CN107803101B - The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology - Google Patents

The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology Download PDF

Info

Publication number
CN107803101B
CN107803101B CN201711047565.5A CN201711047565A CN107803101B CN 107803101 B CN107803101 B CN 107803101B CN 201711047565 A CN201711047565 A CN 201711047565A CN 107803101 B CN107803101 B CN 107803101B
Authority
CN
China
Prior art keywords
mounting rail
demister
spray thrower
lower section
body lower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711047565.5A
Other languages
Chinese (zh)
Other versions
CN107803101A (en
Inventor
刘长富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Original Assignee
Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China filed Critical Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Priority to CN201711047565.5A priority Critical patent/CN107803101B/en
Publication of CN107803101A publication Critical patent/CN107803101A/en
Application granted granted Critical
Publication of CN107803101B publication Critical patent/CN107803101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/14Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
    • B01D53/18Absorbing units; Liquid distributors therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/14Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
    • B01D53/1456Removing acid components
    • B01D53/1481Removing sulfur dioxide or sulfur trioxide

Abstract

Fume desulfurating absorption tower structure, including absorb column foot tower and absorption tower ontology.Absorption tower ontology includes mutually connected ontology lower section and upper section.Demister mounting rail layer and spray thrower mounting rail layer are equipped in ontology lower section.The manufacturing process of absorption tower ontology: manufacture ontology upper casing, upper body lower section, lower body lower section manufacture demister mounting rail layer, spray thrower mounting rail layer, floor stringer;Demister mounting rail and upper body lower section are connected, spray thrower mounting rail and lower body lower section are connected.The i.e. absorption tower ontology that ontology upper section, lower body lower section and upper body lower section are fixed together.

Description

The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology
Technical field
The present invention relates to the manufacturing processes of a kind of absorption tower structure and absorption tower ontology.
Background technique
The pernicious gases such as the sulfur dioxide in flue gas, the nitrogen oxides that generate when fire coal, fuel oil, combustion gas are discharged into atmosphere, cause Acid rain destroys ecological environment, influences the health of people.For the related environmental regulation in China to sulfur dioxide in flue gas, nitrogen oxygen The more stringent control for allowing concentration of emission to propose of compound controls standard, and various flue gas desulfurization technique method and apparatus are met the tendency of And it gives birth to.
Application number 201110386124.4,102512944 B of Authorization Notice No. CN, entitled " fume desulfurizing tower " Chinese patent discloses a kind of fume desulfurizing tower, but that there are body constructions is more complicated, and canvas layer is easily corroded damage, needs Often the problem of replacement.
Summary of the invention
Main inventive purpose of the invention, it is simple to be to provide a kind of structure, processing and manufacturing, a kind of flue gas with long service life Desulfuration absorbing tower structure, and a kind of manufacturing process of absorption tower ontology is provided.
To provide a kind of fume desulfurating absorption tower structure, technical solution used in the present invention is: a kind of flue gas desulfurization absorption Tower structure, including absorb column foot tower and absorption tower ontology.Absorption tower ontology includes ontology lower section and ontology upper section.Ontology upper section is Hollow frustum type which is provided with second level demister pressure difference mouth.Ontology lower section includes upper and lower ontology lower section.Upper body lower section is set There is first order demister pressure difference mouth.The lower end flanges of upper body lower section and ontology upper section are connected.Upper and lower ontology lower section flange is solid Even.The lower end of lower body lower section and absorption column foot tower flange are connected.Upper body lower section is equipped with two layers of demister mounting rail, lower body Lower section is equipped with three layer of spray thrower mounting rail.Each demister mounting rail layer include two isometric demister short beams, two it is isometric Demister mounting rail central sill and one eradicate day with fog beam length beam be installed, and short beam, central sill are symmetrical parallel about long beam.It removes for two layers Corresponding demister mounting rail is coplanar in day with fog mounting rail layer.Two layers is equipped with above every layer of demister beam except spray film inputs Pipe, this two layers except spray film input pipe be interconnected and lower layer except spray film input pipe output end and be mounted on this layer of demister and pacify Fill the demister on beam removes the connection of spray film input port, and upper layer is and corresponding except spray film import except the input terminal of spray film input pipe Connection.Two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail are equipped in each spray thrower mounting rail layer, It is mutually parallel between long and short spray thrower mounting rail and long spray thrower mounting rail.It is upper and lower to spray in three spray thrower mounting rail layers The big angle drenched in the angle between the spray thrower mounting rail in device mounting rail layer is equal to 120 °, the corresponding spray in spray thrower mounting rail layer Leaching device mounting rail divides the size of this hexagonal angle equally.Upper body lower section and ontology upper section are equipped with the first order, second level demister Pressure difference mouth.The top of each spray beam layer is equipped with spray tube.The both ends of demister mounting rail are solid in two layers of demister mounting rail layer Equipped with the connected plate of demister mounting rail, the top of the connected plate of corresponding demister mounting rail is installed with demister mounting rail upstream Be connected plate;The connected plate in demister mounting rail upstream and demister mounting rail are connected, and plate outer edge is equal to be consolidated with upper body lower section inner wall Even.
Here, upper body upper section and ontology upper section are equipped with the first order, second level demister pressure difference mouth, each spray beam layer Top is equipped with spray tube and all uses in general assembly.Above-described fume desulfurating absorption tower structure, structure is concisely reliable, processing system It is easy to make, easy to use and long service life.
Preferably, further including having four isometric floor stringers, adjacent short spray thrower in each spray thrower mounting rail layer Mounting rail and long spray thrower mounting rail floor stringer corresponding with two are connected.In addition, further including having demister mounting rail beam hole envelope Plate and spray thrower mounting rail beam hole sealing plate.Upper body lower section is equipped with corresponding demister mounting rail supported hole, and lower body lower section is set There is corresponding spray thrower mounting rail supported hole.The both ends of demister mounting rail are stretched outside outside demister mounting rail supported hole, demister The both ends of mounting rail and the weldering of upper body lower section connect.The both ends of spray thrower mounting rail are supported on corresponding spray thrower mounting rail supported hole It welds above and with lower body lower section and connects.Each demister mounting rail stretches out under the beam hole and the stretching of each spray thrower mounting rail of upper body lower section Demister mounting rail beam hole sealing plate and spray thrower mounting rail beam hole sealing plate is used to close respectively in the beam hole of ontology lower section.It is further excellent Choosing further includes having demister mounting rail connection support plate to connect support plate with spray thrower mounting rail.Demister mounting rail connection branch Fagging connects the perforation being respectively equipped in support plate with demister mounting rail, spray thrower mounting rail adaptation with spray thrower mounting rail. Demister mounting rail both ends pass through demister mounting rail and connect support plate, and demister mounting rail connects support plate and upper body lower section After weldering connects, demister mounting rail, which connects support plate and welds again with demister mounting rail, to be connected.Spray thrower mounting rail both ends pass through spray thrower Mounting rail connect support plate, spray thrower mounting rail connect support plate and lower body lower section weldering connect after, spray thrower mounting rail again and spray The connection support plate weldering of device mounting rail is drenched to connect.In addition, demister mounting rail, spray thrower mounting rail and floor stringer are rectangle hollow Beam.Ontology upper section is even made of multiple trapezoidal bar segment welderings.This preferred embodiment, structurally reasonable, easy for installation, reliable operation.
In conclusion the beneficial effect of the fume desulfurating absorption tower structure is: fume desulfurating absorption tower is by absorption column foot Tower and absorption tower ontology, which are connected, to be constituted, and absorption tower ontology is made of ontology upper section, upper body lower section, lower body lower section again.Entirely Absorption tower body construction is stablized, and demister mounting rail layer and spray thrower mounting rail are rationally distributed, and easy for installation, reliable operation is whole Body running effect is good.
The present invention, the manufacturing process of absorption tower ontology have step apparent, fabricate easy advantage.Specific manufacture Process is as follows: a kind of manufacturing process of absorption tower ontology, it is characterized in that:
One, it gets out crane first;
Two, ontology upper section is produced:
Three, ontology upper section is sling using crane;
Four, on the body section it is fabricated below go out upper body lower section;
Five, ontology upper section is put on upper body lower section;Ontology upper section and upper body lower section are linked together;Then again The ontology upper section and upper body lower section to connect together is sling using crane;Upper body lower section lower end surface is higher than the height of lower body lower section Degree;
Six, in upper body lower section lower body lower section out fabricated below:
So far the manufacture of absorption tower ontology is completed.The manufacture of absorption tower ontology, step is clearly compact, and manufacture efficiency is high, system The absorption tower ontology long service life produced.
Detailed description of the invention
Fig. 1: overall structure diagram of the invention;
Fig. 2: the schematic diagram of overall structure other direction of the invention;
Fig. 3: one layer of demister mounting rail and demister mounting rail stiffening plate and upper body lower section attachment structure schematic diagram;
Fig. 4: one layer of spray thrower mounting rail and lower body lower section attachment structure schematic diagram;
Fig. 5: the attachment structure schematic diagram of semicircle tubular-type support post and lower body lower section.
In figure: absorption tower ontology 1, ontology upper section 2, ontology lower section 3, upper body lower section 31, lower body lower section 32, demister Mounting rail 4, demister mounting rail short beam 41, demister mounting rail central sill 42, demister install beam length beam 43, spray thrower mounting rail 5, short spray thrower mounting rail 51, long spray thrower mounting rail 52, floor stringer 6, demister mounting rail beam hole sealing plate 7, spray thrower installation The hole Liang Liang sealing plate 8, demister mounting rail connect support plate 9, and spray thrower mounting rail connects support plate 10, remove spray film input pipe 11, Demister beam is connected plate 12, semicircle tubular-type support post 13, semicircle tubular-type support post 14, semicircle tubular-type support post 15, semi-circular tube Type support column 16, semicircle tubular-type support post 17, semicircle tubular-type support post 18, semicircle tubular-type support post 19, first order demister Pressure difference mouth M4, second level demister pressure difference mouth M5.
Specific embodiment
Below with reference to the embodiments and with reference to the accompanying drawing the technical solutions of the present invention will be further described.
A kind of embodiment of fume desulfurating absorption tower structure:
As shown in Figs. 1-5, the present invention includes absorbing column foot tower and absorption tower ontology 1.Absorption tower ontology includes ontology lower section 3 With ontology upper section 2;Ontology upper section is hollow frustum type, which is provided with second level demister pressure difference mouth M5;Ontology lower section include it is upper, Lower body lower section 31,32, upper body lower section are equipped with first order demister pressure difference mouth M4;The lower end of upper body lower section and ontology upper section Flange is connected;Upper and lower ontology lower section flange is connected;The lower end of lower body lower section and absorption column foot tower flange are connected;Under upper body Section is equipped with two layers of demister mounting rail 4, and lower body lower section is equipped with three layer of spray thrower mounting rail 5;Each demister mounting rail layer packet It includes two demister mounting rail short beam 41, two isometric isometric demister mounting rail central sills 42 and one and eradicates day with fog mounting rail Long beam 43, and two short beams, that two central sills are respectively relative to long beam is symmetrical parallel;Corresponding demisting in two layers of demister mounting rail layer Device mounting rail is coplanar;Two layers is equipped with above every layer of demister beam except spray film input pipe 11, this two layers except spray film input pipe phase Intercommunicated and lower layer output end except spray film input pipe and the demister being mounted on this layer of demister mounting rail except spray film Spray film inlet communication and is accordingly removed except the input terminal of spray film input pipe in input port connection, upper layer;Each spray thrower mounting rail Two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail 51,52, short spray thrower mounting rail and length are equipped in layer It is mutually parallel between spray thrower mounting rail;Spray thrower in three spray thrower mounting rail layers, in upper and lower spray thrower mounting rail layer The big angle in angle between mounting rail is equal to 120 °, and the corresponding spray thrower mounting rail in middle spray thrower mounting rail layer divides this equally The size of hexagonal angle;Upper body lower section and ontology upper section are equipped with the first order, the second level demister pressure difference mouth M4, M5, each to spray The both ends that the top of beam layer is equipped with demister mounting rail in spray tube M6, M7, M8, two layers demister mounting rail layer, which are installed with, removes Day with fog mounting rail stiffening plate 12, the top of corresponding demister mounting rail stiffening plate are installed with demister mounting rail upstream and are connected Plate;The connected plate in demister mounting rail upstream and demister mounting rail stiffening plate outer edge are connected with upper body lower section inner wall;It removes Day with fog mounting rail and spray thrower mounting rail are rectangle hollow beam.Further include in each spray thrower mounting rail layer have four it is isometric Floor stringer 6, adjacent short spray thrower mounting rail and long spray thrower mounting rail floor stringer corresponding with two are connected.Floor stringer 6 is Rectangle hollow beam.
It further include having demister mounting rail beam hole sealing plate 7 and spray thrower mounting rail beam hole sealing plate 8;Upper body lower section is equipped with phase The demister mounting rail supported hole answered, lower body lower section are equipped with corresponding spray thrower mounting rail supported hole;Demister mounting rail Both ends are stretched outside outside demister mounting rail supported hole, and the both ends of demister mounting rail and the weldering of upper body lower section connect;Spray thrower mounting rail Both ends be supported on corresponding spray thrower mounting rail supported hole and with lower body lower section weld connect;On each demister mounting rail stretches out Demister mounting rail beam hole sealing plate is used respectively in the beam hole that the beam hole of ontology lower section and each spray thrower mounting rail stretch out lower body lower section It is closed with spray thrower mounting rail beam hole sealing plate.
Preferably, further including thering is demister mounting rail connection support plate 9 to connect support plate 10 with spray thrower mounting rail;It removes Day with fog mounting rail connection support plate is connected with spray thrower mounting rail to be respectively equipped with and demister mounting rail, spray thrower peace in support plate Fill the perforation of beam adaptation;Demister mounting rail both ends pass through demister mounting rail and connect support plate, demister mounting rail connection branch After fagging and the weldering of upper body lower section connect, demister mounting rail, which connects support plate and welds again with demister mounting rail, to be connected;Spray thrower installation Beam both ends pass through spray thrower mounting rail and connect support plate, after spray thrower mounting rail connects support plate and lower body lower section weldering company, spray Leaching device mounting rail connects support plate weldering with spray thrower mounting rail again and connects.Ontology upper section is even made of the trapezoidal steel plate strip section weldering of muti-piece.
In addition, lower body lower section is additionally provided with being connected by both ends and lower body lower section inner wall, horizontal, opening upper half The supporting layer that tubular type support column 13,14,15,16,17,18,19 is constituted, can be used to catch dropping liquid, specific structural details are because being Simple technique, this will not be repeated here.In addition, being required to coat glass flake, such as drench at some positions with anti-corruption needs Beam connects between the section surface and outer surface of semicircle tubular-type support post 15 under support plate and lower body.
A kind of embodiment of the manufacturing process of absorption tower ontology:
One, it gets out crane first;
Two, ontology upper section 2 is produced:
[1] ontology upper section main body is hollow frustum type, is formed by welding by lath;
[2] the lower end weldering of ontology upper section main body is connected with the mounting flange phase connected for the upper end weldering with upper body lower section 31 Ring flange even;
[3] second level demister pressure difference mouth M5;
Three, ontology upper section 2 is sling using crane;
Four, section 2 upper body lower section 31, step out fabricated below includes: on the body
[1] ring flange for being respectively used to be connected with ontology upper section 2 and lower body lower section 32 is produced;
[2] two groups of long, medium and short demister mounting rail groups are produced, every group includes that two isometric demister mounting rails are short 41, two, beam isometric demister mounting rail central sills 42 and one eradicate day with fog installation beam length beam 43;It produces and removes accordingly simultaneously Day with fog mounting rail beam hole sealing plate 7, demister mounting rail connect support plate 9, demister mounting rail stiffening plate 12;
[3] upper body lower section 31, including the perforation of corresponding demister mounting rail and the first order are produced with corresponding steel plate Demister pressure difference mouth M4;
[4] the good corresponding ring flange of solid welding is distinguished in the upper and lower side of upper body lower section 31;
[5] two layers of demister mounting rail installation perforation, two layers of demister installation are produced in the lower end of upper body lower section 31 Beam installs consistency from top to bottom of perforating accordingly in perforation, and every layer is equipped with five groups of demister mounting rails installation perforation, first group of demisting altogether The line of centres of device mounting rail installation perforation and the diameter of upper body lower section 31 are overlapped, another two groups of demister mounting rails installation perforation The line of centres about longest one group demister mounting rail installation perforation the line of centres it is symmetrical two-by-two;
[6] the both ends of demister installation beam length beam in lower layer of upper body lower section 31 of perforation;First carry out first Positioning adjustment, then carry out second of positioning adjustment;
[7] upper demister mounting rail is covered on the both ends for being exposed at 31 outer surface of upper body lower section of demister installation beam length beam Support plate 9 is connected, keeps demister installation beam length beam motionless, demister mounting rail connection support plate 9 is successive and upper body 31 outer surface of lower section and demister installation beam length beam solid welding are together;
[8] sealing plate 7 solid welding in demister mounting rail beam hole is sealed the Liang Kongshang of demister installation beam length beam;
[9] step identical to [8] with [6] successively pacifies corresponding demister mounting rail connection support plate 9 with demister Fill beam central sill, demister mounting rail short beam and the 31 outer surface solid welding of upper body lower section together;Corresponding demister mounting rail The successive solid welding of beam hole sealing plate 7 seals the Liang Kongshang of demister mounting rail central sill, demister mounting rail short beam;
[10] demister installation beam length beam, demister mounting rail central sill have been completed, after demister mounting rail short beam at upper Each demister mounting rail both ends in body lower section 31 are fixed together with demister mounting rail stiffening plate 12 respectively, wherein demister Mounting rail stiffening plate is first together with the 31 inner surface solid welding of upper body lower section;
[11] the step of pressing [6] to [10] installs upper one layer of five elimination day with fog installation beam length beams;
Five, ontology upper section 2 is put on upper body lower section 31;Ontology upper section 2 and upper body lower section 31 are linked together; Then crane is recycled to sling the ontology upper section 2 and upper body lower section 31 to connect together;Under 31 lower end surface of upper body lower section is higher than The height of ontology lower section 32;
Six, in the lower body lower section 32 out fabricated below of upper body lower section 31:
[1] ring flange for being respectively used to be connected with upper body lower section 31 and absorption column foot tower is produced;
[2] three groups of spray thrower mounting rail groups are produced, each spray thrower mounting rail group includes two isometric short spray throwers Mounting rail, two long spray thrower mounting rail 51,52 and four isometric isometric floor stringers 6;In addition, also producing corresponding spray Device mounting rail beam hole sealing plate 8, spray thrower mounting rail connect support plate 10;
[3] lower body lower section 32 is produced with corresponding steel plate, the spray thrower installation including three layers of spray thrower mounting rail group Beam mounting hole;Every layer of spray thrower mounting rail mounting hole shares eight, and eight spray thrower mounting rail mounting holes symmetrically divide in pairs Cloth is in the two sides of the same diameter of approximately the same plane;The symmetrical diameter of most upper one layer of eight spray thrower mounting rail mounting hole and most Big angle in the angle of cut of the symmetrical diameter of eight spray thrower mounting rail mounting hole of next layer is equal to 120 °, intermediate one layer eight spray The symmetrical diameter of device mounting rail mounting hole divides this hexagonal angle equally;It is the distance between two neighboring spray thrower mounting rail group, most upper Distance and basecoat spray thrower mounting rail group of the layer spray thrower mounting rail group apart from 32 upper surface of lower body lower section are apart from lower 32 lower end surface of body lower section is equidistant;
[4] upper and lower side of corresponding ring flange and lower body lower section 32 is connected;The lower end of lower body lower section 32 Ring flange and absorption column foot tower are fixed together;The association of upper body lower section 31 and ontology upper section 2 being connected together is put down, And the upper end of the association and lower body lower section 32 is fixed together by flange arrangement;
[5] a long spray thrower mounting rail is passed through respectively minimum one group of spray thrower mounting rail of lower body lower section 32 Mounting hole, and it is supported on the both ends of the spray thrower mounting rail in the spray thrower mounting rail mounting hole of left and right;First the spray thrower is pacified It fills beam and carries out the first positioning adjustment, then carry out second of positioning adjustment;Then the spray thrower mounting rail fix tightly;[6] at this The both ends of spray thrower mounting rail are nested with spray thrower mounting rail connection support plate 10 respectively;First spray thrower mounting rail is connected and is supported The weldering of the outer surface of plate 10 and lower body lower section 32 connects together, then spray thrower mounting rail is connected support plate 10 and spray thrower installation Beam weldering connects together;Respectively sealed together with the both ends solid welding of spray thrower mounting rail with one block of spray thrower mounting rail beam hole sealing plate 8 The spray thrower mounting rail beam hole;
[7] according to [5] and [6] the good another root long of step solid welding spray thrower mounting rail;
[8] continue the good two short spray thrower mounting rails of step solid welding according to [5] and [6];
[9] upper two floor stringers 6 are welded between two long and short two root spray thrower mounting rail combinations;
[10] middle layer is installed according to the step of [5] to [9], is then installed further in accordance with the step of [5] to [9] most upper Layer;
Seven, produce that length is different according to installation site and different, semicircle tubular-type support post 13,14,15,16,17, 18,19, the both ends of these semicircle tubular-type support posts are connected with lower body lower section inner wall respectively, and these semicircle tubular-type support posts In horizontal, opening upwards state;
So far, the manufacture of absorption tower ontology is completed.

Claims (7)

1. a kind of fume desulfurating absorption tower structure, including column foot tower and absorption tower ontology are absorbed, it is characterized in that: absorption tower ontology packet Include ontology lower section and ontology upper section;Ontology upper section is hollow frustum type, which is provided with second level demister pressure difference mouth;Ontology lower section Including upper and lower ontology lower section, upper body lower section is equipped with first order demister pressure difference mouth;The lower end of upper body lower section and ontology upper section Flange is connected;Upper and lower ontology lower section flange is connected;The lower end of lower body lower section and absorption column foot tower flange are connected;Under upper body Section is equipped with two layers of demister mounting rail, and lower body lower section is equipped with three layer of spray thrower mounting rail;Each demister mounting rail layer includes Two isometric demister mounting rail short beams, two isometric demister mounting rail central sills and one eradicate day with fog and install beam length beam, And two short beams, that two central sills are respectively relative to long beam is symmetrical parallel;Corresponding demister installation in two layers of demister mounting rail layer Beam is coplanar;Two layers is equipped with above every layer of demister beam except spray film input pipe, be interconnected except spray film input pipe for this two layers and Lower layer except the output end of spray film input pipe and connecting except spray film input port for the demister that is mounted on this layer of demister mounting rail Logical, spray film inlet communication and is accordingly removed except the input terminal of spray film input pipe in upper layer;It is equipped in each spray thrower mounting rail layer Two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail, short spray thrower mounting rail and long spray thrower mounting rail Between it is mutually parallel;The folder between spray thrower mounting rail in three spray thrower mounting rail layers, in upper and lower spray thrower mounting rail layer Big angle in angle is equal to 120 °, and the corresponding spray thrower mounting rail in middle spray thrower mounting rail layer divides the size of this hexagonal angle equally; Upper body lower section and ontology upper section are equipped with the first order, second level demister pressure difference mouth, and each top for spraying beam layer is equipped with spray It manages, the both ends of demister mounting rail are installed with demister mounting rail stiffening plate in two layers of demister mounting rail layer, remove accordingly The top of day with fog mounting rail stiffening plate is installed with the connected plate in demister mounting rail upstream;Demister mounting rail upstream be connected plate and Demister mounting rail stiffening plate outer edge is connected with upper body lower section inner wall;Demister mounting rail and spray thrower mounting rail are Rectangle hollow beam.
2. fume desulfurating absorption tower structure according to claim 1, it is characterized in that: also being wrapped in each spray thrower mounting rail layer Include four isometric floor stringers (6), adjacent short spray thrower mounting rail and long spray thrower mounting rail auxiliary corresponding with two Beam is connected.
3. fume desulfurating absorption tower structure according to claim 2, it is characterized in that: floor stringer (6) is rectangle hollow beam.
4. fume desulfurating absorption tower structure according to claim 1, it is characterized in that: further including having demister mounting rail beam hole Sealing plate (7) and spray thrower mounting rail beam hole sealing plate (8);Upper body lower section be equipped with corresponding demister mounting rail supported hole, lower Body lower section is equipped with corresponding spray thrower mounting rail supported hole;The both ends of demister mounting rail are stretched outside demister mounting rail supported hole Outside, the both ends of demister mounting rail and the weldering of upper body lower section connect;The both ends of spray thrower mounting rail are supported on corresponding spray thrower peace It fills on beam supported hole and is welded with lower body lower section and connected;Each demister mounting rail stretches out beam hole and each spray thrower peace of upper body lower section Demister mounting rail beam hole sealing plate and spray thrower mounting rail beam hole sealing plate is used to close respectively in the beam hole that dress beam stretches out lower body lower section.
5. according to fume desulfurating absorption tower structure described in claim 4 any one, it is characterized in that: further including having demister peace Dress beam connection support plate (9) connects support plate (10) with spray thrower mounting rail;Demister mounting rail connects support plate and spray thrower The perforation with demister mounting rail, spray thrower mounting rail adaptation is respectively equipped in mounting rail connection support plate;Demister mounting rail Both ends pass through demister mounting rail and connect support plate, after demister mounting rail connects support plate and upper body lower section weldering company, demisting Device mounting rail, which connects support plate and welds again with demister mounting rail, to be connected;Spray thrower mounting rail both ends pass through spray thrower mounting rail connection branch Fagging, after spray thrower mounting rail connects support plate and lower body lower section weldering company, spray thrower mounting rail connects with spray thrower mounting rail again Support plate weldering is connect to connect.
6. fume desulfurating absorption tower structure described in -5 any one according to claim 1, it is characterized in that: ontology upper section is by muti-piece Trapezoidal steel plate strip section weldering is even constituted.
7. a kind of manufacturing process of absorption tower ontology, it is characterized in that:
One, it gets out crane first;
Two, ontology upper section (2) are produced:
[1] ontology upper section main body is hollow frustum type, is formed by welding by lath;
[2] mounting flange that the lower end weldering of ontology upper section main body is connected with for connecting with the weldering of the upper end of upper body lower section (31) is connected Ring flange;
[3] second level demister pressure difference mouth (M5);
Three, ontology upper section (2) are sling using crane;
Four, section (2) is fabricated below out upper body lower section (31) on the body, and step includes:
[1] ring flange for being respectively used to be connected with ontology upper section (2) and lower body lower section (32) is produced;
[2] two groups of long, medium and short demister mounting rail groups are produced, every group includes two isometric demister mounting rail short beams (41), two isometric demister mounting rail central sills (42) and one eradicate day with fog installation beam length beam (43);It produces simultaneously corresponding Demister mounting rail beam hole sealing plate (7), demister mounting rail connect support plate (9), demister mounting rail stiffening plate (12);
[3] it is produced upper body lower section (31) with corresponding steel plate, including the perforation of corresponding demister mounting rail and the first order are removed Day with fog pressure difference mouth (M4);
[4] the good corresponding ring flange of solid welding is distinguished in the upper and lower side of upper body lower section (31);
[5] two layers of demister mounting rail installation perforation, two layers of demister mounting rail are produced in the lower end of upper body lower section (31) Consistency from top to bottom of perforating accordingly in perforation is installed, every layer is equipped with five groups of demister mounting rails installation perforation, first group of demister altogether The line of centres of mounting rail installation perforation and the diameter of upper body lower section (31) are overlapped, another two groups of demister mounting rails installation perforation The line of centres about longest one group demister mounting rail installation perforation the line of centres it is symmetrical two-by-two;
[6] both ends of demister installation beam length beam are passed through in the perforation of next layer of upper body lower section (31);It is fixed first to carry out first Position adjustment, then carry out second of positioning adjustment;
[7] demister mounting rail is put on the both ends for being exposed at upper body lower section (31) outer surface of demister installation beam length beam to connect Connect support plate (9), keep the demister installation beam length beam it is motionless, demister mounting rail connection support plate (9) successively with upper Body lower section (31) outer surface and demister installation beam length beam solid welding are together;
[8] demister mounting rail beam hole sealing plate (7) solid welding is sealed the Liang Kongshang of demister installation beam length beam;
[9] step identical to [8] with [6] is successively installed corresponding demister mounting rail connection support plate (9) with demister Beam central sill, demister mounting rail short beam and upper body lower section (31) outer surface solid welding are together;Corresponding demister mounting rail Beam hole sealing plate (7) successively solid welding seals the Liang Kongshang of demister mounting rail central sill, demister mounting rail short beam;
[10] demister installation beam length beam, demister mounting rail central sill have been completed, after demister mounting rail short beam under upper body Each demister mounting rail both ends in section (31) are fixed together with demister mounting rail stiffening plate (12) respectively, wherein demister Mounting rail stiffening plate is first together with upper body lower section (31) inner surface solid welding;
[11] the step of pressing [6] to [10] installs upper one layer of five elimination day with fog installation beam length beams;
Five, ontology upper section (2) is put on upper body lower section (31);Ontology upper section (2) and upper body lower section (31) are connected to Together;Then crane is recycled to sling the ontology upper section (2) and upper body lower section (31) to connect together;Under upper body lower section (31) End face is higher than the height of lower body lower section (32);
Six, fabricated below out lower body lower section (32) in upper body lower section (31):
[1] ring flange for being respectively used to be connected with upper body lower section (31) and absorption column foot tower is produced;
[2] three groups of spray thrower mounting rail groups are produced, each spray thrower mounting rail group includes two isometric short spray thrower installations Beam, two isometric long spray thrower mounting rails (51,52) and four isometric floor stringers (6);In addition, also producing corresponding spray Device mounting rail beam hole sealing plate (8), spray thrower mounting rail connect support plate (10);
[3] lower body lower section (32) are produced with corresponding steel plate, the spray thrower mounting rail including three layers of spray thrower mounting rail group Mounting hole;Every layer of spray thrower mounting rail mounting hole shares eight, and eight spray thrower mounting rail mounting holes are symmetrical in pairs In the two sides of the same diameter of approximately the same plane;The symmetrical diameter of most upper one layer of eight spray thrower mounting rail mounting hole and most lower Big angle in the angle of cut of the symmetrical diameter of one layer of eight spray thrower mounting rail mounting hole is equal to 120 °, intermediate one layer of eight spray thrower The symmetrical diameter of mounting rail mounting hole divides this hexagonal angle equally;The distance between two neighboring spray thrower mounting rail group, top layer Distance and basecoat spray thrower mounting rail group of the spray thrower mounting rail group apart from lower body lower section (32) upper surface are apart from lower Body lower section (32) lower end surface is equidistant;
[4] upper and lower side of corresponding ring flange and lower body lower section (32) is connected;The lower end of lower body lower section (32) Ring flange and absorption column foot tower are fixed together;Put down the connection of upper body lower section (31) and ontology upper section (2) being connected together Zoarium, and the upper end of the association and lower body lower section (32) is fixed together by flange arrangement;
[5] minimum one group of the spray thrower mounting rail that a long spray thrower mounting rail passes through lower body lower section (32) is pacified respectively Hole is filled, and is supported on the both ends of the spray thrower mounting rail in the spray thrower mounting rail mounting hole of left and right;First the spray thrower is installed Beam carries out the first positioning adjustment, then carries out second of positioning adjustment;Then the spray thrower mounting rail fix tightly;[6] in the spray The both ends of leaching device mounting rail are nested with spray thrower mounting rail connection support plate (10) respectively;First spray thrower mounting rail is connected and is supported The weldering of the outer surface of plate (10) and lower body lower section (32) connects together, then spray thrower mounting rail connection support plate (10) and sprays The weldering of device mounting rail connects together;Respectively existed with the both ends solid welding of one piece of spray thrower mounting rail beam hole sealing plate (8) and spray thrower mounting rail The spray thrower mounting rail beam hole is sealed together;
[7] according to [5] and [6] the good another root long of step solid welding spray thrower mounting rail;
[8] continue the good two short spray thrower mounting rails of step solid welding according to [5] and [6];
[9] upper two floor stringers (6) are welded between two long and short two root spray thrower mounting rail combinations;
[10] middle layer is installed according to the step of [5] to [9], then installs top layer further in accordance with the step of [5] to [9];
So far, the manufacture of absorption tower ontology is completed.
CN201711047565.5A 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology Active CN107803101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711047565.5A CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711047565.5A CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Publications (2)

Publication Number Publication Date
CN107803101A CN107803101A (en) 2018-03-16
CN107803101B true CN107803101B (en) 2019-10-01

Family

ID=61582997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711047565.5A Active CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Country Status (1)

Country Link
CN (1) CN107803101B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2899917Y (en) * 2006-05-25 2007-05-16 郝成海 Smoke desulfurizing and denitrifying device by ammonia method
CN201073590Y (en) * 2007-07-18 2008-06-18 中建七局安装工程有限公司 Absorbing tower with flue gas desulfurization
CN203540255U (en) * 2013-07-26 2014-04-16 华北电力大学(保定) Fume gas desulfurization defogging device in coal-fired power plant

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2899917Y (en) * 2006-05-25 2007-05-16 郝成海 Smoke desulfurizing and denitrifying device by ammonia method
CN201073590Y (en) * 2007-07-18 2008-06-18 中建七局安装工程有限公司 Absorbing tower with flue gas desulfurization
CN203540255U (en) * 2013-07-26 2014-04-16 华北电力大学(保定) Fume gas desulfurization defogging device in coal-fired power plant

Also Published As

Publication number Publication date
CN107803101A (en) 2018-03-16

Similar Documents

Publication Publication Date Title
CN204073809U (en) Low-temperature plasma industrial
CN103122667A (en) Light-weight steel structure plafond of large-span underground powerhouse of hydroelectric station
CN107803101B (en) The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology
CN205127730U (en) Desulfurization absorption tower with liquid layer is held to vortex
CN106237782A (en) The modularity installation method of active carbon desulfurization denitration adsorption tower
CN203916431U (en) A kind of gaseous oxidation is in conjunction with the flue gas combined desulfurization and denitration device of wet absorption
CN103768930A (en) FCC regenerated flue gas dustproof denitration reactor
CN206240331U (en) Vertical single hop modularization flue gas desulfurization and denitrification absorption/regenerating unit
CN108031267A (en) A kind of industrial smoke high-level cleaner
CN106268171A (en) The installation method of activated carbon smoke eliminator adsorption system
CN105597502A (en) Low-temperature ozone oxidation denitration system
CN207591562U (en) A kind of structure of fume desulfurating absorption tower
CN205288052U (en) Low temperature ozone oxidation deNOx systems
CN202654942U (en) SCR (Selective Catalytic Reduction) plate type denitration catalyst double-module unit assembled box
CN210495900U (en) High-efficient single-tower desulfurization is dust removal defogging device in coordination
CN210145805U (en) Desulfurization spray set
CN204735097U (en) Degree of depth desulphurization unit
CN208482234U (en) A kind of flue gas wet denitration device
CN207605575U (en) A kind of desulfurization carries effect and flue gas even distribution device
CN111701370A (en) High-efficient desulfurization dust removal spray set
CN205164486U (en) Novel improve wet flue gas desulfurization system mass transfer efficiency device
CN206508755U (en) Horizontal single hop modularization flue gas desulfurization and denitrification adsorbent equipment
CN206463732U (en) A kind of exhaust gas purification and treatment device
CN110585911A (en) SCR denitration device
CN206342990U (en) A kind of desulfurizer mist eliminator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant