CN107800150A CN201610806811.XA CN201610806811A CN107800150A CN 107800150 A CN107800150 A CN 107800150A CN 201610806811 A CN201610806811 A CN 201610806811A CN 107800150 A CN107800150 A CN 107800150A
Authority
CN
China
Prior art keywords
battery
echelon
energy
power station
battery case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610806811.XA
Other languages
Chinese (zh)
Inventor
潘杰
胡长冬
史良
黄宏辉
张敏玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Solar Energy Science and Technology Co Ltd
Original Assignee
Shanghai Solar Energy Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Solar Energy Science and Technology Co Ltd filed Critical Shanghai Solar Energy Science and Technology Co Ltd
Priority to CN201610806811.XA priority Critical patent/CN107800150A/en
Publication of CN107800150A publication Critical patent/CN107800150A/en
Pending legal-status Critical Current

Links

Classifications

    • H02J3/383
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J7/00Circuit arrangements for charging or depolarising batteries or for supplying loads from batteries
    • H02J7/34Parallel operation in networks using both storage and other dc sources, e.g. providing buffering
    • H02J7/35Parallel operation in networks using both storage and other dc sources, e.g. providing buffering with light sensitive cells
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/10Photovoltaic [PV]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Photovoltaic Devices (AREA)

Abstract

The method that photovoltaic plant is rationed the power supply is alleviated in a kind of echelon energy storage, collects the battery for the new-energy automobile for completing service life or the lithium battery of other completion service lifes, carries out conformity classification;Echelon utilization is carried out using the battery after screening, echelon energy-accumulating power station is built near photovoltaic plant;Battery management system is established to be managed each battery in echelon energy-accumulating power station;EMS is established, photovoltaic plant, echelon energy-accumulating power station are managed, when photovoltaic power station power generation power is more than setting value, photovoltaic plant is charged by two way convertor to echelon energy-accumulating power station;When photovoltaic power station power generation power is less than setting value, echelon energy-accumulating power station outwards exports electric energy by two way convertor, realizes peak load shifting.The present invention using echelon using energy storage to photovoltaic generation carry out peak load shifting, serve the effect of energy storage, can solve the problem of rationing the power supply, and do not increase the construction cost in power station.

Description

The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage
Technical field
The present invention relates to power system, more particularly to a kind of echelon energy storage to alleviate the method that photovoltaic plant is rationed the power supply.
Background technology
Photovoltaic generation and other new energy are sent out because power network bearing capacity is weak, digestion capability is limited in domestic west area Electricity takes a large amount of margining electric methods so that the operating efficiency of most of photovoltaic plant is very low, and can not realize has to illumination resource Effect utilizes, and causes wasting of resources phenomenon.For this case, design a kind of photovoltaic plant based on echelon energy storage and ration the power supply solution party Case, first, peak load shifting carried out using energy-storage battery, by receiving and store to photovoltaic electric energy on daytime, photovoltaic at night The period that power station can not work is discharged, and can effectively improve photoelectric conversion efficiency, improves resource utilization and reasonable disposition. Secondth, conventional energy-accumulating power station is once put into higher, and the cost recovery time is longer, while battery is faced with aging, eliminates, changes Risk, it will produce higher follow-up maintenance expense, this solution using echelon using energy-storage battery carry out it is secondary Solving this problem using perfection (still has 80% or so capacity, by returning after being expired due to new-energy automobile service life of lithium battery Receiving such battery still has higher use value, and this mode is referred to as echelon utilization).It is had the drawback that to recovery electricity The requirement in pond is higher, has clear and definite regulation to the mode and step for screening battery.
The content of the invention
The purpose of the present invention, just it is to provide for a kind of echelon energy storage and alleviates the method that photovoltaic plant is rationed the power supply.
To achieve these goals, present invention employs following technical scheme:Photovoltaic plant limit is alleviated in a kind of echelon energy storage The method of electricity, comprises the following steps:
The lithium battery of step 1, the battery for collecting the new-energy automobile for completing service life or other completion service lifes, The voltage and internal resistance of battery are detected, carry out conformity classification;
Step 2, using after screening battery carry out echelon utilization, near photovoltaic plant build echelon energy-accumulating power station;
Step 3, battery management system is established to be managed voltage, the temperature information of each battery in echelon energy-accumulating power station, Judge battery status, warning message is provided in time;
Step 4, EMS is established, photovoltaic plant, echelon energy-accumulating power station are managed, work as photovoltaic power station power generation When power is more than setting value, photovoltaic plant is charged by two way convertor to echelon energy-accumulating power station;In photovoltaic power station power generation When power is less than setting value, echelon energy-accumulating power station outwards exports electric energy by two way convertor, realizes peak load shifting.
The conformity classification comprises the following steps:
1) preliminary examination:Voltage inspection is carried out to the battery case of new-energy automobile, judges battery/LECU states;
2) clean:Battery case surface dirt is removed with hair-dryer or dust catcher;First with wet rag by battery case wiped clean, Battery case is wiped with dry wipe remove stain removal again;
3) number:Battery case is numbered, in above the fold adhesive label;
4) take battery case apart, test voltage and the internal resistance of battery case internal parallel battery pack, make a record;Battery case is pressed Classified using voltage, classified by using internal resistance;
7) accessory detects:Check LECU whether normal work;
8) balanced electric discharge completely:Battery case is integrally connected to discharge equipment, 22.5V is discharged to using 100A;Stand 10min;
9) charge:Battery case is integrally connected to charge-discharge machine;Using 50A charging 36min, 10min is stood.
Some areas of rationing the power supply western at present are because economic development relatively lags behind, electricity needs is insufficient, electricity market is narrow and small, separately One side fossil energy and new energy are all more plentiful, are nowhere dissolved which results in generation of electricity by new energy, current solution is done Method is that generation of electricity by new energy is limited, that is, performs policy of rationing the power supply.The present invention is sent out photovoltaic using the energy storage that echelon utilizes Electricity carries out peak load shifting, serves the effect of energy storage.Meanwhile the waste lithium cell that energy storage is utilized using echelon is compared to conventional storage Cost needed for energy system is much lower, has obvious economic value.Therefore, the present invention can solve the problem of rationing the power supply, and not increase The construction cost in power station.Echelon using energy-storage system by EMS BMS carry out the intelligent scheduling energy, photovoltaic send out When electric output power is more than the networking power of local requirement of rationing the power supply, the generated output beyond power of rationing the power supply is subjected to energy storage and filled Electricity.When photovoltaic power output is less than the networking power of local requirement of rationing the power supply, energy storage will be discharged.The construction purpose of the system It is that construction one effectively solves bound problem, improves the application case of the quality of power supply.
Brief description of the drawings
Fig. 1 is artwork used by method of the invention.
Embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.
Artwork is as shown in figure 1, including photovoltaic plant 1, echelon energy-accumulating power station 2, photovoltaic used by the method for the present invention Inverter 3, two way convertor 4, EMS 5, battery management system 6 and transformer 7.
The method of the present invention is to collect battery or other completion uses of the new-energy automobile for completing service life first The lithium battery in life-span, the voltage and internal resistance of battery are detected, carry out conformity classification;
Then echelon utilization is carried out using the battery after screening, echelon energy-accumulating power station is built near photovoltaic plant;
Establish battery management system to be managed voltage, the temperature information of each battery in echelon energy-accumulating power station, judge electricity Pond state, provides warning message in time;EMS is established, photovoltaic plant, echelon energy-accumulating power station are managed, work as light When overhead utility generated output is more than setting value, photovoltaic plant is charged by two way convertor to echelon energy-accumulating power station;In light When overhead utility generated output is less than setting value, echelon energy-accumulating power station outwards exports electric energy by two way convertor, realizes that peak clipping is filled out Paddy.
Above-mentioned conformity classification comprises the following steps:
1) preliminary examination:Voltage inspection is carried out to the battery case of new-energy automobile, judges battery/LECU states;
2) clean:Battery case surface dirt is removed with hair-dryer or dust catcher;First with wet rag by battery case wiped clean, Battery case is wiped with dry wipe remove stain removal again;
3) number:Battery case is numbered, in above the fold adhesive label;
4) take battery case apart, test voltage and the internal resistance of battery case internal parallel battery pack, make a record;Battery case is pressed Classified using voltage, classified by using internal resistance;
7) accessory detects:Check LECU whether normal work;
8) balanced electric discharge completely:Battery case is integrally connected to discharge equipment, 22.5V is discharged to using 100A;Stand 10min;
9) charge:Battery case is integrally connected to charge-discharge machine;Using 50A charging 36min, 10min is stood.

Claims (2)

1. the method that photovoltaic plant is rationed the power supply is alleviated in a kind of echelon energy storage, it is characterised in that comprises the following steps:
The lithium battery of step 1, the battery for collecting the new-energy automobile for completing service life or other completion service lifes, to electricity The voltage in pond and internal resistance are detected, and carry out conformity classification;
Step 2, using after screening battery carry out echelon utilization, near photovoltaic plant build echelon energy-accumulating power station;
Step 3, establish battery management system to be managed voltage, the temperature information of each battery in echelon energy-accumulating power station, judge Battery status, warning message is provided in time;
Step 4, EMS is established, photovoltaic plant, echelon energy-accumulating power station are managed, when photovoltaic power station power generation power During more than setting value, photovoltaic plant is charged by two way convertor to echelon energy-accumulating power station;In photovoltaic power station power generation power During less than setting value, echelon energy-accumulating power station outwards exports electric energy by two way convertor, realizes peak load shifting.
2. the method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage as claimed in claim 1, it is characterised in that:The uniformity sieve Choosing comprises the following steps:
1) preliminary examination:Voltage inspection is carried out to the battery case of new-energy automobile, judges battery/LECU states;
2) clean:Battery case surface dirt is removed with hair-dryer or dust catcher;First with wet rag by battery case wiped clean, then use Dry wipe wipes battery case and removes stain removal;
3) number:Battery case is numbered, in above the fold adhesive label;
4) take battery case apart, test voltage and the internal resistance of battery case internal parallel battery pack, make a record;To battery case by use Voltage is classified, and is classified by using internal resistance;
7) accessory detects:Check LECU whether normal work;
8) balanced electric discharge completely:Battery case is integrally connected to discharge equipment, 22.5V is discharged to using 100A;Stand 10min;
9) charge:Battery case is integrally connected to charge-discharge machine;Using 50A charging 36min, 10min is stood.
CN201610806811.XA 2016-09-07 2016-09-07 The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage Pending CN107800150A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610806811.XA CN107800150A (en) 2016-09-07 2016-09-07 The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610806811.XA CN107800150A (en) 2016-09-07 2016-09-07 The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage

Publications (1)

Publication Number Publication Date
CN107800150A true CN107800150A (en) 2018-03-13

Family

ID=61529903

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610806811.XA Pending CN107800150A (en) 2016-09-07 2016-09-07 The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage

Country Status (1)

Country Link
CN (1) CN107800150A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108599210A (en) * 2018-03-28 2018-09-28 中国电力科学研究院有限公司 A kind of echelon battery energy storage system and method for household photovoltaic power grid
CN109624764A (en) * 2018-09-13 2019-04-16 哈尔滨理工大学 A kind of wind-light-storage electrical automobile mobile charging device and control method utilizing battery energy storage using echelon
CN112838608A (en) * 2021-03-16 2021-05-25 阳光三星(合肥)储能电源有限公司 Energy storage system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103337671A (en) * 2013-06-27 2013-10-02 国家电网公司 Cascade utilization screening method of waste power batteries
CN105244918A (en) * 2015-11-12 2016-01-13 甘肃上航电力运维有限公司 Photovoltaic energy storage power station
CN205104913U (en) * 2015-11-18 2016-03-23 中航锂电(洛阳)有限公司 Flexible energy storage charging system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103337671A (en) * 2013-06-27 2013-10-02 国家电网公司 Cascade utilization screening method of waste power batteries
CN105244918A (en) * 2015-11-12 2016-01-13 甘肃上航电力运维有限公司 Photovoltaic energy storage power station
CN205104913U (en) * 2015-11-18 2016-03-23 中航锂电(洛阳)有限公司 Flexible energy storage charging system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108599210A (en) * 2018-03-28 2018-09-28 中国电力科学研究院有限公司 A kind of echelon battery energy storage system and method for household photovoltaic power grid
CN109624764A (en) * 2018-09-13 2019-04-16 哈尔滨理工大学 A kind of wind-light-storage electrical automobile mobile charging device and control method utilizing battery energy storage using echelon
CN112838608A (en) * 2021-03-16 2021-05-25 阳光三星(合肥)储能电源有限公司 Energy storage system
CN112838608B (en) * 2021-03-16 2024-05-28 阳光储能技术有限公司 Energy storage system

Similar Documents

Publication Publication Date Title
CN103050986B (en) A kind of micro-capacitance sensor and energy storage dispatching method thereof
CN104935045A (en) Battery pack equalization method for energy storage system adopting nickel-series storage batteries
CN104993602A (en) Modular energy storage system
CN202424196U (en) Large-capacity energy storage converter formed by connecting multiple groups of inverter units in parallel
CN203491707U (en) Energy storage system based on cascade utilization of power battery
CN107800150A (en) The method that photovoltaic plant is rationed the power supply is alleviated in echelon energy storage
CN106712257A (en) Photovoltaic energy storage full direct current electric vehicle charging station
CN106655233A (en) Secondary step utilization system of batteries
CN106160144A (en) A kind of household electric automobile high-power rapid charging system
CN202888862U (en) Energy storage inverter suitable for distributed new energy power
CN204156804U (en) A kind of novel household distributed solar energy electrification energy storage system
CN105811030A (en) Lithium-ion battery system balancer and control method thereof
CN203747465U (en) Battery equalization charging device based on ZigBee wireless network
CN204835716U (en) Modular energy storage system
CN104167781A (en) Wind-solar complementary power generation and energy storage control system
CN206277966U (en) Electric voltage equalization system between a kind of automobile power cell module
CN205407293U (en) Can insert little electric wire netting of photovoltaic board and body -building bicycle in a flexible way
CN205355920U (en) Solar energy is from full direct current energy storage charging station of net
CN103560537A (en) Area distribution photovoltaic power supply grid-connected system and control method of area distribution photovoltaic power supply grid-connected system
Rybárik et al. Overview of the Usability of Second-Life Batteries in Smart Distribution Grids
CN203536974U (en) Local distributed grid-connected photovoltaic power supply system
CN207968020U (en) A kind of energy storage device that battery echelon utilizes
CN105914870A (en) Communication base station stand-by power supply system based on activation-type cell and wind-solar complementary power supply system
CN205960666U (en) From complementary power generation system of one -piece type scene that is incorporated into power networks
CN102270862A (en) Vehicle-mounted battery management system having bidirectional and automatic balance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180313