CN107872932A CN201610855621.7A CN201610855621A CN107872932A CN 107872932 A CN107872932 A CN 107872932A CN 201610855621 A CN201610855621 A CN 201610855621A CN 107872932 A CN107872932 A CN 107872932A
Authority
CN
China
Prior art keywords
rack
collector
cabinet
communication
input port
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610855621.7A
Other languages
Chinese (zh)
Other versions
CN107872932B (en
Inventor
刘欣
李星
张敬
高程
李伟光
王军超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Vertiv Tech Co Ltd
Original Assignee
Vertiv Tech Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Vertiv Tech Co Ltd filed Critical Vertiv Tech Co Ltd
Priority to CN201610855621.7A priority Critical patent/CN107872932B/en
Publication of CN107872932A publication Critical patent/CN107872932A/en
Application granted granted Critical
Publication of CN107872932B publication Critical patent/CN107872932B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05KPRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
    • H05K5/00Casings, cabinets or drawers for electric apparatus
    • H05K5/02Details
    • H05K5/0247Electrical details of casings, e.g. terminals, passages for cables or wiring
    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05KPRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
    • H05K7/00Constructional details common to different types of electric apparatus
    • H05K7/14Mounting supporting structure in casing or on frame or rack
    • H05K7/1438Back panels or connecting means therefor; Terminals; Coding means to avoid wrong insertion
    • H05K7/1452Mounting of connectors; Switching; Reinforcing of back panels

Landscapes

  • Engineering & Computer Science (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Cooling Or The Like Of Electrical Apparatus (AREA)

Abstract

The invention discloses a kind of rack and data center, to improve the intelligence degree of rack, simplifies the wiring installation operation of data center.Rack includes cabinet and the collector being integrated in cabinet, collector includes several analog input ports, several digital quantity input ports, communication input port, communication output port and control output end mouth, communication input port is used to be connected with the communication output port of the collector of upper level rack, and communication output port is used to be connected with the communication input port of the collector of next stage rack.Data center uses rack provided in an embodiment of the present invention, can be by multiple racks by the communication input port of collector and communication output port fast cascaded, and the intelligence degree of rack is higher, further, it is also possible to simplify the wiring installation operation of data center.

Description

A kind of rack and data center
Technical field
The present invention relates to technical field of communication equipment, more particularly to a kind of rack and data center.
Background technology
Rack is the important component of data center, and it is that server, interchanger, power supplying and distributing equipment etc. provide installation Space.In order to give the equipment such as server to provide more preferable running environment, data center be typically also equipped with uninterrupted power source, air-conditioning, Monitoring device etc., the collaborative work of equipment room need to be uniformly controlled by monitoring device.
Fast cascaded can not be realized between multiple racks at available data center, the intelligence degree of rack is also than relatively low. In addition, traditional data center needs just start the arrangement of monitoring device in the case where interior of equipment cabinet construction is completed, should Requirement of engineering arranges the equipment such as temperature sensor, humidity sensor, door state monitoring in rack, while also needs to using all kinds of Monitoring device is connected to monitoring host computer by cable, and quantities is larger, and deployment cycle is longer.
The content of the invention
The purpose of the embodiment of the present invention is to provide a kind of rack and data center, to improve the intelligence degree of rack, enters One step, the wiring installation operation of data center can also be simplified.
The embodiments of the invention provide a kind of rack, including cabinet and the collector that is integrated in cabinet, the collection Device includes several analog input ports, several digital quantity input ports, communication input port, communication output port and control Output port processed, the communication input port is used to be connected with the communication output port of the collector of upper level rack, described logical News output port is used to be connected with the communication input port of the collector of next stage rack.
Preferably, rack also includes temperature sensor, humidity sensor, water sensor and the gate-shaped being integrated in cabinet State monitoring device, the temperature sensor and humidity sensor are connected with the analog input port of collector respectively, the water Leaching sensor and door state monitoring device are connected with the digital quantity input port of collector respectively.
More excellent, the cabinet door of the cabinet is provided with opening angle and the adjustable air-supply blinds of open area, described to send The control output end mouth of wind blinds and collector connects.
More excellent, the air-supply blinds includes at least two sections air-supply blinds units along the arrangement of cabinet door short transverse.
Preferably, Time-delay power supply unit is provided with the collector, the Time-delay power supply unit is used to open in collector After dynamic setting duration, powered by the communication input port of the collector of the communication downward one-level rack of output port.
Preferably, rack also includes the wind pressure sensor being integrated in cabinet, the mould of the wind pressure sensor and collector Analog quantity input port connects.
Preferably, rack also includes being integrated in the display screen on the outside of the cabinet door of cabinet, the control of the display screen and collector Output port connection processed.
Data center uses rack provided in an embodiment of the present invention, can input multiple racks by the communication of collector Port and communication output port fast cascaded, the intelligence degree of rack is higher, further, it is also possible to simplify the wiring of data center Installation operation.
The embodiment of the present invention also provides a kind of data center, including multiple cascades set such as foregoing any technical scheme institute The rack stated.The rack of the data center can by the communication input port of collector and communication output port fast cascaded, Intelligence degree is higher, and the wiring installation operation of data center is simplified.
Preferably, it is provided with monitoring host computer in first order rack.
Brief description of the drawings
Fig. 1 is one embodiment of the invention rack schematic diagram;
Fig. 2 is the collector schematic diagram of one embodiment of the invention;
Fig. 3 is that one embodiment of the invention rack cascades schematic diagram;
Fig. 4 is another embodiment of the present invention rack schematic diagram;
Fig. 5 is the collector schematic diagram of another embodiment of the present invention;
Fig. 6 is further embodiment of this invention rack schematic diagram.
Reference:
100- racks;10- monitoring host computers;1- cabinets;2- collectors;3- temperature sensors;7- air-supply blinds;
9- display screens;21- analog inputs port;22- digital quantity input ports;23- communicates input port;
24- communicates output port;25- control output ends mouth;26- Time-delay power supply units.
Embodiment
To improve the intelligence degree of rack, and further simplify the wiring installation operation of data center, the present invention is implemented Example provides a kind of rack and data center.To make the object, technical solutions and advantages of the present invention clearer, lift implement below Example is described in further detail to the present invention.
As shown in Figure 1, Figure 2 and Figure 3, the rack 100 that one embodiment of the invention provides, including cabinet 1 and it is integrated in cabinet Collector 2 in body 1, collector 2 include several analog input ports 21, several digital quantity input ports 22, communication Input port 23, communication output port 24 and control output end mouth 25, communication input port 23 are used to adopt with upper level rack The communication output port connection of storage, communication output port 24 are used to connect with the communication input port of the collector of next stage rack Connect.
As depicted in figs. 1 and 2, in a specific embodiment of the invention, rack 100 also includes the temperature being integrated in cabinet 1 Spend sensor 3, humidity sensor, water sensor and door state monitoring device (humidity sensor, water sensor and door state Monitoring device is not shown in figure), the analog quantity of temperature sensor 3 and humidity sensor respectively by cable and collector 2 is defeated Inbound port 21 is connected, and water sensor and door state monitoring device are connected with the digital quantity input port 22 of collector 2 respectively.By It is integrated in temperature sensor 3, humidity sensor, water sensor and door state monitoring device etc. in cabinet 1, without still further Installation, therefore, can greatly simplify the wiring installation operation inside rack 100.
In the embodiment of the present invention, analog input port 21, the particular number of digital quantity input port 22 are unlimited.Fig. 2 institutes Show in embodiment, analog input port 21 is eight, and T1~T6 is used for cut-in temperature sensor, and H1, H2 are used to access humidity Sensor;Digital quantity input port 22 is three, and wherein D1, D2 are used for two doors for accessing corresponding Door of communication apparatus cabinet and back door is set Condition monitoring device, D3 are used to access water sensor;Input port 23 (IN) is communicated to be used for collector power supply and and higher level The collector communication of rack, can be by communicating input port 23 to collector one-time write physical address, title, model etc. Rack information;Output port 24 (OUT) is communicated to be used to power and communicate to the collector of subordinate's rack;Control output end mouth 25 (DO) 1~3 tunnel control debugging output signal is provided, for connecting adjustment equipment.
As shown in Fig. 2 in the preferred embodiment, Time-delay power supply unit 26, Time-delay power supply unit are provided with collector 2 26 are used for after collector 2 starts setting duration, defeated by communicating the communication of collector of the downward one-level rack of output port 24 Inbound port is powered.As described in Figure 3, the cascade of rack 100 of data center is set, after data center powers, first order rack Collector starts, and is supplied after the t seconds that are delayed by communicating communication input port of the output port to the collector of second level rack Electricity;The collector of second level rack starts, and by communicating collector of the output port to third level rack after the t seconds that are delayed Communicate input port power supply;..., the rest may be inferred, until the collector 2 of all racks 100 starts.
Monitoring host computer 10 can be arranged in first order rack, every grade of rack is in debugging mode by physical address, type Number, the rack information such as bar code stored by communication input mouth to collector, be delayed t seconds downward one-level rack in rack collector In the time of collector power supply, monitoring host computer 10 can gather the letter such as the physical address of the rack, model, bar code by cable Breath, and rack order, formation are arranged according to the sequencing of cascade correspondence position of pressing adaptive in monitoring software interface Reason equipment is automatic corresponding with the virtual configuration figure of software, and physical address is manually entered or using dial-up so as to greatly reduce scene Switch sets the troublesome operation of address.
As shown in figure 4, in the preferred embodiment, the cabinet door of cabinet 1 is provided with opening angle and open area can adjust Air-supply blinds 7, air-supply blinds 7 be connected with the control output end mouth of collector 2.More preferably, blinds 7 of blowing is included along cabinet door height Spend at least two sections air-supply blinds units of direction arrangement.Air-supply blinds can be arranged at the front cabinet door or rear cabinet door of cabinet 1, Air-supply blinds can be respectively provided with front cabinet door and rear cabinet door.
In general, the monitoring host computer of data center also access the infrastructure such as air-conditioning, uninterrupted power source, power distribution cabinet simultaneously Monitoring, the quantity of state and analog quantity information that can be gathered according to each rack collector, the refrigeration of dynamic calculation data center need Ask and air output demand, and adjust the refrigerating capacity output and air quantity output of air-conditioning accordingly, so as to play energy-saving effect, greatly The big PUE for reducing data center (Power Usage Effectiveness, abbreviation PUE, refers to all of data center's consumption The ratio between energy of the energy and IT load consumptions.PUE values represent that the green degree of a data center is higher closer to 1).
The collector 2 of each rack 100 can analyze the refrigeration demand of Single Cabinet, according to list according to information is gathered in cabinet The opening angle and open area of the refrigeration demand adjustment air-supply blinds 7 of rack.For example, persistently raise when cabinet temperature and/or When temperature rise rate of change is larger, the opening angle of increase air-supply blinds;When in rack temperatures at localized regions persistently raise and/or When temperature rise rate of change is larger, increase the open degree of that section of air-supply blinds unit corresponding to the regional area.
In an alternative embodiment of the invention, rack also includes several wind pressure sensors being integrated in cabinet, these wind Pressure sensor is connected with P1~P4 ports of the analog input port 21 of collector 2 shown in Fig. 5., can using the technical scheme To realize refrigeration demand and running status that rack is adjusted by blast state self-adaption.
Preferably, as shown in fig. 6, rack 100 also includes being integrated in the display screen 9 on the outside of the cabinet door of cabinet 1, display screen 9 It is connected with the control output end mouth of collector 2.Display screen can be with each collection capacity state value of Dynamic Announce, and is believed according to collection capacity Breath calculates rack load, when load is in security interval, display screen display green;When load exceeds system early warning threshold values, Display screen shows yellow;When load sets higher limit beyond system, display screen shows that red does eye-catching prompting.Display screen 9 Particular type is unlimited, can be LCDs or organic light-emitting diode (OLED) display screen etc..
To sum up, data center uses rack provided in an embodiment of the present invention, multiple racks can be passed through into the logical of collector Input port and communication output port fast cascaded are interrogated, the intelligence degree of rack is higher, further, it is also possible to simplify data center Wiring installation operation.
Refer to shown in Fig. 3, the embodiment of the present invention also provides a kind of data center, including multiple cascades set as foregoing The rack 100 of any technical scheme.Preferably, monitoring host computer 10 is provided with first order rack.The rack of the data center can So that by the communication input port of collector and communication output port fast cascaded, intelligence degree is higher, the cloth of data center Line installation operation is simplified.
Obviously, those skilled in the art can carry out the essence of various changes and modification without departing from the present invention to the present invention God and scope.So, if these modifications and variations of the present invention belong to the scope of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to comprising including these changes and modification.

Claims (9)

1. a kind of rack, it is characterised in that including cabinet and the collector being integrated in cabinet, the collector includes some Individual analog input port, several digital quantity input ports, communication input port, communication output port and control output end Mouthful, the communication input port is used to be connected with the communication output port of the collector of upper level rack, the communication output end Mouth is used to be connected with the communication input port of the collector of next stage rack.
2. rack as claimed in claim 1, it is characterised in that also include temperature sensor, the humidity biography being integrated in cabinet Sensor, water sensor and door state monitoring device, the temperature sensor and the humidity sensor simulation with collector respectively Input port connection is measured, the digital quantity input port of the water sensor and door state monitoring device respectively with collector connects Connect.
3. rack as claimed in claim 2, it is characterised in that the cabinet door of the cabinet is provided with opening angle and open area Adjustable air-supply blinds, the control output end mouth of the air-supply blinds and collector connect.
4. rack as claimed in claim 3, it is characterised in that the air-supply blinds is included along the arrangement of cabinet door short transverse extremely Few two sections of air-supplies blinds unit.
5. rack as claimed in claim 1, it is characterised in that Time-delay power supply unit is provided with the collector, it is described to prolong When electric supply installation be used for collector start setting duration after, pass through it is described communication the downward one-level rack of output port collector Communication input port power supply.
6. rack as claimed in claim 1, it is characterised in that also include the wind pressure sensor being integrated in cabinet, the wind The analog input port of pressure sensor and collector connects.
7. rack as claimed in claim 1, it is characterised in that also include being integrated in the display screen on the outside of the cabinet door of cabinet, institute The control output end mouth for stating display screen and collector connects.
A kind of 8. data center, it is characterised in that the machine as described in any one of claim 1~7 set including multiple cascades Cabinet.
9. data center as claimed in claim 8, it is characterised in that be provided with monitoring host computer in first order rack.
CN201610855621.7A 2016-09-27 2016-09-27 Cabinet and data center Active CN107872932B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610855621.7A CN107872932B (en) 2016-09-27 2016-09-27 Cabinet and data center

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610855621.7A CN107872932B (en) 2016-09-27 2016-09-27 Cabinet and data center

Publications (2)

Publication Number Publication Date
CN107872932A true CN107872932A (en) 2018-04-03
CN107872932B CN107872932B (en) 2020-06-26

Family

ID=61752340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610855621.7A Active CN107872932B (en) 2016-09-27 2016-09-27 Cabinet and data center

Country Status (1)

Country Link
CN (1) CN107872932B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108718489A (en) * 2018-06-28 2018-10-30 广东电网有限责任公司 A kind of display system and network cabinet component

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201657546U (en) * 2010-05-04 2010-11-24 北京金秋果实电子科技有限公司 Monitoring cabinet
CN102073458A (en) * 2009-11-19 2011-05-25 上海圣桥信息科技有限公司 Startup and shutdown time sequence control device for magnetic disk array storage system
CN102221860A (en) * 2011-06-14 2011-10-19 浙江红苹果电子有限公司 Method and device for infinite signal cascade of back board signals among chassises
CN203191759U (en) * 2013-05-03 2013-09-11 中国地震局地球物理研究所 Digital general data collector
CN104915323A (en) * 2015-06-01 2015-09-16 浪潮集团有限公司 Method for realizing multi-level cascade of multi-unit servers based on FPGA
CN105490556A (en) * 2014-09-29 2016-04-13 株洲变流技术国家工程研究中心有限公司 Converter apparatus

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102073458A (en) * 2009-11-19 2011-05-25 上海圣桥信息科技有限公司 Startup and shutdown time sequence control device for magnetic disk array storage system
CN201657546U (en) * 2010-05-04 2010-11-24 北京金秋果实电子科技有限公司 Monitoring cabinet
CN102221860A (en) * 2011-06-14 2011-10-19 浙江红苹果电子有限公司 Method and device for infinite signal cascade of back board signals among chassises
CN203191759U (en) * 2013-05-03 2013-09-11 中国地震局地球物理研究所 Digital general data collector
CN105490556A (en) * 2014-09-29 2016-04-13 株洲变流技术国家工程研究中心有限公司 Converter apparatus
CN104915323A (en) * 2015-06-01 2015-09-16 浪潮集团有限公司 Method for realizing multi-level cascade of multi-unit servers based on FPGA

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108718489A (en) * 2018-06-28 2018-10-30 广东电网有限责任公司 A kind of display system and network cabinet component
CN108718489B (en) * 2018-06-28 2023-04-18 广东电网有限责任公司 Display system and network cabinet assembly

Also Published As

Publication number Publication date
CN107872932B (en) 2020-06-26

Similar Documents

Publication Publication Date Title
CN101790299B (en) Variable air volume intelligent air current control system
CN204796024U (en) High-density micro-module data center
CN107829967A (en) A kind of equipment cooling fan intelligent management apapratus and method
CN203797864U (en) Data-center fresh-air direct natural cooling system of drawer type structure
CN206611686U (en) A kind of server cabinet with drawer type cabinet
CN107872932A (en) A kind of rack and data center
WO2019100716A1 (en) Cabinet, cabinet operation control method and device
CN202166154U (en) Variable air volume intelligent regulating and controlling system for data machine room
CN204761930U (en) Cold passageway rack of intelligent security type
CN203691841U (en) Low-cost temperature control cabinet
CN205606820U (en) Flexible intelligent new trend system
CN205960461U (en) Moisture -proof electrical cabinet
CN103868148A (en) Data center room air distribution regulating system
CN204796025U (en) Container data center of overhead natural heat exchange case
CN203574998U (en) Radiating system and mixed-signal window-opening controller
CN104365221A (en) Temperature-controlled moisturizing-type germination accelerating machine
CN208013707U (en) A kind of intelligent control device for supporting POE cascade power supplies
CN101998813B (en) Water cooling machine cabinet and system thereof
CN206057499U (en) A kind of high-temperature circulation test machine
CN205450923U (en) Computer network equipment box
CN201582944U (en) Variable air volume intelligent airflow regulation and control system
CN208480097U (en) A kind of intelligent computer network cabinet
CN205694012U (en) A kind of multi-action computer network equipment storage cabinet
CN104684362B (en) Using the rack of temperature control device
CN103292423B (en) A kind of method of multi-online indoor machine and total-heat exchanger interlock

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant