CN107842036A - Composite foundation reinforcement gabion baffling structure and construction method - Google Patents

Composite foundation reinforcement gabion baffling structure and construction method Download PDF

Info

Publication number
CN107842036A
CN107842036A CN201710890457.8A CN201710890457A CN107842036A CN 107842036 A CN107842036 A CN 107842036A CN 201710890457 A CN201710890457 A CN 201710890457A CN 107842036 A CN107842036 A CN 107842036A
Authority
CN
China
Prior art keywords
gabion
filling body
composite foundation
construction
loaded filter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710890457.8A
Other languages
Chinese (zh)
Inventor
刘波
牛运华
石志超
陈培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201710890457.8A priority Critical patent/CN107842036A/en
Publication of CN107842036A publication Critical patent/CN107842036A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0208Gabions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/066Quays

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Revetment (AREA)

Abstract

The invention discloses composite foundation reinforcement gabion baffling structure and construction method, and it includes composite foundation (1), reinforced gabion (2), GSZ (3), loaded filter (4) and filling body (5) composition;Described composite foundation (1) locates below ground level and is made up of more vibro-replacement stone columns (1.1), multiple described reinforced gabions (2) are piled up in the top of described composite foundation (1), filling body (5) is provided with the inside of described reinforced gabion (2), the bottom of the filling body (5) is provided with GSZ (3), loaded filter (4) is provided between described reinforced gabion (2) and described filling body (5);The shortcomings that it is overcome in the prior art because foundation bearing capacity is relatively low, and the filling body after barricade and its wall is by larger deformation or even unstable failure is occurred, there is the advantages of fast easy construction, speed of application, wall body low cost.

Description

Composite foundation reinforcement gabion baffling structure and construction method
Technical field
The present invention relates to the technical fields such as water conservancy, highway and water and soil conservation, are more specifically composite foundation reinforcements Gabion baffling structure and construction method.
Background technology
During the filling of the engineerings such as shore protection levee body, highway subgrade, Dumping Sites, generally use barricade resists pressure of banketing Power.When above-mentioned engineering construction is located at coastal region, river loke shore beach, mollisol area, deep covering layer area, earth formation is more It is made up of Extra-fine sand, silt, silty clay, muck soil, traditional barrier wall structure can not meet filling body after itself and its wall Stability requirement, must be combined using other modes with barricade, the pressure of banketing after sharing lood wall.
Traditional barricade material is concrete or stone masonry, and concrete guard wall is related to concrete production, transports, pours, applies Construction equipment is more, complex procedures;Stone masonry barricade needs manually to build by laying bricks or stones, expends substantial amounts of manpower, speed of application is slow.Chinese patent CN104674841B puts block stone using machinery and quickly forms retaining wall, although improving the degree of barricade mechanized construction, adds The fast speed of application of barricade, but it faces same problem with concrete guard wall, stone masonry barricade:When running into above-mentioned geology bar During the poor situation of part, because foundation bearing capacity is relatively low, the filling body after barricade and its wall will occur larger deformation or even Unstable failure, therefore directly should not be used on mollisol, deep covering layer ground.Chinese patent CN205116214U, Although CN104389320B, CN103321243B are using bored concrete pile, micro-steel pile, screw rod pile, rotary churning pile, mixing pile to barricade Ground has carried out consolidation process, but above-mentioned pile body is plain concrete or reinforced concrete structure, complicated construction technique, work of constructing Phase is grown, and construction costs is high.
When filling body height is higher after barricade, pressure of banketing only is resisted in itself by barricade, can cause bricklaying constructed object Product is huge while higher to the requirement for bearing capacity of ground, and construction cost is also higher.
The content of the invention
The first object of the present invention is the weak point for overcoming above-mentioned background technology, and proposes composite foundation reinforcement gabion Barrier wall structure.
The first object of the present invention is implemented by following technical solution:Composite foundation reinforcement gabion baffling structure, It includes composite foundation, reinforced gabion, GSZ, loaded filter and filling body composition;Described composite foundation be located at ground with It is made up of down and more vibro-replacement stone columns, multiple described reinforced gabions are piled up in the top of described composite foundation, described Reinforced gabion on the inside of be provided with filling body, the bottom of the filling body is provided with GSZ, in described reinforcing bar stone Loaded filter is provided between cage and described filling body.
In the above-mentioned technical solutions:Outer ledge of the described vibro-replacement stone column along described reinforced gabion expands arrangement 2- 3 campsheds.
In the above-mentioned technical solutions:Described reinforced gabion is formed using Site Welding and piles up into triangle;It is and adjacent Described reinforced gabion between the fissure of displacement pile up and use it is U-shaped nail be linked to be an entirety.
In the above-mentioned technical solutions:Described reinforced gabion includes keel reinforcing bar and fabricated bar, described fabricated bar Between use galvanized wire colligation;Described keel reinforcing bar be located at the outside of described fabricated bar and be welded to each other into one it is whole Body.
In the above-mentioned technical solutions:Described GSZ layered arrangement is and described in the inside of described filling body Stack from bottom to top bottom of the filling body along described GSZ;Described GSZ lateral length is more than twice of institute The height for the reinforced gabion stated.
In the above-mentioned technical solutions:Described loaded filter is in tilted layout along on the inside of described reinforced gabion, and described is anti- The upper end of filtering layer flushes with the upper end of described reinforced gabion.
The second object of the present invention is to propose a kind of construction method:The construction party of composite foundation reinforcement gabion baffling structure Method, it comprises the following steps;
1., preparation of construction;Needed to carry out levelling of the land, construction cushion coat laying, stake position unwrapping wire and construction equipment according to construction Arrangement in place, vibrating impacter water spray center are less than 5 centimetres with design stake position centre deviation;
2., vibrating and impacting construction of ballast pile;Determine to shake according to the stake footpath size of foundation soil situation and the vibro-replacement stone column needed Type number is rushed, the sequence of construction of more vibro-replacement stone columns is:Filler in vibrating impacter centering in place → vibroflotation pore-forming, plasma discharge → hole, Vibratory compaction → carry out next stage vibroflotation, until forming vibro-replacement stone column in the foundation soil of composite foundation;When a vibro-replacement stone After stake terminates, the position of mobile vibrating impacter to next described vibro-replacement stone column carries out stake processed;
3., steel bar stone cage retaining wall construction;Reinforced gabion, multiple described steel have been piled up above described composite foundation Muscle gabion, which misplaces, piles up into wall, and the block stone particle diameter in described reinforced gabion is 25-40cm, and is fresh dysgeogenous rock Stone;
4., embankment construction after barricade;Filling body is provided with after described reinforced gabion, described filling body, which uses, to be divided Layer fills, grinding compacting;GSZ layering is arranged in described filling body, described GSZ lift height 50cm; Height of laying length of the described GSZ in described filling body not less than twice of steel bar stone cage retaining wall;Described Loaded filter, the thickness 1m of described loaded filter are set between the side of reinforced gabion and described filling body;Described loaded filter is filled out Build material and use fresh building stones, particle diameter should meet the grading requirement of correlation;
In the above-mentioned technical solutions:Described filling body, reinforced gabion, loaded filter three are using in concordant construction and synchronization Rise.
In the above-mentioned technical solutions:Described loaded filter is in tilted layout along on the inside of described reinforced gabion, and described is anti- The upper end of filtering layer flushes with the upper end of described reinforced gabion.
In the above-mentioned technical solutions:Described reinforced gabion is formed using Site Welding and piles up into triangle;It is and adjacent Described reinforced gabion between the fissure of displacement pile up and use it is U-shaped nail be linked to be an entirety;Described reinforced gabion includes keel steel Muscle and fabricated bar, galvanized wire colligation is used between described fabricated bar;Described keel reinforcing bar is located at described grid The outside of reinforcing bar and it is welded to each other into an entirety.
The invention has the advantages that:1st, steel bar stone cage retaining wall can adapt to certain deformation, especially in yielding ground It is more more notable than the advantage of rigid structure barricade in the case of base or deep covering layer ground.
2nd, steel bar stone cage retaining wall can be process using reinforcing bar and block building stones at the construction field (site), easy for construction, speed of application It hurry up.
3rd, consolidation process is carried out to barricade ground using vibro-replacement stone column, live metaling can be made full use of, with concrete Stake or reinforced concrete pile are compared, and without purchasing reinforcing bar, cement, construction technology is easy, quick.When stake footpath is 60cm, stake is a length of During 8m, concrete-pile comprehensive unit price is 66 yuan/m, and vibro-replacement stone column comprehensive unit price is 45 yuan/m, and pile body cost can reduce by 30% More than.
The 4th, GSZ is set in the filling body after barricade, it is possible to increase the globality and non-deformability of filling body, energy Enough reduce the soil pressure suffered by wall, so as to reduce barricade bricklaying volume and its requirement for bearing capacity to ground, save engineering Investment.
Brief description of the drawings
Fig. 1 is the structural plan of the present invention.
Fig. 2 is the structural plan of reinforced gabion in the present invention.
Fig. 3 is the floor plan of the vibro-replacement stone column in the present invention.
In figure:Composite foundation 1, vibro-replacement stone column 1.1, reinforced gabion 2, keel reinforcing bar 2.1, fabricated bar 2.2, Tu Gongge Grid 3, loaded filter 4, filling body 5.
Embodiment
The performance that the invention will now be described in detail with reference to the accompanying drawings, but they do not form limitation of the invention, only It is for example;Advantages of the present invention will become clearer and be readily appreciated that by explanation simultaneously.
Described composite foundation 1 be using vibroreplacement to original soft foundation or deep covering layer ground at Vibro-replacement stone pile composite foundation after reason, its bearing capacity should meet the requirement of barricade resistant slide and antidumping.Through vibro-replacement stone Bearing Capacity of Composite Foundation R after 1.1 consolidation process of stakesp=[1+m (n-1)] × Rs;RsFor the bearing capacity of original ground;M is to shake Rush the replacement rate of broken stone pile 1.1, m=AP/As, APFor the sectional area of broken stone pile, AsFor the area of composite foundation;N is vibro-replacement stone The load intensity share ratio of 1.1 pile bodies of stake and inter-pile soil, n=Rp/Rs;RpFor the bearing capacity of vibro-replacement stone column 1.1.Vibro-replacement stone Stake 1.1 arranges that retaining wall foundation outer rim expands 2-3 campsheds, and stake footpath D, stake spacing L are counted according to above-mentioned formula using equilateral triangle Point counting analysis determines.
Described reinforced gabion 2 is welded at the construction field (site), and single size is 2m × 1m × 1m (length × width × height).Dragon Bone reinforcing bar 2.1 is located at the outside of fabricated bar 2.2, and is welded with fabricated bar 2.2, and galvanized wire is used between fabricated bar 2.2 Colligation.Reinforced gabion 2 is located on composite foundation, and the fissure of displacement of adjacent two layers reinforced gabion 2 is piled up, and all reinforced gabions 2 are adopted each other It is linked to be entirety with U-shaped nail.Block stone particle diameter in reinforced gabion 2 is 25-40cm, and is fresh dysgeogenous rock.
The layering of GSZ 3 is arranged at the inside of filling body 5 after reinforced gabion 2, the lift height of described GSZ 3 50 centimetres.Laying length of the GSZ 3 in filling body can determine according to actual conditions, typically no less than twice of reinforced gabion 2 pile up height.
Described loaded filter 4 is between reinforced gabion 2 and filling body 5,1 meter described of 4 thickness of loaded filter, to prevent Thin particulate matter after barricade in filling body 5 is pulled away.Loaded filter 4 fills material and uses fresh building stones, and particle diameter should meet correlation Grading requirement.
Shown in reference picture 1-3:Composite foundation reinforcement gabion baffling structure, it includes composite foundation 1, reinforced gabion 2, geotechnique Grid 3, loaded filter 4 and filling body 5 form;Described composite foundation 1 locates below ground level and by more 1.1 groups of vibro-replacement stone column Into multiple described reinforced gabions 2 are piled up in the top of described composite foundation 1, are set in the side of described reinforced gabion 2 There is filling body 5, the bottom of the filling body 5 is provided with GSZ 3, in described reinforced gabion 2 and described geotechnological lattice Loaded filter 4 is provided between grid 3.
Outer ledge of the described vibro-replacement stone column 1.1 along described reinforced gabion 2 expands arrangement 2-3 campsheds.
Described reinforced gabion 2 is formed using Site Welding and is piled up into triangle;And adjacent described reinforced gabion 2 Between the fissure of displacement pile up and use it is U-shaped nail be linked to be an entirety.
Described reinforced gabion 2 includes keel reinforcing bar 2.1 and fabricated bar 2.2, is used between described fabricated bar 2.2 Galvanized wire colligation;Described keel reinforcing bar 2.1 be located at the outside of described fabricated bar 2.2 and be welded to each other into one it is whole Body.
The described layered arrangement of GSZ 3 is in the inside of described filling body 5, and described filling body 5 is along described The bottom of GSZ 3 stack from bottom to top;The described lateral length of GSZ 3 is more than twice of described reinforced gabion 2 height.
Inner side of the described loaded filter 4 along described reinforced gabion 2 is in tilted layout, the upper end of described loaded filter 4 and institute The upper end for the reinforced gabion 2 stated flushes.
Present invention additionally comprises the construction method of composite foundation reinforcement gabion baffling structure, and it comprises the following steps;
1., preparation of construction:Needed to carry out levelling of the land, construction cushion coat laying, stake position unwrapping wire and construction equipment according to construction Arrangement in place, adjustment vibrating impacter water spray center are less than 5 centimetres with design stake position centre deviation;
2., vibrating and impacting construction of ballast pile:Determined according to the stake footpath size of foundation soil situation and the vibro-replacement stone column 1.1 needed Vibrating impacter model, the sequence of construction of more vibro-replacement stone columns 1.1 are:In vibrating impacter centering in place → vibroflotation pore-forming, plasma discharge → hole Filler, vibratory compaction → carry out next stage vibroflotation, until forming vibro-replacement stone column 1.1 in the foundation soil of composite foundation 1;When one After vibro-replacement stone column 1.1 terminates, the position of mobile vibrating impacter to next described vibro-replacement stone column 1.1 carries out stake processed;
3., steel bar stone cage retaining wall construction:Single steel reinforcement cage is transported to Retaining wall field in the prefabricated completion of reinforcement yard Ground, after piling up steel reinforcement cage according to design requirement, then building stones are filled into single steel reinforcement cage.Keel reinforcing bar 2.1 is located at fabricated bar 2.2 outside, and welded with fabricated bar 2.2, galvanized wire colligation is used between fabricated bar 2.2.The trade mark of keel reinforcing bar 2.1 is HRB400, diameter 20mm.The trade mark of fabricated bar 2.2 is HPB235, and diameter 10mm, size of mesh opening is 20cm × 20cm.Reinforcing bar stone Cage 2 is located on composite foundation, and the fissure of displacement of adjacent two layers reinforced gabion 2 is piled up, and all reinforced gabions 2 are linked to be using U-shaped nail each other It is overall.
4., embankment construction after barricade;Filling body 5 is provided with after described reinforced gabion 2, described filling body 5 is adopted With placement in layers, grinding compacting;GSZ 3, which is layered, to be arranged in described filling body 5, and described GSZ 3 is layered thickness Spend 50cm;Height of laying length of the described GSZ 3 in described filling body 5 not less than twice of reinforced gabion 2; Loaded filter 4, the thickness 1m of described loaded filter 4 are set between the side of described reinforced gabion 2 and described filling body 5;It is described Loaded filter 4 fill material use fresh building stones, particle diameter should meet correlation grading requirement.
Described filling body 5, reinforced gabion 2, the three of loaded filter 4 using concordant construction and synchronous rise.
Inner side of the described loaded filter 4 along described reinforced gabion 2 is in tilted layout, the upper end of described loaded filter 4 and institute The upper end for the reinforced gabion 2 stated flushes.
Above-mentioned unspecified part is prior art.

Claims (9)

1. composite foundation reinforcement gabion baffling structure, it is characterised in that:It includes composite foundation (1), reinforced gabion (2), geotechnique Grid (3), loaded filter (4) and filling body (5) composition;Described composite foundation (1) locates below ground level and broken by more vibroflotations Stone mar (1.1) is formed, and multiple described reinforced gabions (2) are piled up in the top of described composite foundation (1), in described reinforcing bar Filling body (5) is provided with the inside of gabion (2), the bottom of the filling body (5) is provided with GSZ (3), described Loaded filter (4) is provided between reinforced gabion (2) and described filling body (5).
2. composite foundation reinforcement gabion baffling structure according to claim 1, it is characterised in that:Described vibro-replacement stone column (1.1) arrangement 2-3 campsheds are expanded along the outer ledge of described reinforced gabion (2).
3. composite foundation reinforcement gabion baffling structure according to claim 1 or 2, it is characterised in that:Described reinforcing bar stone Cage (2) is formed using Site Welding and piles up into triangle;And the fissure of displacement is piled up and adopted between adjacent described reinforced gabion (2) It is linked to be an entirety with U-shaped nail.
4. composite foundation reinforcement gabion baffling structure according to claim 3, it is characterised in that:Described reinforced gabion (2) include keel reinforcing bar (2.1) and fabricated bar (2.2), galvanized wire colligation is used between described fabricated bar (2.2); Described keel reinforcing bar (2.1) is located at the outside of described fabricated bar (2.2) and is welded to each other into an entirety.
5. composite foundation reinforcement gabion baffling structure according to claim 4, it is characterised in that:Described GSZ (3) layered arrangement is in the inside of described filling body (5), and bottom of the described filling body (5) along described GSZ (3) Stack from bottom to top in portion;The height of described reinforced gabion (2) of described GSZ (3) lateral length more than twice.
6. composite foundation reinforcement gabion baffling structure according to claim 5, it is characterised in that:Described loaded filter (4) It is in tilted layout along on the inside of described reinforced gabion (2), the upper end of described loaded filter (4) and described reinforced gabion (2) Upper end flushes.
7. the method for the composite foundation reinforcement gabion baffling structure in claim of constructing 1-6 described in any claim, it is special Sign is:It comprises the following steps;
1., preparation of construction;Need progress levelling of the land, construction cushion coat laying, stake position unwrapping wire and construction equipment in place according to construction Arrangement, vibrating impacter water spray center are less than 5 centimetres with design stake position centre deviation;
2., vibrating and impacting construction of ballast pile;Determine to shake according to the stake footpath size of foundation soil situation and the vibro-replacement stone column (1.1) needed Type number is rushed, the sequence of construction of more vibro-replacement stone columns (1.1) is:In vibrating impacter centering in place → vibroflotation pore-forming, plasma discharge → hole Filler, vibratory compaction → carry out next stage vibroflotation, until forming vibro-replacement stone column (1.1) in the foundation soil of composite foundation (1);When After a piece vibro-replacement stone column (1.1) is terminated, the position system of mobile vibrating impacter to next described vibro-replacement stone column (1.1) Stake;
3., steel bar stone cage retaining wall construction;Pile up reinforced gabion (2) above described composite foundation (1), it is multiple described Reinforced gabion (2), which misplaces, piles up into wall, and the block stone particle diameter in described reinforced gabion (2) is 25-40cm, and is not easy wind to be fresh The rock of change;
4., embankment construction after barricade;Filling body (5), described filling body (5) are provided with after described reinforced gabion (2) Using placement in layers, grinding compacting;GSZ (3) layering is arranged in described filling body (5), described GSZ (3) lift height 50cm;Laying length of the described GSZ (3) in described filling body (5) is not less than twice of reinforcing bar The height of gabion (2) barricade;Loaded filter (4) is set between the side of described reinforced gabion (2) and described filling body (5), The thickness 1m of described loaded filter (4);Described loaded filter (4) fills material and uses fresh building stones, and particle diameter should meet the level of correlation With requiring.
8. the construction method of composite foundation reinforcement gabion baffling structure according to claim 7, it is characterised in that:Described Filling body (5), reinforced gabion (2), loaded filter (4) three are using concordant construction and synchronous rising.
9. the construction method of composite foundation reinforcement gabion baffling structure according to claim 8, it is characterised in that:Described Loaded filter (4) is in tilted layout along on the inside of described reinforced gabion (2), the upper end of described loaded filter (4) and described reinforcing bar The upper end of gabion (2) flushes.
CN201710890457.8A 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure and construction method Pending CN107842036A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710890457.8A CN107842036A (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710890457.8A CN107842036A (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure and construction method

Publications (1)

Publication Number Publication Date
CN107842036A true CN107842036A (en) 2018-03-27

Family

ID=61662045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710890457.8A Pending CN107842036A (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure and construction method

Country Status (1)

Country Link
CN (1) CN107842036A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826227A (en) * 2019-01-03 2019-05-31 中交隧道工程局有限公司 A kind of preparation method and its retaining wall of the bilateral slope mortar flag stone retaining wall of high mountain
CN111764214A (en) * 2020-07-15 2020-10-13 湖南省交建工程集团有限公司 Three-dimensional reinforcement treatment construction method for soft soil roadbed geotechnical synthetic material
CN115418904A (en) * 2022-10-09 2022-12-02 河北建筑工程学院 Construction method for improving roadbed seismic structure
CN115478547A (en) * 2022-10-17 2022-12-16 中国二十冶集团有限公司 Method for arranging bridge and culvert conical slope gabion retaining wall
CN115852766A (en) * 2022-11-16 2023-03-28 山东高速工程建设集团有限公司 Construction method for filling subgrade with slag

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204530620U (en) * 2015-03-14 2015-08-05 上海市水利工程设计研究院有限公司 A kind of novel combination type Ecological Retaining Wall
CN205116214U (en) * 2015-09-29 2016-03-30 中铁第四勘察设计院集团有限公司 Composite foundation check guest retaining wall structure
CN106676993A (en) * 2017-01-20 2017-05-17 山西省交通科学研究院 Roadbed reinforcing system of reinforced gravel framework structure and reinforcing method of roadbed reinforcing system
CN207348085U (en) * 2017-09-27 2018-05-11 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement gabion baffling structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204530620U (en) * 2015-03-14 2015-08-05 上海市水利工程设计研究院有限公司 A kind of novel combination type Ecological Retaining Wall
CN205116214U (en) * 2015-09-29 2016-03-30 中铁第四勘察设计院集团有限公司 Composite foundation check guest retaining wall structure
CN106676993A (en) * 2017-01-20 2017-05-17 山西省交通科学研究院 Roadbed reinforcing system of reinforced gravel framework structure and reinforcing method of roadbed reinforcing system
CN207348085U (en) * 2017-09-27 2018-05-11 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement gabion baffling structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘占军等: "钢筋石笼高挡墙在双沟水电站临时工程中的应用", 《吉林水利》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109826227A (en) * 2019-01-03 2019-05-31 中交隧道工程局有限公司 A kind of preparation method and its retaining wall of the bilateral slope mortar flag stone retaining wall of high mountain
CN111764214A (en) * 2020-07-15 2020-10-13 湖南省交建工程集团有限公司 Three-dimensional reinforcement treatment construction method for soft soil roadbed geotechnical synthetic material
CN115418904A (en) * 2022-10-09 2022-12-02 河北建筑工程学院 Construction method for improving roadbed seismic structure
CN115478547A (en) * 2022-10-17 2022-12-16 中国二十冶集团有限公司 Method for arranging bridge and culvert conical slope gabion retaining wall
CN115478547B (en) * 2022-10-17 2023-06-20 中国二十冶集团有限公司 Setting method of bridge-culvert conical slope gabion retaining wall
CN115852766A (en) * 2022-11-16 2023-03-28 山东高速工程建设集团有限公司 Construction method for filling subgrade with slag

Similar Documents

Publication Publication Date Title
CN107842036A (en) Composite foundation reinforcement gabion baffling structure and construction method
CN109736346B (en) Steel anchor pipe reinforced weathered rock stratum reinforced weighing type retaining wall structure and construction method
CN106988178A (en) A kind of subgrade in soft soil zone widened structure and its construction method
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN105937196B (en) A kind of roadbed peg board formula spells wide structure and construction method
CN108560542A (en) A kind of waste tire cladding builds the two-directed reinforcement and its construction method of slag
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN103510504B (en) High saturated uneven reclaimed ground processing method
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN109653242A (en) Composite foundation reinforcement arch box type barrier wall structure and construction method
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN115142465B (en) Construction method of upward inclined gravity retaining wall
CN206902734U (en) A kind of earth construction of soft foundation zone
CN109680671A (en) A kind of liquefaction foundation treatment method based on building waste
CN105804101A (en) Load-reducing retaining system capable of reducing stress of retaining structure, construction method and applications
CN215976664U (en) Rigid pile composite foundation treatment structure of lower horizontal pipe gallery structure
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination
CN107514008A (en) Composite foundation reinforced cantilever retaining wall structure and construction method
CN108643172A (en) Silt geology vibro-replacement stone compacting pile construction method
CN207348085U (en) Composite foundation reinforcement gabion baffling structure
CN209723024U (en) Composite foundation reinforcement counterfort wall structure
CN207452938U (en) Composite foundation reinforced cantilever retaining wall structure
CN107558490A (en) Composite foundation reinforcement rockfill barrier wall structure and construction method
CN215977211U (en) Structure is handled to compound foundation of tubular pile combination cement mixing pile
CN207419517U (en) Composite foundation reinforcement rockfill barrier wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180327

RJ01 Rejection of invention patent application after publication