CN107784409A - Project templet project management system based on BIM - Google Patents

Project templet project management system based on BIM Download PDF

Info

Publication number
CN107784409A
CN107784409A CN201610733275.5A CN201610733275A CN107784409A CN 107784409 A CN107784409 A CN 107784409A CN 201610733275 A CN201610733275 A CN 201610733275A CN 107784409 A CN107784409 A CN 107784409A
Authority
CN
China
Prior art keywords
project
form work
bim
webserver
management system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610733275.5A
Other languages
Chinese (zh)
Inventor
龚利文
李桦
何兵
付冠超
段宗哲
林闪宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201610733275.5A priority Critical patent/CN107784409A/en
Publication of CN107784409A publication Critical patent/CN107784409A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • General Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Invention is specifically a kind of project templet project management system based on BIM;It includes storing and sending the webserver, the cruise Control Module being connected with the webserver and the branch's computer being connected with the webserver of data message;It is characterized in that the application method of the management system includes:Assembled item basic file, basic model establishment is carried out by BIM softwares by cruise Control Module;Collect form work engineering and set up essential information, form work engineering information model establishment is carried out by BIM softwares by cruise Control Module;Model safety Force Calculation is carried out, form work engineering construction management file is generated and is uploaded to the webserver, each branch computer expert crosses the access webserver and checks form work engineering construction management file, consults and instruct site operation for related personnel.This management system accurate understanding template directly perceived can set up situation before form work engineering site operation, reduce construction operation cost, improve project management level.

Description

Project templet project management system based on BIM
Technical field
Invention is related to the construction management field of engineering project, specifically a kind of project templet work based on BIM Thread management system.
Background technology
Traditional form work engineering site construction management, usually field technician utilize routine according to two-dimensional design drawing Safe software for calculation carries out safe calculating, generation calculated description carries out programming, and scene is constructed after telling somebody what one's real intentions are.Such a management system Data Collection be present and calculate that time-consuming, result of calculation does not cause intuitively to actually use in result of calculation and error be present, calculates in system Error causes the problems such as waste of material.
The content of the invention
It is an object of the present invention to provide a kind of easy to use, the quick accurately modernization project templet work of information issue Thread management system.
In order to achieve the above object, the present invention is realized in:
A kind of project templet project management system based on BIM, it includes storing and sending the network of data message Server, the cruise Control Module being connected with the webserver and the branch's computer being connected with the webserver;The management system The application method of system includes:
Step 1, assembled item basic file, including design drawing, Design of Construction Organization, so that it is determined that project templet engineering information The point of application of model, basic model establishment is carried out by BIM softwares by cruise Control Module;
Step 2, collection form work engineering set up essential information, and form work engineering letter is carried out by BIM softwares by cruise Control Module Cease model creation;The form work engineering information model should be created on the basis of basic model, and according to project progress meter Draw to arrange to define it and set up and remove the time, be easy to its secondary to recycle;
Step 3, model safety Force Calculation is carried out, until meeting security requirement;
Step 4, generation form work engineering construction management file are simultaneously uploaded to the webserver by cruise Control Module,
Step 5, by the webserver by form work engineering construction management file distribution into each branch's computer, looked into for related personnel Read and instruct site operation.
The described project templet project management system based on BIM, design drawing described in step 1 its can carry Breath of winning the confidence includes structure type, floor, structural elements size and absolute altitude, span, strength grade of concrete;Project templet engineering is believed Breath model point of application refers to the concrete application behavior in item construction management of institute's established model, including safe calculated description and arrangement and method for construction Automatic establishment, output high-supported formwork are expounded through peer review scheme, and arrangement and method for construction three-dimensional visualization, material engineering amount statistics, drawing, which is deepened, to be set Meter.
The described project templet project management system based on BIM, the form work engineering described in step 2 are taken If essential information includes support body type, calculation basis, element type and specification, component load, edges of boards vertical rod and beam formwork Collaboration bearing mode, support ground situation, vertical rod in length and breadth away from, step pitch, sweep the floor bar height, base set, vertical rod load-bearing connection side Formula.
The described project templet project management system based on BIM, the peace to model described in step 3 Full Force Calculation need to optimize parameter step, be specifically included in and meet that specification and safety are calculated on the premise of requiring, adjustment is swept The thin end of the scroll is away from ground distance, vertical rod vertically and horizontally spacing, vertical rod step pitch, bridging width and horizontal direction interval step number.
This management system directly perceived accurate before form work engineering site operation can understand template and set up situation, while using can High-supported formwork identification is carried out depending on changing model, safety calculates, arrangement and method for construction and high-supported formwork programming, three-dimensional visualization displaying and scene Confide a technological secret, the construction drawing such as a key output plane, section and full-page proof and each material engineering amount statistics, supporting item portion strengthen Technical scheme is worked out, strict control construction quality and safety, reduces construction operation cost, improves project management level.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
A kind of project templet project management system based on BIM, it includes storing and sending data message The webserver, the cruise Control Module being connected with the webserver and the branch's computer being connected with the webserver;The pipe The application method of reason system includes:
1)The item base documents such as collection design drawing, Design of Construction Organization, form work engineering of identifying project information model point of application, Carry out basic model establishment;The item base document refers to described project scale, design feature, design content, project progress meter Draw and wait help to model the file that personnel understand project specifying information, mainly set comprising bidding document, design drawing, construction organization Meter etc.;Its extractable information of described described Project design drawing mainly includes but is not limited to structure type, floor, structure structure Part size and absolute altitude, span(Beam), strength grade of concrete etc.;Described project templet engineering information model point of application, which refers to, to be built Model concrete application behavior in item construction management, including but not limited to safe calculated description and arrangement and method for construction are worked out automatically, defeated Go out high-supported formwork and be expounded through peer review scheme, arrangement and method for construction three-dimensional visualization, material engineering amount statistics, drawing Deepen Design etc..The base Plinth model is mainly structural information model, according to structural drawings, Design of Construction Organization hierarchical component should be divided to be created, it is Form work engineering information model creates basis. 2)Collect form work engineering and set up essential information, carry out form work engineering information model wound Build;Form work engineering sets up essential information and refers to the component specification relevant with the safe Force Calculation of template and set up parameter, its Including but not limited to support body type, calculation basis, element type and specification, component load, edges of boards vertical rod and beam formwork are assisted Same bearing mode, support ground situation, vertical rod in length and breadth away from, step pitch, sweep the floor bar height, base set, vertical rod load-bearing connected mode Deng.The form work engineering information model should be created on the basis of structural information model, and according to construction program arrangement Define it to set up and remove the time, be easy to its secondary to recycle.
3)Model safety Force Calculation is carried out, parameter information is set up in optimization, until meeting security requirement.Described optimization Set up parameter and refer to that on the premise of specification and safety calculating requirement is met, adjustment sweeps the floor bar away between ground distance, vertical rod vertically and horizontally Away from, vertical rod step pitch, bridging width and horizontal direction interval step number etc..4)According to field application demand, automatic output template work File needed for journey construction management;It is specific in item construction management that field application demand refers mainly to modeled plate engineering information model Using behavior;File needed for form work engineering construction management includes but is not limited to form work engineering information model, form work engineering special project side Case, Deepen Design drawing, material engineering amount statistics etc..The form work engineering information model is reported to a higher authorities for approval available for scheme, expert audits, Cost estimation and visualization are told somebody what one's real intentions are.
5)Above-mentioned model and application file are shared to engineering management cloud platform, consult and instruct site operation for related personnel.

Claims (4)

1. a kind of project templet project management system based on BIM, it includes storing and sending the net of data message Network server, the cruise Control Module being connected with the webserver and the branch's computer being connected with the webserver;Its feature It is that the application method of the management system includes:
Step 1, assembled item basic file, including design drawing, Design of Construction Organization, so that it is determined that project templet engineering information The point of application of model, basic model establishment is carried out by BIM softwares by cruise Control Module;
Step 2, collection form work engineering set up essential information, and form work engineering letter is carried out by BIM softwares by cruise Control Module Cease model creation;The form work engineering information model should be created on the basis of basic model, and according to project progress meter Draw to arrange to define it and set up and remove the time, be easy to its secondary to recycle;
Step 3, model safety Force Calculation is carried out, until meeting security requirement;
Step 4, generation form work engineering construction management file are simultaneously uploaded to the webserver by cruise Control Module,
Step 5, by the webserver by form work engineering construction management file distribution into each branch's computer, looked into for related personnel Read and instruct site operation.
2. the project templet project management system according to claim 1 based on BIM, it is characterised in that step Its extractable information of design drawing described in rapid 1 includes structure type, floor, structural elements size and absolute altitude, span, coagulation Native strength grade;Project templet engineering information model point of application refers to institute's established model concrete application row in item construction management For, including safe calculated description and arrangement and method for construction work out automatically, output high-supported formwork is expounded through peer review scheme, arrangement and method for construction three-dimensional visible Change, material engineering amount statistics, drawing Deepen Design.
3. the project templet project management system according to claim 1 based on BIM, it is characterised in that step Form work engineering described in rapid 2, which sets up essential information, includes support body type, calculation basis, element type and specification, component Load, edges of boards vertical rod cooperate with bearing mode, support ground situation, vertical rod in length and breadth away from, step pitch, sweep the floor bar height, bottom with beam formwork Seat is set, vertical rod load-bearing connected mode.
4. the project templet project management system according to claim 1 based on BIM, it is characterised in that step The safe Force Calculation to model described in rapid 3 need to optimize parameter step, be specifically included in and meet specification and safety meter Calculate on the premise of requiring, adjustment sweeps the floor bar away from ground distance, vertical rod vertically and horizontally spacing, vertical rod step pitch, bridging width and level side To interval step number.
CN201610733275.5A 2016-08-27 2016-08-27 Project templet project management system based on BIM Pending CN107784409A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610733275.5A CN107784409A (en) 2016-08-27 2016-08-27 Project templet project management system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610733275.5A CN107784409A (en) 2016-08-27 2016-08-27 Project templet project management system based on BIM

Publications (1)

Publication Number Publication Date
CN107784409A true CN107784409A (en) 2018-03-09

Family

ID=61439434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610733275.5A Pending CN107784409A (en) 2016-08-27 2016-08-27 Project templet project management system based on BIM

Country Status (1)

Country Link
CN (1) CN107784409A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110782154A (en) * 2019-10-23 2020-02-11 中铁十八局集团有限公司 Construction plan management system based on BIM + GIS
CN110990925A (en) * 2019-11-29 2020-04-10 广联达科技股份有限公司 Template area calculation method and device based on geometric model processing and electronic equipment
CN111027114A (en) * 2019-03-18 2020-04-17 杭州百慕建筑工程有限公司 Method for ensuring safe implementation of high formwork supporting scheme by using BIM technology
CN114065336A (en) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 Revit-based high formwork region inspection method, device, medium and equipment
CN115730362A (en) * 2022-12-14 2023-03-03 中建三局集团(深圳)有限公司 Revit platform-based formwork configuration plug-in unit for cast-in-place structure and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104091215A (en) * 2014-07-22 2014-10-08 上海建科工程咨询有限公司 Project planning management system based on building information model
CN105512730A (en) * 2015-12-02 2016-04-20 中国南方电网有限责任公司 BIM model-based data center operation and maintenance system
CN105696467A (en) * 2016-02-04 2016-06-22 广厦建设集团有限责任公司 Formwork support construction method based on P-BIM technology
CN105868440A (en) * 2016-03-21 2016-08-17 扬州大学 Construction engineering data modeling method based on BIM (Building Information Modeling) technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104091215A (en) * 2014-07-22 2014-10-08 上海建科工程咨询有限公司 Project planning management system based on building information model
CN105512730A (en) * 2015-12-02 2016-04-20 中国南方电网有限责任公司 BIM model-based data center operation and maintenance system
CN105696467A (en) * 2016-02-04 2016-06-22 广厦建设集团有限责任公司 Formwork support construction method based on P-BIM technology
CN105868440A (en) * 2016-03-21 2016-08-17 扬州大学 Construction engineering data modeling method based on BIM (Building Information Modeling) technology

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111027114A (en) * 2019-03-18 2020-04-17 杭州百慕建筑工程有限公司 Method for ensuring safe implementation of high formwork supporting scheme by using BIM technology
CN110782154A (en) * 2019-10-23 2020-02-11 中铁十八局集团有限公司 Construction plan management system based on BIM + GIS
CN110782154B (en) * 2019-10-23 2023-09-15 中铁十八局集团有限公司 Construction planning management system based on BIM+GIS
CN110990925A (en) * 2019-11-29 2020-04-10 广联达科技股份有限公司 Template area calculation method and device based on geometric model processing and electronic equipment
CN114065336A (en) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 Revit-based high formwork region inspection method, device, medium and equipment
CN115730362A (en) * 2022-12-14 2023-03-03 中建三局集团(深圳)有限公司 Revit platform-based formwork configuration plug-in unit for cast-in-place structure and method
CN115730362B (en) * 2022-12-14 2023-08-11 中建三局集团(深圳)有限公司 Revit platform-based mold frame configuration plug-in and method for cast-in-situ structure

Similar Documents

Publication Publication Date Title
CN107784409A (en) Project templet project management system based on BIM
CN108312321B (en) Automatic material distribution method and device of material distributor and automatic material distribution system
CN111062081A (en) Underground continuous wall construction method based on BIM technology
CN105696467A (en) Formwork support construction method based on P-BIM technology
CN104281729B (en) A kind of BIM methods manufactured applied to steel building Digital manufacturing
CN104314310B (en) A kind of building block standardized construction method based on BIM
CN111400812A (en) BIM-based method for designing machining drawing of assembled structure shear wall
CN106709660A (en) BIM-based architectural design method
CN106284976A (en) A kind of aluminum alloy mould plate based on Revit joins mould method
Wijayakumar et al. Automation of BIM quantity take-off to suit QS’s requirements
CN107016625A (en) A kind of total bag enterprise B IM authorizing standard methods of architectural engineering
CN107341290A (en) Beam slab based on BIM is prefabricated with cast-in-place structural quantities extraction system and method
CN111395520B (en) Prefabricated column and superposed beam deep design method based on CAD and WebGl fabricated structures
CN107012860A (en) A kind of construction method of the post Single Pile joint bar positioner based on BIM technology
CN107169231A (en) The Deepen Design method of structural metal containment system based on BIM
CN109583149A (en) Super large lid rolling stock section in-depth modernization system and its construction method based on BIM management
CN109359347A (en) A kind of railway signal outdoor equipment three dimensional arrangement method and device based on BIM
CN112560134A (en) Batch deepening design method of assembled structure laminated slab based on CAD and BIM
CN112561487A (en) Method, device and equipment for calculating construction progress and readable storage medium
CN112215944A (en) Method for rapidly and accurately positioning dangerous boundary based on BIM technology
CN113032872A (en) BIM technology-based integrated resource management and control method for assembly type building progress plan
CN109558629B (en) Method and device for generating reinforcement arrangement scheme
CN209486723U (en) A kind of construction management application platform based on BIM technology application
Lim et al. An experimental study for quality assurance of free-form concrete panels produced by CNC machine
CN112560147A (en) BIM modeling calculation method and system for special-shaped roof lower column structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180309

RJ01 Rejection of invention patent application after publication