it is connected with shield duct piece left member (1-1);Or, assembled hangers suspension member (5) is arranged on In right mounting groove (1-21), by arc section of jurisdiction connecting bolt (2) and segment bolt clamp nut right member (3-2), with shield pipe Piece right member (1-2) is connected;
External chute (6) is arranged on the pendant groove of the assembled hangers suspension member (5) by T-bolt component (8), nesting In (5-4).
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, assembled hangers suspension member (5), bag Include:Hangers (5-1), earhole (5-2), suspension member body (5-3), pendant groove (5-4) and multiple fastening bolt holes (5-6);
Earhole (5-2) is provided with hangers (5-1) end face;
Hangers (5-1) and suspension member body (5-3) are integral type structure;Or, hangers (5-1) is connected with suspension member body (5-3);
Side of the suspension member body (5-3) away from hangers (5-1) is provided with the pendant groove (5-4) that Open Side Down;
Two side channel frame (5-5) bottoms of pendant groove (5-4) are provided with multiple fastening bolt holes (5-6).
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline,
The earhole (5-2) of assembled hangers suspension member (5) is enclosed on one end of arc section of jurisdiction connecting bolt (2), passes through section of jurisdiction spiral shell Bolt clamp nut left member (3-1) is locked;Or, the earhole (5-2) of assembled hangers suspension member (5) is enclosed on arc section of jurisdiction connecting bolt (2) the other end, locked by segment bolt clamp nut right member (3-2).
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, in addition to:Hangers pressing plate (7), Multiple hangers pressing plate fastening bolts (9) and multiple hangers pressing plate clamp nuts (9-1);
External chute (6) passes through T-bolt component (8), hangers pressing plate (7), multiple hangers pressing plate fastening bolts (9) and more Individual hangers pressing plate clamp nut (9-1), nesting are arranged in the pendant groove (5-4) of the assembled hangers suspension member (5).
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, T-bolt component (8), including: T-bolt (8-1) and the broach (8-2) being arranged on T-bolt (8-1) bottom surface;External chute (6), including:C-shaped channel (6-1), the chute broach (6-2) being arranged on C-shaped channel (6-1) platform inner surface and external chute (6) bottom it is external Chute arc surface (6-3);Hangers pressing plate (7), including:Hangers pressing plate arc surface (7-2), with T-bolt (8-1) Corresponding matching T-bolt hole (7-1) and multiple installations with multiple fastening bolt holes (5-6) Corresponding matching of assembled hangers suspension member (5) Through hole (7-3);
T-bolt (8-1) is hung on the both sides platform inner surface of C-shaped channel (6-1) of external chute (6);Wherein, T-shaped spiral shell Broach (8-2) on bolt (8-1) bottom surface engages with the chute broach (6-2) on the platform inner surface of C-shaped channel (6-1);
External chute (6) is pressed in the pendant groove (5-4) of assembled hangers suspension member (5) by hangers pressing plate (7);Wherein, hang Ear pressing plate arc surface (7-2) is brought into close contact with external chute arc surface (6-3);
T-bolt (8-1) passes through T-bolt hole (7-1), and by nut check, so that T-bolt (8-1) is fixed on On hangers pressing plate (7) and on the platform inner surface of external chute (6);
Each hangers pressing plate fastening bolt (9) sequentially pass through respectively multiple installation through-holes (7-3) on hangers pressing plate (7) and After multiple fastening bolt holes (5-6) on assembled hangers suspension member (5), locked by each hangers pressing plate clamp nut (9-1).
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, T-bolt component (8) is fixed with Pipeline suspension and support.
In the above-mentioned prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, in addition to:Section of jurisdiction connecting bolt Pad (4);
Section of jurisdiction connecting bolt pad (4) is arranged on shield duct piece left member (1-1) and segment bolt clamp nut left member (3-1) Between;Or, section of jurisdiction connecting bolt pad (4) is arranged on shield duct piece right member (1-2) and segment bolt clamp nut right member (3-2) Between.
Accordingly, the invention also discloses a kind of peace for the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline Dress method, including:
Segment bolt clamp nut is unclamped, removes section of jurisdiction connecting bolt pad;
The section of jurisdiction connecting bolt pad removed, and the extension of adjustment assembly formula hangers suspension member are replaced using assembled hangers suspension member Ear is to design attitude;
Adjust to design attitude, segment bolt clamp nut is locked, with fixation in the hangers of assembled hangers suspension member Assembled hangers suspension member;
External chute is placed in the pendant groove of assembled hangers suspension member;
The external chute arc surface of the hangers pressing plate arc surface of hangers pressing plate and external chute is brought into close contact, and adjusted outer Chute is put to design attitude;
By hangers pressing plate fastening bolt and hangers pressing plate, T-bolt component is set to be fixed in external chute;
By T-bolt component fixed pipelines suspension and support, and tunnel pipeline and miscellaneous equipment are installed on pipeline suspension and support.
The present invention has advantages below:
1) not damaged, it is relative without the steel planting in structure or to beat expansion bolt with traditional crab-bolt technique, to structure without Destroy, the integrality and durability of shield tunnel in itself is greatly improved, prevent because it is intensive punching caused by section of jurisdiction crack, infiltration, etc. Potential safety hazard.
2) cost is low, prevents waste of material low cost more than 30% without 360 degree of arrangements relative to built-in sliding chute technique, together When also significantly reduce the operation maintenance expense of equipment, equipment installation and safeguard simpler, maintenance cost is greatly reduced.
3) short time limit, equipment installation effectiveness significantly improve, and mechanical and electric equipment installation construction can be with civil engineering cross-operation And do not interfere with each other, it can at least shorten more than 50% relative to traditional crab-bolt technique hydromechanical installer phase.
4) it is environmentally friendly, the construction environment of pipeline and mechanical and electric equipment installation process without dust, noiseless greatly improvement equipment installation, Labor strength is reduced, is belonged to typical " green construction ".
5) highly integrated, each professional equipment in tunnel can be arranged on chute, be easy to change and increase various in the operation phase Equipment.
6) safeguard that simply all parts are replaceable, safeguard and be more convenient, maintenance cost is low.
7) it is construction is simple, quick without pre-buried relative to built-in sliding chute, and to section of jurisdiction intensity without negative effect.
8) convenience and mounting robot that manufacturability, the subsequent maintenance of the rapid processing installation of shield tunnel are safeguarded are improved The possibility of cruising inspection system.
Brief description of the drawings
Fig. 1 is a kind of dimensional structure diagram of assembled hangers suspension member in the embodiment of the present invention;
Fig. 2 is a kind of front view of assembled hangers suspension member in the embodiment of the present invention;
Fig. 3 is Fig. 2 left view;
Fig. 4 is Fig. 2 upward view;
Fig. 5 is a kind of structure for the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline in the embodiment of the present invention Schematic diagram;
Fig. 6 be a kind of assembled hangers suspension member and external chute in the embodiment of the present invention, hangers pressing plate, T-bolt component, The structural representation of annexation between hangers pressing plate fastening bolt;
Fig. 7 be a kind of assembled hangers suspension member in the embodiment of the present invention, external chute, hangers pressing plate, T-bolt component, The separation distributed architecture schematic diagram of hangers pressing plate fastening bolt;
Fig. 8 is a kind of external chute in the embodiment of the present invention, hangers pressing plate, T-bolt component, hangers pressing plate fastening bolt Separation distributed architecture schematic diagram;
Fig. 9 is a kind of dimensional structure diagram of hangers pressing plate in the embodiment of the present invention;
Figure 10 is a kind of front view of hangers pressing plate in the embodiment of the present invention;
Figure 11 is Figure 10 left view;
Figure 12 is Figure 10 upward view;
Figure 13 is a kind of peace for the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline in the embodiment of the present invention The step flow chart of dress method.
Embodiment
It is public to the present invention below in conjunction with accompanying drawing to make the object, technical solutions and advantages of the present invention clearer Embodiment is described in further detail.
Reference picture 1, show a kind of dimensional structure diagram of assembled hangers suspension member in the embodiment of the present invention.Reference picture 2, show a kind of front view of assembled hangers suspension member in the embodiment of the present invention.Reference picture 3, it is Fig. 2 left view.Reference picture 4, it is Fig. 2 upward view.In the present embodiment, assembled hangers suspension member 5, including:Hangers 5-1, earhole 5-2, suspension member body 5- 3rd, pendant groove 5-4 and multiple fastening bolt holes 5-6.
Such as Fig. 1~4, hangers 5-1 is provided with earhole 5-2 on end face.Hangers 5-1 and suspension member body 5-3 is integral type structure; Or, hangers 5-1 is connected with suspension member body 5-3.Sides of the suspension member body 5-3 away from hangers 5-1 is provided with the suspension member that Open Side Down Groove 5-4.Pendant groove 5-4 two side channel frame 5-5 bottoms are provided with multiple fastening bolt holes 5-6.
On the basis of above-described embodiment, it is used for subway tunnel electromechanical equipment the invention also discloses one kind and pipeline is installed Prompt assembling device.Reference picture 5, show a kind of victory installed for subway tunnel electromechanical equipment and pipeline in the embodiment of the present invention The structural representation of assembling device.In the present embodiment, the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, Including:Shield duct piece left member 1-1, shield duct piece right member 1-2, arc section of jurisdiction connecting bolt 2, segment bolt clamp nut left member 3- 1st, segment bolt clamp nut right member 3-2, assembled hangers suspension member 5, external chute 6 and T-bolt component 8.
As Fig. 5, shield duct piece left member 1-1 and shield duct piece right member 1-1 are spliced by arc section of jurisdiction connecting bolt 2.Wherein, One end of arc section of jurisdiction connecting bolt 2 is connected by segment bolt clamp nut left member 3-1 and shield duct piece left member 1-1, The other end of arc section of jurisdiction connecting bolt 2 is connected solid by segment bolt clamp nut right member 3-2 with shield duct piece right member 1-2 It is fixed.
Shield duct piece left member 1-1 bottoms are provided with a left mounting groove 1-11, and it is right that shield duct piece right member 1-2 bottoms are provided with one Mounting groove 1-21.Assembled hangers suspension member 5 is arranged in left mounting groove 1-11, passes through arc section of jurisdiction connecting bolt 2 and section of jurisdiction spiral shell Bolt clamp nut left member 3-1, is connected with shield duct piece left member 1-1;Or, assembled hangers suspension member 5 is arranged on right mounting groove In 1-21, by arc section of jurisdiction connecting bolt 2 and segment bolt clamp nut right member 3-2, it is connected with shield duct piece right member 1-2 solid It is fixed.
External chute 6 is arranged in the pendant groove 5-4 of the assembled hangers suspension member 5 by T-bolt component 8, nesting.
In the preferred embodiment of the present invention, the concrete structure of assembled hangers suspension member 5 can be found in described above, this reality Example is applied to will not be repeated here.
In the preferred embodiment of the present invention, the earhole 5-2 of assembled hangers suspension member 5 is enclosed on arc section of jurisdiction connecting bolt 2 one end, locked by segment bolt clamp nut left member 3-1;Or, the earhole 5-2 of assembled hangers suspension member 5 is enclosed on curved pipe The other end of piece connecting bolt 2, locked by segment bolt clamp nut right member 3-2.
In the preferred embodiment of the present invention, reference picture 6, show that a kind of assembled hangers is hung in the embodiment of the present invention The structural representation of annexation between part and external chute, hangers pressing plate, T-bolt component, hangers pressing plate fastening bolt. Reference picture 7, show a kind of assembled hangers suspension member in the embodiment of the present invention, external chute, hangers pressing plate, T-bolt component, The separation distributed architecture schematic diagram of hangers pressing plate fastening bolt.It is in the present embodiment, described to be used for subway tunnel with reference to Fig. 1~7 Electromechanical equipment and the prompt assembling device of pipeline installation, in addition to:Hangers pressing plate 7, multiple hangers pressing plate fastening bolts 9 and multiple hangers Pressing plate clamp nut 9-1.Wherein, external chute 6 passes through T-bolt component 8, hangers pressing plate 7, multiple hangers pressing plate fastening bolts 9 and multiple hangers pressing plate clamp nut 9-1, nesting are arranged in the pendant groove 5-4 of the assembled hangers suspension member 5.
In the preferred embodiment of the present invention, reference picture 8, a kind of external chute, extension in the embodiment of the present invention are shown Ear pressing plate, T-bolt component, the separation distributed architecture schematic diagram of hangers pressing plate fastening bolt.Reference picture 9, shows the present invention A kind of dimensional structure diagram of hangers pressing plate in embodiment.Reference picture 10, show a kind of hangers pressure in the embodiment of the present invention The front view of plate.Reference picture 11, it is Figure 10 left view.Reference picture 12, it is Figure 10 upward view.
Such as Fig. 1~12, in the present embodiment, T-bolt component 8, can specifically include:T-bolt 8-1 and setting Broach 8-2 on T-bolt 8-1 bottom surfaces.External chute 6, can specifically include:C-shaped channel 6-1, it is arranged on C-shaped channel 6-1's The external chute arc surface 6-3 of chute broach 6-2 and the bottom of external chute 6 on platform inner surface.Hangers pressing plate 7, bag Include:Hangers pressing plate arc surface 7-2, with the T-bolt hole 7-1 of T-bolt 8-1 Corresponding matchings and with assembled hangers suspension member 5 Multiple fastening bolt holes 5-6 Corresponding matchings multiple installation through-hole 7-3.
In the present embodiment, T-bolt 8-1 is hung on the C-shaped channel 6-1 of external chute 6 both sides platform inner surface.Its In, the broach 8-2 on T-bolt 8-1 bottom surfaces engages with the chute broach 6-2 on C-shaped channel 6-1 platform inner surface.
External chute 6 is pressed in the pendant groove 5-4 of assembled hangers suspension member 5 by hangers pressing plate 7;Wherein, hangers pressing plate is justified Cambered surface 7-2 is brought into close contact with external chute arc surface 6-3.
T-bolt 8-1 passes through T-bolt hole 7-1, and by nut check, so that T-bolt 8-1 is fixed on hangers pressure On plate 7 and on the platform inner surface of external chute 6.
Each hangers pressing plate fastening bolt 9 sequentially passes through multiple installation through-hole 7-3 and assembled on hangers pressing plate 7 respectively After multiple fastening bolt holes 5-6 on hangers suspension member 5, locked by each hangers pressing plate clamp nut 9-1.
In the preferred embodiment of the present invention, such as Fig. 5, the victory installed for subway tunnel electromechanical equipment and pipeline Assembling device, it can also include:Section of jurisdiction connecting bolt pad 4.Wherein, section of jurisdiction connecting bolt pad 4 is arranged on shield duct piece left member Between 1-1 and segment bolt clamp nut left member 3-1;Or, section of jurisdiction connecting bolt pad 4 be arranged on shield duct piece right member 1-2 with Between segment bolt clamp nut right member 3-2.
In the preferred embodiment of the present invention, T-bolt component 8 is fixed with pipeline suspension and support, can
Tunnel pipeline and miscellaneous equipment (e.g., subway tunnel electromechanical equipment) are installed on pipeline suspension and support.
, wherein it is desired to illustrate, can be in fastening bolt holes 5-6, T-bolt hole 7-1 and installation through-hole 7-3 hole Screw may also be the hole of non-threaded.Hangers pressing plate fastening bolt 9 can use conventional fastener bolt, such as:Hex bolts.
Based on above-described embodiment, the invention also discloses a kind of prompt dress installed for subway tunnel electromechanical equipment and pipeline The installation method of device.Reference picture 13, show a kind of for subway tunnel electromechanical equipment and pipeline peace in the embodiment of the present invention The step flow chart of the installation method of the prompt assembling device of dress.
In the present embodiment, the installation method of the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, Including:
Step 101, segment bolt clamp nut is unclamped, removes section of jurisdiction connecting bolt pad.
Step 102, the section of jurisdiction connecting bolt pad removed, and adjustment assembly formula hangers are replaced using assembled hangers suspension member The hangers of suspension member is to design attitude.
Step 103, adjusted in the hangers of assembled hangers suspension member to design attitude, segment bolt clamp nut is locked Tightly, with fixing assembling formula hangers suspension member.
Step 104, external chute is placed in the pendant groove of assembled hangers suspension member.
Step 105, the external chute arc surface of the hangers pressing plate arc surface of hangers pressing plate and external chute is brought into close contact, And external chute is adjusted to design attitude.
Step 106, by hangers pressing plate fastening bolt and hangers pressing plate, T-bolt component is made to be fixed in external chute.
Step 107, by T-bolt component fixed pipelines suspension and support, and on pipeline suspension and support install tunnel pipeline and Miscellaneous equipment.
For embodiment of the method, because it is corresponding with device embodiment, so description is fairly simple, correlation Place referring to device embodiment part explanation.
In summary, the prompt dress scheme disclosed by the invention installed for subway tunnel electromechanical equipment and pipeline, assembled The earhole of hangers suspension member is enclosed on the connecting bolt of section of jurisdiction and locked with segment bolt clamp nut, and external cunning is placed with pendant groove Groove, T-bolt are hung on the both sides platform inner surface of the C-shaped channel in external chute, what the platform inner surface of C-shaped channel was provided with Chute broach can be engaged with the broach of T-bolt bottom surface, and hangers pressing plate is pressed on external chute and makes the circular arc of hangers pressing plate Face and the arc surface of external chute are brought into close contact, and T-bolt is inserted in the T-bolt hole for the hangers pressing plate for being pressed in external chute In use nut check again;With hangers pressing plate fastening bolt pass through the through hole of hangers pressing plate for being pressed in external chute, pendant groove it is tight Fixing bolt is locked behind hole, is reached and is fixed external chute and T-bolt component, improves the integrality and durability of shield tunnel, Realize the Fast Installation of subway tunnel electromechanical equipment and pipeline.
Each embodiment in this explanation is described by the way of progressive, what each embodiment stressed be and its The difference of his embodiment, between each embodiment identical similar part mutually referring to.
It is described above, it is only the optimal embodiment of the present invention, but protection scope of the present invention is not limited thereto, Any one skilled in the art the invention discloses technical scope in, the change or replacement that can readily occur in, It should all be included within the scope of the present invention.
The content not being described in detail in description of the invention belongs to the known technology of professional and technical personnel in the field.

Claims (9)

  1. A kind of 1. assembled hangers suspension member, it is characterised in that including:Hangers (5-1), earhole (5-2), suspension member body (5-3), extension Part groove (5-4) and multiple fastening bolt holes (5-6);
    Earhole (5-2) is provided with hangers (5-1) end face;
    Hangers (5-1) and suspension member body (5-3) are integral type structure;Or, hangers (5-1) is connected with suspension member body (5-3);
    Side of the suspension member body (5-3) away from hangers (5-1) is provided with the pendant groove (5-4) that Open Side Down;
    Two side channel frame (5-5) bottoms of pendant groove (5-4) are provided with multiple fastening bolt holes (5-6).
  2. A kind of 2. prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that including:Shield duct piece is left Part (1-1), shield duct piece right member (1-2), arc section of jurisdiction connecting bolt (2), segment bolt clamp nut left member (3-1), section of jurisdiction Bolt clamp nut right member (3-2), assembled hangers suspension member (5), external chute (6) and T-bolt component (8);
    Shield duct piece left member (1-1) is spliced with shield duct piece right member (1-1) by arc section of jurisdiction connecting bolt (2);Wherein, arc One end of section of jurisdiction connecting bolt (2) is connected solid by segment bolt clamp nut left member (3-1) with shield duct piece left member (1-1) Fixed, the other end of arc section of jurisdiction connecting bolt (2) passes through segment bolt clamp nut right member (3-2) and shield duct piece right member (1- 2) it is connected;
    Shield duct piece left member (1-1) bottom is provided with a left mounting groove (1-11), and shield duct piece right member (1-2) bottom is provided with one Right mounting groove (1-21);
    Assembled hangers suspension member (5) is arranged in left mounting groove (1-11), passes through arc section of jurisdiction connecting bolt (2) and segment bolt Clamp nut left member (3-1), it is connected with shield duct piece left member (1-1);Or, assembled hangers suspension member (5) is arranged on right peace It is right with shield duct piece by arc section of jurisdiction connecting bolt (2) and segment bolt clamp nut right member (3-2) in tankage (1-21) Part (1-2) is connected;
    External chute (6) is arranged on the pendant groove (5- of the assembled hangers suspension member (5) by T-bolt component (8), nesting 4) in.
  3. 3. the prompt assembling device according to claim 2 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that Assembled hangers suspension member (5), including:Hangers (5-1), earhole (5-2), suspension member body (5-3), pendant groove (5-4) and multiple tight Fixing bolt hole (5-6);
    Earhole (5-2) is provided with hangers (5-1) end face;
    Hangers (5-1) and suspension member body (5-3) are integral type structure;Or, hangers (5-1) is connected with suspension member body (5-3);
    Side of the suspension member body (5-3) away from hangers (5-1) is provided with the pendant groove (5-4) that Open Side Down;
    Two side channel frame (5-5) bottoms of pendant groove (5-4) are provided with multiple fastening bolt holes (5-6).
  4. 4. the prompt assembling device according to claim 3 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that
    The earhole (5-2) of assembled hangers suspension member (5) is enclosed on one end of arc section of jurisdiction connecting bolt (2), tight by segment bolt Gu nut left member (3-1) is locked;Or, the earhole (5-2) of assembled hangers suspension member (5) is enclosed on arc section of jurisdiction connecting bolt (2) The other end, locked by segment bolt clamp nut right member (3-2).
  5. 5. the prompt assembling device according to claim 3 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that Also include:Hangers pressing plate (7), multiple hangers pressing plate fastening bolts (9) and multiple hangers pressing plate clamp nuts (9-1);
    External chute (6) passes through T-bolt component (8), hangers pressing plate (7), multiple hangers pressing plate fastening bolts (9) and multiple extensions Ear pressing plate clamp nut (9-1), nesting are arranged in the pendant groove (5-4) of the assembled hangers suspension member (5).
  6. 6. the prompt assembling device according to claim 5 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that T-bolt component (8), including:T-bolt (8-1) and the broach (8-2) being arranged on T-bolt (8-1) bottom surface;It is external Chute (6), including:C-shaped channel (6-1), the chute broach (6-2) being arranged on C-shaped channel (6-1) platform inner surface and outer Put the external chute arc surface (6-3) of chute (6) bottom;Hangers pressing plate (7), including:Hangers pressing plate arc surface (7-2), with it is T-shaped The T-bolt hole (7-1) of bolt (8-1) Corresponding matching and multiple fastening bolt holes (5- with assembled hangers suspension member (5) 6) multiple installation through-holes (7-3) of Corresponding matching;
    T-bolt (8-1) is hung on the both sides platform inner surface of C-shaped channel (6-1) of external chute (6);Wherein, T-bolt (8- 1) broach on bottom surface (8-2) engages with the chute broach (6-2) on the platform inner surface of C-shaped channel (6-1);
    External chute (6) is pressed in the pendant groove (5-4) of assembled hangers suspension member (5) by hangers pressing plate (7);Wherein, hangers pressure Plate arc surface (7-2) is brought into close contact with external chute arc surface (6-3);
    T-bolt (8-1) passes through T-bolt hole (7-1), and by nut check, so that T-bolt (8-1) is fixed on hangers On pressing plate (7) and on the platform inner surface of external chute (6);
    Each hangers pressing plate fastening bolt (9) sequentially passes through multiple installation through-holes (7-3) and assembling on hangers pressing plate (7) respectively After multiple fastening bolt holes (5-6) on formula hangers suspension member (5), locked by each hangers pressing plate clamp nut (9-1).
  7. 7. the prompt assembling device according to claim 2 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that T-bolt component (8) is fixed with pipeline suspension and support.
  8. 8. the prompt assembling device according to claim 2 installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that Also include:Section of jurisdiction connecting bolt pad (4);
    Section of jurisdiction connecting bolt pad (4) be arranged on shield duct piece left member (1-1) and segment bolt clamp nut left member (3-1) it Between;Or, section of jurisdiction connecting bolt pad (4) be arranged on shield duct piece right member (1-2) and segment bolt clamp nut right member (3-2) it Between.
  9. A kind of 9. installation method for the prompt assembling device installed for subway tunnel electromechanical equipment and pipeline, it is characterised in that including:
    Segment bolt clamp nut is unclamped, removes section of jurisdiction connecting bolt pad;
    The section of jurisdiction connecting bolt pad removed is replaced using assembled hangers suspension member, and the hangers of adjustment assembly formula hangers suspension member is extremely Design attitude;
    Adjust to design attitude, segment bolt clamp nut is locked, with fixing assembling in the hangers of assembled hangers suspension member Formula hangers suspension member;
    External chute is placed in the pendant groove of assembled hangers suspension member;
    The external chute arc surface of the hangers pressing plate arc surface of hangers pressing plate and external chute is brought into close contact, and adjusts external cunning Groove is to design attitude;
    By hangers pressing plate fastening bolt and hangers pressing plate, T-bolt component is set to be fixed in external chute;
    By T-bolt component fixed pipelines suspension and support, and tunnel pipeline and miscellaneous equipment are installed on pipeline suspension and support.
CN201711298924.4A 2017-12-08 2017-12-08 A kind of assembled hangers suspension member, prompt assembling device and installation method Pending CN107882591A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711298924.4A CN107882591A (en) 2017-12-08 2017-12-08 A kind of assembled hangers suspension member, prompt assembling device and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711298924.4A CN107882591A (en) 2017-12-08 2017-12-08 A kind of assembled hangers suspension member, prompt assembling device and installation method

Publications (1)

Publication Number Publication Date
CN107882591A true CN107882591A (en) 2018-04-06

Family

ID=61773554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711298924.4A Pending CN107882591A (en) 2017-12-08 2017-12-08 A kind of assembled hangers suspension member, prompt assembling device and installation method

Country Status (1)

Country Link
CN (1) CN107882591A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590759A (en) * 2018-06-28 2018-09-28 彭健 A kind of hangers victory assembling device and its installation method
CN109113760A (en) * 2018-07-06 2019-01-01 江苏华威线路设备集团有限公司 A kind of prompt dress engineering method of environmental protection for Fast Installation shield tunnel electromechanical equipment pipeline
CN110087152A (en) * 2019-05-31 2019-08-02 昆山六二丰塑胶电子有限公司 A kind of router shell structure
CN112431610A (en) * 2020-12-17 2021-03-02 华侨大学 Mounting structure and mounting method of shield tunnel auxiliary equipment
WO2021088717A1 (en) * 2019-11-05 2021-05-14 京东数科海益信息科技有限公司 Hanging structure, tunnel rail hanging robot, and tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010058467A (en) * 1999-12-30 2001-07-06 오용한 Apparatus for fixing fan on tunnel wall and method thereof
CN104131821A (en) * 2014-07-17 2014-11-05 江苏华彤新能源科技有限公司 Shield tunnel external groove sheathing groove structure and fixing method of shield tunnel external groove sheathing groove structure
CN204677233U (en) * 2015-02-13 2015-09-30 维机轨道交通科技(镇江)有限公司 The plug-in conduit erecting device in tunnel and hanger device thereof
CN205387956U (en) * 2016-02-03 2016-07-20 维机轨道交通科技(镇江)有限公司 Open hangers
CN205532714U (en) * 2016-02-03 2016-08-31 维机轨道交通科技(镇江)有限公司 Antiskid channel
CN207728391U (en) * 2017-12-08 2018-08-14 康元轨道交通科技(福建)有限公司 A kind of assembled hangers pendant and prompt assembling device
CN210768800U (en) * 2017-11-27 2020-06-16 夏峰 Shield tunnel assembled pipeline braced system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010058467A (en) * 1999-12-30 2001-07-06 오용한 Apparatus for fixing fan on tunnel wall and method thereof
CN104131821A (en) * 2014-07-17 2014-11-05 江苏华彤新能源科技有限公司 Shield tunnel external groove sheathing groove structure and fixing method of shield tunnel external groove sheathing groove structure
CN204677233U (en) * 2015-02-13 2015-09-30 维机轨道交通科技(镇江)有限公司 The plug-in conduit erecting device in tunnel and hanger device thereof
CN205387956U (en) * 2016-02-03 2016-07-20 维机轨道交通科技(镇江)有限公司 Open hangers
CN205532714U (en) * 2016-02-03 2016-08-31 维机轨道交通科技(镇江)有限公司 Antiskid channel
CN210768800U (en) * 2017-11-27 2020-06-16 夏峰 Shield tunnel assembled pipeline braced system
CN207728391U (en) * 2017-12-08 2018-08-14 康元轨道交通科技(福建)有限公司 A kind of assembled hangers pendant and prompt assembling device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590759A (en) * 2018-06-28 2018-09-28 彭健 A kind of hangers victory assembling device and its installation method
CN109113760A (en) * 2018-07-06 2019-01-01 江苏华威线路设备集团有限公司 A kind of prompt dress engineering method of environmental protection for Fast Installation shield tunnel electromechanical equipment pipeline
CN110087152A (en) * 2019-05-31 2019-08-02 昆山六二丰塑胶电子有限公司 A kind of router shell structure
WO2021088717A1 (en) * 2019-11-05 2021-05-14 京东数科海益信息科技有限公司 Hanging structure, tunnel rail hanging robot, and tunnel
CN112431610A (en) * 2020-12-17 2021-03-02 华侨大学 Mounting structure and mounting method of shield tunnel auxiliary equipment
CN112431610B (en) * 2020-12-17 2022-09-06 华侨大学 Mounting structure and mounting method of shield tunnel auxiliary equipment

Similar Documents

Publication Publication Date Title
CN107882591A (en) A kind of assembled hangers suspension member, prompt assembling device and installation method
CN204901062U (en) A three -dimensional antidetonation gallows
EP1122439A3 (en) Hermetic compressor assembly
CN207728391U (en) A kind of assembled hangers pendant and prompt assembling device
CN102518635A (en) Bolt with clamp spring and enclosed profile connecting structure adopting bolt to connect
CN201575234U (en) Hose fixing device
CN206159661U (en) A single small transfer line antidetonation system of hanging
CN207673340U (en) A kind of not damaged pipeline victory dress system
CN108590759A (en) A kind of hangers victory assembling device and its installation method
KR20190019549A (en) Assembly type panel supporting apparatus and panel structure by using of it
CN109458221A (en) A kind of hangers victory assembling device and installation method
CN208456667U (en) A kind of hangers victory assembling device
JP2003239529A (en) Scaffold board support device for veranda handrail
CN211655606U (en) Reinforced external channel
CN103911918B (en) The dismantled and assembled connector of longitudinal beam type sleeper
CN209375043U (en) A kind of cable bearer
CN108915769A (en) A kind of hangers victory assembling device and its installation method
CN205532713U (en) Tunnel joins externally channel mounting structure
CN206859838U (en) A kind of breast board fixing device
CN104988990B (en) Support bracket and its support telescopic bracket method for jacking formwork system
CN109736888A (en) A kind of hangers victory assembling device and installation method
CN208935563U (en) A kind of antidetonation gravitational support slide bearings
CN214144011U (en) Urban municipal drainage pipeline arrangement structure
CN209413944U (en) A kind of hangers victory assembling device
FI80133B (en) VID MONTERING AV BYGGELEMENT ANVAENDBART MONTERINGSBESLAG.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination