CN107803101A - The manufacturing process of fume desulfurating absorption tower structure and absorption tower body - Google Patents

The manufacturing process of fume desulfurating absorption tower structure and absorption tower body Download PDF

Info

Publication number
CN107803101A
CN107803101A CN201711047565.5A CN201711047565A CN107803101A CN 107803101 A CN107803101 A CN 107803101A CN 201711047565 A CN201711047565 A CN 201711047565A CN 107803101 A CN107803101 A CN 107803101A
Authority
CN
China
Prior art keywords
mounting rail
demister
spray thrower
body hypomere
hypomere
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711047565.5A
Other languages
Chinese (zh)
Other versions
CN107803101B (en
Inventor
刘长富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Original Assignee
Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China filed Critical Three Ningbo Branch Cos Of Smelting Group Co Ltd Of China
Priority to CN201711047565.5A priority Critical patent/CN107803101B/en
Publication of CN107803101A publication Critical patent/CN107803101A/en
Application granted granted Critical
Publication of CN107803101B publication Critical patent/CN107803101B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/14Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
    • B01D53/18Absorbing units; Liquid distributors therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B01PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
    • B01DSEPARATION
    • B01D53/00Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols
    • B01D53/14Separation of gases or vapours; Recovering vapours of volatile solvents from gases; Chemical or biological purification of waste gases, e.g. engine exhaust gases, smoke, fumes, flue gases, aerosols by absorption
    • B01D53/1456Removing acid components
    • B01D53/1481Removing sulfur dioxide or sulfur trioxide

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Analytical Chemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Treating Waste Gases (AREA)

Abstract

Fume desulfurating absorption tower structure, including absorb column foot tower and absorption tower body.Absorption tower body includes mutually connected body hypomere and epimere.Demister mounting rail layer and spray thrower mounting rail layer are provided with body hypomere.The manufacturing process of absorption tower body:Manufacture body upper casing, upper body hypomere, lower body hypomere, manufacture demister mounting rail layer, spray thrower mounting rail layer, floor stringer;Demister mounting rail and upper body hypomere are connected, spray thrower mounting rail and lower body hypomere are connected.The i.e. absorption tower body that body epimere, lower body hypomere and upper body hypomere are fixed together.

Description

The manufacturing process of fume desulfurating absorption tower structure and absorption tower body
Technical field
The present invention relates to a kind of manufacturing process for absorbing tower structure and absorption tower body.
Background technology
The pernicious gas such as fire coal, fuel oil, sulfur dioxide in flue gas, nitrogen oxides caused by combustion gas is discharged into air, causes Acid rain, ecological environment is destroyed, influence the health of people.For the relevant environmental regulation in China to sulfur dioxide in flue gas, nitrogen oxygen The more strict control for allowing concentration of emission to propose of compound controls standard, and various flue gas desulfurization technique method and apparatus meet the tendency of And give birth to.
Application number 201110386124.4, the B of Authorization Notice No. CN 102512944, entitled " fume desulfurizing tower " Chinese patent discloses a kind of fume desulfurizing tower, but it is more complicated body construction to be present, canvas layer be easily corroded damage, it is necessary to The problem of often changing.
The content of the invention
The main inventive purpose of the present invention, it is to provide a kind of simple in construction, processing and manufacturing, a kind of flue gas of service life length Desulfuration absorbing tower structure, and a kind of manufacturing process of absorption tower body is provided.
To provide a kind of fume desulfurating absorption tower structure, the technical scheme used in the present invention is:A kind of flue gas desulfurization absorbs Tower structure, including absorb column foot tower and absorption tower body.Absorption tower body includes body hypomere and body epimere.Body epimere is Hollow frustum type, it which is provided with second level demister pressure difference mouth.Body hypomere includes upper and lower body hypomere.Upper body hypomere is set There is first order demister pressure difference mouth.The lower end flanges of upper body hypomere and body epimere are connected.Upper and lower body hypomere flange is consolidated Even.The lower end of lower body hypomere and absorption column foot tower flange are connected.Upper body hypomere is provided with two layers of demister mounting rail, lower body Hypomere is provided with three layer of spray thrower mounting rail.Each demister mounting rail layer include two isometric demister short beams, two it is isometric Demister mounting rail central sill and one eradicate day with fog installation beam length beam, and short beam, central sill are symmetrical parallel on long beam.Remove for two layers Corresponding demister mounting rail is coplanar in day with fog mounting rail layer.Two layers is equipped with above every layer of demister beam except spray film inputs Pipe, this two layers except spray film input pipe be interconnected and lower floor except the output end of spray film input pipe and installed in this layer of demister peace The spray film input port of removing for filling the demister on beam connects, and upper strata is except the input of spray film input pipe is equal and removes spray film import accordingly Connection.Two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail are provided with each spray thrower mounting rail layer, It is mutually parallel between long and short spray thrower mounting rail and long spray thrower mounting rail.In three spray thrower mounting rail layers, upper and lower spray The big angle drenched in the angle between the spray thrower mounting rail in device mounting rail layer is equal to 120 °, the corresponding spray in spray thrower mounting rail layer Leaching device mounting rail divides the size of this hexagonal angle equally.Upper body hypomere and body epimere are provided with the first order, second level demister Pressure difference mouth.The top of each spray beam layer is provided with shower.The both ends of demister mounting rail are solid in two layers of demister mounting rail layer Provided with the connected plate of demister mounting rail, the top of the connected plate of corresponding demister mounting rail is installed with demister mounting rail upstream Be connected plate;The connected plate in demister mounting rail upstream and demister mounting rail are connected, and plate outward flange is equal and upper body hypomere inwall is consolidated Even.
Here, upper body epimere and body epimere are provided with the first order, second level demister pressure difference mouth, each spray beam layer All used provided with shower in general assembly top.Above-described fume desulfurating absorption tower structure, structure is concisely reliable, processing system Make easily, easy to use and service life is grown.
Preferably, also include four isometric floor stringers, adjacent short spray thrower in each spray thrower mounting rail layer Mounting rail and long spray thrower mounting rail floor stringer corresponding with two are connected.In addition, also include demister mounting rail beam hole envelope Plate and spray thrower mounting rail beam hole shrouding.Upper body hypomere is provided with corresponding demister mounting rail supported hole, and lower body hypomere is set There is corresponding spray thrower mounting rail supported hole.The both ends of demister mounting rail are stretched outside demister mounting rail supported hole, demister The both ends of mounting rail and the weldering of upper body hypomere connect.The both ends of spray thrower mounting rail are supported on corresponding spray thrower mounting rail supported hole Weld above and with lower body hypomere and connect.Each demister mounting rail is stretched out under the beam hole and the stretching of each spray thrower mounting rail of upper body hypomere Closed respectively with demister mounting rail beam hole shrouding and spray thrower mounting rail beam hole shrouding in the beam hole of body hypomere.It is further excellent Choosing, also include demister mounting rail connection supporting plate and connect supporting plate with spray thrower mounting rail.Demister mounting rail connection branch Fagging connects the perforation being respectively equipped with supporting plate with demister mounting rail, spray thrower mounting rail adaptation with spray thrower mounting rail. Demister mounting rail both ends connect supporting plate and upper body hypomere through demister mounting rail connection supporting plate, demister mounting rail After weldering connects, demister mounting rail connection supporting plate is welded with demister mounting rail again to be connected.Spray thrower mounting rail both ends pass through spray thrower Mounting rail connect supporting plate, spray thrower mounting rail connection supporting plate and lower body hypomere weldering connect after, spray thrower mounting rail again and spray The connection supporting plate weldering of device mounting rail is drenched to connect.In addition, demister mounting rail, spray thrower mounting rail and floor stringer are rectangle hollow Beam.Body epimere is even made up of multiple trapezoidal bar segment welderings.This preferred scheme, rational in infrastructure, easy for installation, reliable operation.
In summary, the beneficial effect of the fume desulfurating absorption tower structure is:Fume desulfurating absorption tower is by absorption column foot Tower and absorption tower body, which are connected, to be formed, and absorption tower body is made up of body epimere, upper body hypomere, lower body hypomere again.Entirely Absorption tower body construction is stable, and demister mounting rail layer and spray thrower mounting rail are rationally distributed, and easy for installation, reliable operation is whole Body running effect is good.
The present invention, the manufacturing process of absorption tower body, have step apparent, fabricate the advantages of easy.Specific manufacture Process is as follows:A kind of manufacturing process of absorption tower body, it is characterized in that:
First, crane is got out first;
2nd, body epimere is produced:
3rd, a body epimere is sling using crane;
4th, body epimere it is fabricated below go out on body hypomere;
5th, body epimere is put on upper body hypomere;Body epimere and upper body hypomere are linked together;Then recycle Crane slings the body epimere to connect together and upper body hypomere;Upper body hypomere lower surface is higher than the height of lower body hypomere;
6th, upper body hypomere it is fabricated below go out lower body hypomere:
So far the manufacture of absorption tower body is completed.The manufacture of absorption tower body, step is clearly compact, and manufacture efficiency is high, produces Absorption tower body service life length.
Brief description of the drawings
Fig. 1:The overall structure diagram of the present invention;
Fig. 2:The schematic diagram of the overall structure other direction of the present invention;
Fig. 3:One layer of demister mounting rail and demister mounting rail reinforcing plate and upper body hypomere attachment structure schematic diagram;
Fig. 4:One layer of spray thrower mounting rail and lower body hypomere attachment structure schematic diagram;
Fig. 5:The attachment structure schematic diagram of semicircle tubular-type support post and lower body hypomere.
In figure:Absorption tower body 1, body epimere 2, body hypomere 3, upper body hypomere 31, lower body hypomere 32, demister Mounting rail 4, demister mounting rail short beam 41, demister mounting rail central sill 42, demister installation beam length beam 43, spray thrower mounting rail 5, short spray thrower mounting rail 51, long spray thrower mounting rail 52, floor stringer 6, demister mounting rail beam hole shrouding 7, spray thrower installation Liang Liang holes shrouding 8, demister mounting rail connection supporting plate 9, spray thrower mounting rail connection supporting plate 10, except spray film input pipe 11, Demister beam is connected plate 12, semicircle tubular-type support post 13, semicircle tubular-type support post 14, semicircle tubular-type support post 15, semi-circular tube Type support column 16, semicircle tubular-type support post 17, semicircle tubular-type support post 18, semicircle tubular-type support post 19, first order demister Pressure difference mouth M4, second level demister pressure difference mouth M5.
Embodiment
Below by embodiment, and with reference to accompanying drawing, technical scheme is described in further detail.
A kind of embodiment of fume desulfurating absorption tower structure:
As Figure 1-5, the present invention includes absorbing column foot tower and absorption tower body 1.Absorption tower body includes body hypomere 3 and this Body epimere 2;Body epimere is hollow frustum type, which is provided with second level demister pressure difference mouth M5;Body hypomere includes upper and lower Body hypomere 31,32, upper body hypomere are provided with first order demister pressure difference mouth M4;The lower end flanges of upper body hypomere and body epimere It is connected;Upper and lower body hypomere flange is connected;The lower end of lower body hypomere and absorption column foot tower flange are connected;Upper body hypomere is set There is two layers of demister mounting rail 4, lower body hypomere is provided with three layer of spray thrower mounting rail 5;Each demister mounting rail layer includes two The isometric demister mounting rail central sill 42 and one of the isometric demister mounting rail short beam 41, two of root eradicates day with fog installation beam length beam 43, and two short beams, two central sills are respectively symmetrical parallel relative to long beam;Corresponding demister peace in two layers of demister mounting rail layer It is coplanar to fill beam;Two layers is equipped with above every layer of demister beam and removes spray film input pipe 11, is mutually interconnected except spray film input pipe for this two layers Logical and lower floor the output end except spray film input pipe and the demister on this layer of demister mounting rail except spray film input Mouth connection, upper strata is except the input of spray film input pipe is equal and removes spray film inlet communication accordingly;In each spray thrower mounting rail layer Provided with two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail 51,52, short spray thrower mounting rail and long spray It is mutually parallel between device mounting rail;In three spray thrower mounting rail layers, the spray thrower installation in upper and lower spray thrower mounting rail layer Equal to 120 °, the corresponding spray thrower mounting rail in middle spray thrower mounting rail layer divides this hexagonal angle equally at the big angle in angle between beam Size;Upper body hypomere and body epimere are provided with the first order, the second level demister pressure difference mouth M4, M5, each spray beam layer The both ends that top is provided with demister mounting rail in shower M6, M7, M8, two layers demister mounting rail layer are installed with demister peace Beam reinforcing plate 12 is filled, the top of corresponding demister mounting rail reinforcing plate is installed with the connected plate in demister mounting rail upstream;Remove The connected plate in day with fog mounting rail upstream and demister mounting rail reinforcing plate outward flange are connected with upper body hypomere inwall;Demister is pacified It is rectangle hollow beam to fill beam and spray thrower mounting rail.Also include four isometric floor stringers in each spray thrower mounting rail layer 6, adjacent short spray thrower mounting rail and long spray thrower mounting rail floor stringer corresponding with two are connected.Floor stringer 6 is that rectangle is empty Heart beam.
4. fume desulfurating absorption tower structure according to claim 1, it is characterized in that:Also include demister mounting rail Beam hole shrouding 7 and spray thrower mounting rail beam hole shrouding 8;Upper body hypomere is provided with corresponding demister mounting rail supported hole, lower Body hypomere is provided with corresponding spray thrower mounting rail supported hole;Stretch in demister mounting rail supported hole at the both ends of demister mounting rail Outside, the both ends of demister mounting rail and the weldering of upper body hypomere connect;The both ends of spray thrower mounting rail are supported on corresponding spray thrower peace Fill on beam supported hole and welded with lower body hypomere and connected;Each demister mounting rail stretches out beam hole and each spray thrower peace of upper body hypomere Fill beam and stretch out the beam hole of lower body hypomere respectively with demister mounting rail beam hole shrouding and the closing of spray thrower mounting rail beam hole shrouding.
Preferably, also include demister mounting rail connection supporting plate 9 connects supporting plate 10 with spray thrower mounting rail;Remove Day with fog mounting rail connection supporting plate connects with spray thrower mounting rail to be respectively equipped with and demister mounting rail, spray thrower peace in supporting plate Fill the perforation of beam adaptation;Demister mounting rail both ends connect branch through demister mounting rail connection supporting plate, demister mounting rail After fagging and the weldering of upper body hypomere connect, demister mounting rail connection supporting plate is welded with demister mounting rail again to be connected;Spray thrower is installed Beam both ends are welded after connecting through spray thrower mounting rail connection supporting plate, spray thrower mounting rail connection supporting plate and lower body hypomere, spray Leaching device mounting rail connects supporting plate weldering with spray thrower mounting rail and connected again.Body epimere is even made up of the trapezoidal steel plate strip section weldering of polylith.
In addition, lower body hypomere is additionally provided with being connected by both ends and lower body hypomere inwall, horizontal, opening upper half The supporting layer that tubular type support column 13,14,15,16,17,18,19 is formed, can be used to catch dropping liquid, specific structural details are because being Simple technique, it will not be described here.In addition, at the position that some have anti-corruption needs, it is required to coat glass flake, such as drench Beam connects under supporting plate and lower body between section surface and the outer surface of semicircle tubular-type support post 15.
A kind of embodiment of the manufacturing process of absorption tower body:
First, crane is got out first;
2nd, body epimere 2 is produced:
【1】Body epimere main body is hollow frustum type, is formed by welding by lath;
【2】The lower end weldering of body epimere main body is connected with what the mounting flange connected for the upper end weldering with upper body hypomere 31 was connected Ring flange;
【3】Second level demister pressure difference mouth M5;
3rd, a body epimere 2 is sling using crane;
4th, body epimere 2 it is fabricated below go out on body hypomere 31, step includes:
【1】Produce the ring flange for being respectively used to be connected with body epimere 2 and lower body hypomere 32;
【2】Produce two groups of long, medium and short demister mounting rail groups, every group include two isometric demister mounting rail short beams 41, Two isometric demister mounting rail central sills 42 and one eradicate day with fog installation beam length beam 43;Corresponding demister peace is produced simultaneously Fill Liang Liang holes shrouding 7, demister mounting rail connection supporting plate 9, demister mounting rail reinforcing plate 12;
【3】Upper body hypomere 31, including the perforation of corresponding demister mounting rail and first order demisting are produced with corresponding steel plate Device pressure difference mouth M4;
【4】Distinguish solid welding well corresponding ring flange in the upper and lower side of upper body hypomere 31;
【5】Two layers of demister mounting rail installation perforation, two layers of demister mounting rail peace are produced in the lower end of upper body hypomere 31 Corresponding perforation consistency from top to bottom in dress perforation, every layer is provided with five groups of demister mounting rail installation perforation, first group of demister peace altogether The diameter of the line of centres and upper body hypomere 31 that fill beam installation perforation overlaps, in another two groups of demister mounting rails installation perforation Heart line is symmetrical two-by-two on the line of centres of most long one group of demister mounting rail installation perforation;
【6】The both ends of demister installation beam length beam are passed through in the perforation of upper next layer of body hypomere 31;First carry out the first positioning Adjustment, then carry out second of positioning adjustment;
【7】Demister mounting rail connection on set is exposed on the both ends of the outer surface of body hypomere 31 in demister installation beam length beam Supporting plate 9, keep demister installation beam length beam motionless, demister mounting rail is connected the priority of supporting plate 9 and upper body hypomere 31 outer surfaces and the solid welding of demister installation beam length beam are together;
【8】The solid welding of demister mounting rail beam hole shrouding 7 is sealed the Liang Kongshang of demister installation beam length beam;
【9】With【6】Extremely【8】Identical step, corresponding demister mounting rail is connected the priority of supporting plate 9 and demister mounting rail Central sill, demister mounting rail short beam and the outer surface solid welding of upper body hypomere 31 are together;Corresponding demister mounting rail beam hole The priority solid welding of shrouding 7 seals demister mounting rail central sill, the Liang Kongshang of demister mounting rail short beam;
【10】Complete after demister installation beam length beam, demister mounting rail central sill, demister mounting rail short beam under upper body Each demister mounting rail both ends in section 31 are fixed together with demister mounting rail reinforcing plate 12 respectively, and wherein demister is installed Beam reinforcing plate is first together with the upper inner surface solid welding of body hypomere 31;
【11】Press【6】Extremely【10】The step of, five elimination day with fog installation beam length beams of last layer are installed;
5th, body epimere 2 is put on upper body hypomere 31;Body epimere 2 and upper body hypomere 31 are linked together;Then Crane is recycled to sling the body epimere 2 to connect together and upper body hypomere 31;The upper lower surface of body hypomere 31 is higher than lower body The height of hypomere 32;
6th, upper body hypomere 31 it is fabricated below go out lower body hypomere 32:
【1】Produce the ring flange for being respectively used to be connected with upper body hypomere 31 and absorption column foot tower;
【2】Three groups of spray thrower mounting rail groups are produced, each spray thrower mounting rail group includes two isometric short spray thrower installations The isometric floor stringer 6 of beam, two isometric long spray thrower mounting rails 51,52 and four;In addition, also make corresponding spray thrower peace Fill Liang Liang holes shrouding 8, spray thrower mounting rail connection supporting plate 10;
【3】Lower body hypomere 32 is produced with corresponding steel plate, includes the spray thrower mounting rail peace of three layers of spray thrower mounting rail group Fill hole;Every layer of spray thrower mounting rail mounting hole shares eight, and eight spray thrower mounting rail mounting holes are symmetrically distributed in for one group two-by-two The both sides of the same diameter of approximately the same plane;The most symmetrical diameter of eight spray thrower mounting rail mounting holes of last layer and most next Big angle in the angle of cut of the symmetrical diameter of eight spray thrower mounting rail mounting hole of layer is equal to 120 °, middle one layer of eight spray thrower peace The symmetrical diameter of dress beam mounting hole divides this hexagonal angle equally;The distance between two neighboring spray thrower mounting rail group, the superiors' spray Drench device mounting rail group apart from the lower upper surface of body hypomere 32 distance and basecoat spray thrower mounting rail group under lower body The distance of 32 lower surfaces of section is equal;
【4】The upper and lower side of corresponding ring flange and lower body hypomere 32 is connected;The flange of the lower end of lower body hypomere 32 Disk and absorption column foot tower are fixed together;Put down the association being connected together of body hypomere 31 and body epimere 2, and handle The upper end of the association and lower body hypomere 32 is fixed together by flange arrangement;
【5】Minimum one group of spray thrower mounting rail of a long spray thrower mounting rail through lower body hypomere 32 is installed respectively Hole, and the both ends of the spray thrower mounting rail is supported in the spray thrower mounting rail mounting hole of left and right;First to the spray thrower mounting rail The first positioning adjustment is carried out, then carries out second of positioning adjustment;Then the spray thrower mounting rail fix tightly;【6】In the spray The both ends of device mounting rail are nested with spray thrower mounting rail connection supporting plate 10 respectively;Spray thrower mounting rail is first connected supporting plate 10 Outer surface weldering with lower body hypomere 32 is connected together, then spray thrower mounting rail is connected supporting plate 10 and the weldering of spray thrower mounting rail Connect together;Respectively the spray is sealed together with one block of spray thrower mounting rail beam hole shrouding 8 and the both ends solid welding of spray thrower mounting rail Drench device mounting rail beam hole;
【7】According to【5】With【6】The good another root long of step solid welding spray thrower mounting rail;
【8】Continue according to【5】With【6】The good two short spray thrower mounting rails of step solid welding;
【9】Two floor stringers 6 in welding between two long and short two root spray thrower mounting rails combine;
【10】According to【5】Extremely【9】The step of install intermediate layer, then further in accordance with【5】Extremely【9】The step of install the superiors;
7th, produce that length is different according to installation site and different, semicircle tubular-type support post 13,14,15,16,17,18,19, The both ends of these semicircle tubular-type support posts are connected with lower body hypomere inwall respectively, and these semicircle tubular-type support posts are in water The flat, state of opening upwards;
So far, the manufacture of absorption tower body is completed.

Claims (7)

1. a kind of fume desulfurating absorption tower structure, including column foot tower and absorption tower body are absorbed, it is characterized in that:Absorption tower body bag Include body hypomere and body epimere;Body epimere is hollow frustum type, which is provided with second level demister pressure difference mouth;Body hypomere Including upper and lower body hypomere, upper body hypomere is provided with first order demister pressure difference mouth;The lower end of upper body hypomere and body epimere Flange is connected;Upper and lower body hypomere flange is connected;The lower end of lower body hypomere and absorption column foot tower flange are connected;Under upper body Section is provided with two layers of demister mounting rail, and lower body hypomere is provided with three layer of spray thrower mounting rail;Each demister mounting rail layer includes Two isometric demister mounting rail short beams, two isometric demister mounting rail central sills and one eradicate day with fog installation beam length beam, And two short beams, two central sills are respectively symmetrical parallel relative to long beam;Corresponding demister installation in two layers of demister mounting rail layer Beam is coplanar;Be equipped with above every layer of demister beam and remove spray film input pipe for two layers, be interconnected except spray film input pipe for this two layers and Lower floor except spray film input pipe output end and the demister on this layer of demister mounting rail except spray film input port connect Logical, upper strata is except the input of spray film input pipe is equal and removes spray film inlet communication accordingly;It is provided with each spray thrower mounting rail layer Two isometric short spray thrower mounting rails, isometric long spray thrower mounting rail, short spray thrower mounting rail and long spray thrower mounting rail Between it is mutually parallel;In three spray thrower mounting rail layers, the folder between spray thrower mounting rail in upper and lower spray thrower mounting rail layer Equal to 120 °, the corresponding spray thrower mounting rail in middle spray thrower mounting rail layer divides the size of this hexagonal angle equally at big angle in angle; Upper body hypomere and body epimere are provided with the first order, second level demister pressure difference mouth, and each top for spraying beam layer is provided with spray Manage, the both ends of demister mounting rail are installed with demister mounting rail reinforcing plate in two layers of demister mounting rail layer, remove accordingly The top of day with fog mounting rail reinforcing plate is installed with the connected plate in demister mounting rail upstream;Demister mounting rail upstream be connected plate and Demister mounting rail reinforcing plate outward flange is connected with upper body hypomere inwall;Demister mounting rail and spray thrower mounting rail are Rectangle hollow beam.
2. fume desulfurating absorption tower structure according to claim 1, it is characterized in that:Also wrapped in each spray thrower mounting rail layer Include four isometric floor stringers(6), adjacent short spray thrower mounting rail and long spray thrower mounting rail it is corresponding with two auxiliary Beam is connected.
3. fume desulfurating absorption tower structure according to claim 2, it is characterized in that:Floor stringer(6)For rectangle hollow beam.
4. fume desulfurating absorption tower structure according to claim 1, it is characterized in that:Also include demister mounting rail beam hole Shrouding(7)With spray thrower mounting rail beam hole shrouding(8);Upper body hypomere is provided with corresponding demister mounting rail supported hole, lower Body hypomere is provided with corresponding spray thrower mounting rail supported hole;Stretch in demister mounting rail supported hole at the both ends of demister mounting rail Outside, the both ends of demister mounting rail and the weldering of upper body hypomere connect;The both ends of spray thrower mounting rail are supported on corresponding spray thrower peace Fill on beam supported hole and welded with lower body hypomere and connected;Each demister mounting rail stretches out beam hole and each spray thrower peace of upper body hypomere Fill beam and stretch out the beam hole of lower body hypomere respectively with demister mounting rail beam hole shrouding and the closing of spray thrower mounting rail beam hole shrouding.
5. the fume desulfurating absorption tower structure according to claim 4 any one, it is characterized in that:Also include demister peace Fill beam connection supporting plate(9)Supporting plate is connected with spray thrower mounting rail(10);Demister mounting rail connects supporting plate and spray thrower The perforation with demister mounting rail, spray thrower mounting rail adaptation is respectively equipped with mounting rail connection supporting plate;Demister mounting rail Both ends are welded after connecting through demister mounting rail connection supporting plate, demister mounting rail connection supporting plate and upper body hypomere, demisting Device mounting rail connection supporting plate is welded with demister mounting rail again to be connected;Spray thrower mounting rail both ends connect branch through spray thrower mounting rail After fagging, spray thrower mounting rail connection supporting plate and the weldering of lower body hypomere connect, spray thrower mounting rail connects with spray thrower mounting rail again Supporting plate weldering is connect to connect.
6. according to the fume desulfurating absorption tower structure described in claim 1-5 any one, it is characterized in that:Body epimere is by polylith Trapezoidal steel plate strip section weldering is even formed.
7. a kind of manufacturing process of absorption tower body, it is characterized in that:
First, crane is got out first;
2nd, body epimere is produced(2):
【1】Body epimere main body is hollow frustum type, is formed by welding by lath;
【2】The lower end weldering of body epimere main body, which is connected with, to be used for and upper body hypomere(31)Upper end weldering connect mounting flange be connected Ring flange;
【3】Second level demister pressure difference mouth(M5);
3rd, a body epimere is sling using crane(2);
4th, in body epimere(2)It is fabricated below go out upper body hypomere(31), step includes:
【1】Produce and be respectively used to and body epimere(2)And lower body hypomere(32)Connected ring flange;
【2】Two groups of long, medium and short demister mounting rail groups are produced, every group includes two isometric demister mounting rail short beams (41), two pieces isometric demister mounting rail central sills(42)Day with fog installation beam length beam is eradicated with one(43);Produce simultaneously corresponding Demister mounting rail beam hole shrouding(7), demister mounting rail connection supporting plate(9), demister mounting rail reinforcing plate(12);
【3】Upper body hypomere is produced with corresponding steel plate(31), including corresponding demister mounting rail is perforated and the first order is removed Day with fog pressure difference mouth(M4);
【4】In upper body hypomere(31)Upper and lower side difference solid welding well corresponding ring flange;
【5】In upper body hypomere(31)Lower end produce the installation perforation of two layers demister mounting rail, two layers of demister mounting rail Corresponding perforation consistency from top to bottom in installation perforation, every layer is provided with five groups of demister mounting rail installation perforation, first group of demister altogether The line of centres and upper body hypomere of mounting rail installation perforation(31)Diameter overlap, the installation perforation of another two groups of demister mounting rails The line of centres it is symmetrical two-by-two on the line of centres of most long one group of demister mounting rail installation perforation;
【6】The both ends of demister installation beam length beam are passed through upper body hypomere(31)In next layer of perforation;It is fixed first to carry out first Position adjustment, then carry out second of positioning adjustment;
【7】Body hypomere is exposed in demister installation beam length beam(31)Demister mounting rail company is put on the both ends of outer surface Connect supporting plate(9), keep demister installation beam length beam motionless, demister mounting rail connected supporting plate(9)Successively and upper Body hypomere(31)Outer surface and the solid welding of demister installation beam length beam are together;
【8】Demister mounting rail beam hole shrouding(7)Solid welding seals the Liang Kongshang of demister installation beam length beam;
【9】With【6】Extremely【8】Identical step, corresponding demister mounting rail is connected supporting plate(9)Successively installed with demister Beam central sill, demister mounting rail short beam and upper body hypomere(31)Outer surface solid welding is together;Corresponding demister mounting rail Beam hole shrouding(7)Priority solid welding seals demister mounting rail central sill, the Liang Kongshang of demister mounting rail short beam;
【10】Complete after demister installation beam length beam, demister mounting rail central sill, demister mounting rail short beam under upper body Section(31)Interior each demister mounting rail both ends respectively with demister mounting rail reinforcing plate(12)It is fixed together, wherein demister Mounting rail reinforcing plate elder generation and upper body hypomere(31)Inner surface solid welding is together;
【11】Press【6】Extremely【10】The step of, five elimination day with fog installation beam length beams of last layer are installed;
5th, body epimere(2)It is put into body hypomere(31)On;Body epimere(2)With upper body hypomere(31)It is connected to Together;Then crane is recycled to sling the body epimere to connect together(2)With upper body hypomere(31);Upper body hypomere(31)Under End face is higher than lower body hypomere(32)Height;
6th, in upper body hypomere(31)It is fabricated below go out lower body hypomere(32):
【1】Produce and be respectively used to and upper body hypomere(31)And absorb the connected ring flange of column foot tower;
【2】Three groups of spray thrower mounting rail groups are produced, each spray thrower mounting rail group includes two isometric short spray thrower installations Beam, two isometric long spray thrower mounting rails(51,52)With four isometric floor stringers(6);In addition, also make corresponding spray Device mounting rail beam hole shrouding(8), spray thrower mounting rail connection supporting plate(10);
【3】Lower body hypomere is produced with corresponding steel plate(32), include the spray thrower mounting rail of three layers of spray thrower mounting rail group Mounting hole;Every layer of spray thrower mounting rail mounting hole shares eight, eight spray thrower mounting rail mounting holes two-by-two one group it is symmetrical In the both sides of the same diameter of approximately the same plane;The most symmetrical diameter of eight spray thrower mounting rail mounting holes of last layer and most lower Big angle in the angle of cut of the symmetrical diameter of one layer of eight spray thrower mounting rail mounting hole is equal to 120 °, middle one layer of eight spray thrower The symmetrical diameter of mounting rail mounting hole divides this hexagonal angle equally;The distance between two neighboring spray thrower mounting rail group, the superiors Spray thrower mounting rail group is apart from lower body hypomere(32)The distance and basecoat spray thrower mounting rail group of upper surface are apart from lower Body hypomere(32)The distance of lower surface is equal;
【4】Corresponding ring flange and lower body hypomere(32)Upper and lower side be connected;Lower body hypomere(32)Lower end Ring flange and absorption column foot tower are fixed together;Put down body hypomere(31)With body epimere(2)The connection being connected together Zoarium, and the association and lower body hypomere(32)Upper end be fixed together by flange arrangement;
【5】A long spray thrower mounting rail is passed through lower body hypomere respectively(32)Minimum one group of spray thrower mounting rail peace Hole is filled, and the both ends of the spray thrower mounting rail is supported in the spray thrower mounting rail mounting hole of left and right;First the spray thrower is installed Beam carries out the first positioning adjustment, then carries out second of positioning adjustment;Then the spray thrower mounting rail fix tightly;【6】In the spray The both ends of leaching device mounting rail are nested with spray thrower mounting rail connection supporting plate respectively(10);First spray thrower mounting rail is connected and supported Plate(10)With lower body hypomere(32)Outer surface weldering connect together, then spray thrower mounting rail connect supporting plate(10)And spray The weldering of device mounting rail connects together;Respectively with one block of spray thrower mounting rail beam hole shrouding(8)Both ends solid welding with spray thrower mounting rail exists The spray thrower mounting rail beam hole is sealed together;
【7】According to【5】With【6】The good another root long of step solid welding spray thrower mounting rail;
【8】Continue according to【5】With【6】The good two short spray thrower mounting rails of step solid welding;
【9】Two floor stringers in welding between two long and short two root spray thrower mounting rails combine(6);
【10】According to【5】Extremely【9】The step of install intermediate layer, then further in accordance with【5】Extremely【9】The step of install the superiors;
So far, the manufacture of absorption tower body is completed.
CN201711047565.5A 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology Active CN107803101B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711047565.5A CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711047565.5A CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Publications (2)

Publication Number Publication Date
CN107803101A true CN107803101A (en) 2018-03-16
CN107803101B CN107803101B (en) 2019-10-01

Family

ID=61582997

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711047565.5A Active CN107803101B (en) 2017-10-31 2017-10-31 The manufacturing process of fume desulfurating absorption tower structure and absorption tower ontology

Country Status (1)

Country Link
CN (1) CN107803101B (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2899917Y (en) * 2006-05-25 2007-05-16 郝成海 Smoke desulfurizing and denitrifying device by ammonia method
CN201073590Y (en) * 2007-07-18 2008-06-18 中建七局安装工程有限公司 Absorbing tower with flue gas desulfurization
CN203540255U (en) * 2013-07-26 2014-04-16 华北电力大学(保定) Fume gas desulfurization defogging device in coal-fired power plant

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2899917Y (en) * 2006-05-25 2007-05-16 郝成海 Smoke desulfurizing and denitrifying device by ammonia method
CN201073590Y (en) * 2007-07-18 2008-06-18 中建七局安装工程有限公司 Absorbing tower with flue gas desulfurization
CN203540255U (en) * 2013-07-26 2014-04-16 华北电力大学(保定) Fume gas desulfurization defogging device in coal-fired power plant

Also Published As

Publication number Publication date
CN107803101B (en) 2019-10-01

Similar Documents

Publication Publication Date Title
CN103122667B (en) Light-weight steel structure plafond of large-span underground powerhouse of hydroelectric station
CN101642670B (en) Rotational flow dust-removing desulfurization unit
CN202611714U (en) Tunnel assembly type construction trolley without welding
CN107803101A (en) The manufacturing process of fume desulfurating absorption tower structure and absorption tower body
CN205127730U (en) Desulfurization absorption tower with liquid layer is held to vortex
CN205025154U (en) 330kVGIS distribution device place rigid connection sail formula framework
CN205672779U (en) A kind of desulfuration spray tower spray equipment
CN207221679U (en) A kind of high-efficiency low-resistance spray equipment
CN204147759U (en) A kind of device improving wet desulfurization system mass-transfer efficiency
CN108889098B (en) Energy-saving ammonia process modified by gypsum-process desulfurization device
CN201482414U (en) Whirlwind dust removal and desulphurization device
CN207591562U (en) A kind of structure of fume desulfurating absorption tower
CN205886545U (en) Horizontal acid mist purification device
CN205288052U (en) Low temperature ozone oxidation deNOx systems
CN101332406A (en) Spraying system
CN201643975U (en) Spraying device of circulating slurry for desulfurizing flue gas
CN111701370A (en) High-efficient desulfurization dust removal spray set
CN211310172U (en) Large-diameter double-pipe trestle
CN207436639U (en) A kind of compound smoke removal facility of steel-glass reinforced plastic
CN104061580B (en) Process ammonia desulfuration equipment and the technique thereof of flue gas desulfurization band liquid
CN214287445U (en) Arrangement structure of acid gas removal equipment
CN202516470U (en) Combined glass steel desulfurization tower
CN202893507U (en) Wet sintering and desulfurizing flue gas deep purifying device
CN206424778U (en) A kind of controllable corrosion-resistant desulfurizing tower of exiting flue gas flow
CN206414958U (en) A kind of tower inward eddy is homogenized enhancing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant