CN107816116A - A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis - Google Patents
A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis Download PDFInfo
- Publication number
- CN107816116A CN107816116A CN201711077709.1A CN201711077709A CN107816116A CN 107816116 A CN107816116 A CN 107816116A CN 201711077709 A CN201711077709 A CN 201711077709A CN 107816116 A CN107816116 A CN 107816116A
- Authority
- CN
- China
- Prior art keywords
- broken stone
- graded broken
- pipe
- socket
- spigot
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
Abstract
The invention discloses a kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis, belong to draining field, comprise the following steps:(1)Preparation of construction;(2)Surveying setting-out;(3)Pipeline groove excavates;(4)Lay graded broken stone basis;(5)Pipe installing;(6)Inspection shaft is built by laying bricks or stones;(7)Closed-water test.Relative to prior art, beneficial effects of the present invention are:The leakproof advantage of spigot-and-socket reinforced concrete sewer pipe in itself is given full play to, reduces construction costs, shortens the construction period;With convenient material drawing, technique is simple, shorten the duration, saves the advantages such as cost.
Description
Technical field
The invention discloses a kind of spigot-and-socket reinforced concrete sewer pipe installation method based on graded broken stone basis.
Background technology
Spigot-and-socket reinforced concrete sewer pipe is widely used in city as one kind and had stable political situation other drainage systems recently(Such as scape
See draining)In pipeline its have following advantage:1. using " O " shape section, slidingtype rubber ring sealing, have excellent close
Sealing property;2. using flexible interface, installing angle is big, can effectively prevent the pipe joint caused by settlement of foundation, earthquake etc.
Seepy question;3. it is easy for construction, it is reliable quick.
Atlas is installed according to drainpipe at present《Municipal administration drainage channel project and affiliated facility》(06MS201)Construction work
Skill, spigot-and-socket reinforced concrete sewer pipe have two kinds of installation methods, are sandstone basis mounting process and concrete foundation peace respectively
Dress technique.
Atlas《Municipal administration drainage channel project and affiliated facility》(06MS201)The sandstone basis used and concrete foundation are deposited
In following shortcoming:1. need, to the accurate leveling of tube seat, to waste a large amount of manpowers before Pipe installing;2. sandstone basis needs pipeline
Installed in pipe pillow on, and pipe pillow and backing plate be required in advance it is prefabricated, when pipe pillow reach due intensity when could use, this is just needed
Construction period that will be longer;3. concrete foundation is not because operational sequence accounts for any advantage relative to sandstone basis too much yet, more
What is added is time-consuming, laborious, can not also play advantage possessed by spigot-and-socket reinforced concrete sewer pipe completely.
The content of the invention
Long in time limit, costly in the old mounting process of socket joint concrete drain tile to solve the problems, such as, the invention provides hair
The leakproof advantage of spigot-and-socket reinforced concrete sewer pipe in itself is waved, construction costs is reduced, shortens the broken based on grading of construction period
The spigot-and-socket reinforced concrete sewer pipe installation method of stone foundation.
To achieve these goals, the technical solution adopted in the present invention is:A kind of socket joint based on graded broken stone basis
Formula reinforced concrete sewer pipe installation method, it is characterised in that comprise the following steps:(1)Preparation of construction;(2)Surveying setting-out;
(3)Pipeline groove excavates;(4)Lay graded broken stone basis;(5)Pipe installing;(6)Inspection shaft is built by laying bricks or stones;(7)Closed-water test;Its
In:
The step(3)Described in " pipeline groove excavation " refer to according to step(2)In accurate measurement channel excavation side
Line, channel excavation is carried out along excavating sideline.The order of excavation is that excavation is upstream fallen back from downstream.Examined at any time in digging process
Position, size and the bottom land absolute altitude of groove are checked, is not backbreak, and bottom land is flattened roughly;
The step(3)Described in " laying graded broken stone basis " refer to, by deployed graded broken stone mixture, utilize digging
Machine or forklift are backfilling into tube seat, and carry out compacting finishing to the graded broken stone mixture of backfill, it is ensured that its compactness and top surface
Size meets Pipe installing requirement;
The step(5)Described in " Pipe installing " its detailed process be:
A) before the installation of spigot-and-socket reinforced concrete sewer pipe, once review is carried out to basic elevation, pipe centerline and checked, warp
Cross check it is errorless after can carry out pipeline mounting construction.
B) spigot-and-socket reinforced concrete sewer pipe installation comb order be from downstream row upstream.Spigot-and-socket reinforcing bar mixes
The direction of solidifying native drainpipe socket insertion is consistent with current.When limiting needs arrangement placement half-section pipe because of well section distance, half-section pipe
Inspection shaft Inlet and outlet water both sides are come, the half-section pipe of carrying spigots comes the water outlet direction of inspection shaft.
C) pipeline is first clean by the oil removal on the outside of the socket of tube coupling and on the inside of bellmouth before additionally arranging.Advised according to caliber
Lattice select corresponding rubber seal, and in inserted jack groove, it is desirable to accomplish that surrounding is uniform, smoothes out, be distortionless.
D) during down tube, suspension centre is arranged on the center of gravity of pipe.In handling, tube coupling interface is prevented to be damaged.
When e) pacifying pipe, tube coupling is steadily hung down, moves to the interface of comb, adjusts the absolute altitude and axis of tube coupling, then
Symmetrically slowly tensed in both sides with tight pipe chain block and the socket of pipe is inserted into bellmouth, during socket joint pipe, tube coupling
There is still a need for suspend in midair, resistance during reducing tight pipe.After tube coupling socket and bellmouth coincide, the axis and mark of pipe are adjusted
It is high.When tube coupling socket inserts, it should be noted that rubber ring occurs without phenomena such as distortion, de- groove.
F) when pipe socket joint loosens chain block in place, check that the gap n between bell and spigot is 10mm ~ 15mm.
G) macadam-aggregate mix is inserted into pipeline both sides, to obtain fixed -piping, the effect that prevents it to be subjected to displacement.
Preferably, tube seat bottom width is spigot-and-socket reinforced concrete drainage pipe external diameter+every side working width * 2;Often
Side working width:It is 40cm as bore≤500mm;As bore≤1000mm and it is 50cm when being more than 500mm;When in pipe
Footpath≤1500mm and be 60cm when being more than 1000mm;Work as bore>It is 80cm during 1500mm;
Preferably, described graded broken stone mixture is made up of the raw material of following parts by weight:Rubble 60%, aggregate chips 40%.
Preferably, the thickness of graded broken stone mixture layer is not less than 20cm;The width of graded broken stone mixture layer is not small
In drainage pipeline outside dimension+2* per side 10cm;Graded broken stone mixture layer is graded broken stone basis.
Preferably, the mixing and stirring, transport of graded broken stone mixture, backfilling process are as follows:
A) graded broken stone mixture is tested before constructing, compound maximum particle diameter is not more than 25cm;
B) in compound central mix place, the rubble of 60 parts by weight and the aggregate chips of 40 parts by weight are fully mixed and stirred stand-by;
C) graded broken stone mixture is transported;
D) graded broken stone mixture backfills:
The thickness of backfill is not less than adds every side 10cm*2 in 20cm, the width of backfill not less than drainage pipeline external diameter.
Relative to prior art, beneficial effects of the present invention are:Give full play to spigot-and-socket reinforced concrete sewer pipe in itself
Leakproof advantage, reduce construction costs, shorten the construction period;With convenient material drawing, technique is simple, shorten the duration, saves cost
Etc. advantage;This kind of method is low with the requirement on basis to groove, as long as making simple leveling to bottom land, can to carry out grading broken
Stone foundation place mat, then peace pipe, can be carried out inspection shaft immediately and built by laying bricks or stones, closed-water test, backfill to pacify pipe in grooving.This method
Technique is simple, easy for installation, quick construction, short time limit, and expense is low.
Brief description of the drawings
Fig. 1 is that spigot-and-socket reinforced concrete sewer pipe tube seat excavates schematic diagram.
Fig. 2 is spigot-and-socket reinforced concrete sewer pipe graded broken stone basic schematic.
Fig. 3 is spigot-and-socket reinforced concrete sewer pipe interface diagram.
Fig. 4 positions spigot-and-socket reinforced concrete sewer pipe scheme of installation.
Wherein:A is original ground, and B is tube seat wall, and C is graded broken stone basis, and F is trench bottom surfaces, and E is that spigot-and-socket reinforcing bar mixes
Native drainpipe is coagulated, Z is pipe centerline, and a is that pipeline reserves working width per side, and D is outer diameter tube, and C1 is flat base, and C2 is pipe
Seat, G is bellmouth, and H is socket, and J is " O " rubber seal, and n is pipeline gap, and K is wooden a tree, used in making timber for boats, and M is tube coupling to be installed, and L is hand
Cucurbit is drawn, N is chock, and O is steel wire rope.
Embodiment
1,2,3,4 the present invention will be further described below in conjunction with the accompanying drawings.
Specific construction process of the present invention is as follows:
1. preparation of construction:
Graded broken stone mixture is tested before present invention construction, compound maximum particle diameter is not more than 25cm;In compound collection
In mix and stir place, the rubble of 60 parts by weight and the aggregate chips of 40 parts by weight are fully mixed and stirred stand-by;Coordinate control point is carried out at the scene
With the encrypted work of vertical control point.
2. surveying and locating:
A) strictly in-site measurement unwrapping wire is carried out before constructing by design drawing.First surveyed using total powerstation or theodolite and set out pipeline center
Line Z, while survey and set out job site original ground A elevation datas.
B) according to the tube seat bottom surface F design altitudes value that construction drawing provides and live original ground A absolute altitudes, pipe alley is calculated
Groove cutting depth Y and determination groove side slope(That is tube seat wall B)The gradient, spread so as to which basis has surveyed the pipe centerline Z set with lime
Go out the sideline on channel excavation top of the slope both sides suitable for reading.
C) during channel excavation, it should in real time follow up and carry out the control of trench bottom surfaces F (i.e. bottom land) absolute altitude, while should strictly control
Trench bottom surfaces F plan-position and elevation.
3. pipeline groove excavates
Pipeline groove excavates is aided with artificial clear bottom using mechanical equivalent of light excavation.According to the channel excavation sideline of accurate measurement, along opening
Dig sideline and carry out channel excavation.The order of excavation is that excavation is upstream fallen back from downstream.Checked at any time in tube seat in digging process
Heart line Z position, tube seat bottom surface(That is trench bottom surfaces F)Size and absolute altitude, do not backbreak, and tube seat bottom surface is carried out rough whole
It is flat;The size of tube seat bottom surface=outer diameter tube D+ reserved width a*2 of work per side, a are that pipeline reserves working width per side.
4. lay graded broken stone basis
By deployed graded broken stone mixture, it is backfilling into using digging machine or forklift in tube seat, and the graded broken stone of backfill is mixed
Close material(It forms graded broken stone basis C)Carry out compacting finishing, it is ensured that its compactness and top surface size meet Pipe installing requirement;
The width of base C2 wherein in graded broken stone basis is not less than outer diameter tube D+ per side 10cm*2.It is flat in graded broken stone basis
Base C1 is located at below base C2.
5. Pipe installing
A) before spigot-and-socket reinforced concrete sewer pipe E installations, once review is carried out to basic C1 elevations, pipe centerline Z and examined
Look into, pipeline mounting construction can be carried out after review is errorless.
B) spigot-and-socket reinforced concrete sewer pipe E install comb order be from downstream row upstream.Spigot-and-socket reinforcing bar mixes
The direction of solidifying native drainpipe socket H insertions is consistent with current.When limiting needs arrangement placement half-section pipe because of well section distance, half-section pipe
Inspection shaft Inlet and outlet water both sides are come, carrying spigots H half-section pipe comes the water outlet direction of inspection shaft.
C) pipeline is first clean by the oil removal on the outside of the socket H of tube coupling and on the inside of bellmouth G before additionally arranging.According to caliber
Specification selects corresponding rubber seal J, and in inserted jack H grooves, it is desirable to accomplish that surrounding is uniform, smoothes out, be distortionless.
D) during down tube, suspension centre is arranged on the center of gravity of pipe.In handling, tube coupling M interfaces are prevented to be damaged.
When e) pacifying pipe, tube coupling is steadily hung down, moves to the interface of comb, adjusts tube coupling M absolute altitude and axis, then
Symmetrically slowly tensed in both sides with tight pipe chain block L and the socket H of pipe is inserted into bellmouth G, during socket joint pipe, pipe
Section M still needs and suspended in midair, resistance during reducing tight pipe.After tube coupling M sockets H and bellmouth G coincide, the axis of pipe is adjusted
Z and absolute altitude.When tube coupling M sockets H is inserted, it should be noted that rubber seal J occurs without phenomena such as distortion, de- groove.
F) when pipe socket joint loosens chain block L in place, check that the gap n between bell and spigot is 10mm ~ 15mm.
G) macadam-aggregate mix is inserted into pipeline both sides to form base C2, to obtain fixed -piping, prevents it to be subjected to displacement
Effect.
6. inspection shaft is built by laying bricks or stones
Inspection shaft is built by laying bricks or stones according to the inspection shaft pattern of design requirement and position.
7. closed-water test
Closed-water test is carried out according to design requirement.
8. back fill of pipe trough
A) can organize to carry out trench backfill after pipeline closed-water test meets code requirement.It must not contain in backfill earth material organic
Impurity, mud or muck soil must not be used as filler.
B) more than trench bottom to tube top 500 mm scope all should use artificial backfill, can more than more than the cm of tube top 500
Backfilled using machinery, laying compacting should be layered when banketing, its degree of being backfilling and compacted should meet design and code requirement.
The present invention passes through engineering practice, and about 50% can be saved using concrete foundation using above-mentioned technical proposal contrast
Duration, about 40% construction costs can be saved.
The invention is not limited in any way for above-described embodiment, all to be obtained by the way of equivalent substitution or equivalent transformation
Technical scheme, all fall within protection scope of the present invention.
Claims (6)
1. it is a kind of based on graded broken stone basis spigot-and-socket reinforced concrete sewer pipe installation method, it is characterised in that including with
Lower step:(1)Preparation of construction;(2)Surveying setting-out;(3)Pipeline groove excavates;(4)Lay graded broken stone basis;(5)Pipeline is pacified
Dress;(6)Inspection shaft is built by laying bricks or stones;(7)Closed-water test;Wherein:
The step(3)Described in " pipeline groove excavation " refer to according to step(2)In accurate measurement channel excavation side
Line, channel excavation is carried out along excavating sideline;The order of excavation is that excavation is upstream fallen back from downstream;Examined at any time in digging process
Position, size and the bottom land absolute altitude of groove are checked, is not backbreak, and bottom land is flattened roughly;
The step(3)Described in " laying graded broken stone basis " refer to, by deployed graded broken stone mixture, utilize digging
Machine or forklift are backfilling into tube seat, and carry out compacting finishing to the graded broken stone mixture of backfill, it is ensured that its compactness and top surface
Size meets Pipe installing requirement;
The step(5)Described in " Pipe installing " its detailed process be:
A) before the installation of spigot-and-socket reinforced concrete sewer pipe, once review is carried out to basic elevation, pipe centerline and checked, warp
Cross check it is errorless after can carry out pipeline mounting construction;
B) spigot-and-socket reinforced concrete sewer pipe installation comb order be from downstream row upstream;Spigot-and-socket armored concrete
The direction of drainpipe socket insertion is consistent with current;Because when well section distance, which limits needs, arranges placement half-section pipe, half-section pipe comes
Inspection shaft Inlet and outlet water both sides, the half-section pipe of carrying spigots come the water outlet direction of inspection shaft;
C) pipeline is first clean by the oil removal on the outside of the socket of tube coupling and on the inside of bellmouth before additionally arranging;Selected according to caliber specification
With corresponding rubber seal, and in inserted jack groove, it is desirable to accomplish surrounding uniformly, it is smooth-going, distortionless;
D) during down tube, suspension centre is arranged on the center of gravity of pipe;In handling, tube coupling interface is prevented to be damaged;
When e) pacifying pipe, tube coupling is steadily hung down, moves to the interface of comb, adjusts the absolute altitude and axis of tube coupling, then with tight
Pipe chain block symmetrically slowly tenses in both sides inserts bellmouth by the socket of pipe, and during socket joint pipe, tube coupling is still
Need to suspend in midair, resistance during reducing tight pipe;After tube coupling socket and bellmouth coincide, the axis and absolute altitude of pipe are adjusted;
When tube coupling socket inserts, it should be noted that rubber ring is occurred without distortion, the phenomenon of de- groove;
F) when pipe socket joint loosens chain block in place, check that the gap between bell and spigot is 10mm ~ 15mm;
G) macadam-aggregate mix is inserted into pipeline both sides, with fixed -piping, prevents it to be subjected to displacement.
A kind of 2. spigot-and-socket reinforced concrete sewer pipe installation side based on graded broken stone basis according to claim 1
Method, it is characterised in that:Tube seat bottom width is spigot-and-socket reinforced concrete drainage pipe external diameter+every side working width * 2.
A kind of 3. spigot-and-socket reinforced concrete sewer pipe installation side based on graded broken stone basis according to claim 1
Method, it is characterised in that:Described graded broken stone mixture is made up of the raw material of following parts by weight:Rubble 60%, aggregate chips 40%.
A kind of 4. spigot-and-socket reinforced concrete sewer pipe installation side based on graded broken stone basis according to claim 1
Method, it is characterised in that:The thickness of graded broken stone mixture layer is not less than 20cm;The width of graded broken stone mixture layer is not less than row
Waterpipe outside dimension+2* is per side 10cm;Graded broken stone mixture layer is graded broken stone basis.
A kind of 5. spigot-and-socket reinforced concrete sewer pipe installation side based on graded broken stone basis according to claim 1
Method, it is characterised in that:The the mixing and stirring, transport of graded broken stone mixture, backfilling process are as follows:
A) graded broken stone mixture is tested before constructing, compound maximum particle diameter is not more than 25cm;
B) in compound central mix place, the rubble of 60 parts by weight and the aggregate chips of 40 parts by weight are fully mixed and stirred stand-by;
C) graded broken stone mixture is transported;
D) graded broken stone mixture backfills:
The thickness of backfill is not less than adds every side 10cm*2 in 20cm, the width of backfill not less than drainage pipeline external diameter.
A kind of 6. spigot-and-socket reinforced concrete sewer pipe installation side based on graded broken stone basis according to claim 2
Method, it is characterised in that:It is per side working width:It is 40cm as bore≤500mm;As bore≤1000mm and it is more than
It is 50cm during 500mm;As bore≤1500mm and it is 60cm when being more than 1000mm;Work as bore>It is 80cm during 1500mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711077709.1A CN107816116A (en) | 2017-11-06 | 2017-11-06 | A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711077709.1A CN107816116A (en) | 2017-11-06 | 2017-11-06 | A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107816116A true CN107816116A (en) | 2018-03-20 |
Family
ID=61603863
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711077709.1A Pending CN107816116A (en) | 2017-11-06 | 2017-11-06 | A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107816116A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653238A (en) * | 2018-11-23 | 2019-04-19 | 中国五冶集团有限公司 | A kind of total level ground drainage pipeline based process method |
CN112303333A (en) * | 2020-11-18 | 2021-02-02 | 郑州一建集团有限公司 | Construction method of bell and spigot concrete pipe |
CN112594444A (en) * | 2020-11-26 | 2021-04-02 | 中核华辰工程管理有限公司 | Construction method of main water supply pipeline from water plant to mountain |
CN114278786A (en) * | 2021-12-21 | 2022-04-05 | 中交三公局第三工程有限公司 | Pipeline bracket for pipeline installation and socket pipeline construction method |
CN114992383A (en) * | 2022-04-20 | 2022-09-02 | 天津建工城市建设发展有限公司 | Pipeline installation method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204266137U (en) * | 2014-11-25 | 2015-04-15 | 中核华泰建设有限公司 | A kind of novel municipal porous pavement road drainage structure |
CN106759474A (en) * | 2016-11-28 | 2017-05-31 | 南通大学 | The construction method of flexible spigot-and-socket common pipe trench |
-
2017
- 2017-11-06 CN CN201711077709.1A patent/CN107816116A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204266137U (en) * | 2014-11-25 | 2015-04-15 | 中核华泰建设有限公司 | A kind of novel municipal porous pavement road drainage structure |
CN106759474A (en) * | 2016-11-28 | 2017-05-31 | 南通大学 | The construction method of flexible spigot-and-socket common pipe trench |
Non-Patent Citations (1)
Title |
---|
北京土木建筑学会: "《市政基础设施工程 施工组织设计与施工方案》", 30 November 2015 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653238A (en) * | 2018-11-23 | 2019-04-19 | 中国五冶集团有限公司 | A kind of total level ground drainage pipeline based process method |
CN112303333A (en) * | 2020-11-18 | 2021-02-02 | 郑州一建集团有限公司 | Construction method of bell and spigot concrete pipe |
CN112594444A (en) * | 2020-11-26 | 2021-04-02 | 中核华辰工程管理有限公司 | Construction method of main water supply pipeline from water plant to mountain |
CN112594444B (en) * | 2020-11-26 | 2022-05-06 | 中核华辰工程管理有限公司 | Construction method of main water supply pipeline from water plant to mountain |
CN114278786A (en) * | 2021-12-21 | 2022-04-05 | 中交三公局第三工程有限公司 | Pipeline bracket for pipeline installation and socket pipeline construction method |
CN114992383A (en) * | 2022-04-20 | 2022-09-02 | 天津建工城市建设发展有限公司 | Pipeline installation method |
CN114992383B (en) * | 2022-04-20 | 2024-04-05 | 天津建工城市建设发展有限公司 | Pipeline installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107816116A (en) | A kind of spigot-and-socket reinforcing bar Concrete Drainage Pipe installation method based on graded broken stone basis | |
CN104631470B (en) | The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method | |
CN103774616B (en) | From the Ecological Retaining Wall construction method that embedded block is built by laying bricks or stones | |
CN107587557A (en) | Outdoor water engineering construction method | |
CN101565964A (en) | Construction method for mounting outdoor embedded high-density polyethylene double-wall corrugated drain pipe | |
CN205172598U (en) | Pipe curtain spouts a supporting construction soon | |
CN110344423A (en) | A kind of drop shaft sinking forms the construction method of water level for local deep foundation pit under high water level | |
CN107938692A (en) | A kind of draining and recharge construction method and structure | |
CN106759473A (en) | The constructing structure and its construction method of underground pipe gallery and road | |
CN113186924A (en) | Subway foundation pit deep-buried karst cave treatment method | |
CN103938617A (en) | Super-deep underground continuous wall and construction method thereof | |
CN108223910A (en) | A kind of ductile iron pipe passes through the construction method of aqueous soil layer | |
CN108385700A (en) | Slope reinforcement and guard method | |
CN113774917B (en) | Safe construction method for earth and rockfill excavation and side slope supporting engineering | |
CN106122589A (en) | A kind of earth pressure balance method | |
CN104153371A (en) | Grouting-to-stop-water construction method of underwater rubble bed | |
CN110258695A (en) | The construction method of big partial size cobble mixed soil hydraulic grab diaphram wall | |
CN111560958A (en) | Construction method of water-rich deep foundation pit in silty clay stratum | |
CN112609703A (en) | Construction process for supporting soil nailing wall | |
CN108571000A (en) | The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river | |
CN104695458A (en) | Construction method of deep stirring and jet grouting compound pile waterproof curtain | |
CN102430277A (en) | Coarse grid sunk well for physically processing waste water and construction method thereof | |
CN106638675A (en) | Reverse structural steel and bamboo splint soil retaining construction method | |
CN112112657B (en) | New construction method for digging and building inclined shaft of coal mine | |
CN207828994U (en) | It is a kind of draining and recharge constructing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180320 |