CN107877667A - A kind of extra quality water-permeable brick base-material laying method - Google Patents

A kind of extra quality water-permeable brick base-material laying method Download PDF

Info

Publication number
CN107877667A
CN107877667A CN201711172821.3A CN201711172821A CN107877667A CN 107877667 A CN107877667 A CN 107877667A CN 201711172821 A CN201711172821 A CN 201711172821A CN 107877667 A CN107877667 A CN 107877667A
Authority
CN
China
Prior art keywords
mould
fabric
storehouse
bed material
extra quality
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201711172821.3A
Other languages
Chinese (zh)
Inventor
奚月文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Net Rain Environmental Protection Technology Co Ltd
Original Assignee
Guangdong Net Rain Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Net Rain Environmental Protection Technology Co Ltd filed Critical Guangdong Net Rain Environmental Protection Technology Co Ltd
Priority to CN201711172821.3A priority Critical patent/CN107877667A/en
Publication of CN107877667A publication Critical patent/CN107877667A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • B28B13/0215Feeding the moulding material in measured quantities from a container or silo
    • B28B13/026Feeding the moulding material in measured quantities from a container or silo by using a movable hopper transferring the moulding material to the moulding cavities
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B3/00Producing shaped articles from the material by using presses; Presses specially adapted therefor
    • B28B3/02Producing shaped articles from the material by using presses; Presses specially adapted therefor wherein a ram exerts pressure on the material in a moulding space; Ram heads of special form
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/225Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage

Abstract

The invention discloses a kind of extra quality water-permeable brick base-material laying method, the laying depth of bed material and fabric is controlled by the height of the lifter plate setting of mould bottom, first pass through bed material storehouse and bed material is filled up into certain thickness mould, and strike off its surface, then fabric is filled up by whole mould by fabric storehouse, and its surface is struck off, so that two kinds of base-materials laying in mould is uniformly and smooth, thickness is stablized, and the homogeneity of product suppressed is higher, more attractive in appearance.

Description

A kind of extra quality water-permeable brick base-material laying method
Technical field
The present invention relates to a kind of ceramic water-permeable brick production technology, particularly a kind of extra quality water-permeable brick base-material laying method.
Background technology
Water-permeable brick is increasingly favored by government, there is good permeable, permeability as environment-friendly type building material, Rainwater can be made to rapidly permeate into underground, supplement the soil water and underground water, keep soil moisture, improve urban ground plant and soil is micro- The life condition of biology;Absorbable moisture and heat, the humiture of earth's surface local space is adjusted, to regulation urban microclimate, is delayed Solution urban heat land effect plays the role of larger;Municipal drainage and pressure of flood, the pollution to preventing public waters and place can be mitigated Reason sewage has good effect.
The production technology of water-permeable brick generally comprises base-material mixing, compressing, high-temperature firing and storage.Mix Good base-material is required for raw material being routed in corresponding mould before being pressed, but often exists upper and lower two layers Base-material laying is not enough uniformly and smooth, and the thickness low LCL of upper and lower two layers of base-material is accurate, causes to suppress the water-permeable brick levels come Thickness is unstable, and levels boundary is indefinite etc., influences the attractive in appearance of extra quality water-permeable brick.
The content of the invention
To solve the above problems, it is an object of the invention to provide a kind of extra quality water-permeable brick base-material laying method, laying Make that two layers base-material laying up and down is uniformly and smooth, and thickness is stable during base-material, it is higher to suppress the homogeneity of product come, more beautiful See.
Technical scheme is used by the present invention solves its problem:
A kind of extra quality water-permeable brick base-material laying method, comprises the following steps,
S1:Extra quality permeable turn of bed material and fabric are respectively placed in bed material storehouse and fabric storehouse;
S2:The lifter plate of mould bottom is arranged on certain altitude, then bed material storehouse is moved on mould Side, makes bed material fill up mould;
S3:Bed material storehouse is removed, while the bed material in mould is struck off by bed material storehouse;
S4:The interior lifter plate of mould is dropped into bottom, then fabric storehouse is moved to above mould, makes fabric Fill up mould;
S5:Fabric storehouse is removed, while the fabric in mould is struck off by fabric storehouse, completes extra quality water-permeable brick base-material paving If.
Further, after bed material storehouse is moved to above mould by the step S2, in addition to it is reciprocal back and forth at least once Move horizontally.
Further, after fabric storehouse is moved to above mould by the step S4, in addition to it is reciprocal back and forth at least once Move horizontally.
The beneficial effects of the invention are as follows:A kind of extra quality water-permeable brick base-material laying method that the present invention uses, passes through shaping mould The height that the lifter plate of tool bottom is set controls the laying depth of bed material and fabric, first passes through bed material storehouse and fills up bed material necessarily The mould of thickness, and its surface is struck off, then fabric is filled up by whole mould by fabric storehouse, and its surface is scraped It is flat so that two kinds of base-materials laying in mould is uniformly and smooth, and thickness is stable, and it is higher to suppress the homogeneity of product come, It is more attractive in appearance.
Brief description of the drawings
The invention will be further described with example below in conjunction with the accompanying drawings.
Fig. 1 is a kind of front view of extra quality formula installation apparatus used in the present invention;
Fig. 2 is a kind of top view of extra quality formula installation apparatus used in the present invention;
Fig. 3 is a kind of flow chart of extra quality water-permeable brick base-material laying method of the present invention.
Embodiment
Reference picture 1- Fig. 2, a kind of extra quality formula installation apparatus used in the present invention, including, raw material laying platform 1, the original Material laying platform 1 is provided with the mould 11 of depression, and the bottom of mould 11 is provided with one piece of matched lifting The lowering or hoisting gear 13 that plate 12 and driving lifter plate 12 move up and down, the top of raw material laying platform 1 are provided with horizontally moveable Extra quality formula doffer 2, the extra quality formula doffer includes bed material storehouse 21 and fabric storehouse 22.
Further, 1 four jiaos of the platform of raw material laying is provided with support column 14.
Further, raw material laying platform 1 both sides are additionally provided with the guide rail moved horizontally for extra quality formula doffer 2 15, the extra quality both sides of formula doffer 2 are provided with the guide wheel 23 to match with the guide rail 15.
Further, the extra quality formula doffer 2 also includes the motor or cylinder for driving it to move horizontally.
A kind of reference picture 3, extra quality water-permeable brick base-material laying method of the invention, comprises the following steps,
S1:Extra quality permeable turn of bed material and fabric are respectively placed in bed material storehouse 21 and fabric storehouse 22;
S2:The lifter plate 12 of the bottom of mould 11 is arranged on certain altitude, bed material storehouse 21 is then moved to shaping The top of mould 11, makes bed material fill up mould 11;
S3:Bed material storehouse 21 is removed, while the bed material in mould 11 is struck off by bed material storehouse 21;
S4:Lifter plate 12 in mould 11 is dropped into bottom, then fabric storehouse 22 is moved on mould 11 Side, makes fabric fill up mould 11;
S5:Fabric storehouse 22 is removed, while the fabric in mould 11 is struck off by fabric storehouse 22, completes extra quality water-permeable brick Base-material is laid.
Further, after bed material storehouse 21 is moved to the top of mould 11 by the step S2, in addition at least once back and forth Reciprocal horizontal moves.
Further, after fabric storehouse 22 is moved to the top of mould 11 by the step S4, in addition at least once back and forth Reciprocal horizontal moves.
The laying depth of bed material and fabric is controlled by the height of the setting of lifter plate 12 of the bottom of mould 11, first led to Cross bed material storehouse 21 and bed material is filled up into certain thickness mould 11, and its surface is struck off, then by fabric storehouse 22 by fabric Whole mould 11 is filled up, and its surface is struck off so that two kinds of base-materials laying in mould 11 is uniformly and smooth, thick Degree is stablized, and the homogeneity of product suppressed is higher, more attractive in appearance.
It is described above, simply presently preferred embodiments of the present invention, the invention is not limited in above-mentioned embodiment, as long as It reaches the technique effect of the present invention with identical means, should all belong to protection scope of the present invention.

Claims (3)

  1. A kind of 1. extra quality water-permeable brick base-material laying method, it is characterised in that comprise the following steps,
    S1:Extra quality permeable turn of bed material and fabric are respectively placed in bed material storehouse (21) and fabric storehouse (22);
    S2:The lifter plate (12) of mould (11) bottom is arranged on certain altitude, is then moved into bed material storehouse (21) Above pattern tool (11), bed material is set to fill up mould (11);
    S3:Bed material storehouse (21) is removed, while the bed material in mould (11) is struck off by bed material storehouse (21);
    S4:Lifter plate (12) in mould (11) is dropped into bottom, fabric storehouse (22) are then moved to mould (11) top, makes fabric fill up mould (11);
    S5:Fabric storehouse (22) is removed, while the fabric in mould (11) is struck off by fabric storehouse (22), is completed extra quality permeable Brick base-material is laid.
  2. 2. a kind of extra quality water-permeable brick base-material laying method according to claim 1, it is characterised in that the step S2 is the bottom of by After feed bin (21) is moved to above mould (11), in addition to reciprocal horizontal moves back and forth at least once.
  3. 3. a kind of extra quality water-permeable brick base-material laying method according to claim 1, it is characterised in that the step S4 is by face After feed bin (22) is moved to above mould (11), in addition to reciprocal horizontal moves back and forth at least once.
CN201711172821.3A 2017-11-22 2017-11-22 A kind of extra quality water-permeable brick base-material laying method Withdrawn CN107877667A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711172821.3A CN107877667A (en) 2017-11-22 2017-11-22 A kind of extra quality water-permeable brick base-material laying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711172821.3A CN107877667A (en) 2017-11-22 2017-11-22 A kind of extra quality water-permeable brick base-material laying method

Publications (1)

Publication Number Publication Date
CN107877667A true CN107877667A (en) 2018-04-06

Family

ID=61777993

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711172821.3A Withdrawn CN107877667A (en) 2017-11-22 2017-11-22 A kind of extra quality water-permeable brick base-material laying method

Country Status (1)

Country Link
CN (1) CN107877667A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108582420A (en) * 2018-04-19 2018-09-28 佛山市东鹏陶瓷有限公司 A kind of preparation process and its all-body tile of the all-body tile of the single side bed of material
CN113601676A (en) * 2021-08-24 2021-11-05 河北孟石代新材料科技有限公司 Production equipment and production method of high-water-permeability water permeable brick taking inorganic solid waste as raw material
CN113696321A (en) * 2021-11-01 2021-11-26 佛山市高明贝斯特陶瓷有限公司 Ceramic production system based on digital cloth

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108582420A (en) * 2018-04-19 2018-09-28 佛山市东鹏陶瓷有限公司 A kind of preparation process and its all-body tile of the all-body tile of the single side bed of material
CN108582420B (en) * 2018-04-19 2020-06-16 佛山市东鹏陶瓷有限公司 Preparation process of full-body brick with single material layer and full-body brick thereof
CN113601676A (en) * 2021-08-24 2021-11-05 河北孟石代新材料科技有限公司 Production equipment and production method of high-water-permeability water permeable brick taking inorganic solid waste as raw material
CN113601676B (en) * 2021-08-24 2022-12-13 河北孟石代新材料科技有限公司 Production equipment and production method of high-water-permeability water permeable brick taking inorganic solid waste as raw material
CN113696321A (en) * 2021-11-01 2021-11-26 佛山市高明贝斯特陶瓷有限公司 Ceramic production system based on digital cloth

Similar Documents

Publication Publication Date Title
CN107877667A (en) A kind of extra quality water-permeable brick base-material laying method
CN103806437B (en) Double-layer vacuum preloading and hydraulic reclamation soft foundation processing method
ATE537950T1 (en) METHOD AND DEVICE FOR PRODUCING SHAPED BLOCKS WITH FIBERS
KR101332202B1 (en) Automatic block forming device and using the same block
CN201525075U (en) Sand brick press
CN105780612B (en) A kind of prefabricated subway assembled track plate and its construction method
CN105484132B (en) A kind of construction method that novel water permeable pavement is mated formation
CN202519561U (en) Urban road permeable cement concrete pavement structure
CN205348206U (en) Caisson cutting edge props up and establishes structure
CN207415663U (en) A kind of extra quality formula installation apparatus
CN206768934U (en) A kind of cistern
CN105421314A (en) Constructing method of waterlogged farmland water three-dimensional regulating and controlling system
CN107932710A (en) A kind of extra quality formula installation apparatus
CN205889503U (en) Concrete mortar examination mould shedder
CN109267578A (en) A kind of inclined-plane plain concrete construction and its construction method
CN204590034U (en) A kind of dam foundation high pressure grouting structure
CN205093378U (en) Ecological fish pond structure
CN110424439B (en) Prefabricated ceramsite concrete hollow slab shaping tire membrane and construction method thereof
CN204728813U (en) A kind of assembling cantilever enclosure wall with illuminating line
CN107032678A (en) A kind of novel gradient water-permeable brick and its production method
CN209307824U (en) A kind of mold making concrete floor tile
CN206928156U (en) A kind of drainage system based on permeable pavement structure
KR101063314B1 (en) Press block molding machine with double side drain groove
CN205501984U (en) Collapsible loess composite foundation water proof ponding system
CN106812039B (en) A kind of landscape is mated formation floor tile and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20180406